CN1037009A - 电线杆绝缘装置及其制造方法 - Google Patents

电线杆绝缘装置及其制造方法 Download PDF

Info

Publication number
CN1037009A
CN1037009A CN88101558A CN88101558A CN1037009A CN 1037009 A CN1037009 A CN 1037009A CN 88101558 A CN88101558 A CN 88101558A CN 88101558 A CN88101558 A CN 88101558A CN 1037009 A CN1037009 A CN 1037009A
Authority
CN
China
Prior art keywords
cantilever
continuity
fiber
electric wire
short fiber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN88101558A
Other languages
English (en)
Other versions
CN1014624B (zh
Inventor
泰龙特·米歇尔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cahor Electrical Switch Manufacturing Co
Manufacture dAppareillage Electrique de Cahors SA
Original Assignee
Cahor Electrical Switch Manufacturing Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cahor Electrical Switch Manufacturing Co filed Critical Cahor Electrical Switch Manufacturing Co
Publication of CN1037009A publication Critical patent/CN1037009A/zh
Publication of CN1014624B publication Critical patent/CN1014624B/zh
Expired legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/24Cross arms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Materials Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Wood Science & Technology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Insulating Bodies (AREA)
  • Moulding By Coating Moulds (AREA)
  • Insulation, Fastening Of Motor, Generator Windings (AREA)
  • Transition And Organic Metals Composition Catalysts For Addition Polymerization (AREA)
  • Laminated Bodies (AREA)
  • Insulators (AREA)
  • Processing Of Terminals (AREA)
  • Manufacture Of Motors, Generators (AREA)
  • Patch Boards (AREA)
  • Ultra Sonic Daignosis Equipment (AREA)
  • Reinforced Plastic Materials (AREA)
  • Suspension Of Electric Lines Or Cables (AREA)
  • Adornments (AREA)
  • Manufacturing Of Electrical Connectors (AREA)
  • Inorganic Insulating Materials (AREA)
  • Electric Cable Installation (AREA)
  • Electron Sources, Ion Sources (AREA)
  • Superconductors And Manufacturing Methods Therefor (AREA)
  • Medicines Containing Antibodies Or Antigens For Use As Internal Diagnostic Agents (AREA)

Abstract

绝缘装置包括一挠性悬臂,在悬臂的一端有一将 其连结到电线杆上用的构件,在另一端有一将沿垂直 于悬臂的方向伸展的电线吊装在悬臂上用的构件。 悬臂的厚度从连结到电线杆上的装置处向连结电线 的装置处有规则地缩小,而悬臂横截面的高度则是恒 定的。悬臂在其厚度方向上有一系列沿着悬臂长度 方向伸展的连续性矿物纤维层,并且在每两层纤维层 中隔有任意方向分布的短矿物纤维层。这些敷层用 合成树脂结合起来。在悬臂的两侧,在第一层短纤维 和下一层连续性纤维之间,插入一层矿物纤维构 件。

Description

本发明属于一种电线杆上的绝缘装置及其制造工序。
用于传导高、中和低电压电流的电线是利用称做为“装置”的绝缘托架由电线杆或铁塔支撑着的。
在至今的使用中,这种装置是用金属件制成,将其连接到电线杆上,以及沿垂直于该装置的方向悬挂电线。
这些支撑杆是刚性的,所以不能被施加于电线上的力弄弯。但是,由于冰霜、雪或风的原因,这些电线要承受很重的负荷。
由于这些负荷不会导致装置的任何变形,所以,上述很重的负荷会使电线折断,而且,由此形成的扭矩会造成电线杆断裂。
为了避免这些问题,提出这种装置是用一种玻璃纤维增强合成树脂的挠性材料做成的,其横截面从电线杆处规则地缩小。
理想的话,这种装置要具有最大可能的纵向挠性、而能支承最大可能的垂直向负荷。实际上,这种综合考虑是难以实现的。
本发明的目的是确立这种装置,使利用它来达到上述目的,而又不太贵。
本发明的装置是一根挠性臂,它的一端装备有连结到电线杆上的构件,而在其另一端装备有沿垂直于该臂的方向连结电线的构件。该臂的横截面是一个矩形,矩形高度是沿垂直于电线的方向测定的,而矩形宽度是沿平行于电线的方向测定的,而且高大于宽。
根据本发明,该横截面的宽,从该装置连结到电线杆上的那一头向连结电线的那一头有规则地缩小,而横截面的高度则是恒定的。在悬臂的厚度方向上有一系列沿着悬臂长度方向延伸的连续的矿物纤维层,每两层中间夹有一层任意方向排列的短矿物纤维,这些纤维和敷层用合成树脂粘结在一起。
用这种顺序组成的涂有合成树脂的矿物纤维层使该装置依靠它的几何形状具有大的纵向挠性和对垂直负荷的较高的耐受强度。
这些敷层含有沿装置的长度方向延伸的连续性纤维并且用合成树脂连成一体。由于这些敷层是分布于直立面内,使该装置能承受较大的垂直向负荷并且在挠曲较大时不致于折断。另外,由于装置的横截面的铅垂向尺寸比沿电线纵向的大,也由于该横截面从电线杆处开始有规则地缩小,所以该装置具有大的纵向挠性。
含有任意方向分布的短纤维的敷层能分散在上述连续性纤维敷层中的热应力和机械应力。
另外,这一任意方向分布的短纤维中间层使悬臂易于打孔。实际上,如果该装置仅有连续性的纵向纤维,打孔时会造成分层现象。
为了提高装置的抗扭性能,在悬臂的每一侧的第一层短纤维和下一层连续性纤维之间,均插入一层矿物纤维。这个构件包含有位于与装置长度方向成+45°和-45°方向上的长纤维,使其有最佳的抗扭性。
这样,按照本发明,该装置的依次排列的各层的共同作用使该装置具备了所需的机械性能。
按照最佳实施例,具有连续性纤维的这部分大于具有短纤维的那部分。
为了获得探求的机械性能,这个部分是以连续性纤维的首要作用为基础的。如使用最大可能的数量的连续性纤维则是适当的。
根据本发明的最佳方案,要用附加的短纤维层将一定层数的短纤维与下一层长纤维隔开,所述附加短纤维层是从与电红杆连结之处开始延伸到仅占悬臂长度的一部分。这些短纤维层的长度从悬臂厚度的外端向中间处逐渐减小,使悬臂厚度从电线杆向安装电线的装置的端部有规则地缩小。
最好,悬臂的外表面上涂一层能耐受电弧、恶劣气候和紫外线的塑性涂层,这种涂层可采用乙烯-丙烯-二烯-亚甲基(EPDM)共聚物。
根据本发明的另一设想,制造用于电线杆的绝缘装置的工序包括下列各步:
做几根带,这种带子包括一层沿着带子长度方向延伸的连续性纤维和一层预先浸过聚脂树脂的任意方向分布的短纤维,以及可能还有几根和带子长度方向成±45°夹角的纤维构件带;
将这些带切割成若干段,每段的尺寸按照装置所需的长度和高度确定;
按照所需的布局将不同的带段重叠起来;
将这一叠带预热到低于聚脂树脂聚合温度的一个温度值;
将此一叠带放到一模子中,加热并加压,使此叠带成型;
本发明的其他特点和优点将在下面阐述。
下面的附图用作不限制的实例:
图1是表示装上本发明所述的装置的电线杆的上部的正视图;
图2是图1的顶视图;
图3是用放大比例绘出的装置的横截面的正视图;
图4是表示含有连续性纵向纤维的纤维层的部分示意正视图;
图5是表示含有任意方向分布的连续性纤维的纤维层的部分示意正视图;
图6是表示含有以±45°方向分布的长纤维构件的一部分的示意正视图;
图7是表示图4、5和6所示的各敷层并列后的纵剖面的示意平面图;
图8是表示本发明的装置中的不同敷层的、沿装置纵剖面的示意平面图;
图9是表示制造本发明的装置的工序所需的模子的纵剖面图。
在图1和2所示的实施例中,横向装置100是由一挠性悬臂1组成的,在悬臂的一端有一支架2,连结到电线杆3上,而在悬臂的另一端有一接头4,其上带有一电缆夹,在夹子上连有沿垂直于悬臂1的方向伸展的电线6。悬臂1有一矩形横截面(见图3)。在垂直于电线6的平面内测得的该横截面的高度l明显大于在沿平行于图2所示电线6平面的方向测得的该截面的宽度e。
如从图2中能看到的,悬臂1横截面的宽度e从固定到电线杆3上的支架2起向用于连结电线6的接头处有规则地缩小。此外,该截面的高度1是恒定的(见图1)。
悬臂1在其厚度e方向即图2所示的平面内,有一系列含有沿悬臂1的长度L方向延伸的连续性玻璃纤维10(见图4、7、8)的纤维层7a、7b、7c、7d。这些敷层7a、7b、7c、7d是用任意方向分布的短玻璃纤维层隔开的(见图5、7、8)。这两种敷层和它们的纤维是用如聚脂树脂这样的合成树脂粘结在一起的。
另外,在悬臂1的每侧第一层短纤维层11和下一层连续性纤维10的敷层7b之间有玻璃纤维构件的敷层9a、9b,(见图8)。
各种不同敷层对于悬臂1的中心纤维层N说来是两侧对称分布的。
诸如7a、8a、9a的不同敷层,是利用下面要描述的加压模制操作方法靠合成树脂的聚合而粘结在一起的。
连续性纤维10部分最好比短纤维部分11大。连续性纤维10约占所有纤维的总重的80%。因此,短纤维11约占总重的20%。
连续性纤维10和短纤维11最好占总的材料的50~60%,而合成树脂占40~50%。
构件9a(或9b)(见图6)具有一第一系列长纤维12a和一第二系列长纤维12b,第一系列的平行的玻璃纤维按与悬臂1的长度方向L成±45°方向排列的,而第二系列的平行的纤维按与悬臂1的长度方向L成-45°的方向排列的。
此外,从图8可看出:诸如13a、13b、13c的一定数量的短纤维层是从连结电线杆3上的支架2起、仅仅沿着一部分悬臂1长度L伸展的。这些短纤维层13a、13b、13c的长度,从悬臂1的厚度的外端向中央处N逐渐减小,以形成一逐渐减小的厚度e,如图2所示。
另外,悬臂1的外表面上涂有(见图2)一层用弹性体制作的涂层14,该涂层能耐受电弧、恶劣气候和紫外线,其材料为如乙烯-丙烯-二烯-亚甲基(EPDM)共聚物。
将悬臂1连结到电线杆3上所用的支架2以及在悬臂端部4的接头,最好用铝制成并用粘结方法固定到悬臂1上。作为普通金属材料的铝,它的膨胀系数接近制作悬臂1用的复合材料(玻璃纤维、聚脂树脂)的膨胀系数,这样,将支架2和接头4连结到悬臂1上后,就不会有因温度变化影响其性能的危险。
下面是有关按照本发明制造装置的工序的详细说明。
第一步,制作一带,该带依次包括有一沿着带的长度方向伸展的连续性玻璃纤维层10,一任意方向分布的短纤维层11和一玻璃长纤维12a、12b的构件敷层9a,其中玻璃长纤维12a、12b对于带的长度L方向形成±45°夹角。此后,将这些敷层一起浸渍聚脂树脂。
举例说,这种带的组成如下:
聚脂树脂:18%
抗收缩热塑性添加剂:12%
辅药,着色催化剂:3%
矿物填料:12%
玻璃纤维:55%
将预先浸渍过聚脂树脂的一些带切割成如悬臂1这样的长度。
然后,将这些切割后的带段按照图8所示排好,再将它们叠合一起。
然后,将上述叠合件放到一高频预热器中加温至约70℃(低于聚脂树脂聚合温度)。
这样的预热能使明显减小材料在模压加工中形成的热应力。
然后,将预热后的叠合件15放到一对安置在压机中的模子16和17中(见图9),再对其加热到聚脂树脂的聚合温度,此间仍始终加压(见图9中箭头F所示方向)。
然后,从模子中取出上述叠合件15,将其修整、冷却,再磨光,使获得可能的最好表面。
然后,将铝支架2和接头4连结到叠合件的两端。
为此而用的粘合剂可用半导体粘合剂,以避免部分放电问题发生。然后,在如此获得的悬臂外表面上涂上一层基本的粘合剂,再涂上一层EPDM。
鉴于获得的挠性,这样方法制得的装置比起如用模子拉出的具有恒定横截面和惯量的装置更能耐受垂直向负荷。
如此,按照本发明加工的这种装置,当其长L为150厘米,高l为90毫米,厚度e从25毫米缩到20毫米时,能承受大于240担(daN)的垂直向静负荷,其纵向挠度大于5毫米/担(daN)。
之所以能具有这些机械性能,是由于该装置包含有大部分的连续性纵向纤维10。含有沿与装置长度L成+45°和-45°夹角的方向排列的玻璃长纤维12a和12b的构件,使装置的抗扭性能得以提高,而含有任意方向分布的短玻璃纤维层11使装置能分散在构件和相邻的长纤维层中的热应力和机械应力,并能在悬臂1上打孔而不会有分层的危险。
如遇到装置用来承受较小的扭应力的情况,就不必采用构件9a、9b。
应理解的是:本发明并不限于上面刚描述的这些实施例,只要在本发明的构思框架中,可有许多变化或改进方案。
此外,可用如岩石纤维这样的其他的矿物纤维代替玻璃纤维。
另外,可用热定型或热塑性树脂代替聚脂树脂。
此外,可根据要求修改悬臂1的尺寸。
还有,悬臂1可与电线杆成一倾斜角度,而不成垂直状。
此外,在制造装置的工艺中,可不采用先将预先经浸渍处理的纤维带切割成装置的L和l尺寸后再将这些带段一个叠一个的方法,而采用如下一种工艺:
将一具有装置长L尺寸的、具有一连续性纤维层和一预先浸渍过树脂的短纤维层的薄片卷起来,以便做成一包含最大宽度为l并相互结合起来的带子的平整的螺线管,这样,就可做出包含有依次排列的连续性纤维层和短纤维层的叠合件。
为了使厚度规则地减小,可在螺线管的各层之间插进长度不同的带,如图8所示的短纤维层(13a、13b、13c)。

Claims (13)

1、用于吊装电线(6)的电线杆(3)的绝缘装置构成一挠性悬臂(1),其包括将其一端连结到电线杆(3)上的装置(2)及将其另一端连接电线(6)使电线基本上沿垂直于悬臂方向延伸的装置(4,5)。悬臂(1)具有一矩形横截面,该截面中在垂直于电线(6)的平面内测得的高( l)大于该截面中沿平行于电线(6)的方向测得的厚( e),该截面的厚( e)从将悬臂(1)连结到电线杆(3)上的构件(2)向将悬臂连接电线(6)用的构件(4)有规则地缩小;该截面的高( l)是恒定的。悬臂(1)在其厚度方向上有一系列依次排列的、含有沿悬臂的长度(L)方向伸展的连续性矿物纤维(10)的敷层(7a、7b、7c、7d),在每两层上述敷层中夹有一层含有任意方向分布的短矿物纤维(11)的敷层(8a、8b、8c、8d),这些纤维和敷层用合成树脂连结在一起。
2、按权利要求1的装置,在悬臂(1)的每一侧,在第一短纤维层和下一个连续性纤维层之间,有一层矿物纤维构件(9a、9b)。
3、按权利要求1的装置,其中连续性纤维部分(10)大于短纤维部分(11)。
4、按权利要求3的装置,其中连续性纤维部分比短纤维部分好。
5、按权利要求1的装置,其中纤维(10,11)的量占总物质量的50~60%。
6、按权利要求1的装置,其所用的合成树脂是聚脂树脂。
7、按权利要求2的装置,其中构件(9a,9b)有第一系列平行长纤维(12a)和第二系列平行长纤维(12b)。第一系列长纤维方向与悬臂(1)的长度(L)方向成+45°夹角,而第二系列长纤维方向与长度(L)方向成-45°夹角。
8、按权利要求1的装置,其有一定层数的短纤维(11)和与这些层隔开的一连续纤维层(10),用于隔离的是一层仅仅占从与电线杆连续的装置(2)起的悬臂(1)的长度(L)的一部分的短纤维(13a、13b、13c)或一层连续性纤维。短纤维层(13a、13b、13c)或连续性纤维层的长度从悬臂厚度的外端向中央位置(N)逐渐缩短,致使厚度有规则地缩小。
9、按权利要求1的装置,其中悬臂(1)的外表面上要涂一层能耐受电弧、恶劣气候和紫外线的弹性体涂层(14)。
10、按权利要求8的装置,所用的涂层(14)是乙烯-丙烯-二烯-亚甲基共聚物。
11、制造用于吊装电线(6)的电线杆(3)上的绝缘装置的工艺有下列几步:
将包含有一连续性纤维层(7a、7b、7c、7d)和一预先浸饱聚脂树脂的、按任意方向分布的短纤维层(8a、8b、8c、8d)做成带子,该带子还可能包括有沿与带长(L)方向成±45°夹角的方向分布的纤维材料(9a、9b)。
将每根上述带子切割成如装置所需的长度(L)和宽度(l)要求的带段。
按照所要求的布局,将这些带段叠合起来。
将叠合件(15)放于一低于聚脂树脂聚合温度的温度中预热。
将叠合件(15)放到模子(16)中,并施加压力以使这叠合件成形。
12、按权利要求11的工艺,将叠合件(15)放入高频预热炉中,在70℃中预热。
13、制造用于吊装电线的电线杆上的绝缘装置的工艺,也可用一具有装置长L的一连续性纤维层和一预先浸渍树脂的短纤维层的薄片,将此薄片卷起来,以形成一平整的用带子相互结合起来的螺线管,这样,就按连续性纤维层和短纤维层的依次排列关系叠合起来了。为了获得不断减小的厚度,可在两层螺旋层中插进包含有短纤维(13a,13b,13c)或连续性纤维的不同长度的敷层。
CN88101558A 1987-03-20 1988-03-19 电线杆绝缘装置及其制造方法 Expired CN1014624B (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR8703885 1987-03-20
FR8703885A FR2612549B1 (fr) 1987-03-20 1987-03-20 Armement isolant pour poteau de support de lignes electriques et son procede de fabrication

Publications (2)

Publication Number Publication Date
CN1037009A true CN1037009A (zh) 1989-11-08
CN1014624B CN1014624B (zh) 1991-11-06

Family

ID=9349243

Family Applications (1)

Application Number Title Priority Date Filing Date
CN88101558A Expired CN1014624B (zh) 1987-03-20 1988-03-19 电线杆绝缘装置及其制造方法

Country Status (17)

Country Link
US (2) US4867399A (zh)
EP (1) EP0286480B1 (zh)
JP (1) JPS63308169A (zh)
CN (1) CN1014624B (zh)
AT (1) ATE63964T1 (zh)
CA (1) CA1309474C (zh)
DE (2) DE286480T1 (zh)
ES (1) ES2004331B3 (zh)
FI (1) FI87959C (zh)
FR (1) FR2612549B1 (zh)
GR (2) GR880300179T1 (zh)
MY (1) MY100817A (zh)
NO (1) NO168735C (zh)
OA (1) OA08820A (zh)
PH (1) PH24573A (zh)
PT (1) PT87011B (zh)
SG (1) SG74191G (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102668288A (zh) * 2009-08-21 2012-09-12 曼彻斯特大学 用于高压电力网的支撑塔架、绝缘横臂以及绝缘构件
CN102869413A (zh) * 2010-01-05 2013-01-09 伊士登运动公司 具有多个故障面的球棒
CN109054083A (zh) * 2018-06-21 2018-12-21 滁州市三和纤维制造有限公司 一种用于生产电线绝缘层材料用改性矿物纤维
CN110649502A (zh) * 2018-06-27 2020-01-03 国网河南省电力公司检修公司 ±1100kV特高压直流输电线路200kN级硬质绝缘拉棒

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5605017A (en) * 1994-01-13 1997-02-25 Pupi Enterprises L.L.C. Pultruded utility line support structure and method
US5419453A (en) * 1994-02-04 1995-05-30 Lochridge; Jeffrey L. Trash receptacle with bag retainer
ES2154080T3 (es) * 1998-08-06 2001-03-16 Daume Karin Maschinenteile Abrazadera de apriete conductiva para tubos o cables.
US6347488B1 (en) 1999-06-29 2002-02-19 Jeffrey T. Koye Utility pole cross-arm
US6343725B1 (en) 2000-12-19 2002-02-05 Owens-Illinois Closure Inc. Disk-type toggle-action dispensing closure, package and method of assembly
US6834469B2 (en) 2001-01-24 2004-12-28 Geotek, Inc. Utility line support member
EP2130756B1 (en) * 2003-06-11 2012-10-03 CAMPAGNOLO S.r.l. Bicycle component and method for manufacturing such a component
US7578488B2 (en) * 2005-02-01 2009-08-25 The Southern Company Temporary arm gain and saddle
US7750236B2 (en) * 2007-01-09 2010-07-06 The Southern Company Non-boring support system for transmission line structures
US8708845B2 (en) * 2010-01-05 2014-04-29 Easton Sports, Inc. Ball bat including multiple failure planes
WO2014039965A1 (en) * 2012-09-07 2014-03-13 Fives Machining Systems, Inc. Method and apparatus for rapid molding a composite structure
US10159878B2 (en) 2015-08-27 2018-12-25 Easton Diamond Sports, Llc Composite ball bat including a barrel with structural regions separated by a porous non-adhesion layer
WO2018019180A1 (zh) * 2016-07-26 2018-02-01 江苏神马电力股份有限公司 一种横担及包含其的转角塔、耐张塔
US11167190B2 (en) 2017-07-19 2021-11-09 Easton Diamond Sports, Llc Ball bats with reduced durability regions for deterring alteration
US11013967B2 (en) 2017-07-19 2021-05-25 Easton Diamond Sports, Llc Ball bats with reduced durability regions for deterring alteration
US10940377B2 (en) 2018-06-19 2021-03-09 Easton Diamond Sports, Llc Composite ball bats with transverse fibers

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1145447A (fr) * 1955-02-08 1957-10-25 Gar Wood Ind Inc Support tel que poteau électrique ou téléphonique avec gaine en fibres de verre
US3070194A (en) * 1958-01-13 1962-12-25 Mc Graw Edison Co Brace assembly
GB919534A (en) * 1959-10-07 1963-02-27 British Insulated Callenders Cross arms for supporting overhead electric lines
US3408239A (en) * 1965-06-11 1968-10-29 Coast Mfg & Supply Company Method for manufacturing glass fiber reinforced resin impregnated mats
US3299586A (en) * 1965-10-22 1967-01-24 Weyerhaeuser Co Crossarm assembly
US3574104A (en) * 1968-01-24 1971-04-06 Plastigage Corp Glass fiber constructional member
US3527549A (en) * 1968-08-29 1970-09-08 Bendix Corp Motor pump suspension
US3813837A (en) * 1972-10-16 1974-06-04 Cascade Pole Co Fiberglass pole and method and apparatus for fabricating same
US3896858A (en) * 1973-02-28 1975-07-29 William J Whatley Utility pole
US4007075A (en) * 1973-12-10 1977-02-08 Cascade Pole Company Method of making a fiberglass pole
US4141929A (en) * 1974-11-07 1979-02-27 Armco Inc. Unidirectional sheet molding composition and process of preparing same
LU80296A1 (fr) * 1978-09-28 1980-04-21 Bekaert Sa Nv Structures amortissant des vibrations mecaniques
US4220496A (en) * 1979-02-01 1980-09-02 Ppg Industries, Inc. High strength composite of resin, helically wound fibers and chopped fibers and method of its formation
US4292406A (en) * 1979-09-11 1981-09-29 The United States Of America As Represented By The United States Department Of Energy Anaerobic thermophilic culture system
US4539055A (en) * 1982-06-18 1985-09-03 The Babcock & Wilcox Company Fiber pipe protection for water cooled pipes in reheat furnaces
US4695677A (en) * 1985-06-06 1987-09-22 Ruth Dale G Wire tensioning system
JPS62225537A (ja) * 1986-03-27 1987-10-03 Showa Highpolymer Co Ltd 繊維強化樹脂用硬化性組成物
US4682747A (en) * 1986-04-24 1987-07-28 King Jr Halm C Utility insulated cross-arm

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102668288A (zh) * 2009-08-21 2012-09-12 曼彻斯特大学 用于高压电力网的支撑塔架、绝缘横臂以及绝缘构件
CN102668288B (zh) * 2009-08-21 2015-06-24 艾拉贡技术有限公司 用于高压电力网的支撑塔架、绝缘横臂以及绝缘构件
CN102869413A (zh) * 2010-01-05 2013-01-09 伊士登运动公司 具有多个故障面的球棒
CN102869413B (zh) * 2010-01-05 2015-11-25 伊士登棒球/垒球公司 具有多个故障面的球棒
CN109054083A (zh) * 2018-06-21 2018-12-21 滁州市三和纤维制造有限公司 一种用于生产电线绝缘层材料用改性矿物纤维
CN110649502A (zh) * 2018-06-27 2020-01-03 国网河南省电力公司检修公司 ±1100kV特高压直流输电线路200kN级硬质绝缘拉棒

Also Published As

Publication number Publication date
DE286480T1 (de) 1989-02-16
CN1014624B (zh) 1991-11-06
OA08820A (fr) 1989-03-31
JPH0584790B2 (zh) 1993-12-03
PT87011A (pt) 1989-03-30
US4867399A (en) 1989-09-19
EP0286480A3 (en) 1989-07-05
FI87959B (fi) 1992-11-30
CA1309474C (en) 1992-10-27
NO881133D0 (no) 1988-03-15
FR2612549B1 (fr) 1989-06-30
GR880300179T1 (en) 1989-02-23
NO168735C (no) 1992-03-25
FI881230A (fi) 1988-09-21
SG74191G (en) 1991-11-22
FR2612549A1 (fr) 1988-09-23
GR3002034T3 (en) 1992-12-30
EP0286480A2 (fr) 1988-10-12
ES2004331A4 (es) 1989-01-01
MY100817A (en) 1991-02-28
ATE63964T1 (de) 1991-06-15
FI87959C (fi) 1993-03-10
US5009734A (en) 1991-04-23
FI881230A0 (fi) 1988-03-15
ES2004331B3 (es) 1991-12-01
JPS63308169A (ja) 1988-12-15
PT87011B (pt) 1995-05-04
PH24573A (en) 1990-08-03
NO168735B (no) 1991-12-16
NO881133L (no) 1988-09-21
DE3862985D1 (de) 1991-07-04
EP0286480B1 (fr) 1991-05-29

Similar Documents

Publication Publication Date Title
CN1037009A (zh) 电线杆绝缘装置及其制造方法
EP1506085B1 (en) Aluminum conductor composite core reinforced cable and method of manufacture
US5873973A (en) Method for single filament transverse reinforcement in composite prepreg material
US20190353143A1 (en) Method of manufacturing a spar cap
CN1077057C (zh) 用于车辆的车架
CN101034601A (zh) 耐热、低膨胀倍容量复合材料芯铝绞线及制备方法
US5580512A (en) Method for making low cost oriented composite molding compound
CN101052548A (zh) 带有带状设备的冲击吸收设备
CN108885914A (zh) 用于电气列车的吊线缆、其制造方法和安装方法
CN109411164A (zh) 一种复合支柱绝缘子芯棒及其制备方法
CN110305450B (zh) 一种架空线路纤维增强树脂基复合芯及其制备方法
CN101211678A (zh) 单面补强环氧中胶云母带及其制造方法和用途
CN101211679A (zh) 单面补强环氧多胶云母带及其制造方法和用途
CN1240060A (zh) 回转电机的定子线圈
CN109300867B (zh) 一种晶闸管固定用夹持环及其制造方法
CN201717065U (zh) 一种高速有轨电气化机车用车顶复合绝缘子
CN111554440B (zh) 高强铝合金电力传输导线
JP2000167951A5 (zh)
CN111477379A (zh) 一种少胶云母带及其制备方法
CN220075645U (zh) 一种热固化成型预浸带铺层装置
CN117621554A (zh) 一种碳纤维增强复合材料板、制备工艺及其应用
CN115875188A (zh) 叶片梁帽、叶片梁帽的制造方法、叶片和风力发电机组
JPH032227A (ja) ハイブリッドプリプレグ

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C13 Decision
GR02 Examined patent application
C14 Grant of patent or utility model
GR01 Patent grant
C15 Extension of patent right duration from 15 to 20 years for appl. with date before 31.12.1992 and still valid on 11.12.2001 (patent law change 1993)
OR01 Other related matters
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee