CN103559965B - A kind of installation method of supplementary chute and a kind of supplementary chute - Google Patents

A kind of installation method of supplementary chute and a kind of supplementary chute Download PDF

Info

Publication number
CN103559965B
CN103559965B CN201310519786.3A CN201310519786A CN103559965B CN 103559965 B CN103559965 B CN 103559965B CN 201310519786 A CN201310519786 A CN 201310519786A CN 103559965 B CN103559965 B CN 103559965B
Authority
CN
China
Prior art keywords
supplementary chute
glue
insulator
space
supplementary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310519786.3A
Other languages
Chinese (zh)
Other versions
CN103559965A (en
Inventor
马斌
方江
周曙琛
宋波
孙作敬
姜建泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Shenma Electric Power Co Ltd
Original Assignee
Jiangsu Shenma Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shenma Electric Power Co Ltd filed Critical Jiangsu Shenma Electric Power Co Ltd
Priority to CN201310519786.3A priority Critical patent/CN103559965B/en
Publication of CN103559965A publication Critical patent/CN103559965A/en
Application granted granted Critical
Publication of CN103559965B publication Critical patent/CN103559965B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)
  • Insulators (AREA)

Abstract

The present invention discloses a kind of installation method of supplementary chute and a kind of supplementary chute, and the installation method of the supplementary chute comprises the following steps:A, the auxiliary umbrella cover is located on the full skirt to be set;B, the upper and lower ends that the supplementary chute connects with insulator are blocked, makes the space that relative closure is formed between the supplementary chute and the insulator, the space is in communication with the outside by steam vent;C, glue is injected in the space, until the air in the space is drained from the steam vent, makes to be full of the glue in the space.A kind of supplementary chute is disclosed in addition, and on the insulator, the insulator includes some full skirts for installation, and the supplementary chute includes the fixed part for covering the full skirt upper surface, and the fixed part is connected on the full skirt by binding agent, and steam vent is offered on the fixed part.The installation method and supplementary chute of above-mentioned supplementary chute, firmly supplementary chute can be fixed on the insulator, supplementary chute is had longer service life.

Description

A kind of installation method of supplementary chute and a kind of supplementary chute
Technical field
The present invention relates to a kind of power equipment manufacturing field, the installation method of specifically a kind of supplementary chute and a kind of auxiliary Umbrella.
Background technology
Since high voltage power transmission is enabled, outer insulating material usual earlier ceramic material.As atmospheric environment deteriorates, air Pollution flashover accident constantly occurs in the case of contamination, huge loss is caused to power network, sternly for gradation for surface pollution more and more higher, porcelain insulator The even running of power network is have impact on again.Simultaneously as the problems such as heavy rain and icing, the accidents such as the rain of porcelain insulator dodges, ice dodges Tend to take place frequently.
Currently for pollution flashover problem, grid company more recommends composite insulator in new construction.It is but right For the power station built up and be currently running, a kind of method is in the side of porcelain insulator surface spraying RTV/PRTV coating Method, not only cost is high for the method, and restricted lifetime, can not fundamentally ensure longtime running.
The content of the invention
In view of the shortcomings of the prior art, it is an object of the invention to provide a kind of installation method of supplementary chute and a kind of auxiliary The supplementary chute can be firmly fixed on insulator by umbrella, the installation method of the supplementary chute and the supplementary chute, increase supplementary chute Service life.
For achieving the above object, the technology used in the present invention means are as follows:A kind of installation method of supplementary chute, should Supplementary chute is installed on the insulator, and the insulator includes some full skirts, and the supplementary chute includes being covered in consolidating for the full skirt upper surface Determine portion, the installation method of the supplementary chute comprises the following steps:A, the auxiliary umbrella cover is located on the corresponding full skirt;B, it is this is auxiliary The upper and lower ends for helping umbrella to connect with the insulator are blocked, and make the sky that relative closure is formed between the supplementary chute and the insulator Between, the space is in communication with the outside by steam vent;C, glue is injected in the space, until the air in the space is from the exhaust It is drained in hole, make to be full of the glue in the space.
Preferably, above-mentioned steam vent is opened in fixation portions.
Preferably, above-mentioned steam vent is formed by above-mentioned plug.When being blocked in stepb with the plug, reserve One piece, without closure, forms above-mentioned steam vent.
Preferably, hole for injecting glue is offered on above-mentioned supplementary chute, in above-mentioned steps c, above-mentioned glue is injected by the hole for injecting glue In above-mentioned space.
Preferably, in above-mentioned steps c, above-mentioned glue is directly pierced through above-mentioned supplementary chute by syringe needle and entered in above-mentioned space, The glue is injected.Such a method, it is not necessary to hole for injecting glue is additionally opened on the supplementary chute, injecting glue position is not limited to, and injecting glue is convenient. In addition, after injecting glue, the syringe needle is extracted, due to the elasticity of the supplementary chute in itself, the pin hole that the syringe needle pierces out can nature Closure, with the solidification of the glue, the pin hole is closed completely, it is not necessary to extra operation is carried out to pin hole herein.It is more excellent Selection of land, the tip of above-mentioned syringe needle have side, and gum outlet is opened on the side.It is smooth by the syringe needle to be so more conducive to above-mentioned glue Ground flows out, without being obstructed.
Preferably, above-mentioned glue injects in above-mentioned space from the bottom to top.Such a mode, air can be made more to be smoothly discharged out, Avoid forming bubble in the glue, so that influenceing bond quality.
Preferably, after the solidification of above-mentioned glue, the above-mentioned plug of setting is removed.Above-mentioned insulator surface is set to keep light It is clean, to prevent influenceing the insulating properties of insulator.
For achieving the above object, the present invention also provides a kind of supplementary chute, and the supplementary chute is installed on the insulator, and this is exhausted Edge attached bag includes some full skirts, and the supplementary chute includes the fixed part for covering the full skirt surface, and the fixed part is connected to by binding agent On the full skirt, steam vent is offered on the fixed part.The steam vent can be smoothly discharged out the supplementary chute and the insulation in injecting glue Air between son, bond both more firm, bubble will not be produced therebetween, add the supplementary chute uses the longevity Life.
Preferably, hole for injecting glue is offered in fixation portions.When the hole for injecting glue can facilitate injecting glue, injected rubber hose is stretched from there Enter.
The installation method and supplementary chute of above-mentioned supplementary chute, the supplementary chute can be firmly fixed on insulator, two Be not in gap between person, both faying faces will not be caused to be contaminated because of long-term use, so that influenceing insulation The insulating properties of son.The installation method and supplementary chute of the supplementary chute of the present invention, it is ensured that the supplementary chute has longer service life.
Brief description of the drawings
Fig. 1 is the schematic diagram that the supplementary chute 100 of the embodiment of the present invention one is set on insulator 200;
Fig. 2 is the schematic diagram of the syringe needle 300 used in the embodiment of the present invention two;
Fig. 3 is that the applicable another supplementary chute 400 of the installation method of supplementary chute of the present invention is set in showing on insulator 500 It is intended to.
Embodiment
As requested, the embodiment of the present invention will be disclosed here.It is it is to be understood, however, that described herein Embodiment be only the present invention exemplary, it can be presented as various forms.Therefore, what is disclosed here is specific thin Section is not to be considered as limiting, and is merely possible to the basis of claim and is used as be used to instruct those skilled in the art By in practice it is any it is appropriate in a manner of differently using the representational basis of the present invention, including using described herein various Feature simultaneously combines the feature that may do not disclosed clearly here.
Embodiment one:
As shown in figure 1, it is set in the schematic diagram on insulator 200 for the present embodiment supplementary chute 100.Insulator 200 includes Some full skirts 20.Supplementary chute 100 includes the fixed part 14 for being covered in the upper surface of full skirt 20, and the upper end of fixed part 14 is provided with exhaust Hole 11, the lower end of supplementary chute 100 are provided with hole for injecting glue 12.The position that the upper and lower ends of supplementary chute 100 connect with insulator 200 is set There is plug 10.Supplementary chute 100 is provided with space 13 with the surface of full skirt 20, for being subsequently filled with glue.
The installation method of the supplementary chute of the present embodiment comprises the following steps:
A, supplementary chute 100 is set on full skirt 20;
B, supplementary chute 100 is blocked with the upper and lower ends that insulator 200 connects with plug 10, by supplementary chute 100 Opening blocked, retain be reserved in the top of supplementary chute 100 steam vent 11 and auxiliary umbrella lower part hole for injecting glue 12, make auxiliary Help between umbrella 100 and insulator 200 and form the space 13 of relative closure;
C, by the way that glue is filled with space 13 by injected rubber hose insertion hole for injecting glue 12 from the bottom to top, air is made from steam vent 11 Middle discharge, until being full of glue in space 13;
D, after glue solidification, the plug 10 on the surface of insulator 200 is removed.
The installation method and supplementary chute 100 of the supplementary chute of the present embodiment, by being full of glue from the bottom to top in space 13, And solidify afterwards, supplementary chute 100 is firmly fixed on insulator 200, is not in gap between the two, will not be because of long-term Use and cause both faying faces to be contaminated so that influenceing the insulating properties of insulator, and then improve supplementary chute 100 Useful life.
Embodiment two:
As shown in Fig. 2 the schematic diagram for the syringe needle 300 used in the embodiment of the present invention two.One tip is set on syringe needle 300 30, for being pierced into supplementary chute, the other end of syringe needle 300 is connected with injected rubber hose.The side at tip 30 is provided with gum outlet 31, plastic emitting Mouthfuls 31, which are arranged on side, is more conducive to glue and is swimmingly flowed out by syringe needle 300, without being obstructed.Under the supplementary chute of the present embodiment Portion is not required to reserved hole for injecting glue.
The installation method of the supplementary chute of the present embodiment comprises the following steps:
A, auxiliary umbrella cover is located on full skirt;
B, the upper and lower ends that supplementary chute connects with insulator are blocked with plug, the opening of supplementary chute is carried out Closure, retain the steam vent for being reserved in supplementary chute top, make the space that relative closure is formed between supplementary chute and insulator;
C, by the way that syringe needle 300 is pierced into above-mentioned space, glue is filled with space from the bottom to top, makes air from steam vent Middle discharge, until being full of glue in the space;
D, after glue solidification, the plug of insulator surface is removed.
The installation method of the supplementary chute of the present embodiment, in addition to the advantages of installation method of the supplementary chute with embodiment one, Injecting glue is carried out due to being pierced into supplementary chute with syringe needle 300, it is not necessary to additionally opens up hole for injecting glue on supplementary chute, injecting glue position not office Limit, it is easy to operate during injecting glue.After injecting glue, syringe needle 300 is extracted, due to the elasticity of supplementary chute in itself, the pin that syringe needle pierces out Hole meeting Natural closure, with the solidification of glue, pin hole is closed completely, it is not necessary to extra operation is carried out to pin hole herein.
As shown in figure 3, it is set in insulator for the applicable another supplementary chute 400 of the installation method of supplementary chute of the present invention Schematic diagram on 500.Some full skirts 50 are provided with insulator 500.The upper and lower ends of supplementary chute 400 connect with insulator 500 Position is provided with plug 40.Supplementary chute 400 includes the fixed part 44 for being covered in the upper surface of full skirt 50, and the upper end of fixed part 44 is set Steam vent 41 is equipped with, hole for injecting glue 42 is provided with the plug 40 of the lower end of supplementary chute 400(Equally, the plug of the upper end Steam vent can be formed).Supplementary chute 400 is provided with space 43 with the surface of full skirt 50, for being subsequently filled with glue.As shown in Figure 3 Supplementary chute 400 not exclusively coat full skirt 50, the installation method of supplementary chute of the invention is equally applicable to such supplementary chute.
The technology contents and technical characterstic of the present invention have revealed that as above, it being understood, however, that in the creative ideas of the present invention Under, those skilled in the art can make various changes and improve to said structure and material, including individually discloses or want here Ask the combination of the technical characteristic of protection, it will be apparent that other combinations including these features.These deformations and/or combination each fall within this In the involved technical field of invention, and fall into the protection domain of the claims in the present invention.

Claims (5)

1. a kind of installation method of supplementary chute, on the insulator, the insulator includes some full skirts, institute for the supplementary chute installation The fixed part that supplementary chute includes being covered in the full skirt upper surface is stated, the installation method of the supplementary chute comprises the following steps:
A, the auxiliary umbrella cover is located on the corresponding full skirt;
B, the upper and lower ends that the supplementary chute connects with the insulator are blocked by the plug being independently arranged respectively, Make the space that relative closure is formed between the supplementary chute and the insulator, the space is in communication with the outside by steam vent;
C, glue is injected in the space, until the air in the space is drained from the steam vent, makes the space It is interior to be full of the glue;
Wherein, in the step c, the glue is directly pierced through the supplementary chute by syringe needle and entered in the space, by described in Glue injects, and the tip of the syringe needle has side, gum outlet is opened on the side;
D, after glue solidification, the plug of insulator surface is removed.
2. the installation method of supplementary chute as claimed in claim 1, it is characterised in that:The steam vent is opened in the fixed part On.
3. the installation method of supplementary chute as claimed in claim 1, it is characterised in that:The steam vent is by the plug shape Into.
4. the installation method of supplementary chute as claimed in claim 1, it is characterised in that:Hole for injecting glue is offered on the supplementary chute, Glue described in the step c is injected in the space by the hole for injecting glue.
5. the installation method of supplementary chute as claimed in claim 1, it is characterised in that:The glue injects the sky from the bottom to top In.
CN201310519786.3A 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute Active CN103559965B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310519786.3A CN103559965B (en) 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310519786.3A CN103559965B (en) 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute

Publications (2)

Publication Number Publication Date
CN103559965A CN103559965A (en) 2014-02-05
CN103559965B true CN103559965B (en) 2017-11-17

Family

ID=50014187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310519786.3A Active CN103559965B (en) 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute

Country Status (1)

Country Link
CN (1) CN103559965B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105679470B (en) * 2016-03-29 2017-06-13 江苏神马电力股份有限公司 Insulator and its adhesive binding method
WO2020186957A1 (en) * 2019-03-21 2020-09-24 江苏神马电力股份有限公司 Auxiliary skirt and auxiliary skirt mounting method
CN109817398B (en) * 2019-03-21 2021-01-15 江苏神马电力股份有限公司 Method for mounting auxiliary umbrella

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0121133A2 (en) * 1983-03-09 1984-10-10 DÄTWYLER AG Schweizerische Kabel- Gummi- und Kunststoffwerke Method of making an electrical synthetic insulator, and insulator made by the method
CN2084644U (en) * 1990-12-29 1991-09-11 湖北省襄樊电力设备厂 Composite insulator
CN2563718Y (en) * 2002-08-30 2003-07-30 贵州恒昌科技开发有限公司 Silicon rubber dirt-proof flashing increase climbing apron
CN201340766Y (en) * 2008-12-05 2009-11-04 南方电网技术研究中心 Flange for ultra-high voltage post composite insulator
CN201829264U (en) * 2010-10-19 2011-05-11 河南爱迪德电力设备有限责任公司 Porcelain body provided with discontinuous salients at gluing part
CN202563986U (en) * 2012-05-30 2012-11-28 莱州市虹桥电力设备有限公司 Disc double-umbrella porcelain composite insulator
CN202905303U (en) * 2012-11-26 2013-04-24 河北硅谷化工有限公司 Creepage extender used in composite insulation equipment
CN202905311U (en) * 2012-09-28 2013-04-24 内蒙古大唐国际托克托发电有限责任公司 500kV and 220kV composite silicone rubber CT bushing
CN203150328U (en) * 2013-03-24 2013-08-21 吉林泷鑫电气设备有限公司 Composite-insulator enlarged umbrella with reinforcing connection ribs

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6424324A (en) * 1987-07-20 1989-01-26 Nissin Electric Co Ltd Water drip shed of insulating tube

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0121133A2 (en) * 1983-03-09 1984-10-10 DÄTWYLER AG Schweizerische Kabel- Gummi- und Kunststoffwerke Method of making an electrical synthetic insulator, and insulator made by the method
CN2084644U (en) * 1990-12-29 1991-09-11 湖北省襄樊电力设备厂 Composite insulator
CN2563718Y (en) * 2002-08-30 2003-07-30 贵州恒昌科技开发有限公司 Silicon rubber dirt-proof flashing increase climbing apron
CN201340766Y (en) * 2008-12-05 2009-11-04 南方电网技术研究中心 Flange for ultra-high voltage post composite insulator
CN201829264U (en) * 2010-10-19 2011-05-11 河南爱迪德电力设备有限责任公司 Porcelain body provided with discontinuous salients at gluing part
CN202563986U (en) * 2012-05-30 2012-11-28 莱州市虹桥电力设备有限公司 Disc double-umbrella porcelain composite insulator
CN202905311U (en) * 2012-09-28 2013-04-24 内蒙古大唐国际托克托发电有限责任公司 500kV and 220kV composite silicone rubber CT bushing
CN202905303U (en) * 2012-11-26 2013-04-24 河北硅谷化工有限公司 Creepage extender used in composite insulation equipment
CN203150328U (en) * 2013-03-24 2013-08-21 吉林泷鑫电气设备有限公司 Composite-insulator enlarged umbrella with reinforcing connection ribs

Also Published As

Publication number Publication date
CN103559965A (en) 2014-02-05

Similar Documents

Publication Publication Date Title
CN103559965B (en) A kind of installation method of supplementary chute and a kind of supplementary chute
US10066599B2 (en) Spar cap assembly for a wind turbine rotor blade
CN103545062B (en) Auxiliary umbrella cover
CN105121843A (en) Wind turbine blades
CN201298408Y (en) A birds droppings proofing insulator
CN206539106U (en) A kind of antidetonation communications tower
CN203456317U (en) Rainproof insulating rod and brake pull rod containing the same
CN203617048U (en) Auxiliary umbrella cover
CN107968377B (en) Low-cost bunched overhead cable end sealing method
CN104599794B (en) The method for maintaining of maintenance umbrella and insulator
CN204179630U (en) A kind of cable intermediate joint waterproof anti-explosion box
CN206363817U (en) A kind of composite insulator for insulated wire
CN205911332U (en) Novel battery core support and use this battery core support's battery package thereof
CN104538131A (en) Auxiliary shed cover
CN210516348U (en) High-strength extra-high voltage composite insulator
CN205943609U (en) Rain -proof composite post insulator that dodges
CN207367702U (en) A kind of umbrella cover
CN106898441A (en) Umbrella cover and the electrical equipment using the umbrella cover
CN206961557U (en) A kind of flat cable for being used for outdoor pre-buried installation
CN206819819U (en) The electrical equipment of umbrella cover and the application umbrella cover
CN109148060A (en) The preparation method of umbrella cover, electrical equipment and umbrella cover
CN204696630U (en) 110kV dry type silicone rubber for cable terminal
CN205355740U (en) Rainproof net device of joining in marriage
CN109767882A (en) Supplementary chute and insulator containing the supplementary chute
CN205081362U (en) Outdoor protection against electric shock electric power cabinet

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant