CN103559965A - Auxiliary umbrella installing method and auxiliary umbrella - Google Patents

Auxiliary umbrella installing method and auxiliary umbrella Download PDF

Info

Publication number
CN103559965A
CN103559965A CN201310519786.3A CN201310519786A CN103559965A CN 103559965 A CN103559965 A CN 103559965A CN 201310519786 A CN201310519786 A CN 201310519786A CN 103559965 A CN103559965 A CN 103559965A
Authority
CN
China
Prior art keywords
supplementary chute
insulator
space
glue
chute
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310519786.3A
Other languages
Chinese (zh)
Other versions
CN103559965B (en
Inventor
马斌
方江
周曙琛
宋波
孙作敬
姜建泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Shenma Electric Power Co Ltd
Original Assignee
Jiangsu Shenma Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shenma Electric Power Co Ltd filed Critical Jiangsu Shenma Electric Power Co Ltd
Priority to CN201310519786.3A priority Critical patent/CN103559965B/en
Publication of CN103559965A publication Critical patent/CN103559965A/en
Application granted granted Critical
Publication of CN103559965B publication Critical patent/CN103559965B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Insulators (AREA)
  • Electric Cable Installation (AREA)

Abstract

The invention discloses an auxiliary umbrella installing method and an auxiliary umbrella. The auxiliary umbrella installing method comprises the following steps: step a, the auxiliary umbrella is arranged on umbrella skirts where the auxiliary umbrella needs to be arranged in a sleeved mode; step b, the upper end and lower end, connected with an insulator, of the auxiliary umbrella are blocked, so that a relatively closed space is formed between the auxiliary umbrella and the insulator, and the space is communicated with the outside through vent holes; step c, a glue solution is injected in the space till air in the space is completely discharged from the vent holes, and the space is filled with the glue solution. Beside, the invention further discloses the auxiliary umbrella which is mounted on the insulator, wherein the insulator comprises the multiple umbrella skirts, the auxiliary umbrella comprises fixing parts which cover the upper surfaces of the umbrella skirts, and the fixing parts are connected to the umbrella skirts through binders and provided with the vent holes. According to the auxiliary umbrella installing method and the auxiliary umbrella, the auxiliary umbrella can be firmly fixed to the insulator, so that the service life of the auxiliary umbrella is quite long.

Description

A kind of installation method of supplementary chute and a kind of supplementary chute
Technical field
The present invention relates to a kind of power equipment and manufacture field, specifically a kind of installation method of supplementary chute and a kind of supplementary chute.
Background technology
Since enabling high voltage power transmission, outer insulating material usual earlier ceramic material.Along with atmospheric environment worsens, air gradation for surface pollution is more and more higher, and pollution flashover accident constantly occurs porcelain insulator in contamination situation, to electrical network, causes huge loss, has had a strong impact on the even running of electrical network.Meanwhile, due to problems such as heavy rain and icing, the accidents such as the sudden strain of a muscle of the rain of porcelain insulator, ice sudden strain of a muscle are also tending towards taking place frequently.
For pollution flashover problem, grid company is more recommendation composite insulator in new construction at present.Yet for the power station of building up and moving, a kind of method is that the method not only cost is high, and the life-span is limited, cannot fundamentally guarantee long-time running in the method for porcelain insulator surface spraying RTV/PRTV coating.
Summary of the invention
For the deficiencies in the prior art, the object of this invention is to provide a kind of installation method and a kind of supplementary chute of supplementary chute, the installation method of this supplementary chute and this supplementary chute can firmly be fixed on this supplementary chute on insulator, increase the useful life of supplementary chute.
For achieving the above object, the technology used in the present invention means are as follows: a kind of installation method of supplementary chute, this supplementary chute is arranged on insulator, this insulator comprises some full skirts, this supplementary chute comprises the fixed part that covers this full skirt upper surface, and the installation method of this supplementary chute comprises the following steps: a, this supplementary chute is set on this corresponding full skirt; Shutoff is carried out at b, the two ends up and down that this supplementary chute and this insulator are joined, and the ,Gai space, space that forms relative closure between this supplementary chute and this insulator is in communication with the outside by steam vent; C, glue is injected in this space, until the air in this space is drained from this steam vent, make to be full of in this space this glue.
Preferably, above-mentioned steam vent is opened on above-mentioned fixed part.
Preferably, above-mentioned steam vent is formed by above-mentioned plug.While carrying out shutoff with this plug in step b, reserved one is not carried out shutoff, forms above-mentioned steam vent.
Preferably, on above-mentioned supplementary chute, offer hole for injecting glue, in above-mentioned steps c, above-mentioned glue injects in above-mentioned space by this hole for injecting glue.
Preferably, in above-mentioned steps c, above-mentioned glue directly pierces through above-mentioned supplementary chute by syringe needle and enters in above-mentioned space, and this glue is injected.This kind of method, does not need additionally on this supplementary chute, to open hole for injecting glue, and does not limit to injecting glue position, and injecting glue is convenient.In addition, after injecting glue, this syringe needle is extracted, due to the elasticity of this supplementary chute itself, pin hole that this syringe needle stings out can Natural closure, and along with solidifying of this glue, this pin hole is completely closed, does not need pin hole herein to carry out extra operation.More preferably, the tip of above-mentioned syringe needle has on ,Gai side, side and opens gum outlet.Be more conducive to so above-mentioned glue and flowed out swimmingly by this syringe needle, and can not be intercepted.
Preferably, above-mentioned glue injects in above-mentioned space from the bottom to top.This kind of mode, can make air more successfully discharge, and avoids forming bubble in this glue, so that affects bond quality.
Preferably, after above-mentioned glue solidifies, the above-mentioned plug arranging is removed.Make above-mentioned insulator surface keep bright and clean, in case affect the insulation property of insulator.
For achieving the above object, the present invention also provides a kind of supplementary chute, and this supplementary chute is arranged on insulator, this insulator comprises some full skirts, this supplementary chute comprises the fixed part that covers this full skirt surface, and this fixed part is connected on this full skirt by binding agent, on this fixed part, offers steam vent.This steam vent can successfully be discharged the air between this supplementary chute and this insulator when injecting glue, makes both bondings more firm, can not produce bubble by between, has increased the useful life of this supplementary chute.
Preferably, on above-mentioned fixed part, offer hole for injecting glue.When this hole for injecting glue can facilitate injecting glue, injected rubber hose stretches into from here.
The installation method of above-mentioned supplementary chute and supplementary chute, can firmly be fixed on this supplementary chute on insulator, can not have gap between the two, can not cause because of long-term use both faying faces to be polluted, so that affect the insulation property of insulator.The installation method of supplementary chute of the present invention and supplementary chute, can guarantee that this supplementary chute has longer useful life.
Accompanying drawing explanation
Fig. 1 is that the embodiment of the present invention one supplementary chute 100 is set in the schematic diagram on insulator 200;
Fig. 2 is the schematic diagram of the embodiment of the present invention two syringe needle 300 used;
Fig. 3 is that the applicable another kind of supplementary chute 400 of installation method of supplementary chute of the present invention is set in the schematic diagram on insulator 500.
Embodiment
As requested, will disclose the specific embodiment of the present invention here.Yet, should be understood that, disclosed execution mode is only exemplary of the present invention here, it can be presented as various forms.Therefore, here the detail disclosing is not considered to restrictive, and be only as the basis of claim and as for instructing those skilled in the art differently to apply representational basis of the present invention in any appropriate mode of reality, comprise employing disclosed various features in conjunction with the feature that may clearly not disclose here here.
Embodiment mono-:
As shown in Figure 1, for the present embodiment supplementary chute 100 is set in the schematic diagram on insulator 200.Insulator 200 comprises some full skirts 20.Supplementary chute 100 comprises the fixed part 14 that covers full skirt 20 upper surfaces, and the upper end of fixed part 14 is provided with steam vent 11, and the lower end of supplementary chute 100 is provided with hole for injecting glue 12.The supplementary chute position that Shang Xia 100, two ends and insulator 200 join is provided with plug 10.Supplementary chute 100 is provided with space 13 with full skirt 20 surfaces, for the follow-up glue that is filled with.
The installation method of the supplementary chute of the present embodiment comprises the following steps:
A, supplementary chute 100 is set on full skirt 20;
Shutoff is carried out with plug 10 in b, the two ends up and down that supplementary chute 100 and insulator 200 are joined, the opening part of supplementary chute 100 is carried out to shutoff, retain and be reserved in the steam vent 11 on supplementary chute 100 tops and the hole for injecting glue 12 of supplementary chute bottom, make to form between supplementary chute 100 and insulator 200 space 13 of relative closure;
C, by injected rubber hose being inserted to hole for injecting glue 12, glue is filled with in space 13 from the bottom to top, air is discharged from steam vent 11, until be full of glue in space 13;
D, after glue solidifies, remove the plug 10 on insulator 200 surfaces.
The installation method of the supplementary chute of the present embodiment and supplementary chute 100, by be full of from the bottom to top glue in space 13, then solidify, supplementary chute 100 is firmly fixed on insulator 200, can there is not gap between the two, can not cause because of long-term use both faying faces to be polluted, so that affect the insulation property of insulator, and then improve the useful life of supplementary chute 100.
Embodiment bis-:
As shown in Figure 2, be the schematic diagram of the embodiment of the present invention two syringe needle 300 used.One tip 30 is set on syringe needle 300, and for thrusting supplementary chute, the other end of syringe needle 300 is connected with injected rubber hose.Most advanced and sophisticated 30 side is provided with gum outlet 31, and gum outlet 31 is arranged on side and is more conducive to glue and is flowed out swimmingly by syringe needle 300, and can not intercepted.The supplementary chute bottom of the present embodiment does not need reserved hole for injecting glue.
The installation method of the supplementary chute of the present embodiment comprises the following steps:
A, supplementary chute is set on full skirt;
Shutoff is carried out with plug in b, the two ends up and down that supplementary chute and insulator are joined, and the opening part of supplementary chute is carried out to shutoff, retains the steam vent that is reserved in supplementary chute top, makes to form between supplementary chute and insulator the space of relative closure;
C, by syringe needle 300 is thrust in above-mentioned space, glue is filled with in space from the bottom to top, air is discharged from steam vent, until be full of glue in this space;
D, after glue solidifies, remove the plug of insulator surface.
The installation method of the supplementary chute of the present embodiment, except having the advantage of installation method of supplementary chute of embodiment mono-, owing to thrusting supplementary chute with syringe needle 300, carry out injecting glue, do not need additionally on supplementary chute, to offer hole for injecting glue, does not limit to injecting glue position, easy to operate during injecting glue.After injecting glue, syringe needle 300 is extracted, due to the elasticity of supplementary chute itself, pin hole that syringe needle stings out can Natural closure, and along with solidifying of glue, pin hole is completely closed, does not need pin hole herein to carry out extra operation.
As shown in Figure 3, for the applicable another kind of supplementary chute 400 of the installation method of supplementary chute of the present invention is set in the schematic diagram on insulator 500.On insulator 500, be provided with some full skirts 50.The supplementary chute position that Shang Xia 400, two ends and insulator 500 join is provided with plug 40.Supplementary chute 400 comprises the fixed part 44 that covers full skirt 50 upper surfaces, and the upper end of fixed part 44 is provided with steam vent 41, is provided with hole for injecting glue 42(same on the plug 40 of the lower end of supplementary chute 400, and the plug of this upper end also can form steam vent).Supplementary chute 400 is provided with space 43 with full skirt 50 surfaces, for the follow-up glue that is filled with.Supplementary chute 400 is not exclusively coated full skirt 50 as shown in Figure 3, and the installation method of supplementary chute of the present invention is applicable equally to this type of supplementary chute.
Technology contents of the present invention and technical characterstic have disclosed as above; yet be appreciated that; under creative ideas of the present invention; those skilled in the art can make various changes and improve said structure and material; comprise here and to disclose separately or the combination of claimed technical characterictic, comprise significantly other combination of these features.These distortion and/or combination all fall in technical field involved in the present invention, and fall into the protection range of the claims in the present invention.

Claims (10)

1. an installation method for supplementary chute, described supplementary chute is arranged on insulator, and described insulator comprises some full skirts, and described supplementary chute comprises the fixed part that covers described full skirt upper surface, and the installation method of described supplementary chute comprises the following steps:
A, described supplementary chute is set on corresponding described full skirt;
Shutoff is carried out by plug respectively in b, the two ends up and down that described supplementary chute and described insulator are joined, and makes to form between described supplementary chute and described insulator the space of relative closure, and described space is in communication with the outside by steam vent;
C, glue is injected in described space, until the air in described space is drained from described steam vent, make to be full of in described space described glue.
2. the installation method of supplementary chute as claimed in claim 1, is characterized in that: described steam vent is opened on described fixed part.
3. the installation method of supplementary chute as claimed in claim 1, is characterized in that: described steam vent is formed by described plug.
4. the installation method of supplementary chute as claimed in claim 1, is characterized in that: on described supplementary chute, offer hole for injecting glue, described in described step c, glue injects in described space by described hole for injecting glue.
5. the installation method of supplementary chute as claimed in claim 1, is characterized in that: in described step c, described glue directly pierces through described supplementary chute by syringe needle and enters in described space, and described glue is injected.
6. the installation method of supplementary chute as claimed in claim 5, is characterized in that: the tip of described syringe needle has side, on described side, opens gum outlet.
7. the installation method of supplementary chute as claimed in claim 1, is characterized in that: described glue injects in described space from the bottom to top.
8. the installation method of supplementary chute as claimed in claim 1, is characterized in that: after described glue solidifies, the described plug arranging is removed.
9. a supplementary chute, be arranged on insulator, described insulator comprises some full skirts, and described supplementary chute comprises the fixed part that covers described full skirt upper surface, described fixed part is connected on described full skirt by binding agent, it is characterized in that: on described fixed part, offer steam vent.
10. supplementary chute as claimed in claim 9, is characterized in that: on described fixed part, offer hole for injecting glue.
CN201310519786.3A 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute Active CN103559965B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310519786.3A CN103559965B (en) 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310519786.3A CN103559965B (en) 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute

Publications (2)

Publication Number Publication Date
CN103559965A true CN103559965A (en) 2014-02-05
CN103559965B CN103559965B (en) 2017-11-17

Family

ID=50014187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310519786.3A Active CN103559965B (en) 2013-10-29 2013-10-29 A kind of installation method of supplementary chute and a kind of supplementary chute

Country Status (1)

Country Link
CN (1) CN103559965B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017166979A1 (en) * 2016-03-29 2017-10-05 江苏神马电力股份有限公司 Insulator and glue binding method therefor
CN109817398A (en) * 2019-03-21 2019-05-28 江苏神马电力股份有限公司 The installation method of supplementary chute
WO2020186957A1 (en) * 2019-03-21 2020-09-24 江苏神马电力股份有限公司 Auxiliary skirt and auxiliary skirt mounting method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0121133A2 (en) * 1983-03-09 1984-10-10 DÄTWYLER AG Schweizerische Kabel- Gummi- und Kunststoffwerke Method of making an electrical synthetic insulator, and insulator made by the method
JPS6424324A (en) * 1987-07-20 1989-01-26 Nissin Electric Co Ltd Water drip shed of insulating tube
CN2084644U (en) * 1990-12-29 1991-09-11 湖北省襄樊电力设备厂 Composite insulator
CN2563718Y (en) * 2002-08-30 2003-07-30 贵州恒昌科技开发有限公司 Silicon rubber dirt-proof flashing increase climbing apron
CN201340766Y (en) * 2008-12-05 2009-11-04 南方电网技术研究中心 Flange for ultra-high voltage post composite insulator
CN201829264U (en) * 2010-10-19 2011-05-11 河南爱迪德电力设备有限责任公司 Porcelain body provided with discontinuous salients at gluing part
CN202563986U (en) * 2012-05-30 2012-11-28 莱州市虹桥电力设备有限公司 Disc double-umbrella porcelain composite insulator
CN202905303U (en) * 2012-11-26 2013-04-24 河北硅谷化工有限公司 Creepage extender used in composite insulation equipment
CN202905311U (en) * 2012-09-28 2013-04-24 内蒙古大唐国际托克托发电有限责任公司 500kV and 220kV composite silicone rubber CT bushing
CN203150328U (en) * 2013-03-24 2013-08-21 吉林泷鑫电气设备有限公司 Composite-insulator enlarged umbrella with reinforcing connection ribs

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0121133A2 (en) * 1983-03-09 1984-10-10 DÄTWYLER AG Schweizerische Kabel- Gummi- und Kunststoffwerke Method of making an electrical synthetic insulator, and insulator made by the method
JPS6424324A (en) * 1987-07-20 1989-01-26 Nissin Electric Co Ltd Water drip shed of insulating tube
CN2084644U (en) * 1990-12-29 1991-09-11 湖北省襄樊电力设备厂 Composite insulator
CN2563718Y (en) * 2002-08-30 2003-07-30 贵州恒昌科技开发有限公司 Silicon rubber dirt-proof flashing increase climbing apron
CN201340766Y (en) * 2008-12-05 2009-11-04 南方电网技术研究中心 Flange for ultra-high voltage post composite insulator
CN201829264U (en) * 2010-10-19 2011-05-11 河南爱迪德电力设备有限责任公司 Porcelain body provided with discontinuous salients at gluing part
CN202563986U (en) * 2012-05-30 2012-11-28 莱州市虹桥电力设备有限公司 Disc double-umbrella porcelain composite insulator
CN202905311U (en) * 2012-09-28 2013-04-24 内蒙古大唐国际托克托发电有限责任公司 500kV and 220kV composite silicone rubber CT bushing
CN202905303U (en) * 2012-11-26 2013-04-24 河北硅谷化工有限公司 Creepage extender used in composite insulation equipment
CN203150328U (en) * 2013-03-24 2013-08-21 吉林泷鑫电气设备有限公司 Composite-insulator enlarged umbrella with reinforcing connection ribs

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017166979A1 (en) * 2016-03-29 2017-10-05 江苏神马电力股份有限公司 Insulator and glue binding method therefor
CN109817398A (en) * 2019-03-21 2019-05-28 江苏神马电力股份有限公司 The installation method of supplementary chute
WO2020186957A1 (en) * 2019-03-21 2020-09-24 江苏神马电力股份有限公司 Auxiliary skirt and auxiliary skirt mounting method

Also Published As

Publication number Publication date
CN103559965B (en) 2017-11-17

Similar Documents

Publication Publication Date Title
CN103559965A (en) Auxiliary umbrella installing method and auxiliary umbrella
CN103545062A (en) Auxiliary umbrella cover
CN102426879B (en) Phase isolated cast tubular bus and preparation method thereof
CN206481030U (en) A kind of GIS cable termination devices and the GIS device using the device
CN203617048U (en) Auxiliary umbrella cover
CN203983004U (en) A kind of novel large transformer high-voltage bushing
CN105119161B (en) A kind of terminal box
CN206211485U (en) A kind of roof high voltage cable plug-in and pull-off device of electric locomotive or EMUs high-voltaghe compartment
CN205292677U (en) Connecting rod insulated terminal end of car retarder
CN104465157A (en) 10 kV pole-mounted switch protection cover
CN204651109U (en) Pillar insulator
CN203799766U (en) +/- 660kV direct-current composite insulator
CN204046118U (en) A kind of water-tight device of cable end
CN207149505U (en) A kind of full-insulated full-sealed injecting type outdoor high-voltage fuse
CN204696630U (en) 110kV dry type silicone rubber for cable terminal
CN206961786U (en) A kind of arc extinguishing hood mounting structure and its fuse switch
CN205688928U (en) Electric force pole tower bracing wire sheath
CN205943609U (en) Rain-flash-proof composite post insulator
CN206225413U (en) A kind of battery case protective cover
CN203134485U (en) Special-purpose insulation bolt for 10kV bypass cable work equipment
CN202957365U (en) Binding post
CN109148057A (en) A kind of insulator structure
CN105551768A (en) Tank cover connecting and sealing mechanism for transformer tank
CN205194876U (en) Test electricity and touch ring
CN204760149U (en) Compound post insulators of porcelain

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant