CN103821378A - Large-scale steel tubular pillar two-way center line control technology - Google Patents

Large-scale steel tubular pillar two-way center line control technology Download PDF

Info

Publication number
CN103821378A
CN103821378A CN201410082627.6A CN201410082627A CN103821378A CN 103821378 A CN103821378 A CN 103821378A CN 201410082627 A CN201410082627 A CN 201410082627A CN 103821378 A CN103821378 A CN 103821378A
Authority
CN
China
Prior art keywords
steel column
steel
center line
plane
correct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410082627.6A
Other languages
Chinese (zh)
Other versions
CN103821378B (en
Inventor
赵永杰
潘石泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Jinhai Modern Construction Technology Co ltd
Original Assignee
HUNAN JINHAI STEEL STRUCTURE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN JINHAI STEEL STRUCTURE CO Ltd filed Critical HUNAN JINHAI STEEL STRUCTURE CO Ltd
Priority to CN201410082627.6A priority Critical patent/CN103821378B/en
Publication of CN103821378A publication Critical patent/CN103821378A/en
Application granted granted Critical
Publication of CN103821378B publication Critical patent/CN103821378B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to an environment protecting building construction technology, in particular to a large-scale steel tubular pillar two-way center line control technology method. According to the existing large-scale steel tubular pillar or latticed column two-way center line control technology, side sway and torsion are generated due to improper precision control in the manufacturing process, aiming at the above defects and aiming to solve the technical problem, the invention provides the large-scale steel tubular pillar two-way center line control technology for enabling manufacturing of steel pillars and tubular pillars to meet the requirements of safety, economy and reliable use. The large-scale steel tubular pillar two-way center line control technology consists of a lofting measurement and a temporary fixation measurement.

Description

The two-way center line control technology of Large Steel tubular pillar
technical field:
The technology of the present invention relates to Green environmental-protection building construction technology, specifically refers to the two-way center line control technology of Large Steel tubular pillar method.
background technology:
The two-way center line control technology of current Large Steel tubular pillar or lattice column can produce following defect because precision control in manufacturing process is improper:
1: manufacturing process flatness control exists error, cause, after lower prop docking, easily occurring side sway and distortion.
2: in manufacturing process, the control of steel column center line is improper, cause lower prop off-centring, directly affect on-the-spot post beam connection is installed, cause and connect rear steel column bending or on-the-spot steel crane beam distortion, strengthened site construction difficulty and hidden some dangers for to the safety of whole engineering.
3: in manufacturing process single tubular pillar two ends center line control improper, cause bracket tilt, cause crane girder to install.Junction plate and capital junction plate center deflection at the bottom of post, affect that steel column is connected with cast-in fixing bolt or with girder steel or both can only connect upper one.
summary of the invention:
For above-mentioned defect, for solving the problems of the technologies described above, the object of the present invention is to provide the two-way center line control technology of a kind of novel large cylindrical steel tube post, make the making of steel column, tubular pillar reach safety, economy, service-strong requirement.
The two-way center line control technology of Large Steel tubular pillar of the present invention is made up of setting-out measure and temporary fixed measure, it is characterized in that:
A: lofting control:
I. on the steel platform tooling bracket of measuring levelling, bullet is emitted steel column respectively to center line, guarantees that position of center line error meets Construction of Steel Structure inspection of quality code requirement;
II. first confirm two main limb single tube cross centre lines and portray at steel tube end part, two single tubes are put in place on steel platform tooling bracket, require 270 ° of location points of steel pipe cross centre line to overlap with tooling bracket steel column center line on steel platform, adopt messenger wire pendant to check; Other each limbs of blanking steel column are put to formation steel column main body rectangle in place, and between frock and pipe, the upper non-slipping block of pad, prevents steel pipe movement;
III. check distance between 90 ° of location points of two limbs at the steel column upper surface of assembled formation, guarantee steel column main body rectangular dimension, then the center line of the lower prop of having made is extended, guarantee that the center line of upper prop is parallel with the distance of lower prop center line;
IV. measure and control 6 some parallelism with level gauge, prevent side sway in steel column plane;
V. check steel column respectively to size comprehensively, confirm that errorless laggard spot welding fixes, tack weld thickness >=3mm, length ﹥ 40mm, spacing 300~600mm;
B: interim strengthening control measure: I. for preventing that in steel column welding procedure process, steel column upper prop produces plane inner bending distortion, mold is proofreaied and correct temporarily, reinforced to the special interior kernel of section line of steel column plane of doing, Steel for Large Steel Column upper prop and lower prop are proofreaied and correct and located, guarantee that in steel column welding procedure process steel column plane, kernel of section line position is constant, reinforce mold installation employing and be welded and fixed;
II. for preventing that in steel column welding procedure process, steel column upper prop produces out-of plane bending distortion, mold is proofreaied and correct temporarily, reinforced to the special outer kernel of section line of steel column plane of doing, Steel for Large Steel Column upper prop and lower prop are proofreaied and correct and located, guarantee that the outer kernel of section line position of steel column welding procedure process steel column plane is constant;
III. steel column is reinforced and is completely started to carry out steel column welding procedure, and work progress carries out at any time the inside and outside Deformation checking of steel column plane and adjusts center line and proofread and correct temporarily, reinforce bolt on mold and proofread and correct, and guarantees the inside and outside center line straightness accuracy of steel column plane;
IV. steel column welds to be removed center line after complete 24 hours and proofreaies and correct temporarily, reinforces mold.
The technology of the present invention compared with prior art, under equal execution conditions, can reduce to make and proofread and correct cost, improves produce in factory and site construction efficiency, improves installation quality.Eliminate and connect the potential safety hazard such as distortion, unbalance stress that has some setbacks and bring to building because of member.
accompanying drawing explanation:
Accompanying drawing 1 is the bending schematic diagram of the interior upper prop of plane that prior art causes;
Accompanying drawing 2 is bending schematic diagrames of the outer upper prop of plane that prior art causes;
Accompanying drawing 3 is that the two-way center line control technology of Large Steel tubular pillar of the present invention is determined center line alignment schematic diagram;
Accompanying drawing 4 is the two-way center line control technology of Large Steel tubular pillar of the present invention control point schematic diagrames;
Accompanying drawing 5 is control measure schematic diagrames in the two-way center line control technology of Large Steel tubular pillar of the present invention plane;
Accompanying drawing 6 is the outer measure schematic diagrames of the two-way center line control technology of Large Steel tubular pillar of the present invention plane;
Accompanying drawing 7 is that the two-way center line control technology of Large Steel tubular pillar of the present invention is reinforced mold schematic diagram.
The specific embodiment:
Visible with reference to accompanying drawing 1, accompanying drawing 2, original technology is made because of moulding bed, and center line control is unreasonable, causes difficult quality guarantee.Often in distribution upper prop plane or out-of-plane bending, the present invention by reference to the accompanying drawings 3---accompanying drawing 7, further describe, and the two-way center line control technology of Large Steel tubular pillar of the present invention is made up of setting-out measure and temporary fixed measure, and the step of lofting control is:
I. on the steel platform tooling bracket of measuring levelling, bullet is emitted steel column 1 respectively to center line, guarantees that position of center line error meets Construction of Steel Structure inspection of quality code requirement;
II. first confirm two main limb single tube cross centre lines and portray in steel pipe 1 end, two single tubes are put in place on steel platform tooling bracket, require 270 ° of location points of steel pipe cross centre line to overlap with tooling bracket steel column center line on steel platform, adopt messenger wire pendant to check; Other each limbs of blanking steel column are put to formation steel column main body rectangle in place, and between frock and pipe, the upper non-slipping block 2 of pad, prevents steel pipe movement;
III. check distance between 90 ° of location points of two limbs at steel column 1 upper surface of assembled formation, guarantee steel column main body rectangular dimension, then the center line of the lower prop of having made is extended, guarantee that the center line of upper prop is parallel with the distance of lower prop center line;
IV. measure and control 6 some parallelism with level gauge, prevent side sway in steel column 1 plane;
V. check steel column respectively to size comprehensively, confirm errorless
Interim strengthening control measure step is: I. for preventing that in steel column 1 welding procedure process, steel column 1 upper prop 4 produces plane inner bending distortion, mold 3 is proofreaied and correct temporarily, reinforced to the special interior kernel of section line of steel column plane of doing, Steel for Large Steel Column upper prop 4 and lower prop 5 are proofreaied and correct and located, guarantee that in steel column welding procedure process steel column plane, kernel of section line position is constant, reinforce mold installation employing and be welded and fixed;
II. for preventing that in steel column 1 welding procedure process, steel column 1 upper prop 4 produces out-of plane bending distortion, mold 3 is proofreaied and correct temporarily, reinforced to the special outer kernel of section line of steel column plane of doing, Steel for Large Steel Column upper prop 4 and lower prop 5 are proofreaied and correct and located, guarantee that the outer kernel of section line position of steel column welding procedure process steel column plane is constant;
III. steel column is reinforced and is completely started to carry out steel column welding procedure, and work progress carries out at any time the inside and outside Deformation checking of steel column plane and adjusts center line and proofread and correct temporarily, reinforce bolt on mold 3 and proofread and correct, and guarantees the inside and outside center line straightness accuracy of steel column plane;
IV. steel column welds to be removed center line after complete 24 hours and proofreaies and correct temporarily, reinforces mold 3.
Therefore, the two-way center line control technology of novel large cylindrical steel tube post has solved the structural stress problem producing in project installation process, has reduced Construction Cost, has guaranteed engineering construction quality.

Claims (1)

1. the two-way center line control technology of Large Steel tubular pillar is made up of setting-out measure and temporary fixed measure, it is characterized in that:
A: lofting control:
I. on the steel platform tooling bracket of measuring levelling, bullet is emitted steel column respectively to center line, guarantees that position of center line error meets Construction of Steel Structure inspection of quality code requirement;
II. first confirm two main limb single tube cross centre lines and portray at steel tube end part, two single tubes are put in place on steel platform tooling bracket, require 270 ° of location points of steel pipe cross centre line to overlap with tooling bracket steel column center line on steel platform, adopt messenger wire pendant to check; Other each limbs of blanking steel column are put to formation steel column main body rectangle in place, and between frock and pipe, the upper non-slipping block of pad, prevents steel pipe movement;
III. check distance between 90 ° of location points of two limbs at the steel column upper surface of assembled formation, guarantee steel column main body rectangular dimension, then the center line of the lower prop of having made is extended, guarantee that the center line of upper prop is parallel with the distance of lower prop center line;
IV. measure and control 6 some parallelism with level gauge, prevent side sway in steel column plane;
V. check steel column respectively to size comprehensively, confirm that errorless laggard spot welding fixes, tack weld thickness >=3mm, length ﹥ 40mm, spacing 300~600mm;
B: interim strengthening control measure: I. for preventing that in steel column welding procedure process, steel column upper prop produces plane inner bending distortion, mold is proofreaied and correct temporarily, reinforced to the special interior kernel of section line of steel column plane of doing, Steel for Large Steel Column upper prop and lower prop are proofreaied and correct and located, guarantee that in steel column welding procedure process steel column plane, kernel of section line position is constant, reinforce mold installation employing and be welded and fixed;
II. for preventing that in steel column welding procedure process, steel column upper prop produces out-of plane bending distortion, mold is proofreaied and correct temporarily, reinforced to the special outer kernel of section line of steel column plane of doing, Steel for Large Steel Column upper prop and lower prop are proofreaied and correct and located, guarantee that the outer kernel of section line position of steel column welding procedure process steel column plane is constant;
III. steel column is reinforced and is completely started to carry out steel column welding procedure, and work progress carries out at any time the inside and outside Deformation checking of steel column plane and adjusts center line and proofread and correct temporarily, reinforce bolt on mold and proofread and correct, and guarantees the inside and outside center line straightness accuracy of steel column plane;
IV. steel column welds to be removed center line after complete 24 hours and proofreaies and correct temporarily, reinforces mold.
CN201410082627.6A 2014-03-10 2014-03-10 Large-scale steel tubular pillar two-way center line control method Active CN103821378B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410082627.6A CN103821378B (en) 2014-03-10 2014-03-10 Large-scale steel tubular pillar two-way center line control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410082627.6A CN103821378B (en) 2014-03-10 2014-03-10 Large-scale steel tubular pillar two-way center line control method

Publications (2)

Publication Number Publication Date
CN103821378A true CN103821378A (en) 2014-05-28
CN103821378B CN103821378B (en) 2017-01-25

Family

ID=50756643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410082627.6A Active CN103821378B (en) 2014-03-10 2014-03-10 Large-scale steel tubular pillar two-way center line control method

Country Status (1)

Country Link
CN (1) CN103821378B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108712941A (en) * 2016-03-10 2018-10-26 日立造船株式会社 The steel pipe of steel pipe structuring and the welding method of connector

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09189132A (en) * 1996-01-10 1997-07-22 Tokyu Constr Co Ltd Fixing method of column base for steel frame column
CN102434003B (en) * 2011-08-29 2014-04-23 山东寿光第一建筑有限公司 Heavy battened steel column construction process
CN102720371B (en) * 2012-07-04 2015-02-18 中国机械工业建设集团有限公司 Butt joint method for multiple upright posts of steel structure module and temporary butt joint fixing device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108712941A (en) * 2016-03-10 2018-10-26 日立造船株式会社 The steel pipe of steel pipe structuring and the welding method of connector
CN108712941B (en) * 2016-03-10 2020-05-15 日立造船株式会社 Method for welding steel pipe and joint of steel pipe structural member
US11148218B2 (en) 2016-03-10 2021-10-19 Hitachi Zosen Corporation Method for welding steel pipe in steel pipe structure and joint

Also Published As

Publication number Publication date
CN103821378B (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN104141383A (en) Bailey beam suspension formwork supporting system and construction method thereof
CN103821372A (en) Method for installing trusses with different heights
CN105019665A (en) Method for mounting long-span structure beam based on total station
CN103526954B (en) Support for overweight precision embedded part and construction method thereof
CN101736698B (en) Accurate positioning method for cable-stayed bridge pylon cable guide pipe
CN103174302A (en) Construction method for large-diameter barrel cabin top
CN203947771U (en) A kind of Bailey beam pendent form support system
Bošnjak et al. Failure analysis and reconstruction design of the slewing platform mantle of the bucket wheel excavator O&K SchRs 630
CN101347703B (en) Installation technique of metallurgical gas desulfuration absorbing tower
CN103264968A (en) Super high-rise core tube internal and external hanging tower crane support beam structure and construction method thereof
CN107336346A (en) A kind of beam making bench
CN105133881A (en) Modular construction method for high temperature gas cooled reactor nuclear power plant containment bracket section wall
CN103243649A (en) System and method for quickly installing and positioning cable saddle
CN103173582A (en) Method for integral in-position mounting of blast-furnace five-way ball and eduction tubes thereof aloft
CN203867158U (en) Cantilever type scaffold structure with positioning plug for fixation
CN105648923A (en) Stay cable saddle positioning device and positioning method thereof
CN103088843A (en) Comprehensive pipe gallery pre-buried iron piece installing construction method
CN103821378A (en) Large-scale steel tubular pillar two-way center line control technology
CN106351246A (en) Installing method of the integral sleeve of a kind of T -bolt (diameter <= 48mm)
CN110145159B (en) Welding connection contact net hard cross beam and construction method thereof
CN110820942A (en) Construction method for roof overlong overhanging lotus flower modeling steel structure
CN104563525B (en) A kind of box steel arch beam Integral horizontal type group is to method
CN103174300B (en) Viscous damper installation construction method
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN202393382U (en) Hanging center aligning and leveling device for composite furnace shell

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 411100 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1

Patentee after: HUNAN JINHAI STEEL STRUCTURE CO.,LTD.

Address before: 410000 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1

Patentee before: HUNAN JINHAI STEEL STRUCTURE Co.,Ltd.

CP03 Change of name, title or address
TR01 Transfer of patent right

Effective date of registration: 20221215

Address after: 416014 Ma'an Industrial Park, Hexi Town, Jishou City, Xiangxi Tujia and Miao Autonomous Prefecture, Hunan Province

Patentee after: Hunan Jinhai Modern Construction Technology Co.,Ltd.

Address before: 411100 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1

Patentee before: HUNAN JINHAI STEEL STRUCTURE CO.,LTD.

TR01 Transfer of patent right