CN103861901A - Steel column oval man hole door on-the-spot cold bending manufacturing method - Google Patents

Steel column oval man hole door on-the-spot cold bending manufacturing method Download PDF

Info

Publication number
CN103861901A
CN103861901A CN201210541118.6A CN201210541118A CN103861901A CN 103861901 A CN103861901 A CN 103861901A CN 201210541118 A CN201210541118 A CN 201210541118A CN 103861901 A CN103861901 A CN 103861901A
Authority
CN
China
Prior art keywords
steel
steel plate
bending
baffle plate
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210541118.6A
Other languages
Chinese (zh)
Other versions
CN103861901B (en
Inventor
尹兰宁
罗琛晟
李义轩
张朝刚
岳锟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201210541118.6A priority Critical patent/CN103861901B/en
Publication of CN103861901A publication Critical patent/CN103861901A/en
Application granted granted Critical
Publication of CN103861901B publication Critical patent/CN103861901B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The invention relates to a steel column oval man hole door. The steel column oval man hole door on-the-spot cold bending manufacturing method comprises manufacturing a cold bending mold which comprises a semi-circular baffled plate and a straight baffle plate; placing the cold bending cold on site and enabling a travelling or a gantry crane to walk inside; welding stiffened plates on bilateral sides at one end of a to-be-machined steel plate and forming holes in the stiffened plates; arranging two fixing points at the left side and the right side of the on-the-spot ground cold bending mold and connecting a fixed pulley; inserting the other end of the machined steel plate between the semi-circular baffle plate and the straight baffle plate; connecting a steel rope to the holes of the stiffened plates and enabling one end of the steel rope to bypass the fixed pulley to be connected to the travelling crane or a portal crane hook to pull one end of the to-be-machined steel plate to bend downward; disassembling the steel rope, connecting to the other fixed pulley and bending the to-be-machined steel plate to be in place; bending the other steel plate; splicing the two steel plates which achieve bending and welding and connecting. The steel column oval man hole door on-the-spot cold bending manufacturing method enables manufacture to be easy and guarantees the manufacturing period.

Description

The curved preparation method of the oval manhole door Spot Cooling of steel column
Technical field
The present invention relates to the oval manhole door of steel column, relate in particular to the preparation method of the oval manhole door of steel column.
Background technology
In various steel construction industrial premises, be all designed with various visit passages and travelling crane inspection passage now, and this type of passage is often arranged in steel column system, for guarantee personnel walk unimpededly, conventionally design all requires to design manhole in solid-web steel column.This type of manhole is generally oval (two ends are a semi-circular structure, and middle part is rectangle), therefore in steel upper prop manufacturing process, needs to bend elliptical manhole.For the making of this class formation, conventionally adopt fire bending curved and bend or use professional roller mill to carry out machinery in conjunction with mechanical external force to bend.The former complex process, steel plate heating-up temperature cannot accurately be controlled, and simmering and bending hot spot is difficult to accurately determine, and oval molding effect and perception are all poor, and fabrication cycle is longer, is not suitable for batch making; Use roller mill bends, and need to be equipped with professional roller mill, drops into excessively, and field fabrication does not more satisfy the requirements, if entrust professional factory to bend specially manhole plate, increased again cost of manufacture, and fabrication cycle is long.
Summary of the invention
The present invention is intended to address the aforementioned drawbacks, and provides the oval manhole door Spot Cooling of a kind of steel column curved preparation method.The present invention is simple for production, utilizes existing appointed condition, reaches batch and bends, accurately bends the object of elliptical manhole plate, and ensured the making duration.
For addressing the above problem, the curved preparation method of the present invention's oval manhole door Spot Cooling of a kind of steel column, it comprises:
Step 1, clod wash internal model making, this clod wash mold comprises a semicircle baffle plate and a straight baffle plate, the radian of described semicircle baffle plate is determined according to people's bore ends semicircle diameter to be processed;
Step 2, the clod wash mold that step 1 is made is placed on scene, and driving or portal jib crane are walked across interior;
Step 3, in welding stiffened panel in both sides, steel plate one end to be processed, perforate on stiffened panel;
Step 4, ground clod wash mold left and right arranges two fixing points at the scene, and connects a fixed pulley;
Step 5, inserts the other end of the steel plate to be processed through step 3 processing between the semicircle baffle plate and straight baffle plate of clod wash mold; Be connected on the hole as reinforcement with steel cable, the other end is walked around fixed pulley and is connected driving or portal jib crane hook; Driving or portal jib crane start, and pull steel plate to be processed one end to bend downward into 40 °~50 °;
Step 6, pulls down steel wire rope, is connected on another fixed pulley, utilizes driving or portal jib crane that steel plate bending to be processed is put in place;
Step 7, repeating step five and six, bending another steel plate;
Step 8, is shaped completing two bending steel plate splicings, and is welded to connect.
The present invention has solved in batches, has accurately bent the making difficult point of elliptical manhole plate effectively.Conventional fire bending kinking closes that mechanical external force bends method and professional roller mill bends method, and early investment is large, complex process, cost of manufacture is high, fabrication cycle is long.Method of the present invention has effectively solved on-the-spot batch, has accurately bent the practical challenges of this type of Long Circle manhole plate, has avoided large-scale professional equipment to drop into, and greatly reduces the cost of manufacture of this operation, and has ensured fabrication cycle.The present invention is easy to make, economical and practical.
Brief description of the drawings
Below, the present invention is further illustrated by reference to the accompanying drawings:
Fig. 1-Fig. 2 is clod wash schematic diagram of the present invention.
Detailed description of the invention
As depicted in figs. 1 and 2, the curved preparation method of the present invention's oval manhole door Spot Cooling of a kind of steel column, it comprises:
Step 1, clod wash internal model making, this clod wash mold comprises a semicircle baffle plate 2 and baffle plate 3 always, the radian of described semicircle baffle plate is determined according to people's bore ends semicircle diameter to be processed;
Step 2, the clod wash mold 1 that step 1 is made is placed on scene, and driving or portal jib crane are walked across interior;
Step 3, in steel plate to be processed 4 both sides, one end welding stiffened panels 7, perforate on stiffened panel;
Step 4, ground clod wash mold left and right arranges two fixing points 5,6 at the scene, and connects a fixed pulley;
Step 5, inserts the other end of the steel plate to be processed through step 3 processing between the semicircle baffle plate 2 of clod wash mold, straight baffle plate 3; Be connected to steel cable on the hole of stiffened panel, the other end is walked around fixing point 5 fixed pulleys and is connected driving or portal jib crane hook; Driving or portal jib crane start, and pull steel plate to be processed one end to bend downward into 40 °~50 ° (referring to Fig. 1);
Step 6, pulls down steel wire rope, is connected on another drum fixed point 6 fixed pulleys, utilizes driving or portal jib crane by steel plate bending to be processed put in place (referring to Fig. 2);
Step 7, repeating step five and six, bending another steel plate;
Step 8, is shaped completing two bending steel plate splicings, and is welded to connect.

Claims (1)

1. the curved preparation method of the oval manhole door Spot Cooling of steel column, is characterized in that, it comprises:
Step 1, clod wash internal model making, this clod wash mold comprises a semicircle baffle plate and baffle plate always, the radian of described semicircle baffle plate is determined according to people's bore ends semicircle diameter to be processed;
Step 2, the clod wash mold that step 1 is made is placed on scene, and driving or portal jib crane are walked across interior;
Step 3, in welding stiffened panel in both sides, steel plate one end to be processed, perforate on stiffened panel;
Step 4, ground clod wash mold left and right arranges two fixing points at the scene, and connects fixed pulley;
Step 5, inserts the other end of the steel plate to be processed through step 3 processing between the semicircle baffle plate and straight baffle plate of clod wash mold; Be connected to steel cable on the hole of stiffened panel, the other end is walked around fixed pulley and is connected driving or portal jib crane hook; Driving or portal jib crane start, and pull steel plate to be processed one end to bend downward into 40 °~50 °;
Step 6, pulls down steel wire rope, is connected on another fixed pulley, utilizes driving or portal jib crane that steel plate bending to be processed is put in place;
Step 7, repeating step five and six, bending another steel plate;
Step 8, is shaped completing two bending steel plate splicings, and is welded to connect.
CN201210541118.6A 2012-12-14 2012-12-14 The curved preparation method of the oval manhole door Spot Cooling of steel column Active CN103861901B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210541118.6A CN103861901B (en) 2012-12-14 2012-12-14 The curved preparation method of the oval manhole door Spot Cooling of steel column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210541118.6A CN103861901B (en) 2012-12-14 2012-12-14 The curved preparation method of the oval manhole door Spot Cooling of steel column

Publications (2)

Publication Number Publication Date
CN103861901A true CN103861901A (en) 2014-06-18
CN103861901B CN103861901B (en) 2016-02-03

Family

ID=50901256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210541118.6A Active CN103861901B (en) 2012-12-14 2012-12-14 The curved preparation method of the oval manhole door Spot Cooling of steel column

Country Status (1)

Country Link
CN (1) CN103861901B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019117734A1 (en) 2017-12-15 2019-06-20 Garcia Miro Peschiera Alfonso Workbench for the cold intervention, folding, bending, twisting or deformation of metal plates or sheets
CN113334034A (en) * 2021-07-07 2021-09-03 南京科技职业学院 Manufacturing method of eccentric suspension post

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07171628A (en) * 1993-12-20 1995-07-11 Kanai Hiroyuki Method for forming cylindrical work out of flat sheet
RO119825B1 (en) * 2002-12-16 2005-04-29 Prompt-S.A. Main beam
CN201644641U (en) * 2010-03-18 2010-11-24 上海江南长兴重工有限责任公司 Gasket mould for bending thick plate for ship
CN101898207A (en) * 2010-07-12 2010-12-01 燕山大学 Four-point bending progressive die forming method for large straight seam pipe blank
CN202493638U (en) * 2012-03-14 2012-10-17 福州铭林钢塔钢构制造有限公司 Transmission mechanism of manhole ring brake bending machine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07171628A (en) * 1993-12-20 1995-07-11 Kanai Hiroyuki Method for forming cylindrical work out of flat sheet
RO119825B1 (en) * 2002-12-16 2005-04-29 Prompt-S.A. Main beam
CN201644641U (en) * 2010-03-18 2010-11-24 上海江南长兴重工有限责任公司 Gasket mould for bending thick plate for ship
CN101898207A (en) * 2010-07-12 2010-12-01 燕山大学 Four-point bending progressive die forming method for large straight seam pipe blank
CN202493638U (en) * 2012-03-14 2012-10-17 福州铭林钢塔钢构制造有限公司 Transmission mechanism of manhole ring brake bending machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019117734A1 (en) 2017-12-15 2019-06-20 Garcia Miro Peschiera Alfonso Workbench for the cold intervention, folding, bending, twisting or deformation of metal plates or sheets
CN113334034A (en) * 2021-07-07 2021-09-03 南京科技职业学院 Manufacturing method of eccentric suspension post

Also Published As

Publication number Publication date
CN103861901B (en) 2016-02-03

Similar Documents

Publication Publication Date Title
CN103827412B (en) The formula that the screws togather splice of deformed bar and establish threaded deformed bar
CN103861901A (en) Steel column oval man hole door on-the-spot cold bending manufacturing method
CN204098022U (en) Quick positioner of pile foundation steel reinforcement cage owner muscle
CN109183628A (en) A kind of ultra-large type variable cross-section Sarasota reinforcing bar component production method
CN102044938A (en) Method for hoisting large-scale motor by using shoulder-pole hoisting rotor penetration method
CN107989186B (en) A kind of prefabricated concrete structure primary steel feather joint node and its construction method
CN102561706B (en) Internal threading method for spatial large-span prestressed steel structure steel strand
CN106077200B (en) The hot-bending method of the U-shaped sunpender of boiler
CN104659977B (en) Sleeving tool and sleeving method
CN203579194U (en) Large-caliber thin-wall cylindrical pipe jacking section steel reinforcement cage coiling and welding device
CN104594797B (en) A kind of detachable U-shaped cat ladder of hydraulic engineering and manufacture method thereof
CN104361186A (en) Optimizing design method of three-roller guiding device connecting rod mechanism
JP2011190589A (en) Screw type reinforcing bar joint for deformed reinforcing bar, and threaded deformed reinforcing bar
CN204371366U (en) A kind of main muscle positioner of tunnel lining prefabricated pipe section
CN205677129U (en) Prefabricated superimposed sheet electric pipeline constructing device assembly
CN202762754U (en) Embossing and drawing machine
CN202734492U (en) Furnace cover with wall-cooling wall for electric arc furnace
CN206986927U (en) A kind of non-contact attachment structure of the prefabricated piping lane of split-type
CN103231446A (en) Factory production device for inner wallboards of buildings
CN202571635U (en) Automatic control device for welding temperature
CN207308660U (en) Vertical bending press
CN202298312U (en) Serial double-position barrel unit type twisting production device of steel strand
CN203198037U (en) Building internal wallboard industrialized production device
CN206607708U (en) Prefabricated panel and prefabricated panel attachment structure
CN205289235U (en) Stress relieving formula ribbed steel bar dephosphorization apparatus for producing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant