CN103741794B - High-strength bolt hole group steel structure member makes pre-assembly method - Google Patents

High-strength bolt hole group steel structure member makes pre-assembly method Download PDF

Info

Publication number
CN103741794B
CN103741794B CN201410015581.6A CN201410015581A CN103741794B CN 103741794 B CN103741794 B CN 103741794B CN 201410015581 A CN201410015581 A CN 201410015581A CN 103741794 B CN103741794 B CN 103741794B
Authority
CN
China
Prior art keywords
bracket
steel
main part
column main
girder steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410015581.6A
Other languages
Chinese (zh)
Other versions
CN103741794A (en
Inventor
陈武强
吴偲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Yiye Steel Structure Co Ltd
Original Assignee
Wuhan Yiye Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Yiye Steel Structure Co Ltd filed Critical Wuhan Yiye Steel Structure Co Ltd
Priority to CN201410015581.6A priority Critical patent/CN103741794B/en
Publication of CN103741794A publication Critical patent/CN103741794A/en
Application granted granted Critical
Publication of CN103741794B publication Critical patent/CN103741794B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of High-strength bolt hole group steel structure member and make pre-assembly method, comprise step: be placed on pre-assembling platform by straight for steel column main part; By girder steel and bracket blanking as a whole, then utilize bore template to hole, then cut girder steel and bracket, then connect girder steel with bolt and bracket forms girder steel assembly; To support bracket blanking as a whole, and then utilize bore template to hole, then cutting supports and bracket, then connect support with bolt and form supporting component with bracket; According to arrangement diagram, steel column main part and girder steel assembly and supporting component are pre-installed, measure the physical dimension of prepackage errorless after, carry out welding of steel column main part and bracket; Remove bracket and girder steel, bolt between bracket and support.The present invention can improve the perforated percentage of High-strength bolt hole group, and minimizing is done over again, and meanwhile, can also improve the make efficiency of High-strength bolt hole group steel structure member, plays very large positive role to raising labour productivity and reducing energy consumption.

Description

High-strength bolt hole group steel structure member makes pre-assembly method
Technical field
The present invention is specifically related to a kind of High-strength bolt hole group steel structure member and makes pre-assembly method.
Background technology
The steel structure member that frequent design connects with High-strength bolt hole group in power plant engineering, because High-strength bolt hole is more, the perforated percentage in hole requires high, must pre-install.The method of the steel structure member prepackage of current employing mostly is, first make single-piece member, single-piece member is welded after making again, finally carry out the prepackage of all components, the method complicated process, and due to people's job number hole precision be difficult to ensure, accumulative increasing when single-piece member fabrication error is in the end installed, product quality can not get controlling, and bolt often occurs during installation and wears to pass by, need repair in time, and the quality after repairing also is difficult to ensure, therefore the perforated percentage of High-strength bolt hole is low, and after prepackage, rework rate is high, and production efficiency is low.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of High-strength bolt hole group steel structure member to make pre-assembly method, it can improve the perforated percentage of High-strength bolt hole group, minimizing is done over again, simultaneously, the make efficiency of High-strength bolt hole group steel structure member can also be improved, play very large positive role to raising labour productivity and reducing energy consumption.
The technical solution adopted for the present invention to solve the technical problems is:
High-strength bolt hole group steel structure member makes pre-assembly method, and described steel structure member comprises steel column main part, bracket, girder steel and support, and the method comprises the following steps:
S1, be placed on pre-assembling platform by straight for steel column main part;
S2, the bracket blanking as a whole that girder steel and its two ends are connected with steel column main part, then bore template is utilized to carry out the boring of bolt hole group in the junction of girder steel and bracket, again according to drawing requirement cutting girder steel and bracket, the girder steel after then connecting cutting with bolt and bracket form girder steel assembly;
S3, the bracket blanking be as a whole connected with steel column main part with its two ends will be supported, then bore template is utilized to support the boring carrying out bolt hole group with the junction of bracket, support and bracket according to drawing requirement cutting, the support after then connecting cutting with bolt and bracket form supporting component again;
S4, according to arrangement diagram, steel column main part and girder steel assembly and supporting component to be pre-installed, measure the physical dimension of prepackage errorless after, carry out welding of steel column main part and bracket;
S5, after the bracket of all absolute altitudes has welded with steel column main part, bracket and girder steel, bolt between bracket and support are removed.
By technique scheme, step S1 is specially: more piece steel column main part is divided into two rows are straight to be placed on pre-assembling platform, the gap of reserved 5mm between the adjacent steel column main part of every two joint, and the spacing between two row's steel column main parts are fixed by behind designing requirement location.
By technique scheme, described pre-assembling platform is made by H profile steel, and it is highly greater than the height of bracket, and length and width are greater than length and the width of steel column main part.
By technique scheme, described bracket, girder steel and support are made by H profile steel.
The beneficial effect that the present invention produces is: by the bracket of each junction of steel column main part and girder steel, bracket and support Whole blanking respectively, and the boring of High-strength bolt hole group is carried out by bore template, can effectively ensure that aperture size is consistent, and then improve the perforated percentage of high-strength bolt, minimizing is done over again, simultaneously, assemble while can realizing steel structure member by the method, weld simultaneously, improve make efficiency, play very large positive role to raising labour productivity and reducing energy consumption.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described, in accompanying drawing:
Fig. 1 is the top view that steel column main part is placed on pre-assembling platform;
Fig. 2 is the schematic diagram of bracket and girder steel Whole blanking;
Fig. 3 is the schematic diagram that bracket and girder steel entirety are holed;
Fig. 4 is the schematic diagram of bracket and girder steel integral cutting;
Fig. 5 is the schematic diagram that bracket and girder steel entirety are assembled;
Fig. 6 is the prepackage schematic diagram of the embodiment of the present invention.
Wherein, 1-steel column main part, the pre-assembling platform of 2-, 3a-girder steel bracket, 3b-support bracket, 4-girder steel, 5-support, 6-bolt hole group, 7-line of cut, 8-bore template, 9-bolt.
Detailed description of the invention
In order to make object of the present invention, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
As shown in Fig. 1 ~ Fig. 6, High-strength bolt hole group steel structure member makes pre-assembly method, steel structure member comprises steel column main part 1, bracket, girder steel 4 and supports 5, be convenient to distinguish, the bracket be connected with girder steel is girder steel bracket 3a, with the bracket of support and connection for making bracket 3b, the method comprises the following steps:
S1, be placed on pre-assembling platform 2 by straight for steel column main part 1, be specially, more piece steel column main part 1 is divided into two rows are straight to be placed on pre-assembling platform 2, pre-assembling platform 2 is made by H profile steel, it is highly greater than the height of bracket 3, length and width are greater than length and the width of steel column main part 1, steel column main part 1 is also made by H profile steel, between the adjacent steel column main part 1 of every two joint, the gap of reserved 5mm is so that weld when the later stage installs, spacing between two row's steel column main parts 1 is fixed by behind designing requirement location, as shown in Figure 1, the present embodiment is chosen often row three joint steel column main parts and is introduced, and the joint number of steel column main part is relevant with the requirement of steel work Project design, with this method without any relation,
S2, as shown in Fig. 2 ~ Fig. 5, the girder steel bracket 3a blanking as a whole that girder steel 4 and its two ends are connected with steel column main part 1, select H profile steel as making material, the length that the length that the length of this H profile steel equals girder steel 4 adds two girder steel bracket 3a adds cutting gap, then bore template 8 is utilized to carry out the boring of bolt hole group 6 in girder steel 4 and the junction of girder steel bracket 3a, in H profile steel, line of cut 7 is marked again according to drawing requirement, girder steel 4 and girder steel bracket 3a is cut along line of cut 7, then the girder steel 4 after connecting cutting with bolt 9 and girder steel bracket 3a form girder steel assembly, can be that to connect girder steel 4 by junction plate fastening by bolt 9 with girder steel bracket 3a,
S3, support the same S2 of manufacturing process of 5, just the H profile steel length selected of support 5 is different from girder steel, be specially, with reference to Fig. 2 ~ Fig. 5, the support bracket 3b blanking as a whole that support 5 and its two ends are connected with steel column main part 1, select H profile steel as making material, the length that the length of this H profile steel equals support 5 adds two length supporting bracket 3b and adds cutting gap, then bore template 8 is utilized to carry out the boring of bolt hole group 6 in support 5 and the junction supporting bracket 3b, in this H profile steel, line of cut 7 is marked again according to drawing requirement, cut support 5 along line of cut 7 and support bracket 3b, then the support 5 after connecting cutting with bolt 9 forms supporting component with support bracket 3b, can be connect support 5 by junction plate and support bracket 3b and fastening by bolt 9,
S4, as shown in Figure 6, pre-installs steel column main part 1 and girder steel assembly and supporting component according to arrangement diagram, measure the physical dimension of prepackage errorless after, carry out steel column main part 1 and girder steel bracket 3a and support welding of bracket 3b;
S5, the like, after the bracket of all absolute altitudes has welded with steel column main part 1, remove girder steel bracket 3a and girder steel 4, support bolt 9 between bracket 3b and support 5, carry out outward appearance process again, to often save bracket that steel column main part welds with on it as a finished product member, the girder steel disassembled and supporting respectively as a finished product member.
Should be understood that, for those of ordinary skills, can be improved according to the above description or convert, and all these improve and convert the protection domain that all should belong to claims of the present invention.

Claims (2)

1. High-strength bolt hole group steel structure member makes a pre-assembly method, and described steel structure member comprises steel column main part, bracket, girder steel and support, it is characterized in that: the method comprises the following steps:
S1, be placed on pre-assembling platform by straight for steel column main part, more piece steel column main part is divided into two rows are straight to be placed on pre-assembling platform, the gap of reserved 5mm between the adjacent steel column main part of every two joint, spacing between two row's steel column main parts is fixed by behind designing requirement location, described pre-assembling platform is made by H profile steel, it is highly greater than the height of bracket, and length and width are greater than length and the width of steel column main part;
S2, the bracket blanking as a whole that girder steel and its two ends are connected with steel column main part, then bore template is utilized to carry out the boring of bolt hole group in the junction of girder steel and bracket, again according to drawing requirement cutting girder steel and bracket, the girder steel after then connecting cutting with bolt and bracket form girder steel assembly;
S3, the bracket blanking be as a whole connected with steel column main part with its two ends will be supported, then bore template is utilized to support the boring carrying out bolt hole group with the junction of bracket, support and bracket according to drawing requirement cutting, the support after then connecting cutting with bolt and bracket form supporting component again;
S4, according to arrangement diagram, steel column main part and girder steel assembly and supporting component to be pre-installed, measure the physical dimension of prepackage errorless after, carry out welding of steel column main part and bracket;
S5, after the bracket of all absolute altitudes has welded with steel column main part, bracket and girder steel, bolt between bracket and support are removed.
2. method according to claim 1, is characterized in that: described bracket, girder steel and support are made by H profile steel.
CN201410015581.6A 2014-01-14 2014-01-14 High-strength bolt hole group steel structure member makes pre-assembly method Expired - Fee Related CN103741794B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410015581.6A CN103741794B (en) 2014-01-14 2014-01-14 High-strength bolt hole group steel structure member makes pre-assembly method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410015581.6A CN103741794B (en) 2014-01-14 2014-01-14 High-strength bolt hole group steel structure member makes pre-assembly method

Publications (2)

Publication Number Publication Date
CN103741794A CN103741794A (en) 2014-04-23
CN103741794B true CN103741794B (en) 2015-09-16

Family

ID=50498853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410015581.6A Expired - Fee Related CN103741794B (en) 2014-01-14 2014-01-14 High-strength bolt hole group steel structure member makes pre-assembly method

Country Status (1)

Country Link
CN (1) CN103741794B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107023744A (en) * 2016-02-01 2017-08-08 五冶集团上海有限公司 The gap processing method in technique steel construction hound two ends end plate connection face
CN106514151B (en) * 2016-12-06 2018-12-11 大连船舶重工集团装备制造有限公司 It is a kind of to guarantee porous group's latching mechanism part with the process of porosity
CN107283130B (en) * 2017-08-07 2019-06-04 沈阳宝通门业有限公司 The integrated manufacturing method and system of hangar door or aircraft maintenance depressed place frame structure
CN111496471B (en) * 2020-04-07 2022-03-25 太仓红马机械设备制造有限公司 Preparation process of high-strength anti-fatigue steel beam for garbage incinerator
CN112302171B (en) * 2020-10-28 2021-09-21 山东方大杭萧钢构科技有限公司 Steel structure pre-assembly method
CN113967822A (en) * 2021-10-25 2022-01-25 石瀚太 Full-assembly type steel structure self-propelled parking building node hole group machining method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100189216B1 (en) * 1996-11-14 1999-06-01 소광민 Sectional steel house and the executing method thereof
JP2000054635A (en) * 1998-08-06 2000-02-22 Nobutaka Kondo Attaching method for support member in h-steel beam joint spot and its support member
CN101862942B (en) * 2010-06-25 2011-11-09 鞍山东方钢结构有限公司 Production process method of pipe whip restraint steel structure of main power house of nuclear power station conventional island
CN202934161U (en) * 2012-09-17 2013-05-15 江苏中泰桥梁钢构股份有限公司 Drilling template
CN103498509A (en) * 2013-09-25 2014-01-08 张跃 Steel structure combined column system and connecting method thereof

Also Published As

Publication number Publication date
CN103741794A (en) 2014-04-23

Similar Documents

Publication Publication Date Title
CN103741794B (en) High-strength bolt hole group steel structure member makes pre-assembly method
CN204524692U (en) Precision controlling frock
CN105269253A (en) Manufacturing method for steel-structure box beam/box column
CN102962593B (en) The assembling and welding process that the stage gets involved general part founds in group
CN205111169U (en) Stereo garage comb plate preparation frock
CN103567722A (en) Mounting rack assembling and welding method
CN202527885U (en) Pedestal for manufacturing framework of subway pipe piece
CN205200770U (en) Semi -automatic flame cutting machine frock that runs without interruption
CN203973114U (en) The solid welder of a kind of inner supporting type anchor point
CN204912992U (en) Circuit board welding fixture
CN202338746U (en) Interchangeable docking monitoring rod
CN202726365U (en) Connecting lug installing and welding device for rack section of derrick
CN202388161U (en) Flip-over type cab front-low edge welding fixture
CN202639671U (en) Welding device for tower foot of transmission line iron tower
CN204771270U (en) Activity type assembly aid
CN205859372U (en) Electromechanical pipeline casing support and electromechanical pipeline protection device
CN203806972U (en) Connection structure of crane beam and steel column
CN204739046U (en) T type tower section of thick bamboo flange structure
CN202079364U (en) Assembly locator for inner clamping sleeve compensation section of gasification furnace
CN103850279A (en) Framework type bucket rod and excavator
CN203834661U (en) Steel-structure supporting frame
CN211638803U (en) Welding positioning tool for frame structure of fruit and vegetable garbage treatment equipment
CN203599735U (en) Multifunctional support assembling die
CN204031585U (en) The circuit board of brushless direct current motor controller
CN203945966U (en) A kind of brand new mounting bracket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant