CN103806484B - Air lifting underwater desilting construction method - Google Patents

Air lifting underwater desilting construction method Download PDF

Info

Publication number
CN103806484B
CN103806484B CN201410038912.8A CN201410038912A CN103806484B CN 103806484 B CN103806484 B CN 103806484B CN 201410038912 A CN201410038912 A CN 201410038912A CN 103806484 B CN103806484 B CN 103806484B
Authority
CN
China
Prior art keywords
desilting
air
drift
compressor machine
compressed air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410038912.8A
Other languages
Chinese (zh)
Other versions
CN103806484A (en
Inventor
姜骏骏
蔡伟
胡洋
刘旭
刘学应
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Huaneng Engineering Safety Polytron Technologies Inc
Original Assignee
Hangzhou Huaneng Engineering Safety Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Huaneng Engineering Safety Polytron Technologies Inc filed Critical Hangzhou Huaneng Engineering Safety Polytron Technologies Inc
Priority to CN201410038912.8A priority Critical patent/CN103806484B/en
Publication of CN103806484A publication Critical patent/CN103806484A/en
Application granted granted Critical
Publication of CN103806484B publication Critical patent/CN103806484B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an air lifting underwater desilting construction method. The method comprises the following steps of (1) sediment survey and classification, (2) desilting system designing, (3) desilting system processing, (4) construction preparation, (5) main desilting pipe installation, (6) air supply system assembling, (7) diving equipment assembling, (8) high-pressure water system arranging, (9) desilting system test run, (10) sediment pumping drainage, (11) sediment processing, (12) measuring controlling and (13) desilting base face measuring and acceptance check. An air lifting underwater desilting system is few in required device and small in device size, system configuration and arrangement are relatively simple, the system is applicable to desilting work of specific areas such as reservoirs, power stations and hydraulic buildings, carrying is convenient and the range of application is wide; meanwhile, the system can come into service quickly, has the install-and-play advantage and is not interfered by water surface buildings.

Description

Air lifts underwater desilting construction
Technical field
The present invention relates to a kind of construction of underwater desilting, particularly air lifting underwater desilting construction.
Background technology
China is vast in territory, and river course, reservoir, power station etc. are numerous, and the blood vessels that they are all lived for us are responsible for be drunk, lets out The difference in functionalitys such as flood, water drainage, tourism, shipping, generating.But silt is pooled to river course, is commonly formed drift in reservoir with current, Drift easily causes river course blocking, has a strong impact on the use function in river course.For slowing down alluvial, extend the reservoir life-span, traditional Dredging method generally adopts mechanical equivalent of light excavation, and mechanical equivalent of light excavation needs to be equipped with large-scale excavation equipment.During actually used, machinery leaves Dig specific region include reservoir, power station, in water conservancy project construction it is impossible to organize work, large-scale excavation equipment cannot be introduced into;Simultaneously Depth of water larger part, excavation equipment desilting efficiency data is relatively low, and it is not thorough desilting often, wastes time and energy.
Content of the invention
Present invention aim at providing air lifting underwater desilting construction, mainly use compressed air close under water Rise in stopped pipe road in decompression process and form negative pressure, the drift of desilting system bottom is promoted to the mouth of pipe with current and discharges, reach To a system of the purpose moving removing to drift, under normal circumstances, it needs the graininess according to desilting object Different with cleaning object, select random giant or diver to coordinate disturbance bottom drift to imitate with the work improving desilting Rate.At deep water, because hydraulic pressure increases, compressed air discharges the negative pressure producing in decompression process and would be more advantageous this construction In underwater desilting, therefore, it is possible to realize effective Dredging Construction at deep water.This construction can effectively will need to clear up simultaneously Debris, drift move, clean out according to predetermined requirement, therefore, whole system also have a lot of special occasions use Special role and meaning.
In order to solve above-mentioned technical problem, adopt the following technical scheme that:
Air lifts underwater desilting construction:It is characterized in that comprising the steps:
(a)Drift exploration classification:
Drift in desilting region is surveyed, initially with diver manually dive under water method exploration, in region Drift classified and recorded, recorded content includes:Drift amount, species of depositing, drift particle size range etc., obtain Survey log to drift;Then the instrument and equipment of gamma-radiation Density Measuring Instrument and correlation is carried on exploration vessel, by correlator Device equipment is connected with gamma-radiation density;After the completion of connection, go deep in water, pointwise measures downwards, the maximum desilting depth of exploration, Pressure of water-bed each point etc. simultaneously records;
(b)Desilting system designs:
Determine desilting equipment first, include:Shipwreck, collection slag ship, air lifting desilting supervisor, blowpipe Road, compressed air control distributing valve, compressed air reservoir, air compressor machine, diving supply air compressor machine, Multi-stage high-pressure water pump, high pressure Hydraulic giant, compressed air mixed flow case, crane gear;Survey log then in conjunction with drift, determine model, the bore of desilting equipment Deng, and design desilting equipment installation drawing, obtain preliminary desilting system;
(c)Desilting system is processed:
Organizational project management, related director etc. discuss processing for preliminary desilting system, and impropriety is carried out Adjust the desilting system improving;
(d)Preparation of construction:
Workmen is familiar with drawing and construction requirement;Related director according to the workmen in Design of Construction Organization, apply Work plant equipment and material etc. carry out tissue dispatches;Tissue desilting equipment maintenance, maintenance, rent with etc. work, be that engineering is suitable Profit is implemented to carry out sufficient material preparation;Construction equipment is transported on shipwreck and operation platform is built on shipwreck;According to silt Long-pending thing reconnoitres log, carries out repacking arrangement to collection slag ship, accomplishes that collecting slag ship structure meets storage and the requirement of transport drift;
(e)Desilting supervisor install:
According to engineering design requirements, select suitable desilting supervisor, desilting supervisor upper end is floss hole, and lower end is silt dredging Mouthful, desilting supervisor connected using flange;The length of desilting supervisor determines according to maximum operating water depth and floss hole position, desilting master Mouth of pipe footpath determines according to the maximum particle diameter of drift;Then perforate operation is carried out to desilting supervisor's tube wall, this hole is steam vent, opens Hole position is set in the silt dredging mouth end of desilting supervisor, bore and the discharge capacity of air compressor machine that steam vent aperture and quantity are responsible for according to desilting Depending on, steam vent is evenly arranged along tube wall surrounding;After tube wall perforate terminates, mixed flow case is welded to master by fixedly connected part The outside of pipe osseotomy site, forms mixed flow room therefore between mixed flow case and tube wall;Simultaneously according to engineering design requirements, in mixed flow case The interface of upper arrangement respective numbers, interface is used for connecting supply air line, deposits on operation platform after installation;
(f)Air supply system assembles:
Air supply system includes:Compressed air conveying pipeline, compressed air control distributing valve, compressed air reservoir and sky Press, air supply system is deposited on operation platform;Compressed air is generated using air compressor machine, the capacity of air compressor machine is according to desilting Depending on the bore of supervisor, depending on the supply gas pressure of air compressor machine is according to the depth of water:Bore is responsible in the desilting of 200~250mm, supporting sky The capacity of press is in 6~10M3/min;Bore 250~300mm desilting be responsible for the capacity of supporting air compressor machine 12~ 20M3/min;Bore is responsible for the capacity of supporting air compressor machine in 60~100M in the desilting of 300~500mm3/min;Air compressor machine Supply gas pressure is in 0.7~1.5Mpa;
The compressed air delivery pipe of air compressor machine connects compressed air reservoir, same at compressed air reservoir upper outlet Connect compressed air conveying pipeline, this air delivery pipe is supply air line, and distributing valve, distribution are installed on this supply air line Valve controls the amount of entering of compressed air;The end of this supply air line is connected to the seam of mixed flow case, the quantity of supply air line with The interface quantity of mixed flow case is consistent;After the completion of connection, first by shipwreck, air supply system is transported to desilting position with desilting supervisor, Rely on crane gear by desilting main frame tube to water-bed, silt dredging mouth down be aligned drift again, floss hole be aligned collection slag ship simultaneously keeps;
(g)Diving apparatus assembles:
Diving apparatus includes diving supply air compressor machine and breather, and diving supply air compressor machine is installed on operation platform, and It is firm whether inspection installation installs, and breather is communicated with supply air compressor machine, and breather is that diver provides air;
(h)High pressure water system is arranged:
High pressure water system includes giant and Multi-stage high-pressure water pump, and Multi-stage high-pressure water pump is installed on operation platform, and And near diving supply air compressor machine, then check whether that installation is firm;Giant is connected on Multi-stage high-pressure water pump;
(i) desilting system trial operation:
First turn on air compressor machine and generate compressed air, in compressed-air-storing to compressed air storage tank, ducker simultaneously Member puts the suit on, and diving dress connects breather and erects giant, and diver enters the bottom and to desilting position and opens latent Water supplies air compressor machine;It is then turned on controlling distributing valve, desilting supervisor starts to extract drift, and diver is according to actual desilting feelings Condition, is illustrated workmen to open high-pressure hydraulic pump, using giant, drift is rushed under water and disturb, and disturbs situation according to actual punching Position, auxiliary desilting work are disturbed in Reasonable adjustment punching;Adjust distributing valve every 5min between trial run period, change air demand, diver Actual desilting situation is fed back to workmen, workmen checks the working condition of each equipment simultaneously;Construct between trial run period The all processes of personnel record, if each equipment operation condition is good between trial run period, desilting is stable, then carry out next process, no Then check that problem is located and solves, and after solution, can carry out next process;
(j)Drift pump drainage:
First turn on air compressor machine and generate compressed air, in compressed-air-storing to compressed air storage tank, ducker simultaneously Member puts the suit on, and diving dress connects breather and erects giant, and diver enters the bottom and to desilting position and opens latent Water supplies air compressor machine;It is then turned on controlling distributing valve, to optimal position, now compressed air is through air supply pipe for distribution valve regulation Road enters mixed flow room;Compressed air enters through steam vent in desilting supervisor after mixed flow interior extruding, due to compressed air pressure More than atmospheric pressure, the compressed air in desilting supervisor is gradually increasing;In uphill process, in desilting supervisor, form negative pressure, desilting system The drift of system bottom enters silt dredging mouth with current and is gradually promoted to floss hole, finally reaches in collection slag ship, simultaneously according to latent Water person's feedack, is responsible for position by crane gear Reasonable adjustment desilting;Diver, according to actual desilting situation, illustrates to apply Workman person opens high-pressure hydraulic pump, using giant, drift is rushed under water and disturbs, and disturbs situation Reasonable adjustment according to actual punching Position, auxiliary desilting work are disturbed in punching;During desilting, if there is blocking, the method for reopening of holding one's breath is taken to eliminate blocking;Region After the completion of interior desilting, close each equipment, by crane gear and shipwreck, desilting system is moved to non-desilting region, then repeat on State desilting process until the desilting completing in works scope works;
(k)Sludge treatment:
In desilting work process, the drift on collection slag ship gradually increases, when the weight of drift reaches collection slag ship Specified stop dredging operation first when bearing weight, then collection slag shipping delivered to the sludge treatment point specified toppled over, so After return to and work at desilting;So move in circles until the desilting completing in works scope works;
(l)Measurement controls:
1. set up SURVEYING CONTROL NETWORK:Examined according to the design combined factors such as road general layout and job site geographical environment Consider, Reasonable Arrangement measurement controls stake;Again according to the coordinate of construction unit's offer, vertical control point after controlling stake cloth good, will lay The coordinate of polygon control survey point, the measurement of higher degree out, through check errorless after be formed for complete directly instructing measurement construction Coordinate, vertical control network system, and form writing record;
2. control point is surveyed and is set:Project management department checks to measurement control point first, the level providing further according to design department Point carries out the encryption of construction temporary bench mark, and temporary bench mark is arranged at outside range and checks whether temporary bench mark is hard Gu stable, construction period checked to it every three months;Scene, the horizontal control point using and vertical control point are in construction During every three months repetition measurement once;
(m)The measurement of desilting basal plane is checked and accepted:
Using the examination mode of bamboo pole sampling, first bamboo pole is deep to the bottom, bamboo pole bottom has drift to enter, Ran Houxian This bamboo pole is opened in field, if immobilising drift is less than 300mm, is considered as acceptance(check);Otherwise this sample position is carried out Encryption detection, underproof position carries out secondary desilting up to acceptance(check);Field investigation and sampling is carried out by every mono- section of 10m, often Individual 3 points of section;And check and acceptance result is reported supervising engineer, complete this acceptance of work.
Due to adopting technique scheme, have the advantages that:
This construction adopt air lifted underwater desilting method, it is to avoid mechanical equivalent of light excavation specific region include reservoir, It is impossible to organize work in power station, water conservancy project construction, in depth of water larger part, excavation equipment desilting efficiency data is relatively low, desilting not thorough Bottom, the problem wasting time and energy.Air lifts that the equipment that underwater desilting system needs is few, and equipment volume is little, the configuration of system and cloth Put relatively simple, be suitable for the desilting work of the specific regions such as reservoir, power station, water conservancy project construction, convenient in carrying, applicable model Enclose wide;Can comparatively fast come into operation simultaneously, there is plug and play, not disturbed by water surface construction.Clear at the depth of water During silt, due to the increase of hydraulic pressure, compressed air discharges the negative pressure producing in decompression process and would be more advantageous in underwater desilting, can Thoroughly effectively desilting work is realized at deep water.Main pipe in air lifting underwater desilting system is due to being bypass structure , do not have any structural member to stop, drift handling capacity is stronger, debris are more in water conservancy project structure construction waters, alluvial In the case that composition granule is larger, effectively the debris of cleaning, drift can will be needed to extract out according to predetermined requirement, therefore, Whole system is also in special role and the meaning of the use of a lot of special occasions.For different desilting objects, desilting supervisor can To select on demand, and change and be conveniently conducive to lifting dredging effect.This construction has environmental protection and energy saving, input cost simultaneously Low, easy to use feature.
Brief description
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 lifts the artwork of underwater desilting system for air;
Fig. 2 is the structural representation that mixed flow case is connected with desilting supervisor;
The structural representation that Fig. 3 is responsible for for desilting;
Fig. 4 is the structural representation of flange;
Fig. 5 is the connection diagram at the I of Fig. 3.
Wherein:1 be desilting supervisor, 2 be air delivery pipe, 3 be control distributing valve, 4 be air accumulator, 5 be air compressor machine, 6 For supply air compressor machine, 61 be breather, 7 be Multi-stage high-pressure water pump, 71 be giant, 8 be operation platform, 9 be diver, 10 For mixed flow case, 11 be drift, 12 be crane gear, 101 be interface, 102 be fixedly connected part, 13 be floss hole, 14 be inhale Silt mouth, 15 be flange.
Specific embodiment
Air of the present invention lifts underwater desilting construction, is reduced pressure using rising in compressed air under water closed conduit Form negative pressure in journey, the drift 11 of desilting system bottom is promoted to the mouth of pipe with current and discharges, reach removing to drift 11 Move a system of the purpose of removing, under normal circumstances, it needs the graininess according to desilting object different with cleaning object, Select random giant 71 or diver 9 cooperation disturbance bottom drift 11 to improve the work efficiency of desilting.Meanwhile, for Different desilting objects, the caliber size selecting desilting pipeline can be change, and maximum gauge can accomplish 800mm.According to The experience of underwater desilting work, lifts underwater desilting system using air, maximum lifting weight can reach hundreds of kilograms of block stone Or cobble, but also there is relative requirement with supply gas pressure and water, the bore of feed channel with quantity to air demand simultaneously.Running Cheng Zhong, if there is blocking it is also possible to take the method for reopening of holding one's breath to eliminate blocking.
This construction needs to prepare following material:
1st, diving dress, transmitter receiver, some compressed air conveying pipelines 2,300mm bore desilting supervisor 1,450mm bore are clear Silt supervisor 1,800mm bore desilting supervisor 1, control distributing valve 3, air accumulator 4, mixed flow case 10, perforated material, some probes, water Civilian winch, digital display level depth pressure transducer sounding instrument, bamboo pole, flange 15.
2nd, various Escape and Survival Equipments, think that this construction is waterborne and underwater performance, anti-flood control task is heavier, rescues Raw clothing, lifebuoy, oxygen supply device etc. must be equipped with.
3rd, plant:
3.1、6m3The air compressor machine 5 of/min capacity, 60m3The air compressor machine 5 of/min capacity, 100m3The sky of/min capacity Press 5.
3.2nd, shipwreck, collection slag ship, exploration vessel, supply air compressor machine 6, Multi-stage high-pressure water pump 7, giant 71, crane gear 12nd, gamma-radiation Density Measuring Instrument.
The personnel arrangement allotment such as following table of this construction:
Position Number
Supervising engineer 3~4
Diver 3~4
Equipment operation and installation personnel 6~8
Drift conveys personnel 1~2
Common laborer 6~8
Lifting workman 1~2
Quality inspection personnel 1~2
Punching personnel 1~2
Survey crew 2~3
This construction comprises the steps:
(a)Drift exploration classification:
1st, the drift 11 in desilting region is surveyed, using diver 9 manually dive under water method exploration, in region Drift 11 classified and recorded, recorded content includes:Drift 11 amount, drift 11 species, drift 11 particle diameter Scope etc., obtains drift 11 exploration log;
2nd, first the instrument and equipment of gamma-radiation Density Measuring Instrument and correlation is carried on exploration vessel, assembles probe, by direct-reading Digital display level depth pressure transducer sounding instrument is fixed on the corresponding site of probe, and the hydrographic winch of work is firmly welded on On the iron plate of exploration fore.Then probe is connected by shackle with the steel wire rope of hydrographic winch, will be popped one's head in using hydrographic winch Sinking plays measuring point under water, opens gamma-radiation Density Measuring Instrument main frame, and main frame automatic printing goes out this measuring point difference elevation gamma-radiation meter Number;Meanwhile, survey crew record the corresponding gamma-radiation of popping one's head in that digital display level depth pressure transducer sounding instrument shows The underwater penetration counting.After playing measuring point measurement and finishing, will pop one's head in slowly at the uniform velocity to sink, pointwise measures downwards, until probe is inserted Enter drift 11 deep, till probe cannot continue to sink, and record maximum desilting depth, the correlation such as pressure of water-bed each point Data.After this observation station measurement finishes, probe is left the water, with special cleaning meanss, probe is cleaned with water totally, then survey Survey ship moves to next observation station and is surveyed.Guarantee that the regional of engineering is equipped with observation station, representative strong.
(b)Desilting system designs:
Determine desilting equipment first, include:Shipwreck, collection slag ship, air lifting desilting supervisor 1, blowpipe Road 2, compressed air control distributing valve 3, compressed air reservoir 4, air compressor machine 5, diving supply air compressor machine 6, Multi-stage high-pressure water pump 7th, giant 71, compressed air mixed flow case 10, crane gear 12;Survey log then in conjunction with drift 11, determine desilting The model of equipment, bore etc., and design desilting equipment installation drawing, obtain preliminary desilting system;
(c)Desilting system is processed:
Organizational project management, related director etc. discuss processing for preliminary desilting system, and impropriety is carried out Adjust the desilting system improving;
(d)Preparation of construction:
According to overall construction site plan, to reconnoitring on the spot, check absolute altitude and the mutual alignment relation with surrounding buildingses, right Construction domestic water, power supply for construction, face in field to set and carried out with room etc. planning as a whole reasonable arrangement.Before construction, construction manager prepares Each management article of good safety board, safe ban board and seven board one figure, job site, and fire-fighting equipment.Implement technical data, After construction drawing is connected to, the tissue relevant personnel are familiar with construction drawing immediately, must catch main construction drawing link when seeing figure, It is resolved in construction drawing joint examination, reducing will have the design change occurring during construction, from now on to place orders with enterprises for processing materials and to organize as far as possible Construction.
Related director carries out group according to the workmen in Design of Construction Organization, construction equipment and material etc. Knit and dispatch;Tissue desilting equipment maintenance, maintenance, rent with etc. work, be that engineering is smoothly implemented to carry out sufficient material and prepared;To apply Construction equipment is transported on shipwreck and builds operation platform 8 on shipwreck;Log is reconnoitred according to drift 11, collection slag ship is carried out Repacking arrangement, accomplishes that collecting slag ship structure meets storage and the requirement of transport drift 11;
(e)Desilting supervisor install:
According to engineering design requirements, select suitable desilting supervisor 1, desilting supervisor 1 is connected using flange 15, sealing effectiveness Good, it is connected firmly;Desilting supervisor 1 includes silt dredging mouth 14 and floss hole 13, and silt dredging mouth 14 is located under water, floss hole 13 be aligned collection Slag ship, the length of desilting supervisor 1 determines according to maximum operating water depth and floss hole 13 position it is desirable to the length of desilting supervisor 1 surpasses Cross depth capacity 2-3m it is ensured that floss hole 13 can be alignd with collection slag ship;The maximum grain according to drift 11 for 1 bore is responsible in desilting Footpath determines;Maximum caliber can reach 800mm, and desilting supervisor's 1 caliber is bigger, and required air demand is bigger, is used at ordinary times depositing The desilting supervisor 1 of thing 11 cleaning can select the pipeline of below 300mm bore, when existing air compressor machine 5 discharge capacity is subject in limited time, then root Determine that 1 caliber is responsible in desilting according to the discharge capacity of air compressor machine 5:1. require desilting to be responsible for 1 caliber and be more than maximum particle diameter 4-6cm, not only protect Card desilting is unimpeded, and high to air compressor machine 5 utilization rate;2. the relation such as following table of 1 caliber and air compressor machine 5 discharge capacity is responsible in desilting:
Air compressor machine discharge capacity (M3/min) Caliber mm is responsible in desilting
≤6 ≤200
6~10 200~250
12~20 250~300
60~100 300~500
Then 1 tube wall is responsible for desilting and carries out perforate operation, this hole is steam vent, position of opening is located at desilting supervisor's 1 Depending on silt dredging mouth 14 end, steam vent aperture and quantity are according to the bore of desilting supervisor 1 and the discharge capacity of air compressor machine 5, according to following public affairs Formula is calculated:
n=p/s
d=(s/3.14)^0.5
Wherein:N represents the quantity of steam vent;
P represents the discharge capacity of air compressor machine 5;
S represents the bore of desilting supervisor 1;
D represents the aperture of steam vent.
Steam vent is evenly arranged along tube wall surrounding;After tube wall perforate terminates, mixed flow case 10 is passed through fixedly connected part 102 It is welded to the outside of supervisor's osseotomy site, therefore between mixed flow case 10 and tube wall, form mixed flow room;Simultaneously will according to engineering design Ask, the interface 101 of respective numbers is arranged on mixed flow case 10, interface 101 is used for connecting supply air line, deposits in after installation On operation platform 8;
(f)Air supply system assembles:
Air supply system includes:Compressed air conveying pipeline 2, compressed air control distributing valve 3, compressed air reservoir 4 And air compressor machine 5, air supply system is deposited on operation platform 8;Compressed air, the capacity of air compressor machine 5 are generated using air compressor machine 5 Depending on bore according to desilting supervisor 1, depending on the supply gas pressure of air compressor machine 5 is according to the depth of water:Bore is in the desilting of 200~250mm Supervisor 1, the capacity of supporting air compressor machine 5 is in 6~10M3/min;Bore is responsible for 1 supporting air compressor machine 5 in the desilting of 250~300mm Capacity in 12~20M3/min;Bore 300~500mm desilting be responsible for the capacity of 1 supporting air compressor machine 5 60~ 100M3/min;The supply gas pressure of air compressor machine 5 and the relation such as following table of maximum desilting depth:
Maximum desilting depth(m) The supply gas pressure of air engine(Mpa)
≤5 0.7
5~8 0.7~1.3
8~11 1.3~1.5
≥11 1.5~1.7
The compressed air delivery pipe 2 of air compressor machine 5 connects compressed air reservoir 4, at compressed air reservoir 4 upper outlet Same connection compressed air conveying pipeline 2, this air delivery pipe 2 is supply air line, and installs distribution on this supply air line Valve, distributing valve controls the amount of entering of compressed air;The end of this supply air line is connected at the interface 101 of mixed flow case 10, supply The quantity of pipeline is consistent with interface 101 quantity of mixed flow case 10;After the completion of connection, first by shipwreck by air supply system and desilting master Pipe 1 is transported to desilting position, then relies on crane gear 12 that desilting is responsible for 1 frame to the bottom, and silt dredging mouth 14 is directed at drift down 11, floss hole 13 be aligned collection slag ship simultaneously keeps;
(g)Diving apparatus assembles:
Diving apparatus includes diving supply air compressor machine 6 and breather 61, and the bottom of diving supply air compressor machine 6 is equipped with thrust shaft Hold a grade thrust disc, be primarily subjected to the remaining axial force of air compressor machine 5 and the deadweight of rotor.It is configured with connector, diving supply Air compressor machine 6 relies on connector to be firmly attached on the operation platform 8 of shipwreck.Located at gas outlet on air air compressor machine 5, gas outlet is even Connect trachea 61, breather 61 is provided with breathing mask;Air compressor machine 5 produces air, and air, is dived to breathing mask through breather 61 The wearable breathing mask of water person 9 obtains air, thus completing underwater performance.
(h)High pressure water system is arranged:
High pressure water system includes giant 71 and Multi-stage high-pressure water pump 7, and Multi-stage high-pressure water pump 7 is installed on operation platform 8 On, concrete installation process is as follows:
1st, Multi-stage high-pressure water pump 7 is transported to operation platform 8, levelling base;Wedge shape ferrum on pad near fot screw, by base Padded 20~40mm;
2nd, with level indicator check base levelness, levelling after fill base with cement mortar, after cement mortar do after check water Pingdu;
3rd, by the supporting plane of base, the dirt on water pump foot and motor foot plane is cleaned out, and water pump and motor It is placed on base;
4th, adjust pump shaft level, levelling after suitably go up jack panel, in case walking about, to be regulated finish after installation motor, At Heshui, pad, with iron plate, should not retain certain interval between pump shaft coupling and motor coupler;
5th, leveling ruler is placed on shaft coupling, checks whether water pump axis line is overlapped with electrical axis, if misaligned, in motor Or the sole underlay tagger of pump, make two shaft couplings cylindrical equal with leveling ruler, then taking out pad has the tagger of multi-disc, use To replace iron plate through the iron plate of initiative, and to reexamine;
6th, vibration damping installation is carried out using ZT type vibroshock, first press vibration isolation table size, poured cement supporting construction, ground should be lifted To prevent hydrops, supporting construction wants level to high 50mm;
7th, check installation accuracy, measure the interplanar gap of two shaft couplings in several opposite location with clearance gauge, shaft coupling is put down The upper minimum and maximum gap in face one week must not exceed 0.3 millimeter, and two ends centrage is up and down or the difference of left and right must not exceed 0.1 milli Rice.
8th, giant 71 is connected on Multi-stage high-pressure water pump 7, and checks whether connection is firm;
(i) desilting system trial operation:
First turn on air compressor machine 5 and generate compressed air, in compressed-air-storing to compressed air storage tank, ducker simultaneously Member puts the suit on, and diving dress connects breather 61 and erects giant 71, and diver 9 enters the bottom and to desilting position and opens Open diving supply air compressor machine 6;It is then turned on controlling distributing valve 3, desilting supervisor 1 starts to extract drift 11, and diver 9 is according to reality Border desilting situation, is illustrated workmen to open high-pressure hydraulic pump, using giant 71, drift 11 is rushed under water and disturb, according to Actual punching is disturbed the punching of situation Reasonable adjustment and is disturbed position, auxiliary desilting work;Adjust distributing valve every 5min between trial run period, change and supply Tolerance, actual desilting situation is fed back to workmen by diver 9, and workmen checks the working condition of each equipment simultaneously;Examination Run duration workmen records all processes, if each equipment operation condition is good between trial run period, desilting is stable, then under carrying out One procedure, otherwise checks that problem is located and solves, and after solution, can carry out next process;
(j)Drift pump drainage:
First turn on air compressor machine 5 and generate compressed air, in compressed-air-storing to compressed air storage tank, ducker simultaneously Member puts the suit on, and diving dress connects breather 61 and erects giant 71, and diver 9 enters the bottom and to desilting position and opens Open diving supply air compressor machine 6;It is then turned on controlling distributing valve 3, distribution valve regulation is to optimal position, now compressed air warp Supply air line enters mixed flow room;Compressed air enters through steam vent in desilting supervisor 1 after mixed flow interior extruding, because compression is empty The powerful compressed air in atmospheric pressure, desilting supervisor 1 of air pressure is gradually increasing;In uphill process, formed negative in desilting supervisor 1 Pressure, the drift 11 of desilting system bottom enters silt dredging mouth 14 with current and is gradually promoted to floss hole 13, finally reaches collection slag In ship, simultaneously according to diver 9 feedack, it is responsible for 1 position by crane gear 12 Reasonable adjustment desilting;Diver 9 Factually border desilting situation, is illustrated workmen to open high-pressure hydraulic pump, using giant 71, drift 11 is rushed under water and disturb, The punching of situation Reasonable adjustment is disturbed according to actual punching and disturbs position, auxiliary desilting work;During desilting, if there is blocking, take and close The method that gas is reopened eliminates blocking;After the completion of desilting in region, close each equipment, by crane gear 12 and shipwreck by desilting system System moves to non-desilting region, then repeats above-mentioned desilting process until the desilting completing in works scope works;
(k)Sludge treatment:
In desilting work process, the drift 11 on collection slag ship gradually increases, when the weight of drift 11 reaches collection slag When ship specified bears weight, stop dredging operation first, then collection slag shipping delivered to drift 11 process points specified carrying out Topple over;It is then return to work at desilting;So move in circles until the desilting completing in works scope works;
With the carrying out of dredging operation, the drift 11 of process points progressively increases, now need by drift 11 transport to Spoil ground:Close vehicle preferable, that certificate is complete from functional, compartment, in strict accordance with specified link travel.Accomplish to transport Defeated vehicle non-overloading, compartment top is all covered with tarpaulin, it is to avoid in transportation drift 11 be scattered pollution urban road and Surrounding enviroment.For preventing unrest in transportation for the drift 11 from falling, disorderly abandoning problem, in work progress, my bid section will be using opening Dig scene and the two-way method got the ticket endorsed in spoil ground, firmly prevent drift 11 and disorderly fall, disorderly abandon.For ensureing vehicle transport not to urban district Environment, arranges cleanup crew, fallen soil block, mud to vehicle at any time in the segment of drift 11 transport Block is cleaned, and arranges special messenger to be maked an inspection tour.
For the management of cooperation spoil ground, arrange ordinary excavator one in spoil ground, assistance transport vehicle to native, smooth Tu Chang Deng.Spoir height, in strict accordance with planning height, forbids superzone domain, hypervelocity spoir.
(l)Measurement controls:
1st, measurement prepares:
1. to the measuring instrument being used measurement construction before it is necessary to through legal detection department identify after just can use.
2. the engineering control pile being provided according to construction unit, first carries out checking measurement to its coordinate, elevation, checks control point Whether mis-tie misclosure itself is in specification prescribed limit, simultaneously built with intend that construction road is associated according to controlling point coordinates to check Whether there is any discrepancy with this coordinate control system for building and road, through check errorless after could use construction unit provide seat Mark, high process control stake.If finding, controlling stake to check error exceeds《Specifications of surveys》The permission model of defined in GB50208-2002 Enclose, written information should be submitted to it is desirable to again provide to construction unit.
3. set up SURVEYING CONTROL NETWORK:Examined according to the design combined factors such as road general layout and job site geographical environment Consider, Reasonable Arrangement measurement controls stake;Again according to the coordinate of construction unit's offer, vertical control point after controlling stake cloth good, will lay The coordinate of polygon control survey point, the measurement of higher degree out, through check errorless after be formed for complete directly instructing measurement construction Coordinate, vertical control network system, and form writing record.
2nd, the survey at control point sets:
1. project management department checks to measurement control point first, and the bench mark providing further according to design department carries out construction and uses The encryption of temporary bench mark.The setting distance of temporary bench mark is not added some points as principle with surveying height, and typically every 200~300m sets one Point.Temporary bench mark must be arranged at outside range and check interim water with design bench mark translocation closure, temporary bench mark Whether more stable and stronger on schedule, construction period checked to it every three months.
2. every three months repetition measurement is once in work progress for scene, the horizontal control point using and vertical control point.
(m)The measurement of desilting basal plane is checked and accepted:
According to live practical situation, and combine live diver 9 sampling and the measurement result of gamma-radiation Density Measuring Instrument, The relevant regulation enforcement issued by Ministry of Communications of big desilting depth≤10m;Maximum desilting depth >=10m is carried out as claimed below Measurement is checked and accepted:
1st, using bamboo pole sampling as acceptance basis, bamboo pole is progressively goed deep into the bottom to bosom, bamboo pole was moving downward Drift 11 is had to enter in journey;
2nd, the bamboo pole of sampling is opened at scene, if immobilising drift 11 is less than 300mm, is considered as acceptance(check);Otherwise Detection is encrypted to this sample position, underproof position carries out secondary desilting up to acceptance(check);
3rd, field investigation and sampling is carried out by every mono- section of 10m, 3 points of each section, and position is located at wharf apron line, with harbour On the basis of frontal line, 10m is surveyed in sea, and bank side 15m on the basis of the line of wharf apron.
Check and acceptance result is reported supervising engineer, completes this acceptance of work.
The quality assurance measure of this construction is as follows:
1st, before the construction of every procedure, workmen carries out skill according to construction drawing and arrangement and method for construction to relevant construction group Art, quality, written tell somebody what one's real intentions are, content of telling somebody what one's real intentions are includes:Operational approach, key points for operation and quality standard etc..Data of telling somebody what one's real intentions are must in detail, Intuitively, meet job specfication and technique detailed rules and regulations to require, and through the second people check confirmation errorless after, can be delivered for use.Tell somebody what one's real intentions are money Material should properly preserve for future reference.
2nd, strict implement Self-evaluation System, testing staff detects to finished jobs face in time, it is to avoid duplicate construction Phenomenon.
3rd, construction complete and through self-inspection qualified after can be to supervising engineer and the inspection declaration of relevant higher level department, handing-over.
4th, measurement protocol, data, calculating, chart truly completely must must not be altered, and keep properly.Measuring instrument Device is specified by metrological service, periodically carries out measurement verification, and carries out operational maintenance work it is ensured that in good condition.
5th, conscientiously carry out measurement and check system, field operation survey data has to pass through the second people and checks, interior industry measurement becomes Fruit must two people independently calculates, and mutually proofreads it is ensured that the accuracy of Measurement results.
6th, it is to guarantee that construction quality is in slave mode all the time, using ISO9002 quality standard, constantly improve construction quality Check and system of check and acceptance.
The safety measure of this construction is as follows:
1st, project management department sets up construction safety leading group, and project manager appoints group leader, divides leading organ, clearly personal duty Duty, perfects safeguard system.
2nd, the generation of mechanical breakdown and mechanical wounding.Commander obeyed by haulage vehicle, and signal is complete, must not exceed the speed limit, and crosses and branches off Slow down when mouth, chance barrier and blow a whistle, brake is complete, and function is good.
3rd, construction site will arrange traffic red light, traffic indication board and sole duty and dredge personnel, to dredge pedestrian and vehicle. Construction road junction arranges obvious placard, and sets special messenger guard, relieves traffic congestion.
4th, the full-time security official of job site setting, often carries out safety education to workmen, improves safety consciousness, weekly Open once safety regular meeting.
5th, establish and improve various legislative control on safety systems, production safety management is carried out with economic means, prevent industrial injury thing Therefore occur.Production safety management had both relied on the conscious activity of operator, more rely on strict and impartial system of awards and penalties, violator is carried out Economic penalties, to the well-done enthusiasm rewarded, excite workmen's participation safety activities of keeping the safety in production.
6th, job site should be implemented machine security management and be installed system of check and acceptance, and mechanical erection will be according to the safe skill of regulation Art standard is detected, all operations personnel will take appointment with certificate.Determine machine during use and determine people it is ensured that equipment availability.
The environmental conservation of this construction and civilized construction measure are as follows:
1st, civilized construction and environmental conservation are important symbols of Modern Construction, are that construction enterprises one are basic Management work, is also the window of corporate image, should embody the objective of civilized construction and environmental conservation.
2nd, set up with the responsible artificial group leader that constructs, the civilized construction of related personnel's participation and environmental conservation leader's group, from pipe The aspects such as reason tissue, system are set about, and perfect organization and administration work, is civilized construction and environmental conservation lays the foundation.
3rd, education workmen must not arbitrarily topple over and discharge house refuse, the rubbish producing in cleaning work progress in time Rubbish, strives accomplishing neat and artistic in place, does not affect city look and feel, makes job site form one water conservancy construction, the beautification appearance of the city Beautiful scenery.
4th, the temporary facility such as reasonable Arrangement sidewalk, temporary facility, water power, stock ground, processing space, mound field, will occupy to neighbouring The impact of people orthobiosiss is reduced to lowest limit degree, in the hope of the support to project for all round masses, be that engineering is smoothly implemented to carry out Element task.
5th, scene and water sprinkling path dust-proof working are responsible for by civilized construction squad it is ensured that not airborne dust when road has vehicle to pass through And the no puddles of water, mud.
6th, rent and meet the haulage vehicle of environmental requirement and sign an agreement therewith:
A. speed is slowed down at the scene that enters, and prevents airborne dust;
B. vehicle carriage covering is tight, prevents flying upward of unrestrained or fine particulate materials;
C. outside-rent vehicle must accept the inspection of environmental administration and unit in charge of construction;
D. forbid vehicle Dai Nishang road.
These are only the specific embodiment of the present invention, but the technical characteristic of the present invention is not limited thereto.Any with this Based on bright, for solving essentially identical technical problem, realize essentially identical technique effect, done ground simple change, etc. With replacement or modification etc., all it is covered by among protection scope of the present invention.

Claims (1)

1. air lifting underwater desilting construction:It is characterized in that comprising the steps:
The exploration classification of (a) drift:
Drift in desilting region is surveyed, initially with diver manually dive under water method exploration, to the silt in region Long-pending thing is classified and is recorded, and recorded content includes:Drift amount, species of depositing, drift particle size range, deposited Thing surveys log;Then the instrument and equipment of gamma-radiation Density Measuring Instrument and correlation is carried on exploration vessel, by related equipment It is connected with gamma-radiation density;After the completion of connection, go deep in water, pointwise measures downwards, the maximum desilting depth of exploration, water-bed each The pressure of point simultaneously records;
B () desilting system designs:
Determine desilting equipment first, include:Shipwreck, collection slag ship, air lifting desilting supervisor, compressed air conveying pipeline, pressure Contracting air control distributing valve, compressed air reservoir, air compressor machine, diving supply air compressor machine, Multi-stage high-pressure water pump, giant, Compressed air mixed flow case, crane gear;Survey log then in conjunction with drift, determine model, the bore of desilting equipment, and set Meter desilting equipment installation drawing, obtains preliminary desilting system;
C () desilting system is processed:
Organizational project management, related director discuss processing for preliminary desilting system, and impropriety is adjusted To perfect desilting system;
(d) preparation of construction:
Workmen is familiar with drawing and construction requirement;Related director is according to the workmen in Design of Construction Organization, construction machine Tool equipment and material carry out tissue and dispatch;Tissue desilting equipment maintenance, maintenance, rent, with work, are that engineering is smoothly implemented to do Good sufficient material prepares;Construction equipment is transported on shipwreck and operation platform is built on shipwreck;Reconnoitred according to drift Log, carries out repacking arrangement to collection slag ship, accomplishes that collecting slag ship structure meets storage and the requirement of transport drift;
E () desilting supervisor install:
According to engineering design requirements, select suitable desilting supervisor, desilting supervisor upper end is floss hole, and lower end is silt dredging mouth;Clearly The length being responsible for of becoming silted up determines according to maximum operating water depth and floss hole position, and the maximum particle diameter according to drift for the bore is responsible in desilting Determine;Then perforate operation is carried out to desilting supervisor's tube wall, this hole is steam vent, position of opening is located at the silt dredging mouth of desilting supervisor End, depending on the bore that steam vent aperture and quantity are responsible for according to desilting and the discharge capacity of air compressor machine, steam vent is uniform along tube wall surrounding Arrangement;After tube wall perforate terminates, mixed flow case is welded to the outside of supervisor's osseotomy site, therefore mixed flow by fixedly connected part Form mixed flow room between case and tube wall;The interface of respective numbers, interface, simultaneously according to engineering design requirements, are arranged on mixed flow case For connecting supply air line, deposit on operation platform after installation;
F () air supply system assembles:
Air supply system includes:Compressed air conveying pipeline, compressed air control distributing valve, compressed air reservoir and pneumatics Machine, air supply system is deposited on operation platform;Compressed air is generated using air compressor machine, the capacity of air compressor machine is according to desilting master Depending on the bore of pipe, depending on the supply gas pressure of air compressor machine is according to the depth of water:Bore is responsible in the desilting of 200~250mm, supporting pneumatics The capacity of machine is in 6~10M3/min;Bore 250~300mm desilting be responsible for the capacity of supporting air compressor machine 12~ 20M3/min;Bore is responsible for the capacity of supporting air compressor machine in 60~100M in the desilting of 300~500mm3/min;Air compressor machine Supply gas pressure is in 0.7~1.5Mpa;
The compressed air delivery pipe of air compressor machine connects compressed air reservoir, equally connects at compressed air reservoir upper outlet Compressed air conveying pipeline, this air delivery pipe is supply air line, and installs distributing valve, distributing valve control on this supply air line The amount of entering of compressed air processed;The end of this supply air line is connected to the seam of mixed flow case, the quantity of supply air line and mixed flow The interface quantity of case is consistent;After the completion of connection, first by shipwreck, air supply system is transported to desilting position with desilting supervisor, then according to By crane gear by desilting main frame tube to water-bed, silt dredging mouth down be aligned drift, floss hole be aligned collection slag ship simultaneously keeps;
G () diving apparatus assembles:
Diving apparatus includes diving supply air compressor machine and breather, and diving supply air compressor machine is installed on operation platform, and checks It is firm whether installation installs, and breather is communicated with supply air compressor machine, and breather is that diver provides air;
H () high pressure water system is arranged:
High pressure water system includes giant and Multi-stage high-pressure water pump, and Multi-stage high-pressure water pump is installed on operation platform, and leans on Nearly diving supply air compressor machine, then checks whether that installation is firm;Giant is connected on Multi-stage high-pressure water pump;
(i) desilting system trial operation:
First turn on air compressor machine and generate compressed air, in compressed-air-storing to compressed air storage tank, Divers are worn simultaneously Upper diving dress, diving dress connects breather and erects giant, and diver enters the bottom and to desilting position and opens diving confession Gas air compressor machine;It is then turned on controlling distributing valve, desilting supervisor starts to extract drift, and diver, according to actual desilting situation, shows Meaning workmen opens high-pressure hydraulic pump, using giant, drift is rushed under water and disturbs, and disturbs situation according to actual punching reasonable Position, auxiliary desilting work are disturbed in adjustment punching;Adjust distributing valve every 5min between trial run period, change air demand, diver will be real Border desilting situation feeds back to workmen, and workmen checks the working condition of each equipment simultaneously;Workmen between trial run period Record all processes, if each equipment operation condition is good between trial run period, desilting is stable, then carry out next process, otherwise examine Interrogate topic to be located and solve, after solution, next process can be carried out;
(j) drift pump drainage:
First turn on air compressor machine and generate compressed air, in compressed-air-storing to compressed air storage tank, Divers are worn simultaneously Upper diving dress, diving dress connects breather and erects giant, and diver enters the bottom and to desilting position and opens diving confession Gas air compressor machine;It is then turned on controlling distributing valve, distributes valve regulation extremely optimal position, now compressed air is entered through supply air line Enter mixed flow room;Compressed air enters through steam vent in desilting supervisor after mixed flow interior extruding, because compressed air pressure is more than Atmospheric pressure, the compressed air in desilting supervisor is gradually increasing;In uphill process, in desilting supervisor, form negative pressure, desilting system bottom The drift in portion enters silt dredging mouth with current and is gradually promoted to floss hole, finally reaches in collection slag ship, simultaneously according to diver Feedack, is responsible for position by crane gear Reasonable adjustment desilting;Diver, according to actual desilting situation, illustrates constructor Member opens high-pressure hydraulic pump, using giant, drift is rushed under water and disturbs, and disturbs the punching of situation Reasonable adjustment according to actual punching and disturbs Position, auxiliary desilting work;During desilting, if there is blocking, the method for reopening of holding one's breath is taken to eliminate blocking;Clear in region After the completion of silt, close each equipment, by crane gear and shipwreck, desilting system is moved to non-desilting region, then repeat above-mentioned clear Silt process is until complete the desilting work in works scope;
(k) sludge treatment:
In desilting work process, the drift on collection slag ship gradually increases, when the weight of drift reaches the specified of collection slag ship When bearing weight, stop dredging operation first, then collection slag shipping is delivered to the sludge treatment point specified being toppled over, then return Work on at desilting;So move in circles until the desilting completing in works scope works;
L () measurement controls:
1. set up SURVEYING CONTROL NETWORK:Considered according to design road general layout and job site geogen, rationally Lay measurement and control stake;Again according to the coordinate of construction unit's offer, vertical control point, the wire control that will lay after controlling stake cloth good The coordinate of system point, the measurement of higher degree out, through check errorless after be formed for the complete coordinate that can directly instruct measurement construction, elevation Control net system, and form writing record;
2. control point is surveyed and is set:Project management department checks to measurement control point first, clicks through further according to the level that design department provides The encryption of row construction temporary bench mark, temporary bench mark is arranged at outside range and checks that whether firm temporary bench mark is steady Fixed, construction period checked to it every three months;Scene, the horizontal control point using and vertical control point are in work progress Middle every three months repetition measurement is once;
M the measurement of () desilting basal plane is checked and accepted:
Using the examination mode of bamboo pole sampling, first bamboo pole is deep to the bottom, bamboo pole bottom has drift to enter, and then scene is beaten Open this bamboo pole, if immobilising drift is less than 300mm, be considered as acceptance(check);Otherwise this sample position is encrypted Detection, underproof position carries out secondary desilting up to acceptance(check);Field investigation and sampling is carried out by every mono- section of 10m, and each breaks 3, face point;And check and acceptance result is reported supervising engineer, complete this acceptance of work.
CN201410038912.8A 2014-01-27 2014-01-27 Air lifting underwater desilting construction method Active CN103806484B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410038912.8A CN103806484B (en) 2014-01-27 2014-01-27 Air lifting underwater desilting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410038912.8A CN103806484B (en) 2014-01-27 2014-01-27 Air lifting underwater desilting construction method

Publications (2)

Publication Number Publication Date
CN103806484A CN103806484A (en) 2014-05-21
CN103806484B true CN103806484B (en) 2017-02-15

Family

ID=50703836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410038912.8A Active CN103806484B (en) 2014-01-27 2014-01-27 Air lifting underwater desilting construction method

Country Status (1)

Country Link
CN (1) CN103806484B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018459B (en) * 2014-06-05 2017-07-28 中国神华能源股份有限公司 A kind of dredging method of coal mine underground reservoir
CN105155606B (en) * 2014-09-18 2017-06-16 浙江工业大学 A kind of harbour aeration type dredging method
US9714073B2 (en) 2015-10-26 2017-07-25 Ali Salman ALSHAFAI Underwater propulsion belt
CN207129126U (en) * 2017-07-28 2018-03-23 广船国际有限公司 The narrow and small cabin welding ventilation unit of ship
CN109184730A (en) * 2018-08-22 2019-01-11 中铁二局集团有限公司 A kind of construction method quickly cleaning double-shielded TBM shield tail silt
CN110552395B (en) * 2019-09-11 2021-12-21 水利部交通运输部国家能源局南京水利科学研究院 Deep water sediment rapid removal system and method based on pneumatic sediment removal
CN111442905B (en) * 2020-04-07 2022-03-29 水利部交通运输部国家能源局南京水利科学研究院 Simulation system for air overflow and sand discharge

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56159436A (en) * 1980-05-13 1981-12-08 Shigeo Takamura Dredging method using clamshell type water injection pressure air mixing pump
JPS56159437A (en) * 1980-05-13 1981-12-08 Shigeo Takamura Dredging method using hydraulic power shovel water injection pressure air mixing pump
US4647272A (en) * 1980-11-20 1987-03-03 Aluminum Company Of America Method and lift pump for raising liquids
US7690135B2 (en) * 2007-09-23 2010-04-06 Technip France Deep sea mining riser and lift system
CN103114620B (en) * 2013-02-28 2015-02-11 江苏华西村海洋工程服务有限公司 High-power submersed front-and-back-flow-jetting air-lift submarine pipeline ditching machine and ditching technology

Also Published As

Publication number Publication date
CN103806484A (en) 2014-05-21

Similar Documents

Publication Publication Date Title
CN103806484B (en) Air lifting underwater desilting construction method
CN105155606B (en) A kind of harbour aeration type dredging method
CN105714867B (en) A kind of efficiently convenient drag suction dredger and its ecological dredging construction
CN202899587U (en) Large area factory space ground floor concrete planeness construction device
CN104141308A (en) Drill hole prepacked aggregate concrete construction method
Neal et al. Evaluation of the submerged discharge of dredged material slurry during pipeline dredge operations
Dutta et al. A methodology for cumulative impact assessment of opencast mining projects with special reference to air quality assessment
KR101647669B1 (en) Molding system for restoring polluted sediment in the sea
Quadrini et al. Pilot‐scale demonstration of in situ capping of PCB‐containing sediments in the lower Grasse River
CN106764055B (en) Push pipe sight alignment construction
Bowker Forest harvest equipment movement and sediment delivery to streams
KR20190089483A (en) Treatment of nuclear waste exclusively for ocean won Pressurized water double structure nuclear reactor equipment
Nitta et al. Field Verification and Evaluation of Technology Towards Introduction of Underwater Inspection Vehicle
Iliashenko Development and substantiation of technical solutions for dust suppression during mining operations at the open pit mines of the Kirovsk branch of JSC" Apatit"
Tesch et al. Special features of the groundwater management in regard to large construction sites in Berlin, Germany
SITE REMEDIAL ACTION WORK PLAN FOR PHASE 2 DREDGING AND FACILITY OPERATIONS IN 2012
Isichei Environmental impact assessment and environmental evaluation reports
Singh Study and review of emergency management system of tunnerls
Lang et al. Big Data-Based Decision Support Systems
Liu Block Erection Technology
Musthafa Environmental impact assessment for the proposed deep sea dredging to reclaim and develop 3 resort islands in North Male’Atoll lagoon
Shaheen Environmental Impact Assessment
WHAREHOUSE ENVIRONMENTAL IMPACT ASSESSMENT STUDY AND MITIGATION PLAN
SITE REMEDIAL ACTION WORK PLAN FOR PHASE 1 DREDGING AND FACILITY OPERATIONS
KR20180020186A (en) Dual structure of treatment of nuclear waste exclusively for ocean won Nuclear reactor equipment for new type conversion

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 310000 No. 4, building 69, false Hill Road, Hangzhou, Zhejiang

Applicant after: Hangzhou Huaneng engineering safety Polytron Technologies Inc

Address before: 310014 No. 4, building 69, false Hill Road, Hangzhou, Zhejiang

Applicant before: HANGZHOU HUANENG DAM SAFETY ENGINEERING TECHNOLOGY CO., LTD.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant