CN103670439B - 隧道衬砌施工方法 - Google Patents

隧道衬砌施工方法 Download PDF

Info

Publication number
CN103670439B
CN103670439B CN201310663159.7A CN201310663159A CN103670439B CN 103670439 B CN103670439 B CN 103670439B CN 201310663159 A CN201310663159 A CN 201310663159A CN 103670439 B CN103670439 B CN 103670439B
Authority
CN
China
Prior art keywords
concrete
tunnel
layer
carbon type
low
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310663159.7A
Other languages
English (en)
Other versions
CN103670439A (zh
Inventor
赵怀宇
李占岭
孟金波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.
Original Assignee
Hebei Electric Power Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Electric Power Design and Research Institute filed Critical Hebei Electric Power Design and Research Institute
Priority to CN201310663159.7A priority Critical patent/CN103670439B/zh
Publication of CN103670439A publication Critical patent/CN103670439A/zh
Application granted granted Critical
Publication of CN103670439B publication Critical patent/CN103670439B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/91Use of waste materials as fillers for mortars or concrete

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种隧道衬砌施工方法,包括以下步骤:沿隧道纵向的围岩开挖面上间隔施作全断面钢拱架;在相邻钢拱架之间的围岩开挖面上采用湿喷机藉助空气压力高速喷射两层低碳型纤维混凝土层,形成隧道衬砌结构;直至隧道贯通。本发明施工工艺简单,施工过程安全,并且能够减少喷射混凝土回弹率,提高可喷射性能,降低能耗,所形成的衬砌结构韧性高、抗渗性好、耐久性好,尤其适用于矿山法施工的软弱围岩隧道支护。

Description

隧道衬砌施工方法
技术领域
本发明涉及隧道领域,尤其是指一种隧道衬砌的施工方法。
背景技术
衬砌是为防止围岩变形或坍塌,沿隧道洞身周边用钢筋混凝土等材料修建的永久性支护结构。现有的隧道衬砌通常采用复合式衬砌结构,包括初期支护、防水层和二次衬砌。复合式衬砌是分内外两层先后施作的隧道衬砌,在洞室开挖后,先放置钢拱架、挂钢筋网,再施作与围岩密贴的喷射普通混凝土作为初期支护的外层衬砌,待围岩变形基本稳定以后再施作模筑钢筋混凝土内层衬砌,两层衬砌之间设置防水层。
在复合式衬砌结构施作过程中,挂钢筋网是一项费时而危险的工作,而且钢筋网的存在会导致喷射混凝土回弹率大,造成了材料浪费,钢材、混凝土等材料用量大,造价高,施工工艺复杂,施工周期长。
由于钢筋网的存在,喷射混凝土不能很好地与开挖面相贴合,钢筋网和开挖面之间必然形成空洞,为钢筋网的腐蚀留下了隐患。钢筋网上的结构凸起以及喷射施工工艺导致初期支护结构的混凝土层平整度难以控制,致使铺设防水层的基面状况较差,易对防水层本身造成损害,加之由于施工原因,防水层卷材的接茬工艺难以保证焊缝的质量和效果,这些因素都易留下漏水隐患。由于这些安全隐患的存在,隧道在建成运营后容易出现衬砌开裂、渗漏等现象,导致衬砌的整体耐久性达不到设计使用年限。
发明内容
本发明需要解决的技术问题是提供一种工艺简单、成本低廉、无安全隐患的隧道衬砌施工方法。
为解决上述技术问题,本发明所采取的技术方案如下:
隧道衬砌施工方法,具体包括以下步骤:
A.开挖洞室,在洞室内沿隧道纵向的围岩开挖面上间隔施作全断面钢拱架;
B.搅拌低碳型纤维混凝土,采用湿喷机向相邻钢拱架之间围岩开挖面上喷射厚度为20mm±1mm的低碳型纤维混凝土,形成内层混凝土层;
C. 待洞室位移稳定后,再采用湿喷机藉助空气压力向内层混凝土层的外表面高速喷射厚度为10mm±1mm的低碳型纤维混凝土,形成外层混凝土层;
D. 在隧道内纵向重复步骤A至C,直至隧道贯通。
本发明所述步骤A中相邻钢拱架之间的距离优选为750mm。
本发明所述低碳型纤维混凝土每立方米包括以下重量的组分:粉煤灰53.1 Kg~106.2 Kg,硅粉17.7 Kg~53.1 Kg,钢纤维35Kg,聚丙烯纤维0.9 Kg,其余为普通喷射混凝土。
由于采用了上述技术方案,本发明取得的技术进步如下:
本发明是将钢拱架沿隧道开挖面纵向间隔一定距离、全断面布置,将低碳型纤维混凝土藉助湿喷机高速喷射至围岩开挖面上,与钢拱架联合形成低碳型纤维喷射混凝土隧道衬砌结构,工艺简单,成本低廉。低碳型纤维混凝土采用分层施作方法,内层和外层之间的层间界面具有很强粘结力,并能够充分传递剪切力。
本发明所述的低碳型纤维混凝土通过在普通喷射混凝土中添加钢纤维这种高模量纤维,大幅度提高了其韧性和耐久性;添加聚丙烯纤维这种低模量纤维,减少了混凝土的早期塑性收缩裂纹,从而提高了混凝土的抗渗性;添加硅粉和粉煤灰可减少水泥用量,降低水化热,最大限度地减少了表面收缩微裂纹,提高颗粒间紧密性与纤维间粘结性,降低能耗,提高性价比;由于取消了钢筋网,喷射混凝土回弹量损失减小10%以上;由于低碳型纤维混凝土材料性能优越,衬砌厚度可以减薄30%左右,故节省材料;由于衬砌厚度减薄,开挖土方量减小,弃土量减少。因此施工工期缩短,施工工期减少50%以上,从而人工费、机械费降低,地面临时占地时间短。采用低碳型纤维喷射混凝土衬砌,有利于减少回弹率,提高可喷射性能,降低能耗及工程造价,保障施工安全,减少对环境的影响。
附图说明
图1是本发明的结构示意图。
其中:1、钢拱架,2、内层混凝土层,3、外层混凝土层。
具体实施方式
下面结合附图对本发明作更进一步详细说明:
一种隧道衬砌施工方法,具体包括以下步骤:
A.先开挖洞室,在洞室内沿隧道纵向的围岩开挖面上间隔施作全断面钢拱架1,相邻钢拱架1之间的距离为750mm。
B.搅拌低碳型纤维混凝土,采用湿喷机向相邻钢拱架1之间围岩开挖面上喷射厚度为20mm±1mm的低碳型纤维混凝土,形成内层混凝土层2。
本发明所述的低碳型纤维混凝土是在普通喷射混凝土中掺入粉煤灰和硅粉,再配以钢纤维、聚丙烯纤维而形成,制备而成的低碳型纤维混凝土每立方米包括53.1 Kg~106.2 Kg粉煤灰,17.7 Kg~53.1 Kg硅粉,35Kg钢纤维,0.9 Kg聚丙烯纤维,其余为普通喷射混凝土。
C.待洞室位移稳定后,再采用湿喷机藉助空气压力向内层混凝土层2的外表面高速喷射厚度为10mm±1mm的低碳型纤维混凝土,形成外层混凝土层3;内层混凝土层2和外层混凝土层3之间的层间界面具有很强粘结力并可充分传递剪切力。本发明中,钢拱架1、内层混凝土层2以及外层混凝土层3共同构成如图1所示的隧道衬砌结构。
D.在隧道内纵向重复上述步骤,直至隧道贯通。
本发明由于舍弃了传统的复式衬砌中的钢筋网,施工过程更加简单、安全,并且降低了喷射混凝土的回弹率,节省材料,降低能耗。

Claims (2)

1.隧道衬砌施工方法,其特征在于具体包括以下步骤:
A.开挖洞室,在洞室内沿隧道纵向的围岩开挖面上间隔施作全断面钢拱架(1);
B.搅拌低碳型纤维混凝土,采用湿喷机向相邻钢拱架(1)之间围岩开挖面上喷射厚度为20mm±1mm的低碳型纤维混凝土,形成内层混凝土层(2);
C. 待洞室位移稳定后,再采用湿喷机藉助空气压力向内层混凝土层(2)的外表面高速喷射厚度为10mm±1mm的低碳型纤维混凝土,形成外层混凝土层(3);
D. 在隧道纵向重复步骤A至C,直至隧道贯通;
所述低碳型纤维混凝土每立方米包括以下重量的组分:粉煤灰53.1 Kg~106.2 Kg,硅粉17.7 Kg~53.1 Kg,钢纤维35Kg,聚丙烯纤维0.9 Kg,其余为普通喷射混凝土。
2.根据权利要求1所述的隧道衬砌施工方法,其特征在于:步骤A中相邻钢拱架(1)之间的距离为750mm。
CN201310663159.7A 2013-12-10 2013-12-10 隧道衬砌施工方法 Active CN103670439B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310663159.7A CN103670439B (zh) 2013-12-10 2013-12-10 隧道衬砌施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310663159.7A CN103670439B (zh) 2013-12-10 2013-12-10 隧道衬砌施工方法

Publications (2)

Publication Number Publication Date
CN103670439A CN103670439A (zh) 2014-03-26
CN103670439B true CN103670439B (zh) 2015-10-07

Family

ID=50309128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310663159.7A Active CN103670439B (zh) 2013-12-10 2013-12-10 隧道衬砌施工方法

Country Status (1)

Country Link
CN (1) CN103670439B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088646B (zh) * 2014-04-11 2016-02-24 中国水利水电第十一工程局有限公司 一种马蹄形开敞式盾构机的施工方法
CN107740446A (zh) * 2017-10-16 2018-02-27 广州地铁设计研究院有限公司 既有建筑物基础被动补充与洞内托换系统的联合施工方法
CN110578535B (zh) * 2019-10-16 2021-03-23 中铁三局集团第二工程有限公司 应用于软弱围岩隧道的初期支护混凝土湿喷方法
CN110905555A (zh) * 2019-12-11 2020-03-24 湘潭大学 一种隧道用uhpc衬砌结构及其施工方法
CN112377210B (zh) * 2020-09-28 2023-05-02 中煤科工开采研究院有限公司 巷道大气压力支护打孔判别方法及系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2101092B2 (de) * 1971-01-12 1977-08-18 Lütgendorf, Hans Otto, Dr.-Ing., 4370 Mari Bogenfoermiger streckenausbau mit hilfe von segmenten aus beton
RU2024758C1 (ru) * 1991-11-05 1994-12-15 Валериан Алексеевич Лебедев Тоннельная обделка "звезда"
CN101982643A (zh) * 2010-10-13 2011-03-02 天津大学 隧洞预应力混凝土衬砌结构及其施工程序
CN201771517U (zh) * 2010-08-30 2011-03-23 中铁第四勘察设计院集团有限公司 一种隧道支护结构
CN203223229U (zh) * 2013-04-01 2013-10-02 平顶山天安煤业股份有限公司 一种煤矿巷道均布注浆结构

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2101092B2 (de) * 1971-01-12 1977-08-18 Lütgendorf, Hans Otto, Dr.-Ing., 4370 Mari Bogenfoermiger streckenausbau mit hilfe von segmenten aus beton
RU2024758C1 (ru) * 1991-11-05 1994-12-15 Валериан Алексеевич Лебедев Тоннельная обделка "звезда"
CN201771517U (zh) * 2010-08-30 2011-03-23 中铁第四勘察设计院集团有限公司 一种隧道支护结构
CN101982643A (zh) * 2010-10-13 2011-03-02 天津大学 隧洞预应力混凝土衬砌结构及其施工程序
CN203223229U (zh) * 2013-04-01 2013-10-02 平顶山天安煤业股份有限公司 一种煤矿巷道均布注浆结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吕永澎."公路施工员上岗指南—不可不知的500个关键细节",吕永澎,中国建材工业出版社,第266页,2013年7月.《公路施工员上岗指南—不可不知的500个关键细节》.中国建材工业出版社,2013,第266页. *

Also Published As

Publication number Publication date
CN103670439A (zh) 2014-03-26

Similar Documents

Publication Publication Date Title
CN103670439B (zh) 隧道衬砌施工方法
CN102031974B (zh) 煤矿深井巷道穿越断层破碎带管幕超前支护施工方法
CN103016026B (zh) 一种挤压膨胀岩公路隧道支护方法
CN111485913B (zh) 一种巷旁采空区矸石胶结成墙的沿空留巷系统及方法
CN102493821B (zh) 一种高应力巷道煤岩体的支护方法
CN107246273B (zh) 深部巷道钢丝绳网橡胶喷射混凝土支护结构及其施工方法
CN110359915B (zh) 一种适用于四级围岩双线轨道的防水型单层衬砌结构及其制作方法
CN105298517A (zh) 软弱围岩隧道超前加强支护施工方法
CN104612698A (zh) 一种浅埋暗挖隧道上台阶中隔壁施工方法
CN101806217A (zh) 三线并行小净距浅埋、偏压隧道群进洞施工方法
CN103132690B (zh) 一种地下室外墙单侧模板及其支模方法
CN103993902B (zh) 一种瓦斯抽采钻孔两步注浆封孔方法
CN104314585A (zh) 隧道全断面预加固方法及结构
CN102322027A (zh) 一种采用矿山法扩挖盾构隧道建造地铁车站的方法
CN203488189U (zh) 用于脱空整治的隧道结构
CN203321531U (zh) 地下洞室顶拱塌方后的衬砌处理结构
CN204877493U (zh) 一种软岩隧道支护结构
CN103089276A (zh) 深浅孔与高低压耦合注浆工艺
CN103375171A (zh) 一种盾构洞内始发反力架
CN102002950B (zh) 地下结构施工缝分液注浆补强方法
CN105401955A (zh) 一种软土压力隧洞防渗承载结构
CN111255485A (zh) 深井巷道支护结构及施工方法
CN204186394U (zh) 隧道全断面预加固结构
CN202673299U (zh) 一种软弱围岩隧道双层模筑复合式衬砌支护结构
CN103775102A (zh) 潜孔钻跟管成孔回填砼稳定临空面处理塌方施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 050031 No. 6 Jianbei Street, Chang'an District, Shijiazhuang City, Hebei Province

Patentee after: China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.

Address before: 050031 No. 6 Jianbei Street, Chang'an District, Shijiazhuang City, Hebei Province

Patentee before: Hebei Province Power Surveying Design & Research Institute