CN103669181A - Adjusting and fixing pile for road concrete die - Google Patents

Adjusting and fixing pile for road concrete die Download PDF

Info

Publication number
CN103669181A
CN103669181A CN201310601084.XA CN201310601084A CN103669181A CN 103669181 A CN103669181 A CN 103669181A CN 201310601084 A CN201310601084 A CN 201310601084A CN 103669181 A CN103669181 A CN 103669181A
Authority
CN
China
Prior art keywords
anchor ear
adjusting rod
stretch
solid model
draw adjusting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310601084.XA
Other languages
Chinese (zh)
Inventor
闫成林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310601084.XA priority Critical patent/CN103669181A/en
Publication of CN103669181A publication Critical patent/CN103669181A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses an adjusting and fixing pile for a road concrete die. The adjusting and fixing pile comprises a die fixing main rod fixed on a roadbed, a fixing sleeve in contact with a channel steel die, an upper hoop, a lower hoop, an upper stretching adjustment rod and a lower stretching adjustment rod, wherein the upper hoop and the lower hoop are mounted on the die fixing main rod; the upper hoop is connected with the fixing sleeve through the upper stretching adjustment rod; the lower hoop is connected with the fixing sleeve through the lower stretching adjustment rod. The adjusting and fixing pile has the advantages of simple structure, convenience in die mounting and dismounting, reusability, high work efficiency and the like and is suitable for fixing and adjusting the road concrete die.

Description

Road concrete mold is adjusted solid model stake
Technical field
The present invention relates to a kind of channel-section steel mold adjustment device, particularly a kind of road concrete mold is adjusted solid model stake.
Background technology
The not specific device of existing channel-section steel die adjustment, general is all to adopt traditional steel pipe and iron wire colligation solid model, solid model is unreliable simultaneously, at road casting process, easily run mould dislocation, adopt installing/dismounting difficulty in this way, waste time and energy, not easy care, and immobilization material repeat usage is little after using, very waste.
Summary of the invention
The object of this invention is to provide a kind of simple in structure, dress mould and convenient disassembly, the road concrete mold that reusable, work efficiency is high is adjusted solid model stake.
The present invention is achieved in that the stake of road concrete mold adjustment solid model, comprise the solid model mobile jib being fixed on roadbed, the fixedly cutting ferrule contacting with channel-section steel mould, upper anchor ear, lower anchor ear, on stretch draw adjusting rod, under stretch and draw adjusting rod, anchor ear and lower anchor ear are installed on described solid model mobile jib, described upper anchor ear by stretch and draw adjusting rod to be connected with described fixedly cutting ferrule, described lower anchor ear by under stretch and draw adjusting rod to be connected with described fixedly cutting ferrule.Described upper anchor ear and lower anchor ear are arranged on described solid model mobile jib by fastening bolt, on described, stretch and draw adjusting rod one end to be arranged on described upper anchor ear by pivot pin or bolt, the other end is arranged on described fixed card cover upside by pivot pin or bolt, under described, stretch and draw adjusting rod one end to be arranged on described lower anchor ear by pivot pin or bolt, the other end is arranged on described fixedly cutting ferrule downside by pivot pin or bolt.On described, stretch draw adjusting rod and under stretch and draw adjusting rod to be formed along screw by nut pipe box and the anti-of tape spool eye that be rotated in described nut pipe box two ends.Described lower anchor ear is provided with the convenient protruding tongue of removing.
Tool of the present invention has the following advantages: 1. conveniently align and holddown groove steel mould; 2. can directly regulate the holddown groove steel mould of outer curve, not needing is the channel-section steel mould customized of building of the above bend of radius 20m again; 3. can adjust the channel-section steel mould of distortion; 4. descend anchor ear to be provided with protruding tongue for convenience detach, facilitate extracting of solid model mobile jib.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention
The specific embodiment
Below in conjunction with accompanying drawing, the invention will be further described.
Referring to Fig. 1, road concrete mold is adjusted solid model stake, comprise the solid model mobile jib 1 being fixed on roadbed, the fixedly cutting ferrule 5 contacting with channel-section steel mould, upper anchor ear 2, lower anchor ear 4, on stretch draw adjusting rod 7, under stretch and draw adjusting rod 6, anchor ear 2 and lower anchor ear 4 are installed on solid model mobile jib 1, upper anchor ear 2 by stretch and draw adjusting rod 7 to be connected with fixing cutting ferrule 5, lower anchor ear 4 by under stretch and draw adjusting rod 6 to be connected with fixing cutting ferrule 5.Upper anchor ear 2 and lower anchor ear 4 are arranged on solid model mobile jib 1 by fastening bolt 3, on stretch and draw adjusting rod 7 one end to be arranged on upper anchor ear 2 by pivot pin or bolt, the other end is arranged on fixedly cutting ferrule 5 upsides by pivot pin or bolt, under stretch and draw adjusting rod 6 one end to be arranged on lower anchor ear 4 by pivot pin or bolt, the other end is arranged on fixedly cutting ferrule 5 downsides by pivot pin or bolt.On stretch draw adjusting rod 7 and under stretch and draw adjusting rod 6 to be formed along screw 9 by nut pipe box 8 and the anti-of tape spool eye that be rotated in nut pipe box 8 two ends.Lower anchor ear 4 is provided with the convenient protruding tongue 11 of removing.
In the present invention, solid model mobile jib 1 is comprised of diameter 50mm pachydermia seamless steel pipe, housing, screw-thread steel, is generally 600~800mm long, during practical operation, can determine desired depth according to stressed degree, the limit depth steel mould of can rising as high as the banks.
During use, first solid model mobile jib 1 is arranged near on the ground of channel-section steel mould (fixedly the distance of mobile jib and channel-section steel mould should according to above stretch draw adjusting rod 7 with under stretch draw the length of adjusting rod 6 to determine), then by upper anchor ear 2, lower anchor ear 4 and on stretch and draw adjusting rod 7, under stretch and draw adjusting rod 6 to assemble on request, on moving according to actual needs again, lower anchor ear makes, under stretch and draw adjusting rod to open applicable angle, re-use fastening screw 3 by upper, lower anchor ear location, on finally regulating, under stretch and draw adjusting rod, make fixedly cutting ferrule 5 pressing groove steel mould and levelling channel-section steel mould (make channel-section steel mould perpendicular to the ground).
While using on the road at the above turning radius of 20m, by the long #20 channel-section steel of 3~4.5m mould, it is example, behind channel-section steel both mold ends location, the present invention can draw the accommodation limit (by the anti-elongation along screw and the shortening limit) of adjusting rod to determine the position that solid model mobile jib is installed according to upper and lower stretching, then utilize the characteristic of flow of metal, with upper and lower stretching, draw adjusting rod to promote fixedly cutting ferrule 5 to stretch the extremely radian of required adjusting of kerve steel mould, so just saved aim at 20m bend built punching block customized.
The present invention's displacement and dismounting are all very convenient, during dismounting, the lower anchor ear of solid model mobile jib 14 is fixing, then the force of doing using protruding tongue 11 positions of lower anchor ear 4 as crowbar (or jack), just solid model stake easily can be extracted.

Claims (4)

1. road concrete mold is adjusted solid model stake, comprise the solid model mobile jib (1) being fixed on roadbed, the fixedly cutting ferrule (5) contacting with channel-section steel mould, upper anchor ear (2), lower anchor ear (4), on stretch draw adjusting rod (7), under stretch and draw adjusting rod (6), it is characterized in that: anchor ear (2) and lower anchor ear (4) are installed on described solid model mobile jib (1), described upper anchor ear (2) by stretch and draw adjusting rod (7) to be connected with described fixedly cutting ferrule (5), described lower anchor ear (4) by under stretch and draw adjusting rod (6) to be connected with described fixedly cutting ferrule (5).
2. road concrete mold according to claim 1 is adjusted solid model stake, it is characterized in that: described upper anchor ear (2) and lower anchor ear (4) are arranged on described solid model mobile jib (1) by fastening bolt (3), on described, stretch and draw adjusting rod (7) one end to be arranged on described upper anchor ear (2) by pivot pin or bolt, the other end is arranged on described fixedly cutting ferrule (5) upside by pivot pin or bolt, under described, stretch and draw adjusting rod (6) one end to be arranged on described lower anchor ear (4) above by pivot pin or bolt, the other end is arranged on described fixedly cutting ferrule (5) downside by pivot pin or bolt.
3. road concrete mold according to claim 1 and 2 is adjusted solid model stake, it is characterized in that: on described, stretch draw adjusting rod (7) and under stretch and draw adjusting rod (6) to be formed by nut pipe box (8) and the anti-suitable screw (9) that is rotated in the tape spool eye at described nut pipe box (8) two ends.
4. road concrete mold according to claim 1 and 2 is adjusted solid model stake, it is characterized in that: described lower anchor ear (4) is provided with the convenient protruding tongue (11) of removing.
CN201310601084.XA 2013-11-11 2013-11-11 Adjusting and fixing pile for road concrete die Pending CN103669181A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310601084.XA CN103669181A (en) 2013-11-11 2013-11-11 Adjusting and fixing pile for road concrete die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310601084.XA CN103669181A (en) 2013-11-11 2013-11-11 Adjusting and fixing pile for road concrete die

Publications (1)

Publication Number Publication Date
CN103669181A true CN103669181A (en) 2014-03-26

Family

ID=50307897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310601084.XA Pending CN103669181A (en) 2013-11-11 2013-11-11 Adjusting and fixing pile for road concrete die

Country Status (1)

Country Link
CN (1) CN103669181A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107066649A (en) * 2016-12-09 2017-08-18 广东电网有限责任公司惠州供电局 Anchor ear method for determining size and device on electric pole in distribution line
CN108203912A (en) * 2018-01-31 2018-06-26 云南省建设投资控股集团有限公司 A kind of road side template adjusts fixing device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107066649A (en) * 2016-12-09 2017-08-18 广东电网有限责任公司惠州供电局 Anchor ear method for determining size and device on electric pole in distribution line
CN108203912A (en) * 2018-01-31 2018-06-26 云南省建设投资控股集团有限公司 A kind of road side template adjusts fixing device
CN108203912B (en) * 2018-01-31 2024-02-06 云南省建设投资控股集团有限公司 Road side form adjusting and fixing device

Similar Documents

Publication Publication Date Title
CN202467183U (en) Clamping and fixing device of reinforced concrete beam steel formwork
CN102776826B (en) A kind of pavement concrete channel-section steel typified form
CN202925675U (en) Non-return device use for pouring of steel column core concrete in lift-up method
CN204781970U (en) Template fixing device with adjustable
CN103669181A (en) Adjusting and fixing pile for road concrete die
CN202925896U (en) A hole reservation device for constructional engineering
CN204343319U (en) Cableway pipe patten pre-embedded anchoring bolts jig
CN201990922U (en) Adjusting and mold fixing pile for road concrete mold
CN208643834U (en) A kind of control cable anchor ear mold
CN205637578U (en) Roof beam increase cross -section combination steel form
CN105317230A (en) Fixing method of beam and wall pre-embedded horizontal sleeve
CN202787038U (en) Pavement concrete steel channel shaping formwork
CN202064638U (en) Stripping device for building construction formwork
CN205476528U (en) Precast pile device of taking one's place fast
CN203994169U (en) A kind of combined wall board casting mold
CN202039610U (en) Foundation basic template device of steel chimney
CN204299142U (en) A kind of unloading-structure of builder's jack
CN204074826U (en) A kind of engineering steel form distortion adjusting device
CN202248889U (en) Transverse tie rod type anchoring piece for fixing cast-in-place concrete inner mold
CN203066450U (en) Connecting clamp for scaffold
CN202390850U (en) Quick mounting structure for foundation of machine tool
CN205296201U (en) Positioner suitable for post installation of rim of a cup basis
CN201771183U (en) Adjustable type waist-beam mold supporting device
CN205975617U (en) Prestressing force pre -embedded steel pipe device
CN102051888A (en) Method for constructing built-in foundation bolt regulating hole of equipment foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140326