CN103774851B - A kind of assembly method of space curved surface metal curtain wall - Google Patents
A kind of assembly method of space curved surface metal curtain wall Download PDFInfo
- Publication number
- CN103774851B CN103774851B CN201210396776.0A CN201210396776A CN103774851B CN 103774851 B CN103774851 B CN 103774851B CN 201210396776 A CN201210396776 A CN 201210396776A CN 103774851 B CN103774851 B CN 103774851B
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- metal
- metal panel
- panel
- panels
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
- Finishing Walls (AREA)
Abstract
本发明公开了一种空间曲面金属幕墙的装配方法,包括以下步骤:a)设计金属幕墙的空间曲面形状;b)将上述设计好的空间曲面形状以三角形为单元进行计算机模拟放样;c)根据上述计算机模拟放样的结果制作构成金属幕墙的各块三角形金属面板;d)按照上述计算机模拟放样的结果进行测量放线,并将步骤c)中制作的各块三角形金属面板安装于幕墙龙骨以形成步骤a)所设计的空间曲面形状金属幕墙。本发明的技术方案创造性的使用了三角形为单元进行计算机模拟放样以形成所设计的空间曲面形状,并根据计算机模拟放样的结果加工制作各块三角形金属面板,可以解决大曲率过渡的问题,形成具有圆滑曲面的金属幕墙,造型美观。
The invention discloses a method for assembling a metal curtain wall with a space curved surface, which comprises the following steps: a) designing the space curved surface shape of the metal curtain wall; As a result of the computer simulation lofting above, each triangular metal panel that constitutes the metal curtain wall is made; d) According to the result of the computer simulation lofting above, the measurement and setting out are carried out, and the triangular metal panels produced in step c) are installed on the keel of the curtain wall to form Step a) The designed space curved surface shape metal curtain wall. The technical solution of the present invention creatively uses triangles as units for computer simulation lofting to form the designed space curved surface shape, and processes and manufactures each triangular metal panel according to the results of computer simulation lofting, which can solve the problem of large curvature transition and form a The smooth and curved metal curtain wall has a beautiful shape.
Description
技术领域 technical field
本发明涉及一种金属幕墙的装配方法,尤其涉及一种曲面金属幕墙的装配方法。 The invention relates to an assembly method of a metal curtain wall, in particular to an assembly method of a curved metal curtain wall.
背景技术 Background technique
现有的金属幕墙在施工时多采用常规的方形单元,若幕墙的外形为曲面形式,将很难保证曲率,现场施工时,为了形成曲面外形,就需要对现场材料进行二次加工,这种方法虽然能够最终能够形成一般曲率的曲面,但是曲面不够圆滑和流畅,造型效果差,不够美观;而且安装施工的难度也很大,过多材料的二次加工还往往造成浪费。至于大曲率曲面幕墙,方形面板往往无法扭曲到足够幅度因而难以实现。 Conventional square units are often used in the construction of existing metal curtain walls. If the shape of the curtain wall is a curved surface, it will be difficult to ensure the curvature. During on-site construction, in order to form a curved surface shape, it is necessary to perform secondary processing on the site materials. Although the method can finally form a curved surface with general curvature, the curved surface is not smooth and smooth enough, the modeling effect is poor, and the appearance is not good enough; and the installation and construction are also very difficult, and the secondary processing of too many materials often causes waste. As for curtain walls with large curvature surfaces, square panels often cannot be twisted enough to make it difficult to achieve.
发明内容 Contents of the invention
本发明实施例所要解决的技术问题在于,提供一种大曲率的空间曲面金属幕墙的装配方法,使用该方法施工的空间曲面金属幕墙曲面圆滑,造型美观。 The technical problem to be solved by the embodiments of the present invention is to provide an assembly method of a large curvature space curved metal curtain wall. The space curved metal curtain wall constructed by this method has a smooth curved surface and a beautiful appearance.
为了解决上述技术问题,本发明实施例提供了一种空间曲面金属幕墙的装配方法,包括以下步骤: In order to solve the above technical problems, an embodiment of the present invention provides a method for assembling a space curved metal curtain wall, which includes the following steps:
a)设计金属幕墙的空间曲面形状; a) Design the space surface shape of the metal curtain wall;
b)将上述设计好的空间曲面形状以三角形为单元进行计算机模拟放样; b) Carry out computer simulation lofting of the above-mentioned designed space surface shape with triangle as the unit;
c)根据上述计算机模拟放样的结果制作构成金属幕墙的各块三角形金属面板; c) Make each triangular metal panel that constitutes the metal curtain wall according to the results of the above-mentioned computer simulation lofting;
d)按照上述计算机模拟放样的结果进行测量放线,并将步骤c)中制作的各块三角形金属面板安装于幕墙龙骨以形成步骤a)所设计的空间曲面形状金属幕墙。 d) Carry out measurement and setting out according to the results of the above-mentioned computer simulation lofting, and install each triangular metal panel made in step c) on the keel of the curtain wall to form the space curved metal curtain wall designed in step a).
作为上述技术方案的改进,在步骤d)中以六块三角形金属面板为一个幕墙组件进行安装从而形成曲面金属幕墙,所述六块三角形金属面板包括第一、第二、第三、第四、第五、第六金属面板,所述六块金属面板分别安装于三根幕墙龙骨上,所述第一、第二金属面板在上下方向分别位于第三、第五金属面板之间和第四、第六金属面板之间,并且所述第一、第二金属面板各以一角相对的安装于同一根幕墙龙骨形成固定角,所述两块金属面板固定角的对边分别安装于另两根幕墙龙骨形成固定边,所述第三、第五金属面板的固定角设于第一金属面板固定边所在的幕墙龙骨,固定边设于第一金属面板固定角所在的幕墙龙骨,所述第四、第六金属面板的固定角设于第二金属面板固定边所在的幕墙龙骨,固定边设于第二金属面板固定角所在的幕墙龙骨。 As an improvement of the above technical solution, in step d), six triangular metal panels are installed as a curtain wall component to form a curved metal curtain wall, and the six triangular metal panels include the first, second, third, fourth, The fifth and sixth metal panels, the six metal panels are respectively installed on the three curtain wall keels, and the first and second metal panels are respectively located between the third and fifth metal panels and the fourth and fourth metal panels in the vertical direction. Between the six metal panels, and the first and second metal panels are installed on the same curtain wall keel with one corner facing each other to form a fixed angle, and the opposite sides of the fixed angles of the two metal panels are respectively installed on the other two curtain wall keels Form a fixed edge, the fixed angle of the third and fifth metal panels is set on the curtain wall keel where the fixed edge of the first metal panel is located, and the fixed edge is set on the curtain wall keel where the fixed angle of the first metal panel is located, and the fourth and fifth metal panels The fixed corners of the six metal panels are set on the curtain wall keel where the fixed side of the second metal panel is located, and the fixed side is set on the curtain wall keel where the fixed angle of the second metal panel is located.
作为上述技术方案的进一步改进,在步骤d)中,所述金属面板的固定角通过连接构件安装于幕墙龙骨,所述连接构件为条块状,具有一个设有通孔的呈圆环形的端部,所述圆环形端部的厚度薄于连接构件的其他部位,所述连接构件块体上还开有两个长条形连接孔,所述金属面板安装于所述连接构件的长条形连接孔,所述连接构件通过所述圆环形端部的通孔与所述幕墙龙骨螺栓连接。 As a further improvement of the above technical solution, in step d), the fixed angle of the metal panel is installed on the curtain wall keel through a connecting member. end, the thickness of the ring-shaped end is thinner than other parts of the connecting member, and two strip-shaped connecting holes are opened on the block of the connecting member, and the metal panel is installed on the long connecting member A strip-shaped connecting hole, the connecting member is bolted to the curtain wall keel through the through hole at the circular end.
作为上述技术方案的改进,所述幕墙龙骨设有凹槽,所述金属面板固定边卡接于所述幕墙龙骨凹槽。 As an improvement of the above technical solution, the curtain wall keel is provided with a groove, and the fixed edge of the metal panel is clamped to the groove of the curtain wall keel.
作为上述技术方案的改进,安装于相邻两根幕墙龙骨之间的所述金属面板两两之间间隔一定距离缝隙。 As an improvement of the above-mentioned technical solution, the metal panels installed between two adjacent curtain wall keels are separated by a gap with a certain distance.
作为本发明空间曲面金属幕墙的装配方法技术方案的改进,所述金属面板为铝单板。 As an improvement of the technical solution of the assembly method of the space curved metal curtain wall of the present invention, the metal panel is an aluminum veneer.
实施本发明实施例,具有如下有益效果: Implementing the embodiment of the present invention has the following beneficial effects:
本发明的技术方案创造性的使用了三角形为单元进行计算机模拟放样以形成所设计的空间曲面形状,并根据计算机模拟放样的结果加工制作各块三角形金属面板,由于三角形金属面板一点和一线即可确定一个平面,因而只要调整三角形金属面板的一个角的高度,即可改变该三角形金属面板所形成的平面的倾斜度,多个三角形金属面板依次连接并过渡所形成的整体外形即可构成曲面,从而解决了大曲率过渡的问题,保证了整个幕墙表面为圆滑曲面的效果,实现了金属幕墙造型的美观,同时也避免了用其他形状金属面板材料现场二次加工造成的浪费。 The technical solution of the present invention creatively uses triangles as a unit to carry out computer simulation lofting to form the designed space surface shape, and process and manufacture each triangular metal panel according to the results of computer simulation lofting, because the triangle metal panel can be determined by one point and one line Therefore, as long as the height of one corner of the triangular metal panel is adjusted, the inclination of the plane formed by the triangular metal panel can be changed, and the overall shape formed by connecting and transitioning multiple triangular metal panels in sequence can form a curved surface, thus It solves the problem of large curvature transition, ensures the effect of the entire curtain wall surface as a smooth surface, realizes the aesthetic appearance of the metal curtain wall, and avoids the waste caused by secondary processing on site with other shapes of metal panel materials.
附图说明 Description of drawings
图1是本发明一种空间曲面金属幕墙的装配方法实施例中所设计的金属幕墙空间曲面形状的计算机模拟放样图; Fig. 1 is the computer simulation lofting figure of the metal curtain wall spatial curved surface shape designed in the embodiment of the assembly method of a kind of spatial curved metal curtain wall of the present invention;
图2是图1所示实施例中计算机模拟放样图的侧翼局部放大图; Fig. 2 is the partial enlarged view of the flank of the computer simulation lofting diagram in the embodiment shown in Fig. 1;
图3是图1所示实施例中一个幕墙组件的连接示意图; Fig. 3 is a connection schematic diagram of a curtain wall assembly in the embodiment shown in Fig. 1;
图4是图1所示实施例中用于金属面板安装的连接构件的主视结构示意图; Fig. 4 is a schematic diagram of the front view of the connecting member used for metal panel installation in the embodiment shown in Fig. 1;
图5是图4所示连接构件的侧向剖视图; Fig. 5 is a side sectional view of the connecting member shown in Fig. 4;
图6是图1所示实施例中连接构件与金属面板和幕墙龙骨连接的横剖结构示意图。 Fig. 6 is a cross-sectional schematic diagram of the connection between the connecting member and the metal panel and the curtain wall keel in the embodiment shown in Fig. 1 .
图7是图6所示金属面板安装于连接构件的主视结构示意图。 Fig. 7 is a front structural schematic view of the metal panel shown in Fig. 6 installed on the connecting member.
具体实施方式 detailed description
下面结合附图进一步说明本发明的具体实施方式。 The specific implementation manner of the present invention will be further described below in conjunction with the accompanying drawings.
本发明一种空间曲面金属幕墙的装配方法包括以下步骤 A method for assembling a space curved metal curtain wall of the present invention comprises the following steps
a)设计金属幕墙的空间曲面形状; a) Design the space surface shape of the metal curtain wall;
b)将上述设计好的空间曲面形状以三角形为单元进行计算机模拟放样; b) Carry out computer simulation lofting of the above-mentioned designed space surface shape with triangle as the unit;
c)根据上述计算机模拟放样的结果制作构成金属幕墙的各块三角形金属面板; c) Make each triangular metal panel that constitutes the metal curtain wall according to the results of the above-mentioned computer simulation lofting;
d)按照上述计算机模拟放样的结果进行测量放线,并将步骤c)中制作的各块三角形金属面板安装于幕墙龙骨以形成步骤a)所设计的空间曲面形状金属幕墙。 d) Carry out measurement and setting out according to the results of the above-mentioned computer simulation lofting, and install each triangular metal panel made in step c) on the keel of the curtain wall to form the space curved metal curtain wall designed in step a).
在本实施例中,金属幕墙设计为两翼对称的飘带形状,整个立面呈扭曲曲面,如图1所示,图1是本发明一种空间曲面金属幕墙的施工方法实施例中所设计的金属幕墙空间曲面形状的计算机模拟放样图,具体的,采用计算机三维软件进行模拟放样,在本发明的技术方案中,以三角形为单元进行计算机模拟放样,如图2所示,图2是图1所示实施例中计算机模拟放样图的侧翼局部放大图,以三角形为单元进行设计,可以很好的满足扭曲曲面的技术要求。之后,在计算机建模的基础上,形成对每块拼接的金属面板的大样并做成金属面板加工制作图纸,交由厂家进行加工制作。在具体安装金属面板时,同样以计算机模拟放样的结果为依据进行测量放线,并将所加工制作的金属面板安装于幕墙龙骨以形成所设计的空间曲面形状金属幕墙。在具体的施工中,按自上而下的顺序安装金属面板,由于在安装各块金属面板时,相邻金属面板之间间隔的距离难免有误差,需要在施工过程中进行监控,随时进行校对,具体的方式可以是运用全站仪、反射贴片对各工序进行三维坐标检测,将检测结果与控制点的理论坐标进行比较,对误差超限的构件进行校正,并且建立平面控制网和高程控制网运用接口技术使全站仪和计算机二者相连,建立一套完整的全站仪实时测绘系统。具体的,在进行金属面板的安装时,以六块三角形金属面板为一个幕墙组件。如图3所示,图3是图1所示实施例中一个幕墙组件的连接示意图,所述六块三角形金属面板包括第一金属面板11、第二金属面板12、第三金属面板13、第四金属面板14、第五金属面板15、第六金属面板16,其中,第一金属面板11、第三金属面板13、第五金属面板15安装于第一幕墙龙骨、第二幕墙龙骨22之间,第二金属面板12、第四金属面板14、第六金属面板16安装于第二幕墙龙骨22、第三幕墙龙骨23之间,第一金属面板11、第二金属面板12在上下方向分别位于第三金属面板13、第五金属面板15之间和第四金属面板14、第六金属面板16之间,并且所述第一金属面板11的一角111、第二金属面板的一角121相对的安装于同一根幕墙龙骨22形成各自的固定角,金属面板11和金属面板12固定角的对边分别安装于第一幕墙龙骨21和第三幕墙龙骨23形成固定边112和固定边122,而第三金属面板13、第五金属面板15的固定角均设于第一金属面板11固定边112所在的第一幕墙龙骨21,固定边则设于第一金属面板固定角111所在的第二幕墙龙骨22,所述第四金属面板14、第六金属面板16的固定角均设于第二金属面板12固定边122所在的第三幕墙龙骨23,固定边则设于第二金属面板12固定角121所在的第二幕墙龙骨22。采用这样的连接方式,三角形的金属面板以固定一点及一边的方式,结构牢固稳定,只要调整三角形一角的高度,就能调整该块金属面板的倾斜度,当多个幕墙单元连续安装在一起时,依次调整三角形金属面板的倾斜度,就可以形成不同曲率的曲面金属幕墙,从而形成美观的空间曲面造型。 In this embodiment, the metal curtain wall is designed in the shape of a symmetrical streamer with two wings, and the entire facade is a twisted curved surface, as shown in Figure 1. The computer simulation lofting diagram of the curved surface shape of the curtain wall, specifically, the computer three-dimensional software is used to simulate the lofting. In the technical solution of the present invention, the computer simulation lofting is carried out with triangles as the unit, as shown in Figure 2, which is shown in Figure 1 The partial enlarged view of the flank of the computer simulation lofting diagram shown in the embodiment is designed with a triangle as a unit, which can well meet the technical requirements of the twisted surface. After that, on the basis of computer modeling, a large sample of each spliced metal panel is formed and made into a metal panel processing drawing, which is handed over to the manufacturer for processing and production. When installing metal panels, the results of computer simulation lofting are also used as the basis for measurement and setting out, and the processed metal panels are installed on the keel of the curtain wall to form the designed space curved metal curtain wall. In the specific construction, the metal panels are installed in order from top to bottom. Since the distance between adjacent metal panels is inevitably inaccurate when installing each metal panel, it is necessary to monitor during the construction process and proofread at any time , the specific method can be to use the total station and reflective patch to detect the three-dimensional coordinates of each process, compare the detection results with the theoretical coordinates of the control points, correct the components with error exceeding the limit, and establish the plane control network and elevation The control network uses interface technology to connect the total station and the computer to establish a complete real-time surveying and mapping system for the total station. Specifically, when installing metal panels, six triangular metal panels are used as a curtain wall component. As shown in Figure 3, Figure 3 is a schematic diagram of the connection of a curtain wall assembly in the embodiment shown in Figure 1, the six triangular metal panels include a first metal panel 11, a second metal panel 12, a third metal panel 13, a Four metal panels 14, the fifth metal panel 15, and the sixth metal panel 16, wherein the first metal panel 11, the third metal panel 13, and the fifth metal panel 15 are installed between the first curtain wall keel and the second curtain wall keel 22 , the second metal panel 12, the fourth metal panel 14, and the sixth metal panel 16 are installed between the second curtain wall joist 22 and the third curtain wall joist 23, and the first metal panel 11 and the second metal panel 12 are respectively located in the vertical direction Between the third metal panel 13 and the fifth metal panel 15 and between the fourth metal panel 14 and the sixth metal panel 16, and a corner 111 of the first metal panel 11 and a corner 121 of the second metal panel are installed oppositely The same curtain wall keel 22 forms respective fixed angles, the metal panel 11 and the opposite side of the fixed angle of the metal panel 12 are respectively installed on the first curtain wall keel 21 and the third curtain wall keel 23 to form a fixed side 112 and a fixed side 122, and the third The fixed angles of the metal panel 13 and the fifth metal panel 15 are both set on the first curtain wall keel 21 where the fixed side 112 of the first metal panel 11 is located, and the fixed side is set on the second curtain wall keel 22 where the fixed angle 111 of the first metal panel is located , the fixed angles of the fourth metal panel 14 and the sixth metal panel 16 are all set on the third curtain wall keel 23 where the fixed edge 122 of the second metal panel 12 is located, and the fixed edge is set on the fixed angle 121 of the second metal panel 12 The second curtain wall joist 22. Using this connection method, the triangular metal panel is fixed at one point and one side, and the structure is firm and stable. As long as the height of one corner of the triangle is adjusted, the inclination of the metal panel can be adjusted. When multiple curtain wall units are continuously installed together , adjust the inclination of the triangular metal panels in turn to form curved metal curtain walls with different curvatures, thus forming a beautiful space surface shape.
具体的,上述金属面板采用可调节螺栓的连接构件安装于幕墙龙骨,如图4所示,图4是图1所示实施例中金属面板连接构件的结构示意图,所述连接构件为条块状,具有一个设有通孔301的呈圆环形的端部302,该圆环形端部302的厚度薄于连接构件的其他部位,优选为其他部位的厚度的一半,连接构件30还开有两个长条形连接孔303、304,之所以设置为两个长条形连接孔是为了安装牢固稳定的需要,当然也可以仅设置一个长条形连接孔,这也属于本使用新型的技术方案构思之内。前述长条形连接孔由开于连接构件前后两侧的长方形凹槽及从该凹槽贯通的通孔形成,如图5所示,图5是图4所示连接构件实施例的侧向剖视图。金属面板安装于所述连接构件的长条形连接孔,所述连接构件通过所述圆环形端部的通孔与所述幕墙龙骨螺栓连接。 Specifically, the above-mentioned metal panel is installed on the curtain wall keel by means of a connecting member with adjustable bolts, as shown in Figure 4, which is a schematic structural diagram of the connecting member of the metal panel in the embodiment shown in Figure 1, and the connecting member is in the shape of a block , has an annular end 302 provided with a through hole 301, the thickness of the annular end 302 is thinner than other parts of the connecting member, preferably half of the thickness of other parts, the connecting member 30 is also provided with Two strip-shaped connecting holes 303, 304, the reason why they are set as two strip-shaped connecting holes is to meet the needs of firm and stable installation. Of course, only one long-strip-shaped connecting hole can also be provided, which also belongs to the new technology of the present invention. within the concept of the plan. The aforementioned elongated connecting hole is formed by a rectangular groove opened on both sides of the connecting member and a through hole passing through the groove, as shown in Figure 5, which is a side sectional view of the embodiment of the connecting member shown in Figure 4 . The metal panel is installed in the elongated connecting hole of the connecting member, and the connecting member is bolted to the curtain wall keel through the through hole at the circular end.
图6是图1所示实施例中金属幕墙连接构件与金属面板和幕墙龙骨连接的剖视结构示意图,具体而言是第一金属面板11和第二金属面板12安装于第二幕墙龙骨22的示意图。如图所示,第一金属面板11固定角端的背面通过安装板10装配于连接构件30的长条形连接孔303,图7是金属面板安装于连接构件的主视结构示意图,安装板两端与金属面板螺栓连接,中间部位以螺栓连接的方式装配于连接构件30的长条形连接孔303。金属面板12按同样的方式与另一连接构件31相连接,连接构件30和连接构件31均通过其各自设有通孔的圆环形端部与同一幕墙龙骨22螺栓连接。由于金属面板通过安装板安装于连接构件的长条形连接孔,因此只要调整安装板在连接构件长条形连接孔上的位置,以及改变安装板的长度,即可将不同尺寸角度的三角形金属面板安装于连接构件,从而适应了整个金属幕墙不同位置的不同尺寸的三角形金属面板的安装需要。另外,由于连接构件的圆环形端部厚度薄于连接构件的其他部位,因而连接构件30的圆环形端部和连接构件31的圆环形端部在重叠着同时连接于幕墙龙骨22时,该两个连接构件的外表面仍然能够在同一直线上基本对齐,不会一高一低,这保证了相对的两个金属面板11和金属面板12也能对齐,而不会高低不齐。另外,还可以将该圆环形端部的通孔301内径设置的大于连接螺栓的直径,并在通孔上加设偏心垫圈,这样,通过该偏心垫圈将可能出现位置偏差的上下两个连接构件固定在幕墙龙骨时,偏心垫圈在一定程度上可以弥补两个连接构件位置偏差所产生的影响。采用这样的连接构件,通过调节将金属面板11和金属面板12安装于幕墙龙骨22的螺栓,即可改变金属面板11和金属面板12的倾斜度,这样,在金属面板11和金属面板12之间就可以形成一个一定曲率的曲面,多个幕墙组件按同样的方式安装在一起,即可过渡形成曲面的整体外形,这样的连接构件使得所连接的三角形金属面板轻易的解决了大曲率过渡的问题,保证了整个幕墙表面的圆滑曲面的效果,实现了金属幕墙造型的美观。而且,在整个铝板全部安装到位后,也还可以调节固定螺栓的松紧度,以达到理想效果。 Fig. 6 is a schematic cross-sectional structural view of the metal curtain wall connecting member, the metal panel and the curtain wall keel in the embodiment shown in Fig. 1, specifically, the first metal panel 11 and the second metal panel 12 are installed on the second curtain wall keel 22 schematic diagram. As shown in the figure, the back side of the fixed corner end of the first metal panel 11 is assembled to the elongated connection hole 303 of the connecting member 30 through the mounting plate 10. FIG. 7 is a schematic front view of the metal panel installed on the connecting member. It is bolted to the metal panel, and the middle part is assembled in the strip-shaped connecting hole 303 of the connecting member 30 in a bolted manner. The metal panel 12 is connected with another connecting member 31 in the same manner, and both the connecting member 30 and the connecting member 31 are bolted to the same curtain wall keel 22 through their respective circular ends provided with through holes. Since the metal panel is installed on the long connecting hole of the connecting member through the mounting plate, as long as the position of the mounting plate on the long connecting hole of the connecting member is adjusted, and the length of the mounting plate is changed, the triangular The panel is installed on the connecting member, thus meeting the installation needs of triangular metal panels of different sizes at different positions of the entire metal curtain wall. In addition, since the thickness of the annular end of the connecting member is thinner than other parts of the connecting member, when the annular end of the connecting member 30 and the annular end of the connecting member 31 are overlapped and connected to the curtain wall keel 22 , the outer surfaces of the two connecting members can still be substantially aligned on the same straight line without one being high and the other being low, which ensures that the two opposite metal panels 11 and 12 can also be aligned without being uneven. In addition, the inner diameter of the through hole 301 at the annular end can also be set larger than the diameter of the connecting bolt, and an eccentric washer can be added on the through hole, so that the upper and lower two connections that may have positional deviations can be connected through the eccentric washer. When the component is fixed on the curtain wall keel, the eccentric washer can compensate the influence of the position deviation of the two connecting components to a certain extent. With such a connecting member, the inclination of the metal panel 11 and the metal panel 12 can be changed by adjusting the bolts that the metal panel 11 and the metal panel 12 are installed on the curtain wall keel 22, so that between the metal panel 11 and the metal panel 12 A curved surface with a certain curvature can be formed, and multiple curtain wall components can be installed together in the same way to transition to form the overall shape of the curved surface. Such a connecting member makes it easy to solve the problem of large curvature transition for the connected triangular metal panels , to ensure the effect of the smooth curved surface of the entire curtain wall, and to realize the beauty of the metal curtain wall. Moreover, after the entire aluminum plate is installed in place, the tightness of the fixing bolts can also be adjusted to achieve the desired effect.
在该实施例中,幕墙龙骨上还设有凹槽,金属面板固定边卡接于幕墙龙骨的凹槽。另外,安装于相邻两根幕墙龙骨之间的所述金属面板两两之间间隔一定距离缝隙,优选为15mm,如第一金属面板11、第三金属面板13和第五金属面板15之间。每块金属面板固定前,应及时用预先加工好的木楔将板的横缝按所设计宽度进行板缝控制,防止在装其他板时,产生横向或竖向滑移、错缝。由于,本发明的技术方案采用三角形金属面板,其一角和该角的对边已经固定,因而三角形金属面板的安装可以牢固稳定,不需要像现有技术中的一样,为了让方形金属面板安装牢固,在方形金属面板之间的缝隙上填充玻璃胶。面板与面板之间的这种明缝结构可以取得更为良好美观的视觉效果。 In this embodiment, the curtain wall joist is also provided with a groove, and the fixed side of the metal panel is snapped into the groove of the curtain wall joist. In addition, the metal panels installed between two adjacent curtain wall keels are separated by a certain distance gap, preferably 15 mm, such as between the first metal panel 11, the third metal panel 13 and the fifth metal panel 15. . Before each metal panel is fixed, the transverse seam of the board should be controlled according to the designed width with the pre-processed wooden wedge in time to prevent horizontal or vertical slippage and wrong seam when installing other boards. Because the technical scheme of the present invention adopts a triangular metal panel, one corner and the opposite side of the corner have been fixed, so the installation of the triangular metal panel can be firm and stable, and it is not necessary to install the square metal panel firmly as in the prior art. , Fill the gap between the square metal panels with glass glue. This open seam structure between panels can achieve better and more beautiful visual effects.
在本发明实施例的技术方案中,金属面板为铝单板,当然也可以是复合铝板、蜂窝铝板或者不锈钢板等,从综合优质来看,铝单板制作的铝板幕墙不但可得到多种颜色的喷涂表面而且强度好成本低、寿命长,建议推广使用。复合铝板幕墙赶不上单层铝板,它不但具有有毒隐患,而且强度差、寿命低,建议慎重使用。蜂巢铝板作幕墙铝板缺点较多,主要是重量偏大、造价高、密封性差,因而较少使用。 In the technical solution of the embodiment of the present invention, the metal panel is an aluminum veneer, of course, it can also be a composite aluminum panel, a honeycomb aluminum panel, or a stainless steel plate. From the perspective of comprehensive quality, the aluminum panel curtain wall made of aluminum veneer can not only obtain a variety of colors The sprayed surface has good strength, low cost, and long life. It is recommended to promote its use. The composite aluminum panel curtain wall can't keep up with the single-layer aluminum panel. It not only has poisonous hidden dangers, but also has poor strength and low service life. It is recommended to use it with caution. Honeycomb aluminum panels have many disadvantages as curtain wall aluminum panels, mainly due to their large weight, high cost, and poor sealing, so they are rarely used.
本发明的技术方案创造性的使用了三角形为单元进行计算机模拟放样以形成所设计的空间曲面形状,并根据计算机模拟放样的结果加工制作各块三角形金属面板,由于三角形金属面板一点和一线即可确定一个平面,因而只要调整三角形金属面板的一个角的高度,即可改变该三角形金属面板所形成的平面的倾斜度,多个三角形金属面板依次连接并过渡所形成的整体外形即可构成曲面,从而解决了大曲率过渡的问题,保证了整个幕墙表面为圆滑曲面的效果,实现了金属幕墙造型的美观,同时也避免了用其他形状金属面板材料现场二次加工造成的浪费。 The technical solution of the present invention creatively uses triangles as a unit to carry out computer simulation lofting to form the designed space surface shape, and process and manufacture each triangular metal panel according to the results of computer simulation lofting, because the triangle metal panel can be determined by one point and one line Therefore, as long as the height of one corner of the triangular metal panel is adjusted, the inclination of the plane formed by the triangular metal panel can be changed, and the overall shape formed by connecting and transitioning multiple triangular metal panels in sequence can form a curved surface, thus It solves the problem of large curvature transition, ensures the effect of the entire curtain wall surface as a smooth surface, realizes the aesthetic appearance of the metal curtain wall, and avoids the waste caused by secondary processing on site with other shapes of metal panel materials.
以上所揭露的仅为本发明一种较佳实施例而已,当然不能以此来限定本发明之权利范围,因此依本发明权利要求所作的等同变化,仍属本发明所涵盖的范围。 The above disclosure is only a preferred embodiment of the present invention, which certainly cannot limit the scope of rights of the present invention. Therefore, equivalent changes made according to the claims of the present invention still fall within the scope of the present invention.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210396776.0A CN103774851B (en) | 2012-10-18 | 2012-10-18 | A kind of assembly method of space curved surface metal curtain wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210396776.0A CN103774851B (en) | 2012-10-18 | 2012-10-18 | A kind of assembly method of space curved surface metal curtain wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103774851A CN103774851A (en) | 2014-05-07 |
| CN103774851B true CN103774851B (en) | 2016-02-10 |
Family
ID=50567558
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201210396776.0A Expired - Fee Related CN103774851B (en) | 2012-10-18 | 2012-10-18 | A kind of assembly method of space curved surface metal curtain wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103774851B (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106884475A (en) * | 2017-04-21 | 2017-06-23 | 蔡韩琦 | A kind of method for improving building in the style of the ancients post section sets of brackets on top of the columns installation qualification rate |
| CN109900121A (en) * | 2017-12-07 | 2019-06-18 | 中国二十冶集团有限公司 | Annealing furnace light-weight brick furnace wall jumps storehouse masonry method |
| CN108678245B (en) * | 2018-06-07 | 2020-06-05 | 金刚幕墙集团有限公司 | Unit type curved surface aluminum plate curtain wall system |
| CN110821020A (en) * | 2019-11-07 | 2020-02-21 | 湖北麻一建设有限公司 | Construction method of irregular double-curved-surface bamboo-aluminum composite board |
| CN110821061B (en) * | 2019-12-11 | 2025-01-03 | 沈阳远大铝业工程有限公司 | Curtain wall shading system |
| CN111910804B (en) * | 2020-06-28 | 2021-12-07 | 上海市建筑装饰工程集团有限公司 | Three-dimensional space positioning method for special-shaped curtain wall keel |
| CN112814383A (en) * | 2021-01-06 | 2021-05-18 | 上海建工一建集团有限公司 | Construction method of double-layer roof curtain wall structure |
| CN116180971B (en) * | 2022-04-25 | 2025-08-22 | 上海市建筑装饰工程集团有限公司 | A special-shaped architectural aluminum plate and aluminum plate design and installation method |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH09225053A (en) * | 1996-02-28 | 1997-09-02 | Shin Nikkei Co Ltd | Emergency entrances such as sashes and curtain walls using tempered glass and tempered glass unit used for this |
| CN101560802A (en) * | 2009-05-22 | 2009-10-21 | 上海江河幕墙系统工程有限公司 | Elastic forming method for panel of curtain wall and curved-surface building curtain wall |
| EP2112287A1 (en) * | 2008-04-24 | 2009-10-28 | Schüco International KG | Façade or skylight for a building and connection element for same |
| CN102535844A (en) * | 2012-02-10 | 2012-07-04 | 中国建筑第八工程局有限公司 | Construction method for spherical curved surface stainless steel curtain wall |
-
2012
- 2012-10-18 CN CN201210396776.0A patent/CN103774851B/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH09225053A (en) * | 1996-02-28 | 1997-09-02 | Shin Nikkei Co Ltd | Emergency entrances such as sashes and curtain walls using tempered glass and tempered glass unit used for this |
| EP2112287A1 (en) * | 2008-04-24 | 2009-10-28 | Schüco International KG | Façade or skylight for a building and connection element for same |
| CN101560802A (en) * | 2009-05-22 | 2009-10-21 | 上海江河幕墙系统工程有限公司 | Elastic forming method for panel of curtain wall and curved-surface building curtain wall |
| CN102535844A (en) * | 2012-02-10 | 2012-07-04 | 中国建筑第八工程局有限公司 | Construction method for spherical curved surface stainless steel curtain wall |
Non-Patent Citations (2)
| Title |
|---|
| 双曲弧形纯铝板内幕墙的施工;陈苏敏;《浙江建筑》;20091130;第26卷(第11期);第50页第1-2节,第51-52页第3节 * |
| 异型壳体结构的外幕墙施工技术;周晓莉;《建筑施工》;20110430;第33卷(第4期);第307页 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103774851A (en) | 2014-05-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103774851A (en) | Assembling method of spatial curve-surface metal curtain wall | |
| CN104912340B (en) | Construction method for double-curve triangular aluminum plate unit type hanging ceiling | |
| CN205604464U (en) | Exterior wall cladding antidetonation is connecting piece down | |
| CN105804298B (en) | Construction method of honeycomb-shaped convex irregular curtain wall | |
| CN115949173B (en) | A super-high altitude large-area ceiling structure and construction method | |
| CN108678245A (en) | A kind of modular curved surface aluminum plate curtain wall system | |
| CN111910802A (en) | Connecting device of complicated special-shaped curtain wall structure | |
| CN114232997A (en) | Construction method of arc-shaped aluminum plate curtain wall with staggered and laminated folding lines for arc-shaped stage exterior wall decoration | |
| CN208056395U (en) | Unit assembled integration facing light steel keel partition structure | |
| CN105064588B (en) | A kind of completely newly compound furred ceiling and its installation method | |
| CN114232885A (en) | Connection structure and installation method of ceiling board and wall board of integral bathroom | |
| CN209397814U (en) | A snap-fit open keel steel plate ceiling structure | |
| CN204059799U (en) | A kind of installation constitution of railing angular adjustment | |
| CN105155682A (en) | Method for forming circular and square pipe transition joints | |
| CN219011624U (en) | Curtain wall keel installation node device adapting to special-shaped main body structure | |
| CN119754464B (en) | Installation structure and construction method of stone curtain wall | |
| CN203238991U (en) | Clean operating room auxiliary room capable of being quickly assembled in insertion mode | |
| CN203684562U (en) | Anti-crack suspended ceiling structure | |
| CN216920972U (en) | Connection structure of furred ceiling board and wallboard of whole bathroom | |
| CN119825146A (en) | Construction method of outer decorative frame of high-altitude special-shaped large-span curtain wall | |
| CN219509030U (en) | Assembled square steel column wall base layer assembly | |
| CN111894222A (en) | Modular structure design and combination of large-area multi-curved complex artistic facing of indoor theater | |
| CN111910803A (en) | Complicated special-shaped curtain wall structure | |
| CN214498148U (en) | Wall external corner ceramic tile mounting structure | |
| CN103352527B (en) | For the steel keel frame that the staggered floor of curtain wall is installed |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 510060 building, No. three, No. 11, 6 Avenue, Guangzhou, Yuexiu District, Guangdong Co-patentee after: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd. Patentee after: Guangzhou Architectural Decoration Group Co.,Ltd. Address before: 510060 building, No. three, No. 11, 6 Avenue, Guangzhou, Yuexiu District, Guangdong Co-patentee before: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd. Patentee before: GUANGZHOU ALUMINUM DECORATION ENGINEERING CO.,LTD. |
|
| CP01 | Change in the name or title of a patent holder | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160210 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |