The multistory reinforced concrete inner support of deep foundation ditch beam segmentation cutting Integral lifting method
Technical field
The present invention relates to the multistory reinforced concrete inner support of a kind of deep foundation ditch beam segmentation cutting Integral lifting method.
Background technology
In recent years, be accompanied by expressway around city development, the population density increases, urban architecture is constantly towards the development of advanced two sides, highrise building becomes the theme of urban construction, corresponding multi-storey basement, subterranean tunnel, subway, the foundation that shopping street etc. are supporting, make engineering yet to be built usually contiguous highrise building or underground structure etc., the complexity of building surrounding enviroment is restricted the use of foundation pit anchor cable bolting system, being widely applied in recent years of " soldier pile or diaphragm wall+inner support " support system generation, especially take reinforced concrete inner support as main, greatly improved the stability of deep foundation ditch.And along with the increase of the underground degree of depth, the number of plies of inner support also supports and is increased to Multi-layer supporting from one deck.
Conventional concrete support beam method for dismounting has gunpowder demolition blasting, mechanical removal, manual demolition etc.And as temporary support structure ,Yin Qi many places in business district, city, around or building intensive, or close on operated subway, temporary support structure is removed and must be guaranteed temporary supporting system, neighboring buildings, underground installation not to be caused to adverse effect.And during multilayer inner support beam Demolition Construction often by the underground horizontal structure of having constructed as operation platform, this just also proposes higher challenge to method for dismounting.
Summary of the invention
The object of the present invention is to provide a kind of construction period short, low to the requirement of underground horizontal permanent structure, the multistory reinforced concrete inner support of the deep foundation ditch beam segmentation cutting Integral lifting method that construction cost is low.
Technical solution of the present invention is:
A multistory reinforced concrete inner support beam segmentation cutting Integral lifting method, is characterized in that: comprise the following steps:
(1) Internal Force Monitoring
Before removing inner supporting structure and carry out Internal Force Monitoring in whole demolishing process, be first the Internal Force Monitoring to foundation ditch displacement and inner support beam, according to testing result, draw internal force distribution situation, during off-load according to the even off-load of internal force distribution situation;
In demolishing process, emphasis monitoring is carried out in following position:
(1) cheat outer water table measure: adopt steel ruler water-level gauge to monitor at the water level observation well of arranging in advance;
(2) Ground Subsidence Monitoring: with level gauge, scale is monitored on the basic point arranging, with this monitoring absolute altitude, deducting last time absolute altitude be this settling amount, deducts initial absolute altitude for settling amount totally;
(3) the sedimentation of soldier pile stake top and horizontal displacement monitoring: on soldier pile top, measuring point is set, away from foundation ditch position, reference point is being set, with level gauge and scale, monitor;
(4) soldier pile deep horizontal displacement monitoring: with inclinometer, pre-buried inclinometer pipe inwall has longitudinal guide groove of two group of 90 degree, and guide groove is controlled deviational survey orientation, during test, at the bottom of clinometer probe is sink to hole, after temperature stabilization, measures piecemeal displacement from bottom to top;
(5) inner support axle power monitoring: concrete strain meter is embedded in to inner support beam steel gap location, fixes and carefully draw with cable afterwards, be placed in the line box of well in advance, monitor with frequency readings instrument;
(6) support post stake settlement monitoring: monitor on the basic point of stand column pile setting with level gauge;
(7) the internal force of guard post monitoring: reinforcing rib meter is welded on and carries out pre-buriedly on the main muscle of boring soldier pile, monitor with frequency readings instrument;
(8) surrounding building sedimentation deformation monitoring: monitor on the basic point setting with level gauge;
(2) cutting disassembling
Cutting off-load
With rope saw cutting machine, will in support system, contact beam, girder cut-out off-load, two groups of symmetrical operations simultaneously, keep the smooth transition of structure support replacement;
Cutting disassembling
(1) according to brace summer dismounting order, on brace summer to be torn open, finish line of cut;
(2) flat car is installed and with the type wood of the carving piece fixing vehicle wheel of stopping in brace summer below; As rectangular structure has reserving hole, adopt steel structure platform plate to lay;
(3) static line saw: fix rope saw facing brace summer line of cut position, rope saw and brace summer to be torn open are in vertical state;
(4) rope is installed: diamond rope is wrapped on driving wheel and auxiliary wheel, and the line of cut position of finishing winds, debugging rope saw and diamond rope, tighten up diamond rope on brace summer;
(5) cutting unloading: before cutting, diamond-wire saw is carried out to preliminary operation and idle running, determine in equipment operation, the normal situation of water source supply, then cut; Adopt symmetric mode to cut unloading to brace summer;
(6) cutting section brace summer in the situation that the every data monitoring of foundation ditch being stable after foundation ditch bearing stress discharges;
(3) transhipment in foundation ditch
(1) at underground horizontal permanent structure weak part, lay the steel structure platform completed, guarantee flat car by time structural weak position be not subject to load to produce crack;
(2) at foundation pit side-wall wire rope hoist, and at the fixing angle pulley of transit route bending part;
(3), after brace summer has cut, brace summer cutting section falls within on flat car reposefully, split out for the type of the carving wood of the fixed flat planar car piece of stopping, with hoist engine horizontally tracting flat car to loop wheel machine lifting radius;
(4) brace summer Integral lifting
(1) lifting loop wheel machine is set up in the side that can set up loop wheel machine at foundation pit side-wall;
(2) adopt wire rope colligation to fix the brace summer cut length being transported in foundation ditch limit lifting radius;
(3) loop wheel machine brace summer cut length adopts wire rope handling to foundation ditch, on haulage vehicle, to transport building site;
(5) brace summer is broken outside the venue
Brace summer cut length is transported to be avoided near assigned address outside the concentrated place in residential block and center, city; At assigned address, adopt measurements for reduction Convergency fracturing.
The present invention constructs on underground horizontal thin-slab structure, and operation platform is not had to specific (special) requirements, does not need lower thin sheet structured steel pipe support system over the ground to strengthen processing, and only needs underground horizontal thin plate reserved opening and position, reserved shrinkage joint to carry out part reinforcement processing.And brace summer cutting disassembling Shi, bottom does not need to set up steel pipe support.Input amount of on-the-spot steel pipe support material reduces in a large number, and can remove in advance and improve steel pipe support turnover rate.Brace summer adopts rope saw segmentation cutting mode, the structural cracks of avoiding heavy-duty machinery and dismantling concrete slag to cause horizontal structure overburden, and the effective load of controlling each cut length of segmentation cutting affects horizontal structure.Part is laid the weak part of steel platform level of protection structure simultaneously, guaranteed the quality control at each position of horizontal structure.Brace summer segmentation cutting; adopt self-control flat car be transported to can handling margin of foundation pit; reduce foundation ditch side lift lifting radius and loop wheel machine shift count, and guarantee the brace summer cutting at the position that loop wheel machine cannot be close, thereby guarantee that foundation ditch limit can set up little tonnage loop wheel machine and guarantee foundation ditch safety and stability.Brace summer adopts Integral lifting mode, greatly shortens the concrete slag clearance time that the brace summer in foundation ditch is removed, and foundation ditch side lift is only done flowing water lifting operation, quickening construction rhythm, saving duration.Brace summer segmentation cutting has reduced labour intensity, and handling safety is reliable, and powerful has improved cutting power and labor productivity.Work progress noise is low, without dust, environmental protection easy and simple to handle.
Below in conjunction with embodiment, the invention will be further described.
The specific embodiment
A multistory reinforced concrete inner support beam segmentation cutting Integral lifting method, is characterized in that: comprise the following steps:
(1) Internal Force Monitoring
Before removing inner supporting structure and carry out Internal Force Monitoring in whole demolishing process, be first the Internal Force Monitoring to foundation ditch displacement and inner support beam, according to testing result, draw internal force distribution situation, during off-load according to the even off-load of internal force distribution situation;
In demolishing process, emphasis monitoring is carried out in following position:
(1) cheat outer water table measure: adopt steel ruler water-level gauge to monitor at the water level observation well of arranging in advance;
(2) Ground Subsidence Monitoring: with level gauge, scale is monitored on the basic point arranging, with this monitoring absolute altitude, deducting last time absolute altitude be this settling amount, deducts initial absolute altitude for settling amount totally;
(3) the sedimentation of soldier pile stake top and horizontal displacement monitoring: on soldier pile top, measuring point is set, away from foundation ditch position, reference point is being set, with level gauge and scale, monitor;
(4) soldier pile deep horizontal displacement monitoring: with inclinometer, pre-buried inclinometer pipe inwall has longitudinal guide groove of two group of 90 degree, and guide groove is controlled deviational survey orientation, during test, at the bottom of clinometer probe is sink to hole, after temperature stabilization, measures piecemeal displacement from bottom to top;
(5) inner support axle power monitoring: concrete strain meter is embedded in to inner support beam steel gap location, fixes and carefully draw with cable afterwards, be placed in the line box of well in advance, monitor with frequency readings instrument;
(6) support post stake settlement monitoring: monitor on the basic point of stand column pile setting with level gauge;
(7) the internal force of guard post monitoring: reinforcing rib meter is welded on and carries out pre-buriedly on the main muscle of boring soldier pile, monitor with frequency readings instrument;
(8) surrounding building sedimentation deformation monitoring: monitor on the basic point setting with level gauge;
(2) cutting disassembling
Cutting off-load
With rope saw cutting machine, will in support system, contact beam, girder cut-out off-load, two groups of symmetrical operations simultaneously, keep the smooth transition of structure support replacement;
Cutting disassembling
(1) according to brace summer dismounting order, on brace summer to be torn open, finish line of cut;
(2) flat car is installed and with the type wood of the carving piece fixing vehicle wheel of stopping in brace summer below; As rectangular structure has reserving hole, adopt steel structure platform plate to lay;
(3) static line saw: fix rope saw facing brace summer line of cut position, rope saw and brace summer to be torn open are in vertical state;
(4) rope is installed: diamond rope is wrapped on driving wheel and auxiliary wheel, and the line of cut position of finishing winds, debugging rope saw and diamond rope, tighten up diamond rope on brace summer;
(5) cutting unloading: before cutting, diamond-wire saw is carried out to preliminary operation and idle running, determine in equipment operation, the normal situation of water source supply, then cut; Adopt symmetric mode to cut unloading to brace summer;
(6) cutting section brace summer in the situation that the every data monitoring of foundation ditch being stable after foundation ditch bearing stress discharges;
(3) transhipment in foundation ditch
(1) at underground horizontal permanent structure weak part, lay the steel structure platform completed, guarantee flat car by time structural weak position be not subject to load to produce crack;
(2) at foundation pit side-wall wire rope hoist, and at the fixing angle pulley of transit route bending part;
(3), after brace summer has cut, brace summer cutting section falls within on flat car reposefully, split out for the type of the carving wood of the fixed flat planar car piece of stopping, with hoist engine horizontally tracting flat car to loop wheel machine lifting radius;
(4) brace summer Integral lifting
(1) lifting loop wheel machine is set up in the side that can set up loop wheel machine at foundation pit side-wall;
(2) adopt wire rope colligation to fix the brace summer cut length being transported in foundation ditch limit lifting radius;
(3) loop wheel machine brace summer cut length adopts wire rope handling to foundation ditch, on haulage vehicle, to transport building site;
(5) brace summer is broken outside the venue
Brace summer cut length is transported to be avoided near assigned address outside the concentrated place in residential block and center, city; At assigned address, adopt measurements for reduction Convergency fracturing.