CN103831622A - Press fitting equipment for rubber bushing - Google Patents

Press fitting equipment for rubber bushing Download PDF

Info

Publication number
CN103831622A
CN103831622A CN201210474615.9A CN201210474615A CN103831622A CN 103831622 A CN103831622 A CN 103831622A CN 201210474615 A CN201210474615 A CN 201210474615A CN 103831622 A CN103831622 A CN 103831622A
Authority
CN
China
Prior art keywords
positioning fixture
lower clamp
workpiece
lining
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210474615.9A
Other languages
Chinese (zh)
Other versions
CN103831622B (en
Inventor
李佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Goldway Technologies Co Ltd
Original Assignee
Suzhou Goldway Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Goldway Technologies Co Ltd filed Critical Suzhou Goldway Technologies Co Ltd
Priority to CN201210474615.9A priority Critical patent/CN103831622B/en
Publication of CN103831622A publication Critical patent/CN103831622A/en
Application granted granted Critical
Publication of CN103831622B publication Critical patent/CN103831622B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B27/00Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for
    • B25B27/02Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for for connecting objects by press fit or detaching same
    • B25B27/06Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for for connecting objects by press fit or detaching same inserting or withdrawing sleeves or bearing races
    • B25B27/064Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for for connecting objects by press fit or detaching same inserting or withdrawing sleeves or bearing races fluid driven

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Automatic Assembly (AREA)

Abstract

The invention relates to press fitting equipment for a rubber bushing. The press fitting equipment comprises a lower clamp used for fixing a work-piece, and an upper clamp matched with the lower clamp and arranged above the lower clamp. The lower clamp comprises a supporting column fixing the work-piece. The upper clamp is provided with a locating clamp matched with the supporting column and used for arranging the bushing, and a pressing rod capable of extending into the locating clamp and pressing the bushing into the work-piece. The locating clamp comprises a body and a containing cavity penetrating through the body. The containing cavity comprises a containing portion, a first guide portion formed below the containing portion, a buffering portion formed below the first guide portion, and a second guide portion formed below the buffering portion. The first guide portion and the second guide portion are conical so that the bushing can be pressed into the work-piece conveniently.

Description

Rubber bushing press-mounting equipment
Technical field
The present invention relates to a kind of rubber bushing press-mounting equipment.
Background technology
Current rubber bushing press-mounting equipment generally comprises workbench, is arranged on the upper fixture on workbench, the lower clamp coordinating with upper fixture and the drive unit that drives lower clamp to move up and down, fixation workpiece on lower clamp, arranges the depression bar towards lower clamp on lower clamp.While press-fiting, on the fixed position of the outer surface of workpiece, put lining, then move down the lining on workpiece is pressed in workpiece by depression bar.In use, because lining is directly placed on the outer surface of workpiece, while press-fiting, the easy sideslip of lining or ejection, caused certain puzzlement thereby give to press-fit to this kind of rubber bushing press-mounting equipment.
In view of this, be necessary existing shelf to be improved to address the above problem.
Summary of the invention
The object of the present invention is to provide a kind of rubber bushing press-mounting equipment of being convenient to press-fit lining.
For realizing aforementioned object, the present invention adopts following technical scheme: a kind of rubber bushing press-mounting equipment, in order to by bushing press-mounting in workpiece, comprise the lower clamp in order to fixation workpiece, coordinate and be arranged on the upper fixture of lower clamp top with described lower clamp, described lower clamp comprises the support column of fixation workpiece, described upper fixture is provided with and coordinates with described support column and in order to place the positioning fixture of lining and can stretch in positioning fixture bushing press-mounting to the depression bar in workpiece, described positioning fixture comprises our department, connect the host cavity of described our department, described host cavity comprises placement portion, be formed on the first introduction part of below, described placement portion, be formed on the buffer part that the first introduction part issues, and be formed on the second introduction part of buffer part below, described the first introduction part and the second introduction part are all tapered.
As a further improvement on the present invention, described host cavity also comprises the peristome that is formed on top, placement portion, and described peristome is horn mouth.
As a further improvement on the present invention, described placement portion and buffer part are straight-tube shape, and the diameter of buffer part is less than the diameter of placement portion.
As a further improvement on the present invention, described positioning fixture also comprises the chamfered section that is formed on our department's tail end.
As a further improvement on the present invention, described positioning fixture also comprises the flank that outwards protrudes out formation from the end of our department.
As a further improvement on the present invention, described positioning fixture becomes T-shaped.
The invention has the beneficial effects as follows: by the placement portion, the first introduction part, buffer part and the second introduction part that form in positioning fixture, lining be squeezed gradually under the promotion of depression bar and overall dimensions is reduced, thereby being convenient to bushing press-mounting in workpiece.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of rubber bushing press-mounting machine equipment in the specific embodiment of the invention.
Fig. 2 is the structural representation of lower clamp in the rubber bushing press-mounting machine equipment of Fig. 1.
Fig. 3 is the lower clamp of Fig. 2 observation figure on other direction.
Fig. 4 is the structural representation of upper fixture in the rubber bushing press-mounting machine equipment of Fig. 1.
Fig. 5 is the structural representation of positioning fixture in the rubber bushing press-mounting machine equipment of Fig. 1.
Fig. 6 is the cutaway view of the positioning fixture of Fig. 5.
Fig. 7 is the structural representation of stroke frame and drive unit in the rubber bushing press-mounting machine equipment of Fig. 1.
Fig. 8 is the structural representation of installed part in the rubber bushing press-mounting machine equipment of Fig. 1.
Fig. 9 is the structural representation of pre-press and adjutage in the rubber bushing press-mounting machine equipment of Fig. 1.
Figure 10 is the structure chart of lower clamp in the rubber bushing press-mounting machine equipment of Fig. 1, workbench and workpiece.
Figure 11 is the structure chart of lining accommodation apparatus in the rubber bushing press-mounting machine equipment of Fig. 1.
Figure 12 is the part-structure figure of lower clamp in the rubber bushing press-mounting machine equipment of Fig. 1, workbench and workpiece.
The specific embodiment
Refer to Fig. 1 to Figure 12, the rubber bushing press-mounting machine equipment 100 in one embodiment of the invention is in order to be fitted in lining (not shown) in workpiece 7.This rubber bushing press-mounting machine equipment 100 comprises framework 1, be fixed on the stroke frame 4 of the lower clamp 2 on framework 1, the upper fixture 3 that coordinates and be arranged on lower clamp 2 tops with lower clamp 2, fixing upper fixture 3, in order to promote drive unit 5 that upper fixture 3 moves up and down, be fixed on framework 1 and be positioned at lower clamp 2 on one side in order to deposit the lining accommodation apparatus 6 of lining.Above-mentioned lower clamp 2 and upper fixture 3 are combined to form a fixture group 10.This rubber bushing press-mounting machine equipment 100 can complete the frock of three kinds of dissimilar workpiece 7, and corresponding three kinds of dissimilar workpiece 7, to there being the fixture group 10 of three kinds of different models.Framework 1 comprises workbench 11 and in order to support the support body 12 of this workbench 11.Lower clamp 2, stroke frame 4 and lining accommodation apparatus 6 are all fixed on workbench 11.In the present embodiment, this drive unit 5 is pneumatic shuttle.
Lower clamp 2 comprises base 22, be fixed on base 22 and with the vertically disposed support column 23 of base 22, be oppositely arranged on base 22 and in order to two handles 24 of mobile lower clamp 2.Cylinder 232 that support column 23 comprises the flange part 231 fixing with base 22, upwards extend to form from flange part 231, be formed on the holding division 233 of cylinder 232 tops in order to fixation workpiece 7.Holding division 233 comprises the fixing slot 234 being formed in holding division 233, the fixing wall 235 that forms this fixing slot 234 and the stage portion 236 forming in the peripheral indent of fixing wall 235.In the present embodiment, between handle 24 and base 22, be connected through the hinge.
Upper fixture 3 comprise be fixed on stroke frame 4 first substrate 31, be positioned at first substrate 31 belows second substrate 32, connect the expansion link 33 of first substrate 31 and second substrate 32 and be fixed on first substrate 31 and towards the depression bar 34 of second substrate 32.This second substrate 32 is provided with the positioning fixture 35 that runs through and protrude out this second substrate 32.The support column 23 of the corresponding lower clamp 2 of this positioning fixture 35 arranges, be positioned at support column 23 directly over.Depression bar 34 setting corresponding to positioning fixture 35, depression bar 34 be positioned at positioning fixture 35 directly over.Lining is arranged in positioning fixture 35.
Positioning fixture 35 is T-shaped, comprises our department 350, outwards protrudes out formation from the end of our department 350 in order to positioning fixture 35 be fixed on to the flank 351 on second substrate 32 and connect the host cavity 352 of our department 350 and be formed on the chamfered section 358 of our department's 350 tail ends.In the time that upper fixture 3 coordinates with lower clamp 2, thereby positioning fixture 35 conveniently extend in workpiece 7 by this chamfered section 358.This host cavity 352 in order to place lining and by depression bar 34 extend into host cavity 352 interior by the lining in host cavity 352 be pressed into the lining mounting groove 71 of workpiece 7 interior on.
This host cavity 352 comprise be positioned at host cavity 352 peristome 353, be formed on peristome 353 belows in order to place lining placement portion 354, be formed on 354 belows, placement portion the first introduction part 355, be formed on the buffer part 356 of the first introduction part 355 belows and be formed on the second introduction part 357 of buffer part 356 belows.This peristome 353 is horn-like towards host cavity 352 external expansions, because this peristome 353 is horn mouth, institute so that lining enter in positioning fixture 35.The first introduction part 355, the second introduction part 357 are all tapered, and the first introduction part 355 is and reduces gradually shape to buffer part 356 by placement portion 354, and the second introduction part 357 is and reduces gradually shape to host cavity 352 tail ends by buffer part 356.Placement portion 354 and buffer part 356 are straight-tube shape, and the diameter of buffer part 356 is less than the diameter of placement portion 354.
By placement portion 354, the first introduction part 355, buffer part 356 and second introduction part 357 of positioning fixture 35 interior formation, make lining under the promotion of depression bar 34, be squeezed gradually and overall dimensions is reduced, thereby be convenient to bushing press-mounting in workpiece 7.
And by the support column 23 of fixation workpiece 7 is set on upper fixture 3, first substrate 31, second substrate 32 are set on lower clamp 3 and are fixed on first substrate 31 and towards the depression bar 33 of second substrate 32, and on second substrate 32, arrange and can stretch into host cavity 352 and the lining in host cavity 352 is pressed into the positioning fixture 35 in workpiece 7 for depression bar 33, thereby contribute to prevent that lining is press-fiting sideslip in process, and improve the problem that causes not lining not coordinate with workpiece 7 completely due to pressure, improved and press-fited quality.
Stroke frame 4 comprise the location-plate 41, the support positioning plates 41 that are arranged on fixture 3 tops support 42, be positioned at location-plate 41 belows and in order to the installed part 43 of fixing upper fixture 3 and be connected and installed part 43 and the connecting rod 44 of location-plate 41.Support 42 is fixed on workbench 11.Installed part 43 is connected with drive unit 5 and promotes installed part 43 by drive unit 5 and moves up and down.Installed part 43 comprises top board 431, be oppositely arranged on two of top board 431 both sides holds plate 432 and is arranged on the trip bolt 433 on top board 431.Eachly hold holding section 435 that plate 432 comprises the auxiliary section 434 fixing with top board 431, extends to form from auxiliary section 434 downwards, hold plate 432 from holding section 435 towards another and bend the support division 436 extending to form and the notch part 437 forming from holding section 435 front end indents.Above-mentioned top board 431, holding section 435 and support division 436 form one in order to accommodate upper fixture 3 first substrate 31 hold chamber 438.Because notch part 437 is to form from holding section 435 front end indents, described in, this notch part 437 is formed on the both sides of the front port that holds chamber 438.After the first substrate 31 of upper fixture 3 is fixed to and holds in chamber 438, first substrate 31 moves up and down with installed part 43, move up and down and installed part 43 is connected with drive unit 5 and promote installed part 43 by drive unit 5, so indirectly, first substrate 31 is promoted to move up and down by drive unit 5.
On upper fixture 3, offer the screw hole coordinating with trip bolt 433, trip bolt 433 runs through this top board 431, when first substrate 31 accommodate hold chamber 438 interior after, trip bolt 433 is tightened downwards, until the bottom of trip bolt 433 enters in screw hole, thereby upper fixture 3 is fixed on installed part 43.So, there is the installed part 43 and the trip bolt 433 that hold chamber 438 by setting, be convenient to installation, the dismounting of fixture 3, and then can realize quick-replaceable, install fixture 3, shorten the working time.
Upper fixture 3 also comprises two projections 36 in the leading edge of the sidewall that is relatively arranged on first substrate 31.This projection 36 coordinates with notch part 437, prevents first substrate 31 upside-down mountings.In the time of first substrate 31 correct installation, first substrate 31 is inserted into and holds behind chamber 438, and projection 36 enters in notch part 437; In the time of first substrate 31 upside-down mounting, after projection 26 enters into notch part 437, first substrate 31 cannot enter into again and hold in chamber 438, so, can prevent first substrate 31 upside-down mountings by the cooperation of projection 36 and notch part 437.
Upper fixture 3 also comprises the pre-press 38 being connected with second substrate 32 and is opened in the material-saving mouth 39 on second substrate 32, and this pre-press 38 is arranged in material-saving mouth 39.Pre-press 38 is arranged on the top of workpiece 7.Pre-press 38 is fixed on pre-press 38 on second substrate 32 by an adjutage 383.These adjutage 383 one end are fixed on second substrate 32 by being fastenedly connected, and the other end is arranged on top the fixing pre-press 38 of material-saving mouth 39.This pre-press 38 comprises towards workpiece 7 and can make the flexible up and down body of rod 381 and be arranged on the body of rod 381 ends and can support the pre-pressure side 382 on workpiece 7.After can preventing that by this pre-press 38 lining is assembled in workpiece 7, when upper fixture 3 moves up, upper fixture drags on workpiece 7 and moves.By on upper fixture 3, pre-press 38 being set, thereby give precompression of workpiece by pre-press 38, in the time that upper fixture 3 is finished the work reset, prevent that fixture 3 from upwards lifting workpiece 7 and affecting job schedule, and then contribute to increase work efficiency.
Two that on workbench 11, are provided with in order to fixing lower clamp 2 are the keeper 13 that diagonal angle arranges.Each keeper 13 comprises the second clamping limb 132 of the first clamping limb 131 and the first clamping limb 131 square crossing settings and is formed and rectangular clamping part 132 by the first clamping limb 131 and the second clamping limb 132.Two clamping parts 132 are oppositely arranged and are relatively held on two diagonal angles of base 22.On workbench 11, offer fixing hole.Be provided with pilot pin 15 at this fixing hole, by this pilot pin 15, lower clamp 2 fixed, thus relative, on lower clamp 2, offer the bolt hole coordinating with this fixing hole.Bolt hole is formed on base 22, and connects base 22.There is the first clamping limb 131 by arranging on the workbench 11 at framework 1, realized the location of the base 22 to lower clamp 2 with the keeper 13 of the first fixing arm 131 the second clamping limb 132 arranged in a crossed manner and the clamping part 133 that formed by the first fixing arm 131 and the second fixing arm 132, thereby be convenient to the installation of lower clamp 2.
Lining accommodation apparatus 6 comprises placing the feet 67 in order to supported frame 62 on the magazine 61 of lining, the bracing frame 62 of fixing magazine 61 and stationary work-table 11.Guardrail 64 that bracing frame 62 comprises two rail portion that are oppositely arranged 63, extend to form on rail portion 63 laterals, connect two guardrails 64 and in order to support the baffle plate 65 at magazine 61 front ends.Rail portion 63 is compared workbench 11 and is the extension of acute angle angle.And because this rail portion 63 is obliquely installed, so after being positioned at the lining in front in magazine 61 and taking out, the lining at rear can be filled up room above at once, be convenient to staff from the interior feeding of magazine 61, contribute to increase work efficiency.This magazine 61 comprises diapire 611, the respectively antetheca 612 that upwards extends to form and be oppositely arranged from diapire 611 and rear wall 613, the two side 614 that upwards extends to form and be oppositely arranged from diapire 611 respectively.The height of antetheca 612 is less than the height of rear wall 613, and the cephalolateral margin 615 of two side 614 tilts towards antetheca 612.Guardrail 64 is arranged on the outside of two side 614.For the ease of magazine 61 is installed, this rail portion 63 has the guide part 66 that extends magazine 61.
Rubber bushing press-mounting machine equipment 100 also comprise detecting in the positioning fixture 35 of fixture 3 whether accommodate the anti-neglected loading checkout gear 9 of lining, in order to identify the automatic identification equipment 8 of fixture group 10 models.
Positioning fixture 35 also comprises the detection hole 359 arranged in a crossed manner with host cavity 352, and this detection hole 359 is arranged on the both sides of placement portion 354 and is communicated with this placement portion 354.Our department 350 is run through in this detection hole 359, and is positioned at the top of second substrate 32.Anti-neglected loading checkout gear 9 comprise on the support 42 that is fixed on stroke frame 4 and be arranged on the infrared facility 91 of positioning fixture 35 1 sides, relatively infrared facility 91 is arranged on the reflector 92 of positioning fixture 35 opposite sides.Infrared facility 91 is fixed on the support 42 of stroke frame 4, and reflector 92 is fixed on second substrate 32.
The infrared ray that this infrared facility 91 is carried can project on reflector 92 by the detection hole 359 of positioning fixture 35.Above-mentioned positioning fixture 35 and leakage proof detection device 9 form a leakproof detection system.In the time being placed with lining in positioning fixture 35, the infrared ray that infrared facility 91 is exported, not projecting on reflector 92 by being stopped by lining in detecting hole 359, now, can be judged in positioning fixture 35 and is placed with lining by this leakproof detection system; In the time not placing lining in positioning fixture 35, the infrared ray that infrared facility 91 is exported directly projects on reflector 92 by detecting hole 359, now, can be judged in positioning fixture 35 and not placed lining by this leakproof detection system.Realize in intelligent decision positioning fixture 35, whether there is lining by this leakproof detection system, thereby do not need to detect manually, prevent positioning fixture 35 neglected loading linings.
The above-mentioned frock of having mentioned rubber bushing press-mounting machine equipment 100 and can complete three kinds of dissimilar workpiece 7, and corresponding three kinds of dissimilar workpiece 7, to there being the fixture group 10 of three kinds of different models.Every sleeve clamp group 10 comprises upper fixture 3 and the lower clamp 2 that coupling arranges.Lower clamp 2 bases 22 of every sleeve clamp group 10 comprise be formed on the cog region 26 of base 22 bottoms and be arranged on 25, two identifying holes of two identifying holes in this cog region 26 according to arrangement position in three kinds of different cipher code set of the interior formation of cog region 26.The corresponding a kind of cipher code set of every sleeve clamp group 10.Automatic identification equipment 8 comprises that three are fixed on the mount pad 82 on workbench 11 in order to the inductive head 81 of recognition code group with by inductive head 81.This automatic identification equipment 8 is arranged on the bottom of workbench 11, offers induction through hole on workbench 11, and inductive head 81 can detect the identifying hole 25 in identification cog region 26 by this induction through hole.Thereby judgement is installed in the classification of fixture group 10 on workbench 11.Above-mentioned fixture group 10 and automatic identification equipment 8 are combined to form an automatic recognition system.Whether install correctly thereby can realize intelligent decision fixture group 10 by this automatic recognition system, prevent the generation of misloading phenomenon.Above-mentioned identifying hole 26 forms from base 22 indents.
Upper fixture 3 also can form another automatic recognition system with another automatic identification equipment 8.A side at upper fixture 3 forms a cog region, two identifying holes is set cog region 26 is interior, and two identifying holes form three kinds of different cipher code set in cog region according to arrangement position.Automatic identification equipment 8 comprises the inductive head 81 of two recognition code groups and by inductive head 81 fixed mountings 82, this mount pad 82 can be fixed on stroke frame 4.
Introduce in detail the operation principle of the rubber bushing press-mounting machine equipment 100 of the present embodiment below.
By the handle 24 on lower clamp 2, the base on lower clamp 2 22 is placed on workbench 11, then screwed in place bolt 15.Owing to being provided with keeper 13 on workbench 11, so can fast lower clamp 2 be fixed on workbench 11.Whether after installation lower clamp 2, start automatic identification equipment 8, detecting is the needed lower clamp 2 of this task.
Upper fixture 3 is inserted into holding in chamber 438 of stroke frame 4, then tightens trip bolt 433.Owing to being provided with on projection 36, stroke frame 4 and being provided with notch part 437 on upper fixture 3, so can prevent fixture upside-down mounting, also accelerate the set-up time of upper fixture 3.Now, start the automatic identification equipment 8 coordinating with upper fixture 3, in detection, whether fixture 3 is correct.
Workpiece 7 is fixed on the support column 23 of lower clamp 2.In lining accommodation apparatus 6, get lining, at the interior lining that arranges of positioning fixture 35.Start in anti-neglected loading checkout gear 9 detection and location fixtures 35 simultaneously and whether be provided with lining.
The installed part 43 that drive unit 5 promotes stroke frame 4 moves down, because upper fixture 3 is fixed on installed part 43, so lower clamp 3 is along with installed part 43 moves down until the positioning fixture 35 on the second substrate 32 of lower clamp 3 is inserted in the lining mounting groove 71 of workpiece 7.Now, the pre-press 38 on upper fixture 3 supports on workpiece 7, and the body of rod 381 of pre-press 38 is the state of tightening.After positioning fixture 35 is inserted into workpiece 7, second substrate 32 stops mobile, drive unit 5 still promotes installed part 43 and moves down, and first substrate 32 moves down with installed part 43 until the depression bar 34 on first substrate 32 is inserted in positioning fixture 35 and the lining in positioning fixture 35 is pressed into workpiece 7.
After depression bar 34 is pressed into lining to workpiece 7, drive unit 5 stops moving down, and changes into and moving, and drive unit 5 resets, and stroke frame 4, upper fixture 3 also reset simultaneously.In the time resetting, drive unit 5 pulls the installed part 43 of stroke frame 4 to move up, and upper fixture 3 also moves up with installed part 43.The positioning fixture 35 of upper fixture 3 separate with workpiece 7 before, pre-press 38 supports on workpiece 7 always, so on upper fixture 3, pre-press 38 is last parts that contact with workpiece 7.In the time that upper fixture 3 resets, complete the work of rubber bushing press-mounting machine equipment 100.
In sum, above-mentioned rubber bushing press-mounting machine equipment 100 is by support column 23, positioning fixture 35 and stretch into that positioning fixture 35 is interior to be pressed into lining to the depression bar 35 in workpiece 7 and to coordinate, prevent that lining is press-fiting sideslip in process, simultaneously, again by automatic identification equipment 8 and leakage proof detection device 9, prevent misloading and prevent that neglected loading phenomenon from occurring, thereby realize Intelligent Measurement, operating efficiency and the raising of overall raising equipment press-fit quality.
Although be example object, the preferred embodiment of the present invention is disclosed, but those of ordinary skill in the art will recognize, in the situation that not departing from by the disclosed scope and spirit of the present invention of appending claims, various improvement, increase and replacement are possible.

Claims (6)

1. a rubber bushing press-mounting equipment, in order to by bushing press-mounting in workpiece, it is characterized in that: described rubber bushing press-mounting equipment comprises the lower clamp in order to fixation workpiece, coordinate and be arranged on the upper fixture of lower clamp top with described lower clamp, described lower clamp comprises the support column of fixation workpiece, described upper fixture is provided with and coordinates with described support column and in order to place the positioning fixture of lining and can stretch in positioning fixture bushing press-mounting to the depression bar in workpiece, described positioning fixture comprises our department, connect the host cavity of described our department, described host cavity comprises placement portion, be formed on the first introduction part of below, described placement portion, be formed on the buffer part that the first introduction part issues, and be formed on the second introduction part of buffer part below, described the first introduction part and the second introduction part are all tapered.
2. positioning fixture according to claim 1, is characterized in that: described host cavity also comprises the peristome that is formed on top, placement portion, and described peristome is horn mouth.
3. positioning fixture according to claim 2, is characterized in that: described placement portion and buffer part are straight-tube shape, and the diameter of buffer part is less than the diameter of placement portion.
4. positioning fixture according to claim 3, is characterized in that: described positioning fixture also comprises the chamfered section that is formed on our department's tail end.
5. positioning fixture according to claim 4, is characterized in that: described positioning fixture also comprises the flank that outwards protrudes out formation from the end of our department.
6. positioning fixture according to claim 5, is characterized in that: described positioning fixture becomes T-shaped.
CN201210474615.9A 2012-11-21 2012-11-21 Rubber bushing press-mounting equipment Expired - Fee Related CN103831622B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210474615.9A CN103831622B (en) 2012-11-21 2012-11-21 Rubber bushing press-mounting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210474615.9A CN103831622B (en) 2012-11-21 2012-11-21 Rubber bushing press-mounting equipment

Publications (2)

Publication Number Publication Date
CN103831622A true CN103831622A (en) 2014-06-04
CN103831622B CN103831622B (en) 2016-12-21

Family

ID=50795687

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210474615.9A Expired - Fee Related CN103831622B (en) 2012-11-21 2012-11-21 Rubber bushing press-mounting equipment

Country Status (1)

Country Link
CN (1) CN103831622B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107127571A (en) * 2015-08-14 2017-09-05 葛云龙 A kind of motor control mainboard assemble mechanism
CN107214502A (en) * 2017-07-20 2017-09-29 万向钱潮(上海)汽车系统有限公司 A kind of brake caliper parking executive module assembly equipment and its application method
CN111112994A (en) * 2020-01-21 2020-05-08 汪涛 Steering engine bush press-in machine

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4226016A (en) * 1979-03-02 1980-10-07 The United States Of America As Represented By The Secretary Of The Army Method of removing a track pin from a track shoe
JPH0767767B2 (en) * 1991-03-30 1995-07-26 東海ゴム工業株式会社 Anti-vibration rubber bush assembly device
CN201471128U (en) * 2009-07-16 2010-05-19 合肥车桥有限责任公司 Rubber bushing pressing device
CN102069376B (en) * 2010-12-31 2012-07-04 宁波泛亚汽车部件有限公司 Bush fixture
CN102528421A (en) * 2011-12-14 2012-07-04 苏州工业园区高登威科技有限公司 Bushing fixture applicable to mounting sensor
CN102528430A (en) * 2011-12-14 2012-07-04 苏州工业园区高登威科技有限公司 Bush fixing press-mounting machine for automobile gearbox

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107127571A (en) * 2015-08-14 2017-09-05 葛云龙 A kind of motor control mainboard assemble mechanism
CN107171508A (en) * 2015-08-14 2017-09-15 葛云龙 Motor control mainboard assemble mechanism and its method of work
CN107214502A (en) * 2017-07-20 2017-09-29 万向钱潮(上海)汽车系统有限公司 A kind of brake caliper parking executive module assembly equipment and its application method
CN111112994A (en) * 2020-01-21 2020-05-08 汪涛 Steering engine bush press-in machine
CN111112994B (en) * 2020-01-21 2022-07-19 芜湖挺优机电技术有限公司 Steering engine bush press-in machine

Also Published As

Publication number Publication date
CN103831622B (en) 2016-12-21

Similar Documents

Publication Publication Date Title
CN103831623A (en) Press fitting equipment for rubber bushing
CN205551860U (en) Crashproof roof beam welding jig before car
CN104440069A (en) Integrated equipment used for installation and detection of screws
CN107243759A (en) A kind of Rapid workpiece clamping device
CN202479301U (en) Automatic heading machine
CN103831622A (en) Press fitting equipment for rubber bushing
CN103831609A (en) Press fitting equipment for rubber bushing
CN103831607A (en) Press fitting equipment for rubber bushing
CN103831608A (en) Press fitting equipment for rubber bushing
CN103831614A (en) Press fitting equipment for rubber bushing
CN103831615A (en) Press fitting equipment for rubber bushing
CN203495629U (en) Pneumatic positioning fixture
CN203495803U (en) Multipoint positioning pneumatic clamp
CN103831610A (en) Press fitting equipment for rubber bushing
CN103831612A (en) Press fitting equipment for rubber bushing
CN103831611A (en) Press fitting equipment for rubber bushing
CN207126763U (en) A kind of positioning tool based on the spray painting of brake block backboard
CN201871921U (en) Automatic mounting device for external clamp springs
CN205020564U (en) Automatic calibration equipment that detects in boats and ships wind channel
CN211332006U (en) Be applied to automatically controlled anchor clamps quick change base of workstation
CN209365658U (en) A kind of cylinder body mark fixture with hole location detecting function
CN205464998U (en) A auxiliary fixtures for installing driving motor support
CN103231229B (en) Universal joint processing device
CN103867868A (en) Oiling equipment of operating rod
CN204449741U (en) A kind of universal passenger vehicle attaches together frock

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 215121 No. 88 Zhuang Road, Suzhou Industrial Park, Jiangsu, China

Applicant after: SUZHOU INDUSTRIAL PARK GOLDWAY TECHNOLOGIES CO., LTD.

Address before: 215121, 2-2F-A, China Science and technology industrial square, 8 Exhibition Road, Suzhou Industrial Park, Jiangsu, China

Applicant before: Goldway Technologies Co., Ltd.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161221