CN103787191B CN201410039931.2A CN201410039931A CN103787191B CN 103787191 B CN103787191 B CN 103787191B CN 201410039931 A CN201410039931 A CN 201410039931A CN 103787191 B CN103787191 B CN 103787191B
Authority
CN
China
Prior art keywords
suspension rod
concrete block
hollow concrete
corner
lower beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410039931.2A
Other languages
Chinese (zh)
Other versions
CN103787191A (en
Inventor
张克文
李正改
樊敬涛
钱健
李涛
任志成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd
HWAKING CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd
HWAKING CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd, HWAKING CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd
Priority to CN201410039931.2A priority Critical patent/CN103787191B/en
Publication of CN103787191A publication Critical patent/CN103787191A/en
Application granted granted Critical
Publication of CN103787191B publication Critical patent/CN103787191B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Revetment (AREA)

Abstract

A kind of corner hollow concrete block special hoisting bar, it includes the first suspension rod (2) and the second suspension rod (3) being articulated with on same hinge axis (1), for supporting a bracer (5) of corner hollow concrete block (4), described the first suspension rod (2) and the second suspension rod (3) are constituted by lower beam (6) and the upper boom (7) tilted towards lower beam (6) left oblique upper, described bracer (5) is connected with the bottom of lower beam (6) and towards the left obliquely downward extension of lower beam (6), described the first suspension rod (2) and the second suspension rod (3) in the raw time two upper booms (7) be mutually flared out, two lower beams (6) draw in, when described the first suspension rod (2) and the second suspension rod (3) are in lifting state, two lower beams (6) are mutually flared out, two upper booms (7) draw in.This corner hollow concrete block special hoisting bar not only can lift by crane but also the safest.

Description

Corner hollow concrete block special hoisting bar
Technical field
The present invention relates to a kind of suspension bracket, particularly relate to a kind of corner hollow concrete block special hoisting bar.
Background technology
In the concrete revetment on seashore or river bank, the most all laying the concrete block surface layer as slope formula shore protection, this concrete block has Having stability strong, anti-wave effect is good, is easy to the most again make and facilitate the advantages such as installation, therefore widely used by hydraulic engineering design.
And due to will washing away for a long time and corroding by sea water, so corner hollow concrete block typically becomes the most thereon when manufacturing Type goes out suspension hook.Therefore when lifting, how to design and can lift by crane and the suspension bracket of safety, especially for lifting by crane as shown in Figure 1 Weight reaches 2t even 3t and above ultra-large type corner hollow concrete block is particularly important.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of not only can lifting but also the corner hollow concrete block special hoisting bar of safety.
For solving above-mentioned technical problem, the technical scheme that the present invention provides is: it includes that be articulated with on same hinge axis first hangs Bar and the second suspension rod, for supporting a bracer of corner hollow concrete block, the first described suspension rod and the second suspension rod are by lower beam and court The upper boom that the left oblique upper of lower beam tilts is constituted, and described bracer is connected with the bottom of lower beam and towards the left obliquely downward extension of lower beam, The first described suspension rod and the second suspension rod in the raw time two upper booms be mutually flared out, two lower beams draw in, described first When suspension rod and the second suspension rod are in lifting state, two lower beams are mutually flared out, two upper booms draw in;Described the first suspension rod or second It is additionally provided with on the medial wall of the upper boom of suspension rod and is easy to corner hollow concrete block special hoisting bar and puts into corner hollow concrete block center hole or from four The bayonet lock that angle hollow concrete block center hole takes out, this bayonet lock is made up of the bull stick being arranged in a mutually vertical manner and kelly, and bar rotation is installed On the medial wall of wherein upper boom, and kelly is when external force rotates bull stick, and both can be placed in can on the medial wall of this root upper boom Level is placed on the projection at another root upper boom medial wall.
The first described suspension rod and the second suspension rod symmetry are articulated with on hinge axis.
Described hinge axis is between the first suspension rod and the second suspension rod and is positioned at the link position of upper boom and lower beam, described One suspension rod and the second suspension rod in the raw time two lower beams be collapsed into vertical parallel shape, at the first described suspension rod and the second suspension rod When the state of lifting, two upper booms are collapsed into vertical parallel shape.
Described bull stick is additionally provided with the safety of being easy to extended to outside upper boom and rotates the operating handle of bull stick.
The both sides of described lower beam are additionally provided with and increase the offset auxiliary of area of lower beam and corner hollow concrete block center hole inwall and support block.
It is respectively symmetrically on the upper boom of the first described suspension rod and the upper boom of the second suspension rod and is provided with the lifting hole(eyelet) being easy to suspension hook lifting.
After using above structure, present invention have the advantage that the corner hollow concrete block special hoisting bar of the present invention utilizes corner hollow The center hole of concrete block, uses two suspension rods that can simultaneously rotate relative to same hinge axis, and makes to be formed between the upper boom of suspension rod folder Angle, so when lifting, utilizes the gravity of corner hollow concrete block self, and the lower beam of suspension bracket opens toward both sides the most naturally, now connects It is connected on the bracer bottom lower beam and the most firmly supports the bottom of whole corner hollow concrete block, the lower beam opened propping up the most tightly The inwall of corner hollow concrete block center hole so that it is sliding can not be produced and keep stable.In sum, the corner of the present invention is empty Heart concrete block special hoisting bar can realize weight reaching 2t even 3t and the lifting of above ultra-large type corner hollow concrete block, during lifting Safety coefficient high, lifting speed is also fast, and whole special hoisting bar compact conformation rationally, design ingenious, it is simple, convenient to make. After additionally bayonet lock is arranged, the kelly of bayonet lock is set level, then can prevent two lower beams from opening, it is simple to it is empty that corner put into by whole special hoisting bar In the center hole of heart concrete block, it is easy to again after rigging out whole special hoisting bar in the center hole of corner hollow concrete block simultaneously Take out.
Being articulated with on hinge axis as improvement, the first described suspension rod and the second suspension rod symmetry, when making lifting, stress more steadily may be used Lean on.
As improvement, described hinge axis is between the first suspension rod and the second suspension rod and is positioned at the link position of upper boom and lower beam, The first described suspension rod and the second suspension rod in the raw time two lower beams be collapsed into vertical parallel shape, the first described suspension rod and When two suspension rods are in lifting state, two upper booms are collapsed into vertical parallel shape, make the first suspension rod and the second suspension rod opposite from hinge axle rotate and open The amplitude opened keeps maximizing, more conducively the lifting of the corner hollow concrete block that the safety of lifting is different with size.
As improvement, described bull stick is additionally provided with the safety of being easy to extended to outside upper boom and rotates the operating handle of bull stick, handle Setting can make operator rotate bull stick outside two upper booms, eliminates the potential safety hazard operating bull stick between two upper booms and exist.
As improvement, the both sides of described lower beam are additionally provided with increase lower beam and corner hollow concrete block center hole inwall and offset area Auxiliary supports block, auxiliary support block increase lower beam during lifting with the clamping area of the inwall of corner hollow concrete block center hole, Further increase security performance.
It is easy to hanging of suspension hook lifting as being respectively symmetrically on improvement, the upper boom of the first described suspension rod and the upper boom of the second suspension rod to be provided with Hole, facilitates the suspension hook operation to special hoisting bar in hoisting process.
Accompanying drawing explanation
Fig. 1 is the main TV structure schematic diagram of the corner hollow concrete block special hoisting bar of the present invention.
Fig. 2 is the partial structurtes schematic diagram (now on upper boom, bayonet lock does not shows) of the corner hollow concrete block special hoisting bar of the present invention.
Fig. 3 is the structural representation of the corner hollow concrete block of the present invention.
As shown in the figure: 1, hinge axis, the 2, first suspension rod, the 3, second suspension rod, 4, corner hollow concrete block, 4.1, center hole, 5, bracer is propped up, 6, lower beam, 7, upper boom, 7.1, projection, 7.2, lifting hole(eyelet), 8, bayonet lock, 8.1, bull stick, 8.11, operation handlebar Hands, 8.2, kelly, 9, auxiliary support block.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings.
As it can be seen, a kind of corner hollow concrete block special hoisting bar, it includes the first suspension rod 2 He being articulated with on same hinge axis 1 Second suspension rod 3, for supporting bracer 5 of corner hollow concrete block 4.In the present embodiment, the first suspension rod 2 and the second suspension rod 3 Inwall on be all welded with the steel pipe being coaxially disposed, the first suspension rod 2 and the second suspension rod 3 then by hinge axis 7 is sheathed on Realize hinged with hinge axis 7 in two steel pipes that axle is arranged.
The first described suspension rod 2 and the second suspension rod 3 are constituted by lower beam 6 and the upper boom 7 tilted towards the left oblique upper of lower beam 6.Institute The bracer 5 stated is connected with the bottom of lower beam 6 and towards the left obliquely downward extension of lower beam 6.Described the first suspension rod 2 and second hangs Bar 3 in the raw time two upper booms 7 are mutually flared out, two lower beams 6 draw in.The first described suspension rod 2 and the second suspension rod 3 two lower beams 6 are mutually flared out, two upper booms 7 draw in when being in lifting state.
In the present embodiment, the first described suspension rod 2 and the second suspension rod 3 symmetry are articulated with on hinge axis 1;Described hinge axis 1 Between the first suspension rod 2 and the second suspension rod 3 and be positioned at the link position of upper boom 7 and lower beam 6, the first described suspension rod 2 During with the second suspension rod 3 in the raw, two lower beams 6 are collapsed into vertical parallel shape, the first described suspension rod 2 and the second suspension rod 3 When being in lifting state, two upper booms 7 are collapsed into vertical parallel shape.
It addition, as the improvement project of the present embodiment, on the first described suspension rod 2 or the medial wall of the upper boom 7 of the second suspension rod 3 It is additionally provided with and is easy to corner hollow concrete block special hoisting bar and puts into corner hollow concrete block 4 center hole 4.1 or from corner hollow concrete block 4 The bayonet lock 8 that central hole hole 4.1 is taken out.This bayonet lock 8 is made up of the bull stick 8.1 being arranged in a mutually vertical manner and kelly 8.2.Bull stick 8.1 turns Move and be installed on the medial wall of a wherein upper boom 7, and kelly 8.2 both can be placed in this root upper boom when external force rotates bull stick 8.1 Can level be placed on the projection 7.1 at another root upper boom 7 medial wall again on the medial wall of 7.
In the present embodiment: described bull stick 8.1 is additionally provided with the operation handlebar extending to be easy to rotate safely bull stick 8.1 outside upper boom 7 Hands 8.11;The both sides of described lower beam 6 are additionally provided with increase lower beam 6 and corner hollow concrete block 4 center hole 4.1 inwall and offset face Long-pending auxiliary supports block 9;It is respectively symmetrically to be provided with on the upper boom 7 of the first described suspension rod 2 and the upper boom 7 of the second suspension rod 3 and is easy to hang Hook the lifting hole(eyelet) 7.2 hung.
Lifting process:
1, before lifting, special hoisting bar is on the ground, and the kelly of bayonet lock is set level and is placed on projection.
2, utilize suspension hook to lift by crane special hoisting bar, special hoisting bar is put into the center hole of corner hollow concrete block.
3, the kelly of bayonet lock is rested on the inwall of upper boom.
4, utilizing suspension hook to lift by crane special hoisting bar, now, two upper booms of special hoisting bar close up to centre, and two lower beams are opened the most naturally Opening, two lower beams and a bracer block and hold inwall and the bottom of corner hollow concrete block the most respectively, now can lift by crane.
5, after the lifting of corner hollow concrete block puts in place, put down suspension hook, then the kelly of bayonet lock is set level, the most just can be by Special-purpose hanger Frame is released from the center hole of corner hollow concrete block, can carry out the lifting of next corner hollow concrete block.

Claims (6)

1. a corner hollow concrete block special hoisting bar, it is characterised in that: it includes be articulated with on same hinge axis (1) first Suspension rod (2) and the second suspension rod (3), it is used for supporting a bracer (5) of corner hollow concrete block (4), described the first suspension rod (2) Constitute by lower beam (6) and the upper boom (7) tilted towards lower beam (6) left oblique upper with the second suspension rod (3), described lower beam (6) being straight-bar, described bracer (5) is connected with the bottom of lower beam (6) and towards the left obliquely downward extension of lower beam (6), Described the first suspension rod (2) and the second suspension rod (3) in the raw time two upper booms (7) be mutually flared out, two lower beams (6) Draw in, when described the first suspension rod (2) and the second suspension rod (3) are in lifting state two lower beams (6) be mutually flared out, two Upper boom (7) draws in;It is additionally provided with on described the first suspension rod (2) or the medial wall of the upper boom (7) of the second suspension rod (3) and is easy to Corner hollow concrete block special hoisting bar puts into corner hollow concrete block (4) center hole (4.1) or from hollow concrete block (4) center, corner The bayonet lock (8) that hole (4.1) takes out, this bayonet lock (8) is made up of the bull stick (8.1) being arranged in a mutually vertical manner and kelly (8.2), Bull stick (8.1) rotates and is installed on the medial wall of a wherein upper boom (7), and kelly (8.2) rotates bull stick (8.1) in external force Shi Jike is placed on the medial wall of this root upper boom (7) and level can be placed on the projection (7.1) at another root upper boom (7) medial wall again On.
Corner the most according to claim 1 hollow concrete block special hoisting bar, it is characterised in that: described the first suspension rod (2) It is articulated with on hinge axis (1) with the second suspension rod (3) symmetry.
Corner the most according to claim 2 hollow concrete block special hoisting bar, it is characterised in that: described hinge axis (1) position Between the first suspension rod (2) and the second suspension rod (3) and be positioned at the link position of upper boom (7) and lower beam (6), described First suspension rod (2) and the second suspension rod (3) in the raw time two lower beams (6) be collapsed into vertical parallel shape, described first When suspension rod (2) and the second suspension rod (3) are in lifting state, two upper booms (7) are collapsed into vertical parallel shape.
Corner the most according to claim 1 hollow concrete block special hoisting bar, it is characterised in that: described bull stick (8.1) also sets There is the operating handle (8.11) extending to be easy to rotate safely bull stick (8.1) outside upper boom (7).
Corner the most according to claim 1 hollow concrete block special hoisting bar, it is characterised in that: the two of described lower beam (6) Side be additionally provided with increase lower beam (6) with corner hollow concrete block (4) center hole (4.1) inwall offset area auxiliary support block (9).
Corner the most according to claim 1 hollow concrete block special hoisting bar, it is characterised in that: described the first suspension rod (2) Upper boom (7) and the second suspension rod (3) upper boom (7) on be respectively symmetrically be provided be easy to suspension hook lifting lifting hole(eyelet) (7.2).
CN201410039931.2A 2014-01-27 2014-01-27 Corner hollow concrete block special hoisting bar Active CN103787191B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410039931.2A CN103787191B (en) 2014-01-27 2014-01-27 Corner hollow concrete block special hoisting bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410039931.2A CN103787191B (en) 2014-01-27 2014-01-27 Corner hollow concrete block special hoisting bar

Publications (2)

Publication Number Publication Date
CN103787191A CN103787191A (en) 2014-05-14
CN103787191B true CN103787191B (en) 2016-08-10

Family

ID=50663328

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410039931.2A Active CN103787191B (en) 2014-01-27 2014-01-27 Corner hollow concrete block special hoisting bar

Country Status (1)

Country Link
CN (1) CN103787191B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0337850A1 (en) * 1988-04-12 1989-10-18 Automobiles Peugeot Handling device for receptacles such as containers
DE19750784A1 (en) * 1997-11-06 1999-05-20 Mannesmann Ag Gripper especially for packing machines
CN201049864Y (en) * 2007-06-07 2008-04-23 抚顺铝业有限公司 Turnover fixture for prebaked-anode
CN201433040Y (en) * 2009-07-03 2010-03-31 齐齐哈尔轨道交通装备有限责任公司 Side-frame integral sand core hooking assembly and lifting hook
CN202164041U (en) * 2011-07-18 2012-03-14 中交第一航务工程局有限公司 Four-foot hollow square block lifting appliance
CN203667802U (en) * 2014-01-27 2014-06-25 华锦建设集团股份有限公司 Hanging bracket special for quadrangular hollow concrete blocks

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0337850A1 (en) * 1988-04-12 1989-10-18 Automobiles Peugeot Handling device for receptacles such as containers
DE19750784A1 (en) * 1997-11-06 1999-05-20 Mannesmann Ag Gripper especially for packing machines
CN201049864Y (en) * 2007-06-07 2008-04-23 抚顺铝业有限公司 Turnover fixture for prebaked-anode
CN201433040Y (en) * 2009-07-03 2010-03-31 齐齐哈尔轨道交通装备有限责任公司 Side-frame integral sand core hooking assembly and lifting hook
CN202164041U (en) * 2011-07-18 2012-03-14 中交第一航务工程局有限公司 Four-foot hollow square block lifting appliance
CN203667802U (en) * 2014-01-27 2014-06-25 华锦建设集团股份有限公司 Hanging bracket special for quadrangular hollow concrete blocks

Also Published As

Publication number Publication date
CN103787191A (en) 2014-05-14

Similar Documents

Publication Publication Date Title
CN103276886B (en) Overhanging frame at position of high-rise building sloping roof outer eave window and construction method thereof
CN214167097U (en) Lifting appliance for integral steel reinforcement framework of railway box girder
CN208166514U (en) A kind of crane high altitude operation nacelle device
CN103787191B (en) Corner hollow concrete block special hoisting bar
JP2016079616A (en) Hoisting device for gabion
CN202016863U (en) Material pouring device
CN205936369U (en) Municipal works construction is with inspection shaft ladder
CN203667802U (en) Hanging bracket special for quadrangular hollow concrete blocks
CN204778321U (en) Reinforcement cage hoisting device
CN209455923U (en) Detachable rectangular elements hoisting structure
CN206159649U (en) Pipeline suspends bracket in midair
CN206476660U (en) A kind of existing railway sound barrier panel lifting appliance for installing
CN204551494U (en) Construction equipment is transferred in a kind of steel sheet-pile cofferdam inner support superposition
CN205452962U (en) Work platform frame
CN205348798U (en) Formula that has a down dip concrete well -bucket
CN205330176U (en) Lower extreme open type concrete well -bucket
CN202969944U (en) Concrete pouring blanking appliance
CN206219042U (en) Overlength storehouse plate hoist device
CN202481940U (en) Hoisting mechanism of steel frame
CN207861804U (en) A kind of PC prefabricated components transport vehicle and carrier frame
CN206189829U (en) Auto -lock lifting foot hand rack
CN205558447U (en) Found pole appurtenance
CN207618888U (en) A kind of track plates hook assembly
CN208700403U (en) A kind of support device that hollow shaft coiled material is carried
CN208948713U (en) A kind of construction site is used to the support frame of lifting machinery equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant