CN103711115A CN201310622646.9A CN201310622646A CN103711115A CN 103711115 A CN103711115 A CN 103711115A CN 201310622646 A CN201310622646 A CN 201310622646A CN 103711115 A CN103711115 A CN 103711115A
Authority
CN
China
Prior art keywords
water
rock
fetching head
head
water taking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310622646.9A
Other languages
Chinese (zh)
Other versions
CN103711115B (en
Inventor
刘显群
吴建国
沈又幸
钱海平
李琪
童建国
艾月平
黄建武
杨涛
邱纪龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Energy source in China construction group Zhejiang Province Power Design Institute Co., Ltd
Original Assignee
Zhejiang Electric Power Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Electric Power Design Institute filed Critical Zhejiang Electric Power Design Institute
Priority to CN201310622646.9A priority Critical patent/CN103711115B/en
Publication of CN103711115A publication Critical patent/CN103711115A/en
Application granted granted Critical
Publication of CN103711115B publication Critical patent/CN103711115B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a foundation reinforcement and connector combination of an integral floating water taking head and a construction method. The foundation reinforcement and connector combination comprises a water taking head foundation. The water taking head foundation is reinforced by the aid of rock-socketed cast-in-place piles and is excavated, and rubble is filled back into the water taking head foundation; pile sleeves are arranged at the bottom of the water taking head, underwater concrete is filled into gaps of the pile sleeves of the rock-socketed cast-in-place piles via reserved grout pipes, and the rock-socketed cast-in-place piles are nested in the water taking head. The construction method includes a, reasonably arranging the rock-socketed cast-in-place piles according to actual conditions of the water taking head and computation results and reinforcing the foundation; b, excavating a foundation region of the water taking head and filling the rubble into the foundation region; c, arranging the pile sleeves for sleeving the rock-socketed cast-in-place piles at the bottom of the water taking head and reserving the grout pipes when the water taking head is manufactured; d, temporarily plugging the reserved grout pipes of the water taking head; e, filling the underwater concrete from the tops of the reserved grout pipes into the nesting gaps of the rock-socketed cast-in-place piles nested in the water taking head.

Description

A kind of ground stabilization of whole transportation by driving formula water-fetching head and joint and construction method
Technical field
What the present invention relates to is a kind of ground stabilization and joint and construction method at the whole transportation by driving formula of complex environment coastal power plant water-fetching head, belongs to power generation plant technology field.
Background technology
Deposits in Eastern Coastal China economic development is at present rapid, and power demand is large, the requirement improving in order to meet this area economic development and people's living standard, and country often needs every year to drop into huge fund and is used for building large-size thermal power plant.Large-size thermal power plant addressing should take into full account convenience and the economy of Coal Transport, taking and discharging, also should consider to save the factors such as soil and environmental protection simultaneously.Therefore numerous large-size thermal power plants are generally arranged in seashore.Seashore power plant generally adopts once-though cooling mode, by the forms such as water-fetching head are set, from deep trouth, fetches water.As better in water-fetching head foundation condition, take the direct transportation by driving of whole transportation by driving formula water intake to put in place and sinking is at present conventional a kind of mode.If water-fetching head foundation condition is complicated, and subaqueous work environment is severe, adopt routinely steel drum cofferdam to construct, but the method engineering quantity is large, long in time limit, and there is certain risk.
Take certain power plant in Zhejiang water-fetching head as example, waters of living in is marine outfall, Qiantang River briny environment, complex geologic conditions (the weak mud in top, rock stratum, the bottom end face gradient is precipitous), it is very large that construction is subject to Qiantang River tidal bore function influence, needs the factor of consideration very complicated.Design suitable intake strucure form and form of construction work, be no matter to engineering, to meet that design water intaking requires, structure durability requirement and safety of structure requirement, or construct enforcement smoothly, construction quality and can construction speed be guaranteed, can construction costs controlledly be all very important.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, and provide a kind of safe and reliable, facilitate feasible, can complete the installation of whole transportation by driving formula water intake, meet engineering safety and schedule requirement, reduce ground stabilization and joint and the construction method of the whole transportation by driving formula of the coastal power plant water-fetching head of construction costs.
The object of the invention is to complete by following technical solution: ground stabilization and the joint of the whole transportation by driving formula of coastal power plant water-fetching head, it comprises: one adopts piles set into rock to carry out the water-fetching head ground of consolidation process, described water-fetching head foundation dredging backfill have piece stone leveling, and the piles set into rock arranging on the ground of described water-fetching head, the suitable height of backfill piece stone is risen out in its stake.
The bottom of described water-fetching head is provided with for being nested with the pile protection of piles set into rock, and it is consistent that the height of described pile protection and described rock-socketed bored concrete pile are risen out backfill piece stone height; Described water-fetching head also pours into by reserved grout pipe the space that underwater concrete is nested with the pile protection of piles set into rock by water-fetching head and fills from top, thereby water-fetching head and piles set into rock are consolidated.
The ground stabilization of the whole transportation by driving formula of coastal power plant water-fetching head and a construction method for joint as mentioned above, the method comprises the steps:
A: according to water-fetching head actual conditions and result of calculation, rational piles set into rock is set and carries out ground stabilization;
B: the foundation region of water-fetching head excavates and backfill piece stone, and the rock-socketed bored concrete pile on water-fetching head ground is risen out the suitable height of backfill piece stone;
C: when water-fetching head is made, bottom is provided for being nested with the pile protection of piles set into rock, it is consistent that the height of its pile protection and described rock-socketed bored concrete pile are risen out backfill piece stone height; Reserved grout pipe when water-fetching head is made;
D: the reserved grout pipe of water-fetching head carries out temporary plugging, water-fetching head transportation by driving is put in place and sinking after, water-fetching head is enclosed within on piles set into rock;
E: fill in the reserved grout pipe arranging by the water-fetching head space that water-fetching head is nested with to the pile protection of piles set into rock of being in the milk from top, thereby water-fetching head and piles set into rock are consolidated.
Compared with prior art, advantage of the present invention is: from overall plan, adopt whole transportation by driving formula water intake to reduce construction costs, shortened the duration.Under whole transportation by driving formula water intake scheme, take the present invention, solved the difficult problem that the ground stabilization of complex environment water-fetching head and joint are processed.According to of the present invention, water-fetching head sinking does not need too high precision, has reduced difficulty of construction, has guaranteed can complete smoothly the sinking of water-fetching head under adverse circumstances.Underwater grouting had both guaranteed reliable be connected of water-fetching head with stake, made again easy construction feasible.
Whole transportation by driving formula water-fetching head of the present invention has the features such as cost is low, the construction period is short, and risk is controlled.
Accompanying drawing explanation
Fig. 1 is structural plan of the present invention schematic diagram.
Fig. 2 is structural profile schematic diagram of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing, the present invention is done to detailed introduction: shown in Fig. 1,2, ground stabilization and the joint of the whole transportation by driving formula of coastal power plant of the present invention water-fetching head, it comprises: one adopts piles set into rock to carry out the water-fetching head ground 1 of consolidation process, described water-fetching head ground 1 excavation backfill have piece stone 2, and the piles set into rock 3 arranging on the ground 1 of described water-fetching head.
Described water-fetching head 4 is provided with for being placed on the pile protection 5 on piles set into rock 3, described water-fetching head 4 also pours into by reserved grout pipe 6 space that underwater concrete is nested with the pile protection 5 of piles set into rock by water-fetching head and fills, thereby water-fetching head 4 and piles set into rock 3 are consolidated.
The ground stabilization of the whole transportation by driving formula of coastal power plant water-fetching head and a construction method for joint as mentioned above, the method comprises the steps:
A: according to water-fetching head actual conditions and result of calculation, rational piles set into rock is set and carries out ground stabilization;
B: the foundation region of water-fetching head excavates and backfill piece stone, and the rock-socketed bored concrete pile on water-fetching head ground is risen out the suitable height of backfill piece stone;
C: when water-fetching head is made, bottom is provided for being nested with the pile protection of piles set into rock, it is consistent that the height of its pile protection and described rock-socketed bored concrete pile are risen out backfill piece stone height; Reserved grout pipe when water-fetching head is made;
D: the reserved grout pipe of water-fetching head carries out temporary plugging, water-fetching head transportation by driving is put in place and sinking after, water-fetching head is enclosed within on piles set into rock;
E: fill in the reserved grout pipe arranging by the water-fetching head space that water-fetching head is nested with to the hole of piles set into rock of being in the milk from top, thereby water-fetching head and piles set into rock are consolidated.
Embodiment:
Certain power plant in Zhejiang engineering is usingd Seawater of Hangzhou Bay as circulating cooling water source.Hangzhou Wan is strong tidal sea world-famous gulf.At the incoming tide, tidal wave imports into from off-lying sea, has two bursts of trends to the east of the mouth of Kingsoft, and rise and rise with northeast in the southeast, to the north of five dishes, crosses, and Ganpu directly becomes along Hangzhou Wan north side.During ebb tide, marine site, the Hangzhou Wan southeast first falls, and impels Hangzhou Wan fluctuation tide main shaft for consistent.General flood strength is large, and half tide mean flow rate is 1.16m/s, and actual measurement Peak Flow Rate reaches 2.45m/s.The point bar in six li of gulfs has respectively suitable, a counterclockwise backflow to occur in flood tide intermediary and later stages and ebb tide later stage.Top, stratum, water-fetching head position is mud, and bottom is rock stratum, and the rock stratum face gradient is precipitous, and the gradient is greater than 60 °.It is very large that water-fetching head construction is subject to Qiantang River tidal bore function influence, and foundation condition is complicated.For guaranteeing that water-fetching head ground stabilization and joint are processed to construct, complete smoothly, take the specific embodiment as follows:
The first step: according to water-fetching head actual conditions and result of calculation, rational piles set into rock is set and carries out ground stabilization;
Second step: water-fetching head foundation region excavates and backfill piece stone washes away problem to solve, and water-fetching head rock-socketed bored concrete pile is risen out the suitable height of backfill piece stone;
The 3rd step: when water-fetching head is made, bottom is provided for being nested with the pile protection of piles set into rock, it is consistent that the height of its pile protection and described rock-socketed bored concrete pile are risen out backfill piece stone height; Reserved grout pipe when water-fetching head is made;
The 4th step: the reserved grout pipe of water-fetching head carries out temporary plugging, water-fetching head transportation by driving is put in place and sinking after, water-fetching head is enclosed within on piles set into rock;
The 5th step: fill in the reserved grout pipe arranging by the water-fetching head space that water-fetching head is nested with to the pile protection of piles set into rock of being in the milk from top, thereby water-fetching head and piles set into rock are consolidated.
According to this programme, under adverse circumstances, can complete smoothly sinking and the installation of water-fetching head, meet engineering safety and schedule requirement, reduce construction costs.

Claims (3)

1. ground stabilization and the joint of a whole transportation by driving formula water-fetching head, it comprises: one adopts piles set into rock to carry out the water-fetching head ground of consolidation process, it is characterized in that described water-fetching head foundation dredging backfill have piece stone, and the piles set into rock arranging on the ground of described water-fetching head, the suitable height of backfill piece stone is risen out in its stake.
2. ground stabilization and the joint of whole transportation by driving formula water-fetching head according to claim 1, the bottom that it is characterized in that described water-fetching head is provided with for being nested with the encapsulation of piles set into rock, described water-fetching head also pours into by reserved grout pipe the space that underwater concrete is nested with the encapsulation of piles set into rock by water-fetching head and fills, thereby water-fetching head and piles set into rock are consolidated.
3. the ground stabilization of whole transportation by driving formula water-fetching head and a construction method for joint as claimed in claim 1 or 2, the method comprises the steps:
A: according to water-fetching head actual conditions and result of calculation, rational piles set into rock is set and carries out ground stabilization;
B: the foundation region of water-fetching head excavates and backfill piece stone, and the rock-socketed bored concrete pile on water-fetching head ground is risen out the suitable height of backfill piece stone;
C: when water-fetching head is made, bottom is provided for being nested with the encapsulation of piles set into rock, it is consistent that the height of its encapsulation and described rock-socketed bored concrete pile are risen out backfill piece stone height; Reserved grout pipe when water-fetching head is made;
D: the reserved grout pipe of water-fetching head carries out temporary plugging, water-fetching head transportation by driving is put in place and sinking after, water-fetching head is enclosed within on piles set into rock;
E: fill in the reserved grout pipe arranging by the water-fetching head space that water-fetching head is nested with to the encapsulation of piles set into rock of being in the milk from top, thereby water-fetching head and piles set into rock are consolidated.
CN201310622646.9A 2013-11-30 2013-11-30 A kind of ground stabilization of overall transportation by driving formula water-fetching head and joint and construction method Active CN103711115B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310622646.9A CN103711115B (en) 2013-11-30 2013-11-30 A kind of ground stabilization of overall transportation by driving formula water-fetching head and joint and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310622646.9A CN103711115B (en) 2013-11-30 2013-11-30 A kind of ground stabilization of overall transportation by driving formula water-fetching head and joint and construction method

Publications (2)

Publication Number Publication Date
CN103711115A true CN103711115A (en) 2014-04-09
CN103711115B CN103711115B (en) 2016-01-20

Family

ID=50404435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310622646.9A Active CN103711115B (en) 2013-11-30 2013-11-30 A kind of ground stabilization of overall transportation by driving formula water-fetching head and joint and construction method

Country Status (1)

Country Link
CN (1) CN103711115B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104074234A (en) * 2014-07-16 2014-10-01 中国能源建设集团广东省电力设计研究院 Inland water collecting opening structure of power plant circulating water system and construction method thereof
CN110258725A (en) * 2019-05-13 2019-09-20 中国华冶科工集团有限公司 Water works water tank fabrication and installation method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102086634A (en) * 2011-01-07 2011-06-08 广东省电力设计研究院 Marine underwater assembled water intake and construction method thereof
JP2011220108A (en) * 2011-07-06 2011-11-04 Railway Technical Research Institute Embankment construction method on soft ground and embankment structure thereof
GB2497274A (en) * 2011-11-24 2013-06-12 Aspin Foundations Ltd Vehicle station platform system
CN203213136U (en) * 2013-01-24 2013-09-25 中交公路规划设计院有限公司 Caisson and pile combined foundation of consolidated subsoil
CN203684205U (en) * 2013-11-30 2014-07-02 浙江省电力设计院 Foundation reinforcement and joint for integral floating intake head

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102086634A (en) * 2011-01-07 2011-06-08 广东省电力设计研究院 Marine underwater assembled water intake and construction method thereof
JP2011220108A (en) * 2011-07-06 2011-11-04 Railway Technical Research Institute Embankment construction method on soft ground and embankment structure thereof
GB2497274A (en) * 2011-11-24 2013-06-12 Aspin Foundations Ltd Vehicle station platform system
CN203213136U (en) * 2013-01-24 2013-09-25 中交公路规划设计院有限公司 Caisson and pile combined foundation of consolidated subsoil
CN203684205U (en) * 2013-11-30 2014-07-02 浙江省电力设计院 Foundation reinforcement and joint for integral floating intake head

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104074234A (en) * 2014-07-16 2014-10-01 中国能源建设集团广东省电力设计研究院 Inland water collecting opening structure of power plant circulating water system and construction method thereof
CN104074234B (en) * 2014-07-16 2016-02-03 中国能源建设集团广东省电力设计研究院有限公司 The interior river intake structure of electric power plant circulating water system and construction method thereof
CN110258725A (en) * 2019-05-13 2019-09-20 中国华冶科工集团有限公司 Water works water tank fabrication and installation method

Also Published As

Publication number Publication date
CN103711115B (en) 2016-01-20

Similar Documents

Publication Publication Date Title
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN104631475A (en) Safe and fast construction method of down-traversing river shallow depth bored tunnel
CN101787698B (en) Anti-corrosion inclusion bored concrete pile used for saline soil foundation and construction method thereof
CN102345300A (en) Construction method of underground structures of seacoasts and artificial islands
CN104805854A (en) Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN110512593A (en) Reclaimation area ultra-deep ground-connecting-wall structure and its construction method
CN109281313A (en) A kind of Prefabricated composite box diaphram wall and its construction method
CN104947697A (en) Construction method for rapidly enclosing weir by utilizing Larsen steel sheet piles
CN103397634A (en) Anchoring construction method for fastener steel tube pile cofferdam
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN103711115B (en) A kind of ground stabilization of overall transportation by driving formula water-fetching head and joint and construction method
CN209669900U (en) Tunnel construction cofferdam structure in water-bed highly permeable sandy soil layer
CN104060573A (en) Method for quickly building dyke on coral island
CN203684205U (en) Foundation reinforcement and joint for integral floating intake head
CN103711143B (en) The jointing of a kind of transportation by driving formula diversion box culvert ground stabilization and construction method
CN103306248A (en) High dam spillway foundation drainage system and excavation method
CN203876952U (en) Pontoon system for immersed pipes to pass through rivers
CN113356247B (en) Large deep foundation protection lock catch steel pipe pile cofferdam structure and construction method thereof
CN204456178U (en) Large-scale immersed tube tunnel dry-docking side slope toe steel plate structure
CN103981858A (en) Anti-tilt pipe piles protected by latticed cement-soil continuous walls and construction method thereof
CN202954373U (en) Pile foundation structure of photovoltaic power station
CN203684270U (en) Foundation reinforcing and connecting connector of floating type water diversion box culvert
CN203321523U (en) Large-span high-side-wall underground space building
CN102031821B (en) Pile-wall type draining hole of circular water of seaside power plant with soft soil foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 68 GUCUI Road, Hangzhou, Zhejiang Province

Patentee after: Energy source in China construction group Zhejiang Province Power Design Institute Co., Ltd

Address before: No. 68 GUCUI Road, Hangzhou, Zhejiang Province

Patentee before: Zhejiang Electric Power Design Institute