CN103821079A - Combined box girder sea-crossing bridge and construction method thereof - Google Patents

Combined box girder sea-crossing bridge and construction method thereof Download PDF

Info

Publication number
CN103821079A
CN103821079A CN201410094374.4A CN201410094374A CN103821079A CN 103821079 A CN103821079 A CN 103821079A CN 201410094374 A CN201410094374 A CN 201410094374A CN 103821079 A CN103821079 A CN 103821079A
Authority
CN
China
Prior art keywords
box girder
ultra
bridge
performance concrete
high performance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410094374.4A
Other languages
Chinese (zh)
Other versions
CN103821079B (en
Inventor
李立峰
周聪
侯立超
侯嘉庆
裴必达
吴文朋
胡思聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CN201410094374.4A priority Critical patent/CN103821079B/en
Publication of CN103821079A publication Critical patent/CN103821079A/en
Application granted granted Critical
Publication of CN103821079B publication Critical patent/CN103821079B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种组合箱梁跨海大桥及其施工方法。跨海大桥包括桥墩和由桥墩支承的组合箱梁,组合箱梁由高强混凝土顶板、超高性能混凝土底板和一对超高性能混凝土腹板围成,组合箱梁内沿桥梁纵向布置有体内及体外预应力钢束,其结构简单、耐久性良好。施工方法包括以下步骤:S1:进行桩基、承台和桥墩的施工,预制槽型梁;S2:浇筑高强混凝土顶板形成一跨组合箱梁,张拉组合箱梁内的体内及体外预应力钢束;S3:将组合箱梁整体吊装至临时支座上;S4:安装永久支座,现浇相邻跨湿接缝;S5:拆除临时支座,完成体系转化;S6:在相邻跨湿接缝处张拉体内预应力钢束,形成多跨连续梁结构;S7:完成桥面铺装及附属设施施工,其工艺简单,施工便捷迅速。

A composite box girder cross-sea bridge and a construction method thereof. The cross-sea bridge includes bridge piers and composite box girders supported by bridge piers. The composite box girder is surrounded by a high-strength concrete roof, an ultra-high-performance concrete bottom plate and a pair of ultra-high-performance concrete webs. The external prestressed steel beam has simple structure and good durability. The construction method includes the following steps: S1: construction of pile foundations, caps and piers, and prefabrication of channel beams; S2: pouring high-strength concrete roof to form a one-span composite box girder, tensioning the internal and external prestressed steel in the composite box girder S3: Hoist the composite box girder as a whole on the temporary support; S4: Install the permanent support, and cast the wet joints of adjacent spans; S5: Remove the temporary The internal prestressed steel tendons are stretched at the joints to form a multi-span continuous beam structure; S7: Complete the bridge deck pavement and ancillary facilities construction, the process is simple, and the construction is convenient and fast.

Description

一种组合箱梁跨海大桥及其施工方法A composite box girder cross-sea bridge and its construction method

技术领域 technical field

本发明涉及桥梁技术,尤其涉及一种组合箱梁跨海大桥及其施工方法。 The invention relates to bridge technology, in particular to a combined box girder cross-sea bridge and a construction method thereof.

背景技术 Background technique

现如今的跨海大桥非通航孔采用的多数为预应力混凝土箱梁、钢—混组合梁及钢箱梁方案。如杭州湾跨海大桥海上引桥采用70m预应力混凝土连续梁方案,滩涂区引桥采用50m预应力混凝土连续梁方案;青岛海湾大桥海上非通航孔采用60m预应力混凝土连续梁方案;东海大桥非通航孔采用70m预应力混凝土连续梁方案;港珠澳大桥非通航孔采用120m钢桁叠合连续梁桥及85m连续钢—混组合梁方案。而这些方案均存在着诸多问题。 Nowadays, most of the non-navigation holes of cross-sea bridges adopt prestressed concrete box girder, steel-concrete composite beam and steel box girder scheme. For example, the approach bridge of the Hangzhou Bay Bridge adopts a 70m prestressed concrete continuous beam scheme, the approach bridge in the tidal flat area adopts a 50m prestressed concrete continuous beam scheme; A 70m prestressed concrete continuous girder scheme is adopted; a 120m steel truss laminated continuous girder bridge and an 85m continuous steel-concrete composite girder scheme are adopted for the non-navigable opening of the Hong Kong-Zhuhai-Macao Bridge. However, there are many problems in these schemes.

预应力混凝土箱梁桥是目前应用最为广泛的一种桥梁结构形式。但长期以来的工程实践和应用现状反映出预应力混凝土箱梁桥存在很多的劣势。首先,恒载对控制截面产生的内力占到了总内力的80%以上,跨径越大,这个比例也就越大,甚至有可能达到90%左右,这大大制约了桥梁的跨越能力,同时受海上吊装能力的限制,吊装吨位不宜过大,因此预应力混凝土箱梁桥的跨径一般不会太大。这样带来的问题是:基础数量增加,进而导致对水流影响大、架梁次数多、架梁工期长等一系列问题;同时由于常规混凝土抗拉强度小的特点,为了尽可能地加大跨径,大跨径桥梁通常采用增大截面尺寸和板件厚度的方式提高其截面刚度以满足结构受力要求,这不仅增加了箱梁自重和工程造价,同时也增加了施工难度;另外,混凝土腹板由于受力的复杂性和构造处理、施工上的一些原因,大部分都会出现斜裂缝,这种斜裂缝不仅会导致桥梁结构刚度和强度的降低,还会加速钢筋的锈蚀,而锈蚀的钢筋则会引起体积的膨胀,从而使混凝土开裂,特别是在海洋这种弱碱性环境下,将进一步破坏混凝土的受力性能,降低材料的耐久性和结构的承载能力,影响到桥梁的美观和使用寿命。 Prestressed concrete box girder bridge is the most widely used bridge structure at present. However, the long-term engineering practice and application status reflect that there are many disadvantages of prestressed concrete box girder bridges. First of all, the internal force generated by the dead load on the control section accounts for more than 80% of the total internal force. The larger the span, the greater the proportion, and it may even reach about 90%. This greatly restricts the spanning capacity of the bridge. Due to the limitation of hoisting capacity at sea, the hoisting tonnage should not be too large, so the span of prestressed concrete box girder bridges is generally not too large. The problems brought about by this are: the number of foundations increases, which in turn leads to a series of problems such as large impact on water flow, many times of beam erection, and long construction period of beam erection; at the same time, due to the low tensile strength of conventional concrete, in order to increase the span as much as possible diameter, long-span bridges usually increase the cross-section rigidity by increasing the cross-sectional size and plate thickness to meet the structural force requirements, which not only increases the self-weight and project cost of the box girder, but also increases the difficulty of construction; in addition, the concrete Due to the complexity of the force and some reasons in the structural treatment and construction of the web, most of the oblique cracks will appear. Such oblique cracks will not only reduce the rigidity and strength of the bridge structure, but also accelerate the corrosion of steel bars. Reinforcement will cause the expansion of the volume, which will cause the concrete to crack, especially in the weak alkaline environment of the ocean, which will further damage the mechanical performance of the concrete, reduce the durability of the material and the bearing capacity of the structure, and affect the beauty of the bridge and service life.

若跨海大桥采用钢结构或钢—混组合结构,其跨径确实能够较预应力混凝土连续梁桥有较大幅度的增加,但是海水呈弱碱性,对钢和混凝土结构有较强的腐蚀作用,钢材在海洋环境的耐久性差,后期维护费用高。并且含钢结构桥梁造价高,若跨海大桥非通航孔采用钢结构桥型,其经济性将较差。 If the sea-crossing bridge adopts a steel structure or a steel-concrete composite structure, its span can indeed be greatly increased compared with the prestressed concrete continuous girder bridge, but seawater is weakly alkaline and has strong corrosion on steel and concrete structures As a result, the durability of steel in the marine environment is poor, and the later maintenance costs are high. Moreover, the cost of bridges with steel structures is high. If the non-navigation holes of the sea-crossing bridge adopt steel structure bridges, the economy will be poor.

目前,有一些大跨径箱梁桥采用主跨中部采用高性能轻集料混凝土(如主跨为301m的挪威斯托尔马桥)和主跨中部采用钢箱梁(如主跨为330m的重庆石板坡长江大桥复线桥)等方式来提高其跨越能力,也有采用腹板竖向预应力筋等方法来降低箱梁开裂风险,虽然这些方法有一定效果,但是这些方案设计和施工过程较为复杂,同时箱梁开裂的问题也未得到根本性解决。 At present, some long-span box girder bridges use high-performance lightweight aggregate concrete in the middle of the main span (such as the Stolma Bridge in Norway with a main span of 301m) and steel box girders in the middle of the main span (such as the 330m main span bridge). Chongqing Shibanpo Yangtze River Bridge double-track bridge) and other methods to improve its spanning capacity, and methods such as web vertical prestressed tendons to reduce the risk of box girder cracking. Although these methods have certain effects, the design and construction process of these schemes are relatively complicated At the same time, the problem of box girder cracking has not been fundamentally solved.

除此之外,国内也有学者提出了称之为预应力超高性能混凝土连续箱梁桥的桥型,该桥型的主要特点为全桥均采用超高性能混凝土材料,但此种桥型也存在着诸多问题。首先,该桥型由于板件厚度过薄不能布置过多体内索,因此体外预应力索较多,由于体外索暴露在空气中耐久性差,由此带来的养护问题和后期拉索更换问题、费用都比较大;并且由于全桥采用超高性能混凝土,所有板件均为薄板型结构,整个桥梁的自重较普通混凝土箱梁桥有较大幅度的降低,由此带来了车辆荷载作用下主梁应力幅过大,由此带来的疲劳问题值得深究,对主梁的长久受力不利;由于主梁采用薄板型结构,其截面的抗弯及抗扭刚度较小,因此必须设置较多的横隔板来抵抗主梁的扭转与畸变作用,由此也会带来体外预应力布置和转向难的问题;此外,由于板件过薄所带来的预应力张拉过程中张拉处局部应力超限问题也值得关注。 In addition, some scholars in China have also proposed a bridge type called prestressed ultra-high performance concrete continuous box girder bridge. There are many problems. First of all, because the thickness of the plate is too thin, too many internal cables cannot be arranged in this bridge type, so there are many external prestressed cables. Since the external cables are exposed to the air, the durability is poor, which brings maintenance problems and later cable replacement problems. The cost is relatively high; and because the whole bridge uses ultra-high performance concrete, and all the slabs are thin-slab structures, the self-weight of the whole bridge is greatly reduced compared with ordinary concrete box girder bridges. The stress amplitude of the main girder is too large, and the fatigue problem caused by it is worthy of further study, which is not good for the long-term stress of the main girder; since the main girder adopts a thin-plate structure, the bending and torsional rigidity of its section is small, so it must be set Many diaphragms are used to resist the torsion and distortion of the main girder, which will also bring about the difficulty of external prestressing arrangement and steering; The problem of local stress exceeding the limit is also worthy of attention.

发明内容 Contents of the invention

本发明要解决的技术问题是克服现有技术的不足,提供一种结构简单、耐久性能良好、适用于大跨径、应用前景广阔的组合箱梁跨海大桥,以及工艺流程简单,施工简便、快捷、迅速的组合箱梁跨海大桥施工方法。 The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art, to provide a combined box girder cross-sea bridge with simple structure, good durability, suitable for large spans, and broad application prospects, as well as simple technological process, convenient construction, A fast and rapid construction method for a combined box girder cross-sea bridge.

为解决上述技术问题,本发明采用以下技术方案: In order to solve the problems of the technologies described above, the present invention adopts the following technical solutions:

一种组合箱梁跨海大桥,包括桥墩和由桥墩支承的组合箱梁,所述组合箱梁由高强混凝土顶板、超高性能混凝土底板和一对超高性能混凝土腹板围成,所述组合箱梁内沿桥梁纵向布置有体外预应力钢束和体内预应力钢束。 A composite box girder cross-sea bridge, comprising a bridge pier and a composite box girder supported by the bridge pier, the composite box girder is surrounded by a high-strength concrete roof, an ultra-high-performance concrete bottom plate and a pair of ultra-high-performance concrete webs, the combination Inside the box girder, there are external prestressed steel beams and internal prestressed steel beams arranged along the longitudinal direction of the bridge.

作为上述技术方案的进一步改进: As a further improvement of the above technical solution:

所述超高性能混凝土底板和一对超高性能混凝土腹板整体预制成槽型梁结构。 The ultra-high-performance concrete bottom plate and a pair of ultra-high-performance concrete webs are integrally prefabricated into a channel beam structure.

所述超高性能混凝土腹板顶部设有用于与高强混凝土顶板连接的卡槽,所述卡槽沿桥梁纵向排列有多条。 The top of the ultra-high-performance concrete web is provided with slots for connecting with the high-strength concrete roof, and there are multiple slots arranged longitudinally along the bridge.

所述跨海大桥的跨径为90m~120m。 The span of the sea-crossing bridge is 90m-120m.

所述跨海大桥为简支变连续桥型。 The sea-crossing bridge is simply supported variable continuous bridge type.

所述超高性能混凝土底板厚度为15~20cm,超高性能混凝土腹板的厚度为16~22cm,所述高强混凝土顶板的厚度为26~30cm,所述组合箱梁内每15~20m设置1道横隔板。 The thickness of the ultra-high-performance concrete bottom plate is 15-20cm, the thickness of the ultra-high-performance concrete web is 16-22cm, the thickness of the high-strength concrete roof is 26-30cm, and 1 Road partition.

一种如上所述组合箱梁跨海大桥的施工方法,包括以下步骤: A construction method for a combined box girder cross-sea bridge as described above, comprising the following steps:

S1:在现场进行桩基、承台和桥墩的施工,同时在预制场将超高性能混凝土腹板与超高性能混凝土底板预制成槽型梁; S1: On-site construction of pile foundations, caps and piers, and at the same time prefabrication of ultra-high-performance concrete webs and ultra-high-performance concrete bottom slabs into channel beams in the prefabrication yard;

S2:在槽型梁上浇筑高强混凝土顶板形成一跨组合箱梁,或将预制好的高强混凝土顶板通过湿接缝与槽型梁连接形成一跨组合箱梁,同时张拉组合箱梁内的体外及体内预应力钢束; S2: Pour a high-strength concrete roof on the channel beam to form a one-span composite box girder, or connect the prefabricated high-strength concrete roof to the channel beam through wet joints to form a one-span composite box girder, and simultaneously tension the composite box girder External and internal prestressed steel beams;

S3:在桥墩上安装临时支座,将组合箱梁整体吊装至临时支座上; S3: Install temporary supports on the pier, and hoist the combined box girder to the temporary supports as a whole;

S4:安装永久支座,现浇相邻跨湿接缝; S4: Install permanent support, cast-in-place adjacent span wet joints;

S5:待相邻跨湿接缝混凝土强度达到90%后,拆除临时支座,完成体系转化; S5: After the concrete strength of the adjacent wet joint reaches 90%, the temporary support is removed to complete the system transformation;

S6:在相邻跨湿接缝处张拉体内预应力钢束,形成多跨连续梁结构; S6: Stretch the internal prestressed steel tendons at the wet joints of adjacent spans to form a multi-span continuous beam structure;

S7:完成桥面铺装及附属设施施工。 S7: Complete the bridge deck pavement and ancillary facilities construction.

作为上述技术方案的进一步改进: As a further improvement of the above technical solution:

在预制所述槽型梁时,在超高性能混凝土腹板顶面浇筑成具有卡槽的结构,所述卡槽沿桥梁纵向排列有多条。 When the channel beam is prefabricated, a structure with slots is poured on the top surface of the ultra-high performance concrete web, and a plurality of slots are arranged along the longitudinal direction of the bridge.

所述超高性能混凝土底板和超高性能混凝土腹板由弯曲抗拉强度20MPa~40MPa、抗压强度200MPa~300MPa的超高性能混凝土制成。 The ultra-high-performance concrete bottom plate and the ultra-high-performance concrete web are made of ultra-high-performance concrete with a bending tensile strength of 20MPa-40MPa and a compressive strength of 200MPa-300MPa.

所述超高性能混凝土底板和超高性能混凝土腹板由活性粉末混凝土、超高性能纤维增强混凝土、注浆纤维混凝土、密实配筋复合材料或工程胶凝复合材料浇筑而成。 The ultra-high-performance concrete base plate and ultra-high-performance concrete web are poured from active powder concrete, ultra-high-performance fiber-reinforced concrete, grouted fiber concrete, densely reinforced composite materials or engineering cementitious composite materials.

与现有技术相比,本发明的优点在于: Compared with the prior art, the present invention has the advantages of:

本发明的组合箱梁跨海大桥,采用由高强混凝土顶板、超高性能混凝土底板和一对超高性能混凝土腹板围成的组合箱梁,超高性能混凝土底板和一对超高性能混凝土腹板能够保证组合箱梁具有足够的强度,且厚度需求低,能够显著减轻组合箱梁的自重,从而有效提升组合箱梁的跨越能力,并且增强其抗震性能;由于组合箱梁自重轻、跨径大,因此可以显著减少桥墩数量,降低工程造价,并且减小对海洋水流的影响;由于超高性能混凝土的高致密性,其抗腐蚀等耐久性指标均较普通混凝土有较大提升,能够很好适应海洋的弱碱性环境,整体耐久性能卓越;超高性能混凝土底板和超高性能混凝土腹板可抵抗大跨径桥梁中可能出现的拉应力,大大提高海上桥梁结构的耐久性,降低箱梁的开裂风险,使本发明在防范箱梁开裂方面有足够的保障;本发明的组合箱梁跨海大桥结构简单、自重较轻、施工简便、能够有效降低混凝土箱梁存在的开裂风险、耐久性能良好,可适用于大跨径桥梁,特别是跨海大桥非通航孔的施工,具有广阔的应用前景。 The combined box girder cross-sea bridge of the present invention adopts a combined box girder surrounded by a high-strength concrete roof, an ultra-high-performance concrete bottom plate and a pair of ultra-high-performance concrete webs, an ultra-high-performance concrete bottom plate and a pair of ultra-high-performance concrete webs The slab can ensure that the combined box girder has sufficient strength and low thickness requirements, and can significantly reduce the self-weight of the combined box girder, thereby effectively improving the spanning capacity of the combined box girder and enhancing its seismic performance; due to the light weight of the combined box girder, the span Therefore, the number of piers can be significantly reduced, the project cost can be reduced, and the impact on ocean currents can be reduced; due to the high density of ultra-high performance concrete, its durability indicators such as corrosion resistance are greatly improved compared with ordinary concrete, and can be easily It is well adapted to the weak alkaline environment of the ocean, and has excellent overall durability; the ultra-high-performance concrete floor and ultra-high-performance concrete web can resist the tensile stress that may occur in long-span bridges, greatly improving the durability of offshore bridge structures and reducing box load. The cracking risk of the beam makes the present invention have sufficient protection in preventing box girder cracking; the composite box girder cross-sea bridge of the present invention is simple in structure, light in weight, easy to construct, can effectively reduce the cracking risk of concrete box girder, and is durable It has good performance and is suitable for the construction of long-span bridges, especially the non-navigation holes of sea-crossing bridges, and has broad application prospects.

本发明的组合箱梁跨海大桥施工方法,在预制场将超高性能混凝土腹板与超高性能混凝土底板预制成槽型梁,高强混凝土顶板可现浇,也可预制,从而大大缩短桥梁建造的时间,其工艺流程简单,对施工设备需求低,保证了本发明的施工建造可行性;且施工简便、快捷、迅速,对于保证工期、提高施工效率有重要意义。 In the construction method of the combined box girder cross-sea bridge of the present invention, the ultra-high-performance concrete web and the ultra-high-performance concrete bottom plate are prefabricated into channel beams in the prefabrication field, and the high-strength concrete roof can be cast-in-situ or prefabricated, thereby greatly shortening the bridge The construction time is simple, the technological process is simple, and the demand for construction equipment is low, which ensures the construction feasibility of the present invention; and the construction is simple, fast and rapid, which is of great significance for ensuring the construction period and improving construction efficiency.

附图说明 Description of drawings

图1是本发明组合箱梁跨海大桥的结构示意图。 Fig. 1 is a schematic structural view of the composite box girder cross-sea bridge of the present invention.

图2是图1的A-A剖视放大图。 Fig. 2 is an enlarged cross-sectional view of A-A in Fig. 1 .

图3是图1的B-B剖视放大图。 FIG. 3 is an enlarged cross-sectional view taken along line B-B of FIG. 1 .

图4是图3的C-C剖视放大图。 Fig. 4 is an enlarged cross-sectional view taken along line C-C of Fig. 3 .

图5是本发明组合箱梁跨海大桥施工方法的流程示意图。 Fig. 5 is a schematic flow chart of the construction method of the composite box girder cross-sea bridge of the present invention.

图6是本发明组合箱梁跨海大桥施工方法进行至S3步骤时的结构示意图。 Fig. 6 is a schematic structural view of the construction method of the composite box girder cross-sea bridge of the present invention when it proceeds to step S3.

图7是本发明组合箱梁跨海大桥施工方法进行至S4步骤时的结构示意图。 Fig. 7 is a structural schematic view of the construction method of the composite box girder cross-sea bridge of the present invention when it is carried out to step S4.

图8是本发明组合箱梁跨海大桥施工方法进行至S6步骤时的结构示意图。 Fig. 8 is a schematic structural view of the construction method of the composite box girder cross-sea bridge of the present invention when it is carried out to step S6.

图9是本发明组合箱梁跨海大桥施工方法进行至S7步骤时的结构示意图。 Fig. 9 is a schematic diagram of the structure of the construction method of the composite box girder cross-sea bridge of the present invention when step S7 is carried out.

图中各标号表示: Each label in the figure means:

1、桥墩;2、组合箱梁;21、高强混凝土顶板;22、超高性能混凝土底板;23、超高性能混凝土腹板;231、卡槽;24、体外预应力钢束;25、横隔板;26、体内预应力钢束;3、桩基;4、承台;5、相邻跨湿接缝。 1. Bridge pier; 2. Composite box girder; 21. High-strength concrete roof; 22. Ultra-high performance concrete bottom plate; 23. Ultra-high performance concrete web; 231. Card slot; 24. External prestressed steel beam; 25. Transverse 26. Internal prestressed steel tendon; 3. Pile foundation; 4. Cap; 5. Adjacent span wet joints.

具体实施方式 Detailed ways

图1至图4示出了本发明的一种组合箱梁跨海大桥实施例,该跨海大桥包括桥墩1和由桥墩1支承的组合箱梁2,桥墩1底部由承台4和桩基3支承,组合箱梁2由高强混凝土顶板21、超高性能混凝土底板22和一对超高性能混凝土腹板23围成,组合箱梁2内沿桥梁纵向布置有体外预应力钢束24及体内预应力钢束26。本发明的组合箱梁跨海大桥,采用由高强混凝土顶板21、超高性能混凝土底板22和一对超高性能混凝土腹板23围成的组合箱梁2,超高性能混凝土底板22和一对超高性能混凝土腹板23能够保证组合箱梁2具有足够的强度,且厚度需求低,能够显著减轻组合箱梁2的自重,从而有效提升组合箱梁2的跨越能力,并且增强其抗震性能;由于组合箱梁2自重轻、跨径大,因此可以显著减少桥墩1数量,降低工程造价,并且减小对海洋水流的影响;由于超高性能混凝土的高致密性,其抗腐蚀等耐久性指标均较普通混凝土有较大提升,能够很好适应海洋的弱碱性环境,整体耐久性能卓越;超高性能混凝土底板22和超高性能混凝土腹板23可抵抗大跨径桥梁中可能出现的拉应力,大大提高海上桥梁结构的耐久性,降低箱梁的开裂风险,使本发明在防范箱梁开裂方面有足够的保障;本发明的组合箱梁跨海大桥结构简单、自重较轻、施工简便、能够有效降低混凝土箱梁存在的开裂风险、耐久性能良好,可适用于大跨径桥梁,特别是跨海大桥非通航孔的施工,具有广阔的应用前景。 Fig. 1 to Fig. 4 have shown a kind of composite box girder cross-sea bridge embodiment of the present invention, and this cross-sea bridge comprises pier 1 and the composite box girder 2 supported by pier 1, and the bottom of pier 1 is made of cap 4 and pile foundation 3 supports, the composite box girder 2 is surrounded by a high-strength concrete top slab 21, an ultra-high performance concrete bottom slab 22 and a pair of ultra-high performance concrete webs 23, inside the composite box girder 2 there are external prestressed steel beams 24 and internal Prestressed steel tendon 26. The combined box girder cross-sea bridge of the present invention adopts a combined box girder 2 surrounded by a high-strength concrete top plate 21, an ultra-high performance concrete bottom plate 22 and a pair of ultra-high performance concrete webs 23, an ultra-high performance concrete bottom plate 22 and a pair of The ultra-high-performance concrete web 23 can ensure that the combined box girder 2 has sufficient strength and low thickness requirements, and can significantly reduce the self-weight of the combined box girder 2, thereby effectively improving the spanning capacity of the combined box girder 2 and enhancing its seismic performance; Due to the light weight and large span of the combined box girder 2, the number of piers 1 can be significantly reduced, the project cost can be reduced, and the impact on ocean currents can be reduced; due to the high density of ultra-high performance concrete, its durability indicators such as corrosion resistance Compared with ordinary concrete, they are greatly improved, can well adapt to the weakly alkaline environment of the ocean, and have excellent overall durability; Stress greatly improves the durability of the bridge structure at sea, reduces the risk of cracking of the box girder, so that the present invention has sufficient protection in preventing cracking of the box girder; the composite box girder cross-sea bridge of the present invention is simple in structure, light in weight, and easy to construct , It can effectively reduce the cracking risk of concrete box girders, and has good durability. It can be applied to long-span bridges, especially the construction of non-navigable holes in cross-sea bridges, and has broad application prospects.

本实施例中,超高性能混凝土底板22和一对超高性能混凝土腹板23整体预制成槽型梁结构,便于施工,可大大提高施工效率。超高性能混凝土腹板23顶部设有用于与高强混凝土顶板21连接的卡槽231,卡槽231沿桥梁纵向排列有多条,卡槽231可增强腹板与顶板的协同工作性,使组合箱梁2成为一个整体以共同抵抗外力作用。 In this embodiment, the ultra-high-performance concrete bottom plate 22 and a pair of ultra-high-performance concrete webs 23 are integrally prefabricated into a channel beam structure, which is convenient for construction and can greatly improve construction efficiency. The top of the ultra-high-performance concrete web 23 is provided with a slot 231 for connecting with the high-strength concrete roof 21. There are multiple slots 231 arranged longitudinally along the bridge. Beam 2 becomes a whole to jointly resist external force.

进一步的,跨海大桥的跨径为90m~120m,跨海大桥为简支变连续桥型。所述超高性能混凝土底板22厚度为15~20cm,超高性能混凝土腹板23的厚度为16~22cm,高强混凝土顶板21的厚度为26~30cm,组合箱梁2内每15~20m设置1道横隔板25,横隔板25的布置密度适当,可减小箱梁的扭转变形以及畸变变形,且不影响预应力钢束的安装。本实施例中,超高性能混凝土底板22厚度为15cm,超高性能混凝土腹板23的厚度为20cm,高强混凝土顶板21桥轴中心线处的厚度为30cm,组合箱梁2内每15米设置1道横隔板25。 Further, the span of the sea-crossing bridge is 90m to 120m, and the sea-crossing bridge is a simply supported variable continuous bridge type. The thickness of the ultra-high-performance concrete bottom plate 22 is 15-20cm, the thickness of the ultra-high-performance concrete web 23 is 16-22cm, the thickness of the high-strength concrete roof 21 is 26-30cm, and a The transverse diaphragm 25 and the arrangement density of the transverse diaphragm 25 are appropriate, which can reduce the torsional deformation and distortion deformation of the box girder, and will not affect the installation of the prestressed steel tendons. In this embodiment, the thickness of the ultra-high performance concrete bottom plate 22 is 15 cm, the thickness of the ultra-high performance concrete web 23 is 20 cm, the thickness of the high-strength concrete top plate 21 at the center line of the bridge axis is 30 cm, and the composite box girder 2 is set every 15 meters. 1 road diaphragm 25.

图5至图9示出了本发明的一种组合箱梁跨海大桥施工方法实施例,下面结合上述实施例中的组合箱梁跨海大桥对本发明的组合箱梁跨海大桥施工方法作进一步说明。 Fig. 5 to Fig. 9 have shown a kind of composite box girder cross-sea bridge construction method embodiment of the present invention, below in conjunction with the composite box girder cross-sea bridge in the above-mentioned embodiment the construction method of composite box girder cross-sea bridge of the present invention will be further carried out illustrate.

本实施例的组合箱梁跨海大桥施工方法包括以下步骤: The construction method of the combined box girder cross-sea bridge of the present embodiment comprises the following steps:

S1:在现场进行桩基3、承台4和桥墩1的施工,同时在预制场将超高性能混凝土腹板23与超高性能混凝土底板22预制成槽型梁; S1: Construction of the pile foundation 3, cap 4 and bridge pier 1 is carried out on site, and at the same time, the ultra-high performance concrete web 23 and the ultra-high performance concrete bottom plate 22 are prefabricated into channel beams in the prefabrication yard;

S2:在槽型梁上浇筑高强混凝土顶板21形成一跨组合箱梁2,或将预制好的高强混凝土顶板21通过湿接缝与槽型梁连接形成一跨组合箱梁2,同时张拉组合箱梁2内的体外预应力钢束24及体内预应力钢束26; S2: Pour the high-strength concrete roof 21 on the channel beam to form a one-span composite box girder 2, or connect the prefabricated high-strength concrete roof 21 to the channel beam through wet joints to form a one-span composite box girder 2, and stretch the composite box girder at the same time The externally prestressed steel tendons 24 and the internally prestressed steel tendons 26 in the box girder 2;

S3:在桥墩1上安装临时支座,将组合箱梁2整体吊装至临时支座上; S3: install a temporary support on the pier 1, and hoist the combined box girder 2 onto the temporary support as a whole;

S4:安装永久支座,现浇相邻跨湿接缝5; S4: Install permanent support, cast-in-place adjacent span wet joints 5;

S5:待相邻跨湿接缝5混凝土强度达到90%后,拆除临时支座,完成体系转化; S5: After the concrete strength of the adjacent wet joint 5 reaches 90%, the temporary support is removed to complete the system transformation;

S6:在相邻跨湿接缝5处张拉体内预应力钢束,形成多跨连续梁结构; S6: Stretch prestressed steel tendons in the body at 5 adjacent span wet joints to form a multi-span continuous beam structure;

S7:完成桥面铺装及附属设施施工。 S7: Complete the bridge deck pavement and ancillary facilities construction.

本发明的组合箱梁跨海大桥施工方法,在预制场将超高性能混凝土腹板23与超高性能混凝土底板22预制成槽型梁,高强混凝土顶板21可现浇,也可预制,从而大大缩短桥梁建造的时间,其工艺流程简单,对施工设备需求低,保证了本发明的施工建造可行性;且施工简便、快捷、迅速,对于保证工期、提高施工效率有重要意义。 In the construction method of the combined box girder cross-sea bridge of the present invention, the ultra-high-performance concrete web 23 and the ultra-high-performance concrete bottom plate 22 are prefabricated into channel beams in the prefabrication field, and the high-strength concrete top plate 21 can be cast-in-situ or prefabricated, thereby The time for bridge construction is greatly shortened, the technological process is simple, and the demand for construction equipment is low, which ensures the feasibility of the construction of the present invention; and the construction is simple, fast and rapid, which is of great significance for ensuring the construction period and improving construction efficiency.

本实施例中,在预制槽型梁时,在超高性能混凝土腹板23顶面浇筑成具有卡槽231的结构,卡槽231沿桥梁纵向排列有多条,使超高性能混凝土腹板23与高强混凝土顶板21之间具有更高的连接强度。 In this embodiment, when the channel beam is prefabricated, a structure with slots 231 is poured on the top surface of the ultra-high performance concrete web 23, and there are multiple slots 231 arranged longitudinally along the bridge, so that the ultra-high performance concrete web 23 It has higher connection strength with the high-strength concrete roof 21.

本实施例中,超高性能混凝土底板22和超高性能混凝土腹板23由弯曲抗拉强度20MPa~40MPa、抗压强度200MPa~300MPa的超高性能混凝土制成。 In this embodiment, the ultra-high performance concrete bottom plate 22 and the ultra-high performance concrete web 23 are made of ultra-high performance concrete with a bending tensile strength of 20MPa-40MPa and a compressive strength of 200MPa-300MPa.

本实施例中,超高性能混凝土底板22和超高性能混凝土腹板23由活性粉末混凝土或超高性能纤维增强混凝土或注浆纤维混凝土或密实配筋复合材料或工程胶凝复合材料浇筑而成,本实施例选用活性粉末混凝土。 In this embodiment, the ultra-high-performance concrete bottom plate 22 and the ultra-high-performance concrete web 23 are poured from reactive powder concrete, ultra-high-performance fiber-reinforced concrete, or grouted fiber concrete, or densely reinforced composite materials or engineering cementitious composite materials. , This embodiment selects active powder concrete.

虽然本发明已以较佳实施例揭露如上,然而并非用以限定本发明。任何熟悉本领域的技术人员,在不脱离本发明技术方案范围的情况下,都可利用上述揭示的技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例。因此,凡是未脱离本发明技术方案的内容,依据本发明技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均应落在本发明技术方案保护的范围内。 Although the present invention has been disclosed above with preferred embodiments, it is not intended to limit the present invention. Any person familiar with the art, without departing from the scope of the technical solution of the present invention, can use the technical content disclosed above to make many possible changes and modifications to the technical solution of the present invention, or modify it into an equivalent implementation of equivalent changes example. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention shall fall within the protection scope of the technical solution of the present invention.

Claims (10)

1.一种组合箱梁跨海大桥,包括桥墩(1)和由桥墩(1)支承的组合箱梁(2),其特征在于:所述组合箱梁(2)由高强混凝土顶板(21)、超高性能混凝土底板(22)和一对超高性能混凝土腹板(23)围成,所述组合箱梁(2)内沿桥梁纵向布置有体内预应力钢束(26)和体外预应力钢束(24)。 1. A combined box girder cross-sea bridge, comprising a bridge pier (1) and a combined box girder (2) supported by the bridge pier (1), characterized in that: the combined box girder (2) is made of a high-strength concrete roof (21) , an ultra-high performance concrete bottom plate (22) and a pair of ultra-high performance concrete webs (23), the composite box girder (2) is arranged with internal prestressed steel tendons (26) and external prestressed beams (26) along the longitudinal direction of the bridge Steel Beam (24). 2.根据权利要求1所述的组合箱梁跨海大桥,其特征在于:所述超高性能混凝土底板(22)和一对超高性能混凝土腹板(23)整体预制成槽型梁结构。 2. The combined box girder cross-sea bridge according to claim 1, characterized in that: the ultra-high performance concrete floor (22) and a pair of ultra-high performance concrete webs (23) are integrally prefabricated into a channel beam structure . 3.根据权利要求1或2所述的组合箱梁跨海大桥,其特征在于:所述超高性能混凝土腹板(23)顶部设有用于与高强混凝土顶板(21)连接的卡槽(231),所述卡槽(231)沿桥梁纵向排列有多条。 3. The combined box girder cross-sea bridge according to claim 1 or 2, characterized in that: the top of the ultra-high performance concrete web (23) is provided with a slot (231) for connecting with the high-strength concrete roof (21) ), there are multiple slots (231) arranged longitudinally along the bridge. 4.根据权利要求1或2所述的组合箱梁跨海大桥,其特征在于:所述跨海大桥的跨径为90m~120m。 4. The combined box girder sea-crossing bridge according to claim 1 or 2, characterized in that: the span of the sea-crossing bridge is 90m-120m. 5.根据权利要求1或2所述的组合箱梁跨海大桥,其特征在于:所述跨海大桥为简支变连续桥型。 5. The combined box girder sea-crossing bridge according to claim 1 or 2, characterized in that: the sea-crossing bridge is a simple-support variable-continuous bridge type. 6.根据权利要求1或2所述的组合箱梁跨海大桥,其特征在于:所述超高性能混凝土底板(22)厚度为15~20cm,超高性能混凝土腹板(23)的厚度为16~22cm,所述高强混凝土顶板(21)的厚度为26~30cm,所述组合箱梁(2)内每15~20m设置1道横隔板(25)。 6. The composite box girder cross-sea bridge according to claim 1 or 2, characterized in that: the thickness of the ultra-high performance concrete floor (22) is 15-20 cm, and the thickness of the ultra-high performance concrete web (23) is 16-22cm, the thickness of the high-strength concrete roof (21) is 26-30cm, and a transverse partition (25) is arranged every 15-20m in the composite box girder (2). 7.一种如权利要求1至6中任一项所述组合箱梁跨海大桥的施工方法,其特征在于:包括以下步骤: 7. A construction method for the combined box girder cross-sea bridge according to any one of claims 1 to 6, characterized in that: comprising the following steps: S1:在现场进行桩基(3)、承台(4)和桥墩(1)的施工,同时在预制场将超高性能混凝土腹板(23)与超高性能混凝土底板(22)预制成槽型梁; S1: Construction of pile foundation (3), cap (4) and bridge pier (1) is carried out on site, and ultra-high performance concrete web (23) and ultra-high performance concrete bottom plate (22) are prefabricated in the prefabrication yard at the same time channel beam; S2:在槽型梁上浇筑高强混凝土顶板(21)形成一跨组合箱梁(2),或将预制好的高强混凝土顶板(21)通过湿接缝与槽型梁连接形成一跨组合箱梁(2),同时张拉组合箱梁(2)内的体外预应力钢束(24)与体内预应力钢束(26); S2: Pour the high-strength concrete roof (21) on the channel beam to form a one-span composite box girder (2), or connect the prefabricated high-strength concrete roof (21) to the channel beam through wet joints to form a one-span composite box girder (2), while tensioning the external prestressed steel tendons (24) and the internal prestressed steel tendons (26) in the combined box girder (2); S3:在桥墩(1)上安装临时支座,将组合箱梁(2)整体吊装至临时支座上; S3: Install temporary supports on the pier (1), and hoist the combined box girder (2) onto the temporary supports as a whole; S4:安装永久支座,现浇相邻跨湿接缝(5); S4: Install permanent support, cast-in-place adjacent span wet joints (5); S5:待相邻跨湿接缝(5)混凝土强度达到90%后,拆除临时支座,完成体系转化; S5: After the concrete strength of the adjacent wet joint (5) reaches 90%, the temporary support is removed to complete the system transformation; S6:在相邻跨湿接缝(5)处张拉体内预应力钢束,形成多跨连续梁结构; S6: Stretch the internal prestressed steel beam at the adjacent span wet joints (5) to form a multi-span continuous beam structure; S7:完成桥面铺装及附属设施施工。 S7: Complete the bridge deck pavement and ancillary facilities construction. 8.根据权利要求7所述的施工方法,其特征在于:在预制所述槽型梁时,在超高性能混凝土腹板(23)顶面浇筑成具有卡槽(231)的结构,所述卡槽(231)沿桥梁纵向排列有多条。 8. The construction method according to claim 7, characterized in that: when the channel beam is prefabricated, a structure with a slot (231) is poured on the top surface of the ultra-high performance concrete web (23), and the There are multiple card slots (231) arranged longitudinally along the bridge. 9.根据权利要求7所述的施工方法,其特征在于:所述超高性能混凝土底板(22)和超高性能混凝土腹板(23)由弯曲抗拉强度20MPa~40MPa、抗压强度200MPa~300MPa的超高性能混凝土制成。 9. The construction method according to claim 7, characterized in that: the ultra-high performance concrete floor (22) and the ultra-high performance concrete web (23) have a bending tensile strength of 20MPa-40MPa and a compressive strength of 200MPa- Made of 300MPa ultra-high performance concrete. 10.根据权利要求7至9中任一项所述的施工方法,其特征在于:所述超高性能混凝土底板(22)和超高性能混凝土腹板(23)由活性粉末混凝土、超高性能纤维增强混凝土、注浆纤维混凝土、密实配筋复合材料或工程胶凝复合材料浇筑而成。 10. The construction method according to any one of claims 7 to 9, characterized in that: the ultra-high performance concrete floor (22) and the ultra-high performance concrete web (23) are made of active powder concrete, ultra-high performance concrete Fiber-reinforced concrete, grouted fiber concrete, densely reinforced composite materials or engineering cementitious composite materials are poured.
CN201410094374.4A 2014-03-14 2014-03-14 A kind of combined box beam bridge spanning the sea and construction method thereof Expired - Fee Related CN103821079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410094374.4A CN103821079B (en) 2014-03-14 2014-03-14 A kind of combined box beam bridge spanning the sea and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410094374.4A CN103821079B (en) 2014-03-14 2014-03-14 A kind of combined box beam bridge spanning the sea and construction method thereof

Publications (2)

Publication Number Publication Date
CN103821079A true CN103821079A (en) 2014-05-28
CN103821079B CN103821079B (en) 2016-08-24

Family

ID=50756347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410094374.4A Expired - Fee Related CN103821079B (en) 2014-03-14 2014-03-14 A kind of combined box beam bridge spanning the sea and construction method thereof

Country Status (1)

Country Link
CN (1) CN103821079B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002819A (en) * 2015-07-24 2015-10-28 华东交通大学 Gradient-structure composite bridge pier
CN105888076A (en) * 2016-04-19 2016-08-24 浙江工业大学 A kind of construction method of water corridor
CN105908629A (en) * 2016-04-27 2016-08-31 中铁大桥局集团有限公司 Descending movable framework for highway box girder at highway and railway combined construction section and application method of descending movable framework
CN106192726A (en) * 2016-08-30 2016-12-07 西安公路研究院 A kind of V-arrangement web beam structure and construction method thereof
CN106835932A (en) * 2017-04-01 2017-06-13 同济大学 UHPC combined box beams
CN106988217A (en) * 2017-04-07 2017-07-28 中交第二公路勘察设计研究院有限公司 Interlaced anchorage arrangement and construction method of super-long prestressed steel beams
CN108086133A (en) * 2018-02-08 2018-05-29 湖南工业大学 Ultra-high performance concrete Simply supported non-uniform beam cloth muscle constructs and its method for bridge construction
CN108252210A (en) * 2018-04-09 2018-07-06 长沙理工大学 Segment cast-in-situ UHPC bridge beam section joint and construction method thereof
CN109057148A (en) * 2018-09-29 2018-12-21 中路杜拉国际工程股份有限公司 Ultra-high performance concrete is without regular reinforcement Prestressed U type beam and its construction method
CN109914216A (en) * 2019-03-29 2019-06-21 湖南大学 A kind of assembled box beam combined type node across ultra-high performance concrete greatly and attaching method thereof
CN110004815A (en) * 2019-03-29 2019-07-12 辽宁省交通规划设计院有限责任公司 A kind of non-prestressed simply supported continuous bridge and its construction method
CN110924287A (en) * 2019-09-24 2020-03-27 中铁二局第三工程有限公司 A semi-fabricated large-span composite box girder and construction method thereof
CN111496996A (en) * 2020-04-21 2020-08-07 周力 Construction process of large-span assembly type steel-concrete combined simply-supported box girder
CN111549658A (en) * 2020-05-30 2020-08-18 同济大学 Continuous bridge joint structure and continuous box girder bridge structure
CN111962474A (en) * 2020-08-28 2020-11-20 华南理工大学 Ultra-high performance concrete light rectangular aqueduct body
CN112523061A (en) * 2020-11-24 2021-03-19 广西交通设计集团有限公司 UHPC stiffened prestressed concrete box girder bridge structure and construction process thereof
CN113202010A (en) * 2021-05-07 2021-08-03 中交一公局集团有限公司 Prestressed concrete cast-in-place box girder structure and construction method thereof
CN114892505A (en) * 2022-05-11 2022-08-12 中铁第四勘察设计院集团有限公司 Combined gate-type pier structure and construction method
CN115323892A (en) * 2022-07-04 2022-11-11 湖南大学 A light composite box girder structure and construction method thereof
CN115491940A (en) * 2022-08-22 2022-12-20 中交第一公路勘察设计研究院有限公司 Steel-concrete combined structure roadbed for freeway in frozen soil area and construction method
CN115627691A (en) * 2022-11-09 2023-01-20 中交投资南京有限公司 Steel-concrete composite plate structure of medium-small span bridge and construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264533A (en) * 2004-03-18 2005-09-29 Taisei Corp PC box girder extrusion construction method
CN101225639A (en) * 2008-01-28 2008-07-23 上海市城市建设设计研究院 Construction Technology of Simply Supported Variable Continuous Box Girder Structure and Its Simply Supported Variable Continuous Box Girder Structure
CN101747002A (en) * 2008-12-19 2010-06-23 鞍钢房产建设有限公司 High-strength concrete
CN101979774A (en) * 2010-10-15 2011-02-23 东南大学 FRCC Railway Box Girder with Partial External Prestressing and Fine Grain Reinforcement
CN102211908A (en) * 2011-03-21 2011-10-12 江苏建华管桩有限公司 Method for preparing high-performance concrete and application
CN102352597A (en) * 2011-11-04 2012-02-15 湖南大学 Prestressed ultrahigh-performance concrete continuous box girder bridge and construction method thereof
KR20120115026A (en) * 2011-04-08 2012-10-17 주식회사 코아이엔씨 Structure and construction method of prestressed precast beam
CN202610694U (en) * 2012-06-12 2012-12-19 华北水利水电学院 Steel fiber light concrete and high-strength concrete overlaid pouring composite beam
CN203755134U (en) * 2014-03-14 2014-08-06 湖南大学 Combined box girder cross-sea bridge

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005264533A (en) * 2004-03-18 2005-09-29 Taisei Corp PC box girder extrusion construction method
CN101225639A (en) * 2008-01-28 2008-07-23 上海市城市建设设计研究院 Construction Technology of Simply Supported Variable Continuous Box Girder Structure and Its Simply Supported Variable Continuous Box Girder Structure
CN101747002A (en) * 2008-12-19 2010-06-23 鞍钢房产建设有限公司 High-strength concrete
CN101979774A (en) * 2010-10-15 2011-02-23 东南大学 FRCC Railway Box Girder with Partial External Prestressing and Fine Grain Reinforcement
CN102211908A (en) * 2011-03-21 2011-10-12 江苏建华管桩有限公司 Method for preparing high-performance concrete and application
KR20120115026A (en) * 2011-04-08 2012-10-17 주식회사 코아이엔씨 Structure and construction method of prestressed precast beam
CN102352597A (en) * 2011-11-04 2012-02-15 湖南大学 Prestressed ultrahigh-performance concrete continuous box girder bridge and construction method thereof
CN202610694U (en) * 2012-06-12 2012-12-19 华北水利水电学院 Steel fiber light concrete and high-strength concrete overlaid pouring composite beam
CN203755134U (en) * 2014-03-14 2014-08-06 湖南大学 Combined box girder cross-sea bridge

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002819A (en) * 2015-07-24 2015-10-28 华东交通大学 Gradient-structure composite bridge pier
CN105888076A (en) * 2016-04-19 2016-08-24 浙江工业大学 A kind of construction method of water corridor
CN105888076B (en) * 2016-04-19 2018-05-29 浙江工业大学 A kind of construction method in corridor waterborne
CN105908629A (en) * 2016-04-27 2016-08-31 中铁大桥局集团有限公司 Descending movable framework for highway box girder at highway and railway combined construction section and application method of descending movable framework
CN105908629B (en) * 2016-04-27 2018-03-30 中铁大桥局集团有限公司 Downlink movable mould frame and its application method for combined highway and metro section highway box beam
CN106192726B (en) * 2016-08-30 2018-11-13 西安公路研究院 A kind of V-arrangement web beam structure and its construction method
CN106192726A (en) * 2016-08-30 2016-12-07 西安公路研究院 A kind of V-arrangement web beam structure and construction method thereof
CN106835932A (en) * 2017-04-01 2017-06-13 同济大学 UHPC combined box beams
CN106988217B (en) * 2017-04-07 2020-03-13 中交第二公路勘察设计研究院有限公司 Staggered anchoring arrangement mode and construction method for ultra-long prestressed steel bundles
CN106988217A (en) * 2017-04-07 2017-07-28 中交第二公路勘察设计研究院有限公司 Interlaced anchorage arrangement and construction method of super-long prestressed steel beams
CN108086133A (en) * 2018-02-08 2018-05-29 湖南工业大学 Ultra-high performance concrete Simply supported non-uniform beam cloth muscle constructs and its method for bridge construction
CN108252210A (en) * 2018-04-09 2018-07-06 长沙理工大学 Segment cast-in-situ UHPC bridge beam section joint and construction method thereof
CN109057148A (en) * 2018-09-29 2018-12-21 中路杜拉国际工程股份有限公司 Ultra-high performance concrete is without regular reinforcement Prestressed U type beam and its construction method
CN109914216B (en) * 2019-03-29 2024-04-16 湖南大学 A prefabricated large-span ultra-high performance concrete box girder combined node and connection method thereof
CN109914216A (en) * 2019-03-29 2019-06-21 湖南大学 A kind of assembled box beam combined type node across ultra-high performance concrete greatly and attaching method thereof
CN110004815A (en) * 2019-03-29 2019-07-12 辽宁省交通规划设计院有限责任公司 A kind of non-prestressed simply supported continuous bridge and its construction method
CN110924287A (en) * 2019-09-24 2020-03-27 中铁二局第三工程有限公司 A semi-fabricated large-span composite box girder and construction method thereof
CN111496996A (en) * 2020-04-21 2020-08-07 周力 Construction process of large-span assembly type steel-concrete combined simply-supported box girder
CN111549658A (en) * 2020-05-30 2020-08-18 同济大学 Continuous bridge joint structure and continuous box girder bridge structure
CN111962474A (en) * 2020-08-28 2020-11-20 华南理工大学 Ultra-high performance concrete light rectangular aqueduct body
CN112523061A (en) * 2020-11-24 2021-03-19 广西交通设计集团有限公司 UHPC stiffened prestressed concrete box girder bridge structure and construction process thereof
CN112523061B (en) * 2020-11-24 2022-06-14 广西交通设计集团有限公司 UHPC stiffened prestressed concrete box girder bridge structure and construction process thereof
CN113202010A (en) * 2021-05-07 2021-08-03 中交一公局集团有限公司 Prestressed concrete cast-in-place box girder structure and construction method thereof
CN114892505A (en) * 2022-05-11 2022-08-12 中铁第四勘察设计院集团有限公司 Combined gate-type pier structure and construction method
CN115323892A (en) * 2022-07-04 2022-11-11 湖南大学 A light composite box girder structure and construction method thereof
CN115491940A (en) * 2022-08-22 2022-12-20 中交第一公路勘察设计研究院有限公司 Steel-concrete combined structure roadbed for freeway in frozen soil area and construction method
CN115491940B (en) * 2022-08-22 2024-04-30 中交第一公路勘察设计研究院有限公司 Highway steel-concrete combined structure roadbed in frozen soil area and construction method
CN115627691A (en) * 2022-11-09 2023-01-20 中交投资南京有限公司 Steel-concrete composite plate structure of medium-small span bridge and construction method

Also Published As

Publication number Publication date
CN103821079B (en) 2016-08-24

Similar Documents

Publication Publication Date Title
CN103821079B (en) A kind of combined box beam bridge spanning the sea and construction method thereof
CN102352597B (en) Prestressed ultrahigh-performance concrete continuous box girder bridge and construction method thereof
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN103046463B (en) Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof
CN103758023B (en) Prestressed concrete and steel truss mixed continuous rigid frame bridge and construction method thereof
CN102296525B (en) Support system mixed combined beam cable-stayed bridge and construction method thereof
CN103696355B (en) The light-duty combined bridge structure of a kind of superhigh tenacity concrete slab-girder steel
CN103924505B (en) Use prefabricated steel-concrete combination T beam and the construction method of Wavelike steel webplate
CN105839510B (en) A kind of steel and ultra-high performance concrete composite continuous bridge structure and its construction method
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN103266574B (en) Simply-supported box girder bridge strengthening method with oblique cables
CN101644024B (en) Prestress steel purlin-concrete combined continuous rigid frame bridge and construction method thereof
CN102535328B (en) In-pipe prestressed steel-pipe truss composite simply-supported beam structure
CN105369729A (en) External prestressing corrugated steel web T-shaped beam and construction method
CN102966050A (en) Longitudinal connection method for steel-concrete combined beam and existing reinforced concrete T beam
CN101298756A (en) Technique for widening concrete box girder without increasing foot stall steel component
CN106192726B (en) A kind of V-arrangement web beam structure and its construction method
CN107119583A (en) A kind of T-shaped rigid frame bridge back of the body tower oblique pull ruggedized construction of double width and its construction method
CN107142830B (en) Steel pipe web prestress steel-concrete combined girder structure and construction method
CN216712702U (en) UHPC board and concrete combined frame slab bridge
CN108060634A (en) Duplexing font ultra-high performance concrete-normal concrete composite beam bridge girder construction and its construction method
CN203755134U (en) Combined box girder cross-sea bridge
CN103603263B (en) Railway Prestressed Concrete trough girder partial cable-stayed bridge
CN107119582B (en) A T-shaped rigid frame bridge back tower cable-stayed reinforcement structure and its construction method
CN115287992A (en) Combined box girder structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160824

Termination date: 20200314

CF01 Termination of patent right due to non-payment of annual fee