CN103835526A - Method for dismantling large concrete structure - Google Patents
Method for dismantling large concrete structure Download PDFInfo
- Publication number
- CN103835526A CN103835526A CN201410106966.3A CN201410106966A CN103835526A CN 103835526 A CN103835526 A CN 103835526A CN 201410106966 A CN201410106966 A CN 201410106966A CN 103835526 A CN103835526 A CN 103835526A
- Authority
- CN
- China
- Prior art keywords
- top board
- horizon bar
- wall
- cylinder
- vertical rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 21
- 238000010586 diagram Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention relates to the field of large concrete structures, in particular to a method for dismantling a large concrete structure. The technical problem to be solved is to provide a large concrete structure dismantling method which can dismantle the large concrete structure conveniently and safely. The method for dismantling the large concrete structure comprises a top plate, a column body and a wall body, wherein the column body and the wall body are arranged below the top plate and used for supporting the top plate, and the method comprises the following steps: a. selecting a vertical rod, a horizontal rod and a fastener; b. the top end of the vertical rod is tightly contacted with the top plate, and the end of the horizontal rod is tightly contacted with the column body or the wall body and is fixed through a fastener; c. cutting the top plate, and hoisting the top plate away through hoisting equipment; d. cutting the column body and the wall body, and hoisting the column body and the wall body away through hoisting equipment; e. and (5) dismantling the vertical rods and the horizontal rods. The method is simple and easy to implement in practical use, and greatly solves the problem that the traditional dismantling process excessively depends on a travelling crane pre-hoisting mode, particularly the dismantling of a large structure in use.
Description
Technical field
The present invention relates to large-sized concrete structure field, especially a kind of large-sized concrete structural demolition method.
Background technology
For concrete constructions such as factory buildings, in the time that needs are removed, the technological means adopting is at present to adopt a lot of drivings to lift in advance measure in the periphery of top board, could pulling down safety such as the top board being cut, cylinder and bodies of wall.But, be subject to the restriction of operation region, frequency of utilization and the scope restriction (generally can only hold a vehicling operation in a region) of driving, such method for dismounting with regard to performance place obvious defect, especially concerning some complicated irregular structure bodies, with cutting again after the pre-lifting of driving, on time and job area, all can not meet actual requirement.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of large-sized concrete structural demolition method of dismounting large-sized concrete structure of comparatively Portable safety.
The technical solution adopted for the present invention to solve the technical problems is: large-sized concrete structural demolition method, and comprise top board, and be arranged at cylinder and the body of wall of top board below for roof supporting, comprise the following steps:
A, choose at least one vertical rod, at least one horizon bar and at least one for by the fastener fastening intersection area of vertical rod and horizon bar according to the bulk of large-sized concrete structure to be removed;
B, by the bottom surface close contact of the top of described vertical rod and top board, by termination and cylinder or the body of wall close contact of described horizon bar next-door neighbour's cylinder and body of wall, and by fastener, crossing vertical rod and horizon bar are fixed;
C, by cutting equipment, top board is cut, described top board cutting seam separates with cylinder top board with body of wall, and by hanging device, top board is hung;
D, by cutting equipment, cylinder and body of wall are cut, and by hanging device, cylinder and body of wall are hung;
E, dismounting vertical rod and horizon bar.
Further, described top board is that bottom surface is the plane top board of plane.
Further, in described horizon bar, the interplanar spacing between horizon bar and the bottom surface of plane top board is topmost at least 20cm.
Further, described top board is that bottom surface is the cascaded surface type top board of cascaded surface.
Further, in described horizon bar, in horizon bar topmost and cascaded surface type top board, the cascaded surface spacing between the bottom surface in the top is at least 20cm.
Further, described top board is that bottom surface is the tapered plane type top board of tapered plane.
Further, in described horizon bar, the tapered plane spacing between horizon bar and the bottom surface top of tapered plane type top board is topmost at least 20cm.
The invention has the beneficial effects as follows: the present invention, first in conjunction with the space size of large-sized concrete structure to be removed, chooses vertical rod and the horizon bar of appropriate size; Then, by the bottom surface close contact of the top of described vertical rod and top board, by termination and cylinder or the body of wall close contact of described horizon bar next-door neighbour's cylinder and body of wall, and by fastener, crossing vertical rod and horizon bar are fixed, ensure that like this vertical rod provides strong support to top board, horizon bar not only provides support for cylinder or body of wall, and simultaneously also by vertical rod support column; Last, remove according to the order of first top board, rear cylinder or body of wall, after dismounting finishes, can be easily by vertical rod and horizon bar dismounting.The present invention is simple and easy to do in the time that reality is used, and has greatly solved in traditional dismounting operation the undue mode that relies on the pre-lifting of driving, also can, with treating that the concrete concrete structure of dismounting chooses dismounting measure flexibly, remove among large-scale Xtah Crude Clay structure while especially use.
Brief description of the drawings
Fig. 1 is that the present invention is applied to the schematic diagram that plane top board is removed.
Fig. 2 is that the present invention is applied to the schematic diagram that cascaded surface type top board is removed.
Fig. 3 is that the present invention is applied to the schematic diagram that tapered plane type top board is removed.
In figure, be labeled as: vertical rod 1, horizon bar 2, fastener 3, top board 4, plane top board 41, cascaded surface type top board 42, tapered plane type top board 43, body of wall 5, cylinder 6, top board cutting seam 7, interplanar spacing D1, cascaded surface space D 2, tapered plane space D 3.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is further described.
Large-sized concrete structural demolition method as shown in Figure 1, Figure 2, Figure 3 shows, comprises top board 4, and is arranged at cylinder 6 and the body of wall 5 of top board 4 belows for roof supporting 4, comprises the following steps:
A, choose at least one vertical rod 1, at least one horizon bar 2 and at least one for by the fastener 3 fastening intersection area of vertical rod 1 and horizon bar 2 according to the bulk of large-sized concrete structure to be removed;
B, by the bottom surface close contact of the top of described vertical rod 1 and top board 4, described horizon bar 2 is close to termination and cylinder 6 or body of wall 5 close contacts of cylinder 6 and body of wall 5, and by fastener 3 by fixing crossing vertical rod 1 and horizon bar 2;
C, by cutting equipment, top board 4 is cut, described top board cutting seam 7 separates with cylinder 6 top board 4 with body of wall 5, and by hanging device, top board 4 is hung;
D, by cutting equipment, cylinder 6 and body of wall 5 are cut, and by hanging device, cylinder 6 and body of wall 5 are hung;
E, dismounting vertical rod 1 and horizon bar 2.
In actual operation, many vertical rods 1 and the described support system of the orthogonal crossing formation of many horizon bars 2 often.General, need to adopt the concrete structure of method for dismounting of the present invention all to belong to comparatively large-scale concrete structure.In the time of concrete placement vertical rod 1 and horizon bar 2, first by the bottom surface close contact of the top of vertical rod 1 and top board 4, thereby ensure that the bottom surface that vertical rod 1 is top board 4 provides support; Then horizon bar 2 is close to termination and cylinder 6 or body of wall 5 close contacts of cylinder 6 and body of wall 5, thereby ensures to provide support for cylinder 6 or body of wall 5; For the intersection area of vertical rod 1 and horizon bar 2, fastening by fastener 3.Completing after above-mentioned Bracing Systems structure, can remove operation.Concrete dismounting operation is first by cutting equipment, top board 4 to be cut, and described top board cutting seam 7 separates with cylinder 6 top board 4 with body of wall 5, and by hanging device, top board 4 is hung.As shown in Figure 1, general, cutting seam 7 tracks are that vertical direction cuts along top board 4 thickness directions, ensure that hanging device can hang top board 4 easily.Next, by cutting equipment, cylinder 6 and body of wall 5 are cut, and by hanging device, cylinder 6 and body of wall 5 are hung.So far, completed the complete removal work to large-sized concrete structure.Last, remove vertical rod 1 and horizon bar 2 by dismounting fastener 3.The present invention allows the dismounting operation of large-sized concrete structure greatly simplify, and has also broken away to a great extent the dependence to the outer carrier strip part of equipment, construction environment etc. in conventional solution, has not only improved dismounting efficiency, has also reduced dismounting cost.
Generally speaking, as shown in Figure 1, the top board 4 of large-sized concrete structure can be divided into plane top board 41, cascaded surface type top board 42, tapered plane type top board 43 three types substantially.In conjunction with concrete dismounting experience, steel cable is well socketed on top board 4 in the time that top board 4 is left under order for convenient, taking plane top board 41 as example, can be chosen in the interplanar spacing D1 between horizon bar 2 and the bottom surface of plane top board 41 topmost in horizon bar 2 and be at least 20cm.Such space provides very sufficient operating space for operating personnel arrange steel cable.Based on same thought, for cascaded surface type top board 42, can selection level bar 2 in horizon bar 2 topmost and cascaded surface type top board 42 the cascaded surface space D 2 between the bottom surface in the top be at least 20cm.For tapered plane type top board 43, can selection level bar 2 in tapered plane space D 3 between horizon bar 2 and the bottom surface top of tapered plane type top board 43 be topmost at least 20cm.
The present invention, through the application of practice, not only allows the dismounting operation of large-sized concrete structure greatly simplify, and in addition, owing to having saved the operations such as the pre-lifting measure of driving, also allows dismounting cost greatly reduce.The present invention is particularly useful for removing large-sized concrete structure.
Claims (7)
1. large-sized concrete structural demolition method, comprises top board (4), and is arranged at cylinder (6) and the body of wall (5) of top board (4) below for roof supporting (4), it is characterized in that, comprises the following steps:
A, choose at least one vertical rod (1), at least one horizon bar (2) and at least one for by fastener (3) fastening the intersection area of vertical rod (1) and horizon bar (2) according to the bulk of large-sized concrete structure to be removed;
B, by the bottom surface close contact of the top of described vertical rod (1) and top board (4), by termination and cylinder (6) or body of wall (5) close contact of described horizon bar (2) next-door neighbour's cylinder (6) and body of wall (5), and by fastener (3), crossing vertical rod (1) and horizon bar (2) are fixed;
C, by cutting equipment, top board (4) is cut, described top board cutting seam (7) separates with cylinder (6) top board (4) with body of wall (5), and by hanging device, top board (4) is hung;
D, by cutting equipment, cylinder (6) and body of wall (5) are cut, and by hanging device, cylinder (6) and body of wall (5) are hung;
E, dismounting vertical rod (1) and horizon bar (2).
2. large-sized concrete structural demolition method as claimed in claim 1, is characterized in that: the plane top board (41) that described top board (4) is plane for bottom surface.
3. large-sized concrete structural demolition method as claimed in claim 2, is characterized in that: the interplanar spacing (D1) being positioned in described horizon bar (2) between horizon bar (2) and the bottom surface of plane top board (41) is topmost at least 20cm.
4. large-sized concrete structural demolition method as claimed in claim 1, is characterized in that: the cascaded surface type top board (42) that described top board (4) is cascaded surface for bottom surface.
5. large-sized concrete structural demolition method as claimed in claim 4, is characterized in that: in described horizon bar (2), be arranged in horizon bar (2) and the cascaded surface spacing (D2) of cascaded surface type top board (42) between the bottom surface of the top topmost and be at least 20cm.
6. large-sized concrete structural demolition method as claimed in claim 1, is characterized in that: the tapered plane type top board (43) that described top board (4) is tapered plane for bottom surface.
7. large-sized concrete structural demolition method as claimed in claim 6, is characterized in that: the tapered plane spacing (D3) being positioned in described horizon bar (2) between horizon bar (2) and the bottom surface top of tapered plane type top board (43) is topmost at least 20cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410106966.3A CN103835526A (en) | 2014-03-21 | 2014-03-21 | Method for dismantling large concrete structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410106966.3A CN103835526A (en) | 2014-03-21 | 2014-03-21 | Method for dismantling large concrete structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103835526A true CN103835526A (en) | 2014-06-04 |
Family
ID=50799386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410106966.3A Pending CN103835526A (en) | 2014-03-21 | 2014-03-21 | Method for dismantling large concrete structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103835526A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105569376A (en) * | 2015-12-17 | 2016-05-11 | 上海建工一建集团有限公司 | Demolition construction method for building wall |
CN108166770A (en) * | 2017-11-27 | 2018-06-15 | 广东精特建设工程有限公司 | Exempt from a kind of cutting method of support about the cutting of building structure column |
CN108518083A (en) * | 2018-03-27 | 2018-09-11 | 五冶集团上海有限公司 | The Demolition Construction method of main sintering building |
CN108678422A (en) * | 2018-05-29 | 2018-10-19 | 五冶集团上海有限公司 | The method for dismounting of steel stack |
CN108908752A (en) * | 2017-07-21 | 2018-11-30 | 东营联润信息科技有限公司 | A kind of enclosure wall cutting translating device |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10184037A (en) * | 1996-12-25 | 1998-07-14 | Ishii Iron Works Co Ltd | Construction method of water-containing type gas holder |
JP2010065460A (en) * | 2008-09-11 | 2010-03-25 | Besutera Kk | Method for dismantling large-sized storage tank |
JP2011069117A (en) * | 2009-09-25 | 2011-04-07 | Taisei Corp | Disassembling method of structure |
JP2012127131A (en) * | 2010-12-16 | 2012-07-05 | Taisei Corp | Structure demolition method and structure demolition system |
CN102650170A (en) * | 2012-05-03 | 2012-08-29 | 中国十七冶集团有限公司 | Vibration-free cutting method for equipment concrete foundation |
CN103291085A (en) * | 2013-06-07 | 2013-09-11 | 陈春来 | Concrete static force cutting dismantling construction method |
-
2014
- 2014-03-21 CN CN201410106966.3A patent/CN103835526A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10184037A (en) * | 1996-12-25 | 1998-07-14 | Ishii Iron Works Co Ltd | Construction method of water-containing type gas holder |
JP2010065460A (en) * | 2008-09-11 | 2010-03-25 | Besutera Kk | Method for dismantling large-sized storage tank |
JP2011069117A (en) * | 2009-09-25 | 2011-04-07 | Taisei Corp | Disassembling method of structure |
JP2012127131A (en) * | 2010-12-16 | 2012-07-05 | Taisei Corp | Structure demolition method and structure demolition system |
CN102650170A (en) * | 2012-05-03 | 2012-08-29 | 中国十七冶集团有限公司 | Vibration-free cutting method for equipment concrete foundation |
CN103291085A (en) * | 2013-06-07 | 2013-09-11 | 陈春来 | Concrete static force cutting dismantling construction method |
Non-Patent Citations (2)
Title |
---|
朱科峰: "闹市区钢筋混凝土结构切割拆除技术", 《建筑施工》 * |
飞虹: "钢筋混凝土切割拆除方案", 《科技创新与应用》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105569376A (en) * | 2015-12-17 | 2016-05-11 | 上海建工一建集团有限公司 | Demolition construction method for building wall |
CN108908752A (en) * | 2017-07-21 | 2018-11-30 | 东营联润信息科技有限公司 | A kind of enclosure wall cutting translating device |
CN108166770A (en) * | 2017-11-27 | 2018-06-15 | 广东精特建设工程有限公司 | Exempt from a kind of cutting method of support about the cutting of building structure column |
CN108518083A (en) * | 2018-03-27 | 2018-09-11 | 五冶集团上海有限公司 | The Demolition Construction method of main sintering building |
CN108518083B (en) * | 2018-03-27 | 2020-09-11 | 五冶集团上海有限公司 | Dismantling construction method of sintering main workshop |
CN108678422A (en) * | 2018-05-29 | 2018-10-19 | 五冶集团上海有限公司 | The method for dismounting of steel stack |
CN108678422B (en) * | 2018-05-29 | 2020-10-20 | 五冶集团上海有限公司 | Method for dismantling steel chimney |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103835526A (en) | Method for dismantling large concrete structure | |
CN103669655B (en) | Deformation joint both walls body concrete pouring construction process | |
CN204266590U (en) | Sump, hoistway formwork bed die anti-floating system | |
CN201148730Y (en) | Super large diameter cylindrical silo hydraulic slip mold construction operating platform | |
CN103790398B (en) | Non-pre-support dismantling method for large concrete structure | |
CN102900021B (en) | Split mounting type bridge wet joint construction method | |
CN204475841U (en) | Self lift type shaft template device | |
CN204199686U (en) | Without outrigger concrete parapet formwork system | |
CN106276577A (en) | The suspension bracket of a kind of framework isolated footing and operational approach | |
CN104179342A (en) | Hanging cage and construction method thereof for mounting profiled steel sheets on steel structural workshop wall surface | |
CN112963015B (en) | Tunnel dismantling construction method in collinear connection with existing subway line below | |
CN109208938A (en) | Armoured concrete slab orients lossless static(al) and processing method is cut and disassembled | |
CN202810211U (en) | Template removing tool | |
CN103174309A (en) | Umbrella-shaped finalization shed | |
CN204059206U (en) | A kind of bridge construction Support bracket | |
CN203755422U (en) | Detachable drainage ditch form board device with entablature | |
CN207749840U (en) | A kind of wallboard mounting machine | |
CN203200719U (en) | Hanging type slope pouring template device | |
CN108643925A (en) | Intersect the cycle construction method of the tunneling section under mid-board engineering method | |
CN104727569B (en) | Large Towers equipment increase method | |
CN204875544U (en) | T type roof beam pterygoid lamina reinforcing bar fetal membrane | |
JP2010203053A (en) | Method for demolishing ceiling | |
CN202745044U (en) | Purpose-made rigid support body construction structure strengthening rigidity of reinforcement cage | |
CN204311753U (en) | Column type shuttering fastening member | |
CN105696783A (en) | Detachable overhanging I-steel positioning mechanism |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140604 |