CN103790514B - Umbrella bores suspension system - Google Patents

Umbrella bores suspension system Download PDF

Info

Publication number
CN103790514B
CN103790514B CN201410054718.9A CN201410054718A CN103790514B CN 103790514 B CN103790514 B CN 103790514B CN 201410054718 A CN201410054718 A CN 201410054718A CN 103790514 B CN103790514 B CN 103790514B
Authority
CN
China
Prior art keywords
umbrella
bores
suspension system
winch
upper layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410054718.9A
Other languages
Chinese (zh)
Other versions
CN103790514A (en
Inventor
崔喜旺
申保军
杨永军
宋彦辉
吴海燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201410054718.9A priority Critical patent/CN103790514B/en
Publication of CN103790514A publication Critical patent/CN103790514A/en
Application granted granted Critical
Publication of CN103790514B publication Critical patent/CN103790514B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention provides a kind of umbrella and bore suspension system, comprise hanging scaffold, umbrella brill, wire rope, column, assembly pulley, winch, steel wire loop and base; Wherein, hanging scaffold comprises upper layer disc and lower floor's dish, is connected and fixed between upper layer disc and lower floor's dish by column, and winch is arranged on lower floor's dish; Floor installation is at the close position at the center of upper layer disc, and assembly pulley is suspended on base by steel wire loop; Winch is connected with assembly pulley by lay winding wire ropes; Umbrella bores the below being suspended in assembly pulley.Utilize above-mentioned according to umbrella brill suspension system provided by the invention, adopt winch to coordinate the mode of assembly pulley to replace boom hoist cable to suspend umbrella in midair to bore, umbrella bores not easily to tilt, ensure construction safety, and, transferring, on to carry in the process that umbrella bores without the need to contacting with hole top signal, reduce the potential safety hazard of constructor, accelerate speed of application.

Description

Umbrella bores suspension system
Technical field
The present invention relates to pit mining technical field, more specifically, relate to a kind of umbrella and bore suspension system.
Background technology
Along with the mines such as colliery are dug well the development of technology and the raising of mechanization degree, existing dig well construction in, umbrella bores and hammer drill has become the special equipment of digging well and constructing, thus replace hand-hammer drilling and half mechanical execution equipment, first bore blasthole drilling by umbrella, hammer drill is adopted to tunnel after explosion, in light-gauge shaft excavation construction, usual employing is lightweight, the umbrella that specification is little bores, lifting centre distance wellbore centre due to umbrella brill during rock drilling is nearer, boom hoist cable suspention umbrella is used to bore as long as improved a little by hanging scaffold, just can prevent drilling cramp from toppling over, but in the shaft excavation construction of big cross section, because shaft section is large, the lifting centre distance wellbore centre that umbrella bores is far away, boom hoist cable suspention is used during rock drilling, umbrella bores easy inclination even topples over, construction safety cannot be ensured, and, umbrella is carried on boring, need when transferring to contact with hole top signal, there is the potential safety hazard of constructor, simultaneously, umbrella is carried on boring, the speed transferred is slow, affect construction speed.
Therefore, a kind of technical scheme solved the problem newly is needed.
Summary of the invention
In view of the above problems, the object of this invention is to provide a kind of umbrella and bore suspension system, to solve when the shaft excavation of big cross section is constructed, use boom hoist cable suspention umbrella bores the problem that easy inclination is even toppled over.
Umbrella provided by the invention bores suspension system, comprises hanging scaffold, umbrella brill, wire rope, column, assembly pulley, winch, steel wire loop and base; Wherein, hanging scaffold comprises upper layer disc and lower floor's dish, is connected and fixed between upper layer disc and lower floor's dish by column, and winch is arranged on lower floor's dish; Floor installation is at the close position at the center of upper layer disc, and assembly pulley is suspended on base by steel wire loop; Winch is connected with assembly pulley by lay winding wire ropes; Umbrella bores the below being suspended in assembly pulley.
Wherein, assembly pulley comprises the movable pulley and fixed pulley that are linked together by wire rope; Umbrella bores on suspention movable pulley; Fixed pulley is suspended on base by steel wire loop.
Wherein, the marginal position coiled in upper layer disc and lower floor is respectively arranged with and surely coils device.
Wherein, this umbrella bores is that six arm hydraulic pressure umbrellas bore.
Wherein, this base is i iron.
Wherein, this winch is slow motion winch.
Wherein, upper layer disc and lower floor's dish are respectively arranged with horn mouth.
Utilize above-mentioned according to umbrella brill suspension system provided by the invention, adopt winch to coordinate the mode of assembly pulley to replace boom hoist cable to suspend umbrella in midair to bore, umbrella bores not easily to tilt, ensure construction safety, and, transferring, on to carry in the process that umbrella bores without the need to contacting with hole top signal, reduce potential safety hazard, accelerate speed of application.
In order to realize above-mentioned and relevant object, will describe in detail and the feature particularly pointed out in the claims after one or more aspect of the present invention comprises.Explanation below and accompanying drawing describe some illustrative aspects of the present invention in detail.But what these aspects indicated is only some modes that can use in the various modes of principle of the present invention.In addition, the present invention is intended to comprise all these aspects and their equivalent.
Accompanying drawing explanation
By reference to the content below in conjunction with the description of the drawings and claims, and understand more comprehensively along with to of the present invention, other object of the present invention and result will more be understood and should be readily appreciated that.In the accompanying drawings:
Fig. 1 is the structure chart boring suspension system according to the umbrella of the embodiment of the present invention.
Label identical in all of the figs indicates similar or corresponding feature or function.
Reference numeral wherein comprises: upper layer disc 2, lower floor's dish 3, winch 4, base 6, steady dish device 7, column 8, movable pulley 9, fixed pulley 10, umbrella brill 11, wire rope 12, steel wire loop 13, horn mouth 14.
Detailed description of the invention
In the following description, for purposes of illustration, in order to provide the complete understanding to one or more embodiment, many details have been set forth.But, clearly, also these embodiments can be realized when there is no these details.In other example, one or more embodiment for convenience of description, known structure and equipment illustrate in block form an.
Below with reference to accompanying drawing, specific embodiments of the invention are described in detail.
Fig. 1 shows the structure of boring suspension system according to the umbrella of the embodiment of the present invention.
As shown in Figure 1, the umbrella shown in the present embodiment bores suspension system, comprises hanging scaffold, umbrella bores 11 and wire rope 12, assembly pulley, winch 4, steel wire loop 13 and base 6.
Wherein, hanging scaffold is dual layer discs, comprises upper layer disc 2 and lower floor's dish 3, is linked together between upper layer disc 2 and lower floor's dish 3 by column 8; In addition, hanging scaffold also can be multilayer disc, convenient construction personnel operation on hanging scaffold, and the number of plies of hanging scaffold is specifically determined according to practice of construction situation; Assembly pulley comprises fixed pulley 10 and movable pulley 9, and movable pulley 9 is positioned at the below of fixed pulley 10, and is linked together by wire rope.
In order to avoid measuring center line, open a through hole at the close position at the center of upper layer disc 2, mounting seat 6 on this through hole, this base 6 suspends fixed pulley 10 in midair by steel wire loop 12.
Lower floor's dish 3 is provided with winch 4, winch 4 will be distal to the distance of base 6 apart from the center of upper layer disc 2 apart from the distance at the center of lower floor's dish 3, winch 4 is linked together by lay winding wire ropes 12 and fixed pulley 10, an enough large through hole (work in place of boring for transferring umbrella is prepared) is opened in the center of lower floor's dish 3, pass through hole for movable pulley 9 and freely activity in through hole, and the movable pulley 9 be positioned at below fixed pulley suspends umbrella brill 11 in midair.
The present invention coordinates the mode of assembly pulley to suspend umbrella brill 11 in midair by winch 4, thus the mode replacing well head to overhang wire rope suspends umbrella brill 11 in midair, because shaft section is large, the mode adopting well head to overhang wire rope is suspended umbrella in midair and is bored 11, it is comparatively far away that it promotes wellbore centre in center to center distance, and umbrella bores 11 easy inclinations even topples over, and adopts winch 4 in the present invention to coordinate the mode of assembly pulley to suspend umbrella brill in midair, because of it, to promote centre distance wellbore centre comparatively near, then umbrella bores 11 and can not tilt and even topple over.
Wherein, in order to increase the stability of hanging scaffold, at the marginal position of upper layer disc 2 and lower floor's dish 3, many covers steady dish device 7 can be installed, be prior art owing to surely coiling device, therefore no longer illustrate in describing the invention.
For the ease of the turnover up and down of well-bucket, 3 collinear positions can be coiled in upper layer disc 2 and lower floor and open at least one horn mouth 14 respectively.
In addition, in a specific embodiment of the present invention, base 6 adopts has some strength and the object that can entangle steel wire loop 13, particularly, adopts i iron as base.
In order to strengthen fixing upper layer disc 2 and lower floor's dish 3, column should adopt the higher material of intensity to make.In a specific embodiment of the present invention, adopt the higher i iron of intensity as column.
In addition, the six arm hydraulic pressure umbrellas of the umbrella drilling in the embodiment of the present invention bore, and winch is slow motion winch.
In order to more detailed description umbrella of the present invention bores suspension system, below will the present invention will be described from working design aspect.
According to the practical experience of constructor, select the slow motion winch of 3 tons, be arranged on hanging scaffold bottom dish apart from wellbore centre 3m position;
Install a long I25a i iron of 2m (object is for geing out of the way measuring center line) apart from upper layer disc center 250mm, i iron installs a Φ 28mm steel wire loop for hanging assembly pulley.
Slow motion winch twines Φ 16mm wire rope and connects suspension assembly pulley, installs U-shaped ring suspension hydraulic umbrella and bore below assembly pulley.Pulley selects lifting capacity to be that 20t remains silent suspension ring type.
The selection of wire rope:
(1) six arm hydraulic pressure umbrellas bore the gross weight coordinating hammer drill is 12.5t;
(2) the minimum breaking force 157KN of 6 × 19-Φ 16-1870 wire rope,
Wire rope total Fracture Force ∑ F is total=157 × 1.24 ÷ 9.8=19.87 tons, then the always disrumpent feelings of 8 wire rope is 158.96 tons, wire rope maximum pendency height 25m, wire rope every hundred meters of weight 0.0944 ton, wire rope weight 0.1888 ton can be ignored, therefore, on this basis, safety factor is 158.96/(12.5+0.1888)=12.53, meet safety code, meet instructions for use.
In addition, depending on country rock situation, when needing eccentric slotting during rock drilling, steel wire loop and I25a i iron according to circumstances need to adjust, and umbrella brill also suitably can depart from certain distance in well to be fixed.
The mode adopting well head to overhang wire rope is transferred umbrella and is bored 11, due to umbrella bore transfer to shaft bottom from well head time, boom hoist cable to wellbore centre distance between 1.4m ~ 1.8m, easy operation, general umbrella bores transfers program and is: transfer umbrella drill change shaft bottom when being about 300mm, stopping is transferred, put base well, by taking hook by force, umbrella brill is pushed in well, transfer umbrella and be drilled into base, connect blast main and water pipe (first wanting little wind only to manage interior dirt) subsequently, connect ball valve, start air motor and make operation of oil pump, supply pressure oil.Handle column oil path valve and rise support arm, stretch out support arm pawl and prop up the borehole wall, overall umbrella loosens hoisting rope a little after boring vertical fixing, and makes it to help umbrella and bores, prevent drilling cramp from toppling over.When column is fixed, necessary vertical bore negative, to avoid hole deviation and to produce card pricker phenomenon.
And adopt umbrella of the present invention to bore suspension system to transfer program that umbrella bores and above-mentioned to transfer the program that umbrella bores identical, when transferring umbrella and boring 11, open winch, coordinate assembly pulley to transfer umbrella by winch 4 and bore 11, when umbrella brill 11 is about 300mm apart from shaft bottoms, stops transferring, put firm banking well, by taking hook by force, umbrella brill is moved to central authorities, and then transfer on umbrella brill 11 to firm banking.
Can be found out by above-mentioned embodiment, umbrella provided by the invention bores suspension system, in the shaft excavation construction of big cross section, can guarantee that the umbrella suspended in midair bores to tilt, ensure construction safety, and, umbrella does not need to contact with hole top signal when boring put-on and delegated, reduces the potential safety hazard of constructor, simultaneously, promote the speed that umbrella bores put-on and delegated, and then accelerating construction progress.
Describe above with reference to accompanying drawing the umbrella proposed according to the present invention in an illustrative manner and bore suspension system.But, it will be appreciated by those skilled in the art that the umbrella proposed for the invention described above bores suspension system, on the basis not departing from content of the present invention, various improvement can also be made to the details that realizes wherein.Therefore, protection scope of the present invention should be determined by the content of appending claims.

Claims (6)

1. umbrella bores a suspension system, comprises hanging scaffold, umbrella bores and wire rope, it is characterized in that, described umbrella bores suspension system and also comprises column, assembly pulley, winch, steel wire loop and base; Wherein,
Described hanging scaffold comprises upper layer disc and lower floor's dish, and described upper layer disc and described lower floor dish are connected and fixed by described column;
Described assembly pulley comprises the movable pulley and fixed pulley that are linked together by wire rope; Described umbrella bores and is suspended on described movable pulley; Described fixed pulley is suspended on described base by described steel wire loop; And,
Described winch is arranged on described lower floor dish, is connected with described fixed pulley by lay winding wire ropes;
Described floor installation is at the close position at the center of described upper layer disc.
2. umbrella as claimed in claim 1 bores suspension system, it is characterized in that, is respectively arranged with surely coils device at the marginal position of described upper layer disc and described lower floor dish.
3. umbrella as claimed in claim 1 bores suspension system, it is characterized in that, it is that six arm hydraulic pressure umbrellas bore that described umbrella bores.
4. umbrella as claimed in claim 1 bores suspension system, and it is characterized in that, described base is i iron.
5. umbrella as claimed in claim 1 bores suspension system, and it is characterized in that, described winch is slow motion winch.
6. umbrella as claimed in claim 1 bores suspension system, it is characterized in that, described upper layer disc and described lower floor dish are respectively arranged with horn mouth.
CN201410054718.9A 2014-02-18 2014-02-18 Umbrella bores suspension system Active CN103790514B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410054718.9A CN103790514B (en) 2014-02-18 2014-02-18 Umbrella bores suspension system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410054718.9A CN103790514B (en) 2014-02-18 2014-02-18 Umbrella bores suspension system

Publications (2)

Publication Number Publication Date
CN103790514A CN103790514A (en) 2014-05-14
CN103790514B true CN103790514B (en) 2016-03-30

Family

ID=50666527

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410054718.9A Active CN103790514B (en) 2014-02-18 2014-02-18 Umbrella bores suspension system

Country Status (1)

Country Link
CN (1) CN103790514B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3187379B2 (en) * 1998-11-18 2001-07-11 戸田建設株式会社 Wellhead sealing device
CN201546731U (en) * 2009-05-25 2010-08-11 中交隧道工程局有限公司 Ultra-large diameter deep shaft engineering construction supporting device
CN202181898U (en) * 2011-08-18 2012-04-04 中煤矿山建设集团有限责任公司 Special hanging scaffold for sheathing and building inner-layer well wall in vertical shaft sinking construction
CN202755977U (en) * 2012-08-23 2013-02-27 山东矿业管理技术服务集团有限公司 Stable plate fixing device for vertical shaft digging and building construction
CN202900281U (en) * 2012-10-15 2013-04-24 杨福辉 Strut type well lid door opening and closing device
CN103277104A (en) * 2013-06-17 2013-09-04 中国矿业大学 Sinking platform in-well hanging equipment and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3187379B2 (en) * 1998-11-18 2001-07-11 戸田建設株式会社 Wellhead sealing device
CN201546731U (en) * 2009-05-25 2010-08-11 中交隧道工程局有限公司 Ultra-large diameter deep shaft engineering construction supporting device
CN202181898U (en) * 2011-08-18 2012-04-04 中煤矿山建设集团有限责任公司 Special hanging scaffold for sheathing and building inner-layer well wall in vertical shaft sinking construction
CN202755977U (en) * 2012-08-23 2013-02-27 山东矿业管理技术服务集团有限公司 Stable plate fixing device for vertical shaft digging and building construction
CN202900281U (en) * 2012-10-15 2013-04-24 杨福辉 Strut type well lid door opening and closing device
CN103277104A (en) * 2013-06-17 2013-09-04 中国矿业大学 Sinking platform in-well hanging equipment and method

Also Published As

Publication number Publication date
CN103790514A (en) 2014-05-14

Similar Documents

Publication Publication Date Title
CN104389607B (en) Novel drilling and blasting method shaft drilling machine
CN103924977A (en) Center-pillared full-face shaft drilling machine
CN208236413U (en) A kind of shaft construction device
JPH10169355A (en) Composite type pipe lifting device for excavating large water depth
CN103696774A (en) Development method of blind shaft frame for surface and underground parallel construction
CN101858213A (en) Drilling, loading, transporting and anchoring integrated machine with dual platforms and four arms for coal roadway
CN109487843A (en) A kind of underwater open caisson development machine and its construction method
CN108533268A (en) A kind of shaft construction device and its application method
CN103213905A (en) Underground hoisting system
CN216043503U (en) Single-rail anchor rod hanging drill carriage
CN203742602U (en) Central stand column full-section vertical shaft drilling machine
CN103790514B (en) Umbrella bores suspension system
CN102777186A (en) Full-hydraulic self-moving type template device of vertical shaft wall
CN107288640B (en) A kind of nothing is surely restricted self-supporting modularization vertical shaft driving and masonry construction device
CN103277104A (en) Sinking platform in-well hanging equipment and method
CN106050260A (en) Non-stop production reconstruction method for tower-type external shaft hoisting system
RU137573U1 (en) MECHANIZED COMPLEX FOR PERFORMING VERTICAL TRUNKS OF MINING ENTERPRISES
CN106368619A (en) Novel gas drainage drilling rig with self-moving and stabilizing device
CN103850687B (en) A kind of applicable multi-functional hanging scaffold of shaft excavation machine
CN205591926U (en) Do not have self -supporting modularization shaft of surely restricting and dig step construction equipment
CN108626482A (en) The construction method of vertical gas pipe is installed using anti-well drilling machine
CN207892530U (en) A kind of impact holing formula shaft development device
CN1469017A (en) High slope rock and soil anchoring construction method and apparatus
RU2039280C1 (en) Excavating and loading complex for opencast mining
CN202300385U (en) Top rock bolt anchor cable drilling machine of comprehensive mechanical stone drift development machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant