CN103500475B - A kind of adjustment method, system of office buildings gate control system - Google Patents

A kind of adjustment method, system of office buildings gate control system Download PDF

Info

Publication number
CN103500475B
CN103500475B CN201310392733.XA CN201310392733A CN103500475B CN 103500475 B CN103500475 B CN 103500475B CN 201310392733 A CN201310392733 A CN 201310392733A CN 103500475 B CN103500475 B CN 103500475B
Authority
CN
China
Prior art keywords
control system
gate control
party
request
monitoring terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310392733.XA
Other languages
Chinese (zh)
Other versions
CN103500475A (en
Inventor
宁强
刘永亮
燕晋春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Security and Fire Technology Co Ltd
Original Assignee
China Security and Fire Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Security and Fire Technology Co Ltd filed Critical China Security and Fire Technology Co Ltd
Priority to CN201310392733.XA priority Critical patent/CN103500475B/en
Publication of CN103500475A publication Critical patent/CN103500475A/en
Application granted granted Critical
Publication of CN103500475B publication Critical patent/CN103500475B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Debugging And Monitoring (AREA)

Abstract

The present invention is applicable to intelligent building technical field, provide a kind of adjustment method, system of office buildings gate control system, described method comprises: gate control system simulator reads the configuration information pre-set, and described configuration information comprises access controller information in the office buildings gate control system of needs simulation, door information, worker information, card image in building; Gate control system simulator according to described configuration information, and in conjunction with the commissioning requirements generation system signal of user; Gate control system simulator sends described system signal to gate control system monitoring terminal, debugs described system signal is sent to Third party system by gate control system monitoring terminal.The present invention, due to the real equipment environment without the need to building office buildings gate control system, compared to existing technology, having that the construction cycle is short, equipment investment is few and debugging advantage easily.

Description

A kind of adjustment method, system of office buildings gate control system
Technical field
The invention belongs to intelligent building technical field, particularly relate to a kind of adjustment method, system of office buildings gate control system.
Background technology
In the debug process of the remote monitoring terminal of the building security door of routine, usually need the equipment in kind such as some safety doors, safety door monitoring and controlling system, remote monitoring terminal and corresponding software systems, then set up debugging enironment.Safety door monitoring and controlling system needs by the data of each safety door in bus collection office buildings gate control system and the data of cell controller, then these data are processed, and the status information of each safety door is sent to remote monitoring terminal, the screen of remote monitoring terminal shows.Such debug process has a lot of inconvenience, such as:
1, the construction cycle is affected
In exploitation debug process, if safety door monitoring and controlling system is directly connected in actual office buildings gate control system, due to the uncertainty of Software function test result, may impact gate control system actual working environment, therefore, for avoiding testing the impact on the real work of office buildings gate control system, development and testing personnel need according to actual conditions, build and debug physical device system, adding the workload that staff builds test physical device system.In test process, also some unpredictable failure problems may be there are in physical device system, for the software developer of hardware system being ignorant of office buildings gate control system, solve relevant issues, too increase some unnecessary difficulty and workloads, reduce work efficiency, extend the project development cycle.
2, the investment of equipment
In uniting and adjustment test process, safety door monitoring and controlling system connects real office buildings gate control system, at least needs the real equipment such as a set of access control equipment and a station server main frame to build actual door access control system environment, to meet the demand for test environment.So, the equipment that buying debugging needs adds cost of development.
3, debugging inconvenience
Use true gate control system, all data messages all come from access control equipment system.Data message is that the rule normally run according to gate control system produces.When various fault tested by needs, during gate control system reference performance, be not easy to simulate various fault-signal.And when testing when needs gate control system normally works, gate control system likely produces fault.This true gate control system cannot meet the uncertainty of test environment, for software project development and test job cause very big inconvenience.In addition, when in the device systems built, number of devices is less, gate control system cannot provide the information of the mass data needed for test, also just cannot the load capacity of software system.
Summary of the invention
Embodiments provide a kind of adjustment method, system of office buildings gate control system, being intended to solve prior art when carrying out the debugging of office buildings gate control system, needing the problem of building real facility environment.
On the one hand, provide a kind of adjustment method of office buildings gate control system, described method comprises:
Gate control system simulator reads the configuration information pre-set, and described configuration information comprises access controller information in the office buildings gate control system of needs simulation, door information, worker information, card image in building;
Gate control system simulator according to described configuration information, and in conjunction with the commissioning requirements generation system signal of user;
Gate control system simulator sends described system signal to gate control system monitoring terminal, debugs described system signal is sent to Third party system by gate control system monitoring terminal.
On the other hand, provide a kind of adjustment method of office buildings gate control system, described method comprises:
The system signal that gate control system monitoring terminal receiving gate access control system simulator sends, described system signal is that gate control system simulator is according to the configuration information pre-set, and to generate in conjunction with the commissioning requirements of user, described configuration information comprises worker information, card image in access controller information in the office buildings gate control system of needs simulation, door information, building;
Gate control system monitoring terminal forwards described system signal and debugs to Third party system.
Further, after the system signal that described gate control system monitoring terminal receiving gate access control system simulator sends, also comprise:
Gate control system monitoring terminal represents with the form of animation the information that described system signal comprises.
Further, forward described system signal to after Third party system is debugged at described gate control system monitoring terminal, also comprise:
Gate control system monitoring terminal receives third party's request that Third party system sends;
If described third party request is subscription data request, then gate control system monitoring terminal extracts corresponding data encapsulation according to described subscription data request and becomes Packet Generation to Third party system from described system signal.
Further, forward described system signal to after Third party system is debugged at described gate control system monitoring terminal, also comprise:
Described subscription data request adds in subscription data request list by gate control system monitoring terminal;
After described gate control system monitoring terminal receives third party's request of Third party system transmission, also comprise:
If described third party's request is anti-subscription data request, then gate control system monitoring terminal gate control system monitoring terminal deletes subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request.
Further, after described gate control system monitoring terminal receives third party's request of Third party system transmission, also comprise:
If described third party's request is control command request, then gate control system monitoring terminal forwards described control command request to gate inhibition's simulator, to generate new system signal by gate inhibition's simulator according to described control command request, then forward described new system signal to Third party system by gate inhibition's simulator.
Again on the one hand, provide a kind of gate control system simulator, described gate control system simulator comprises:
Configuration information acquiring unit, for reading the configuration information pre-set, described configuration information comprises access controller information in the office buildings gate control system of needs simulation, door information, worker information, card image in building;
System signal generation unit, for according to described configuration information, and in conjunction with the commissioning requirements generation system signal of user;
System signal transmitting element, for sending described system signal to gate control system monitoring terminal, debugs described system signal is sent to Third party system by gate control system monitoring terminal.
Another aspect, provides a kind of gate control system monitoring terminal, and described gate control system monitoring terminal comprises:
System signal reception unit, for the system signal that receiving gate access control system simulator sends, described system signal is that gate control system simulator is according to the configuration information pre-set, and to generate in conjunction with the commissioning requirements of user, described configuration information comprises worker information, card image in access controller information in the office buildings gate control system of needs simulation, door information, building;
System signal retransmission unit, debugs to Third party system for forwarding described system signal.
Further, described gate control system monitoring terminal also comprises:
Animation broadcast unit, for representing the information that described system signal comprises with the form of animation.
Further, described gate control system monitoring terminal also comprises:
Third party's request reception unit, for receiving third party's request that Third party system sends;
Subscription data requesting processing, if be subscription data request for described third party's request, then extract corresponding data encapsulation according to described subscription data request and becomes Packet Generation to Third party system from described system signal;
Request list generation unit, for adding in subscription data request list by described subscription data request;
Anti-subscription data request unit, if be anti-subscription data request for described third party's request, then deletes subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request;
Control command requesting processing, if be control command request for described third party's request, then forward described control command request to gate inhibition's simulator, to generate new system signal by gate inhibition's simulator according to described control command request, then forward described new system signal to Third party system by gate inhibition's simulator.
Again on the one hand, a kind of debug system of office buildings gate control system is provided, described debug system comprises Third party system, gate control system simulator as above and gate control system monitoring terminal as above, described gate control system simulator is connected with described gate control system monitoring terminal, and described gate control system monitoring terminal is connected with described Third party system.
In the embodiment of the present invention, by gate control system simulator office buildings gate control system that is virtually reality like reality, and the system signal generated for debugging, to forward this system signal to Third party system by gate control system monitor terminal, carried out the debugging of office buildings gate control system according to this system signal by Third party system.Due to the real equipment environment without the need to building office buildings gate control system, compared to existing technology, have that the construction cycle is short, equipment investment is few and debug advantage easily.
Accompanying drawing explanation
Fig. 1 is the realization flow figure of the adjustment method of the office buildings gate control system that the embodiment of the present invention one provides;
The realization flow figure of the adjustment method of the office buildings gate control system that Fig. 2 embodiment of the present invention two provides;
Fig. 3 is the structured flowchart of the gate control system simulator that the embodiment of the present invention three provides;
Fig. 4 is the structured flowchart of the gate control system monitoring terminal that the embodiment of the present invention four provides;
Fig. 5 is the structured flowchart of the debug system of the office buildings gate control system that the embodiment of the present invention five provides.
Embodiment
In order to make object of the present invention, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
In embodiments of the present invention, by gate control system simulator office buildings gate control system that is virtually reality like reality, and the system signal generated for debugging, to forward this system signal to Third party system by gate control system monitor terminal, carried out the debugging of office buildings gate control system according to this system signal by Third party system.
Below in conjunction with specific embodiment, realization of the present invention is described in detail:
Embodiment one
Fig. 1 shows the realization flow of the adjustment method of the office buildings gate control system that the embodiment of the present invention one provides, and be described for gate control system simulator side, details are as follows:
In step S101, gate control system simulator reads the configuration information pre-set, and configuration information comprises access controller information in the office buildings gate control system of needs simulation, door information, worker information, card image in building.
In the present embodiment, when first time runs the debug system of office buildings gate control system, configuration information manually can add after debug system is run, also can before operation debug system, in configuration database, insert relevant configuration information in advance, then the Connecting quantity preserved in the configuration file of the Connecting quantity of configuration database is modified as corresponding configuration database.When again running, debug system directly will read corresponding configuration information according to configuration file later, now, if necessary, and can Update Table storehouse Connecting quantity or additions and deletions configuration information.It should be noted that, configuration information can be stored in configuration database, can certainly be stored in a configuration file in the form of a file, concrete configuration information stores in which way, be not restricted in the present embodiment, be stored in configuration database for configuration information at this and be described.
The debug system of office buildings gate control system operationally, automatically configuration file can be read, the Connecting quantity of configuration database is comprised in configuration file, as the IP address of configuration database place main frame, the database name, database user name, database password etc. of configuration database, default configuration data storehouse is at the machine (127.0.0.1).Also communication port numbers TCPPort is comprised in configuration file.Configuration file format is as follows:
; Configuration database
[DataBase]
IP=xxx.xxx.xxx.xxx (as 127.0.0.1) (IP address)
Dbname=xxx(is as BIS) (database name)
Username=xxx(is as sa) (database user name)
Pwd=xxx(is as 123456) (database password)
; TCP communication port numbers
[TCP]
TCPPort=xxx (as 6000)
If need the Connecting quantity revising configuration database, can revise the configuration of the configuration database of gate inhibition's analogue system, debug system can by the Connecting quantity of amendment write configuration file.
Wherein, configuration information comprises access controller information in the office buildings access control system of needs simulation, door information, worker information, card image in building.
Worker information in office buildings gate inhibition debug system can configure as required in gate control system simulator and increase needs are simulated access controller, door information and building and card image, and can automatically the relevant information of configuration be kept in tables of data corresponding to configuration database; Also can by advance the worker information needed in the access controller of simulation, door information and building and card image being inserted in tables of data corresponding to configuration database, realize the configuration of worker information in access controller, door information and building and card image.If the worker information existed in the configuration database of configuration in access controller, door information and building and card image, debug system then can read configuration file, connect configuration database according to the configuration database Connecting quantity provided in configuration file, directly from configuration database, read relevant configuration information.
In step s 102, gate control system simulator according to configuration information, and in conjunction with the commissioning requirements generation system signal of user.
In the embodiment of the present invention, gate control system simulator according to configuration information, and can generate in conjunction with the commissioning requirements of the user in debug system the system signal debugged required for office buildings gate control system.
During practical operation, the mode that office buildings gate inhibition debug system needs artificial initialization system signal to generate, debug system supports the generating mode of three kinds of system signals, is respectively and manually inputs generating mode, logic generating mode and stochastic generation mode.
Wherein, manually input generating mode is used for manually arranging system signal;
Logic generating mode is used for by setting logic generation system signal, and periodic signal during this system signal, can simulate the normal operation of office buildings gate control system, and Third party system can be debugged according to this system signal.Such as, according to the uptime section of office buildings gate control system, in a period of time before being on duty and After Hours, produce a large amount of system signals, within other time period, produce system signal at random.And for example, the office buildings gate control system system signal that (as 9:00) generation is fixing at a fixed time (as some safety door of simulation is opened) can being set or set office buildings gate control system every regular time (as one minute), producing the system signal required for debugging (as opened the door) etc. constantly;
Stochastic generation mode is used for stochastic generation system signal, generally applies when power system capacity and the load debugging of office buildings gate control system.
The system signal of office buildings gate control system can be divided into five aspects:
1), system supervisory signal, comprise the mode of operation, user's access permission group etc. of the authority of user's card image, system alarm pattern, door;
2), access controller signal, comprise the online and off-lined signal of access controller;
3), gate signal, comprise that door is normally opened, door opened extremely, door is normally closed, door is closed extremely, door opens time-out, Men Wei opens and door group coordinated signals etc.;
4), signal of swiping the card, comprising swipes the card enter with gate signal of swiping the card out, illegally stick into door with go out gate signal;
5), alerting signal, comprise an exception and open that warning, door abnormal close warnings, door opens time-out warning, Men Wei opens warning, illegally sticks into door alarm, illegally blocks the alerting signals such as door alarm.
After generating mode for debug system selecting system signal, debug system according to configuration information, can generate corresponding system signal in conjunction with concrete commissioning requirements.The generating mode of the system signal of debug system acquiescence is stochastic generation mode.After system signal generates, the system signal of generation can be sent to gate control system monitoring terminal by gate control system simulator.
In step s 103, gate control system simulator transmitting system signal, to gate control system monitoring terminal, is debugged this system signal is sent to Third party system by gate control system monitoring terminal.
In the present embodiment, the system signal received from gate control system simulator is sent to Third party system and debugs by gate control system monitoring terminal.Simultaneously, gate control system monitoring terminal can represent with the form of animation the information comprised by this system signal, such as, and the warning message of simulation enabling, the action of closing the door, door and user card punching information etc., and be presented on the operation interface of gate control system monitoring terminal, display system signals intuitively.In addition, on operation interface, the essential information of this analog gate can also be seen, the access controller address belonging to this, door address, with door title, this mode of operation etc. of this door linkage.
The present embodiment, by gate control system simulator office buildings gate control system that is virtually reality like reality, and the system signal generated for debugging, to forward this system signal to Third party system by gate control system monitor terminal, carried out the debugging of office buildings gate control system according to this system signal by Third party system.Due to the real equipment environment without the need to building office buildings gate control system, compared to existing technology, have that the construction cycle is short, equipment investment is few and debug advantage easily.
One of ordinary skill in the art will appreciate that all or part of step realized in the various embodiments described above method is that the hardware that can carry out instruction relevant by program has come, corresponding program can be stored in a computer read/write memory medium, described storage medium, as ROM/RAM, disk or CD etc.
Embodiment two
Fig. 2 shows the realization flow of the adjustment method of the office buildings gate control system that the embodiment of the present invention two provides, and be described for gate control system monitoring terminal side, details are as follows:
In step s 201, the system signal that gate control system monitoring terminal receiving gate access control system simulator sends, wherein, system signal is that gate control system simulator is according to the configuration information pre-set, and to generate in conjunction with the commissioning requirements of user, this configuration information comprises worker information, card image in access controller information in the office buildings gate control system of needs simulation, door information, building.
As a preferred embodiment of the present invention, gate control system monitoring terminal represents with the form of animation the information that system signal comprises, such as, the operation interface of gate control system monitoring terminal plays simulation is opened the door, the action of closing the door, the warning message of door and user card punching information etc., display system signals intuitively.In addition, on the operation interface of gate control system monitoring terminal, the essential information of this analog gate can also be seen, the access controller address belonging to this, door address, with door title, this mode of operation etc. of this door linkage.
In step S202, gate control system monitoring terminal forwards the system signal received and debugs to Third party system.
In step S203, gate control system monitoring terminal receives third party's request that Third party system sends.
In the embodiment of the present invention, Third party system can also be docked by gate control system monitoring terminal and gate control system simulator, gate control system monitoring terminal can according to Third party system send third party request send corresponding data to Third party system, with realize gate control system simulator, between gate inhibition's monitor terminal and Third party system docking debugging.Wherein, Third party system can need transmission three kinds of third party's requests to gate control system monitoring terminal according to debugging, and these three kinds of requests are respectively subscription data request, anti-subscription data request and control command request.
After third party's request is sent out, the Third party system sent request can receive a rreturn value.Whether this rreturn value is successfully executed for illustration of the request sent, and runs succeeded and returns success flag " 1 ", performs unsuccessfully to return unsuccessfully to identify " 0 ".Only have rreturn value to be the request of success flag " 1 ", gate control system simulator just can perform corresponding operation.
Third party asks in process, and gate control system monitoring terminal, in the process run, can check whether the third party's request receiving Third party system and send continuously.If receive this third party request, gate control system monitoring terminal can check whether this request meets request format specification, if do not meet request format specification, this request just abandons and do not process by system, returns to Third party system request failure; If meet request format specification, then judge the classification that third party asks, if subscription data request, then forward in step 204; If anti-subscription data request, then forward in step 205; If control command request, then forward in step 206.
In step S204, if this third party request is subscription data request, then gate control system monitoring terminal extracts corresponding data encapsulation according to this subscription data request and becomes Packet Generation to Third party system from system signal.
In the present embodiment, subscription data request is divided into real time data request and historical data request.Real time data request comprises the real-time status (Men Kai or door close) of subscribing to door, mode of operation, the booking reader's card using information of subscribing to door, subscribes to warning message, subscribes to access controller presence etc.Historical data request mainly refers to subscribes to some changeless data, as the essential information, access controller list etc. of the door of gate control system simulator simulation.Receive after real time data pulls subscription in first time, gate control system simulator when coherent signal changes, can ceaselessly push the Third party system of relevant information to the request of initiation subscription data, until Third party system cancels subscriptions.Gate control system simulator, after receiving historical data request, only can return a secondary data, because these data are changeless.
Concrete, after gate inhibition's monitor terminal receives subscription data request, this subscription data request is added in subscribe request list, after, corresponding data encapsulation can be extracted according to the subscribe request in subscribe request list from system signal and become Packet Generation to Third party system.When the system signal subscribed to changes, gate inhibition's monitor terminal extracts corresponding data encapsulation and becomes packet from the system signal after this change, is then sent to Third party system corresponding in subscription list.For the real-time status of door, access controller presence and mode of operation, system signal changes and refers to that certain signal is no longer lasting when lasting till certain time point, namely this signal there occurs change, as door was closed originally, then door has been opened, now the state of door just there occurs change, and for example certain mode of operation started often opens, then as required this mode of operation is arranged to normally closed, then the mode of operation of door there occurs change, for another example certain access controller is online at first, then due to some setting, this controller off-line, for user card punching information and warning message, signal changes and refers to and produce new data-signal, as certain user has opened certain door with card brush, new card using information can be produced, and for example certain door there occurs in certain time event of illegally swiping the card, now not only can produce card using information, also can produce alert event, that is card using information and warning message there occurs change.
In step S205, if the third party's request received is anti-subscription data request, then gate control system monitoring terminal deletes the subscription data request corresponding with this anti-subscription data request according to this anti-subscription data request.
In embodiments of the present invention, after the subscription data request receiving Third party system transmission, this subscription data request can add in subscribe request list by gate control system monitoring terminal.Follow-up, after gate control system monitoring terminal receives the anti-subscription data request corresponding with this subscription data request, the subscription data request corresponding with anti-subscription data request can be found from subscribe request list, and it is deleted from subscribe request list.Delete this subscription data request from subscribe request list after, when the system signal that this subscription data pulls subscription changes, will no longer propelling data to Third party system.Anti-subscription data request is contrary with subscription data request, and that is cancel subscriptions request of data.After have sent the anti-subscription data request corresponding with subscription data request, the data subscription request sent will no longer be had an effect, and the Third party system namely sending subscription data request no longer will receive related data.
In step S206, if the third party's request received is control command request, then gate control system monitoring terminal forwards this control command request to gate inhibition's simulator, to generate new system signal by gate inhibition's simulator according to this control command request, then forward this new system signal to Third party system by gate inhibition's simulator.
In embodiments of the present invention, gate control system monitoring terminal forwards control command request to gate inhibition's simulator, by the requirement of gate control system simulator according to control command request, generate new system signal, then the new system signal generated is sent to gate control system monitoring terminal, finally by gate control system monitoring terminal, this new system signal is forwarded to Third party system and debugs.It should be noted that: a control command can control generation signal, also can control to generate multiple signal, but must be the signal of same, as a control command can change the door state (open the door, close the door) of one or more, when controlling multiple, as required different doors can be arranged to different states, as a door is opened, other door is closed, but in the order of this control gate state, can not while control gate state, the mode of operation of control gate.
The present embodiment, gate control system monitor terminal receiving gate access control system simulator office buildings gate control system that is virtually reality like reality and the system signal generated, and forward this system signal to Third party system, carried out the debugging of office buildings gate control system according to this system signal by Third party system.Due to the real equipment environment without the need to building office buildings gate control system, avoid the defect that prior art needs to build equipment debugging environment in kind, can the system signal of display simulation intuitively, have that equipment investment is few, the construction cycle is short, debugging is convenient and arbitrarily can produce the advantage that a large amount of system signal carries out debugging.
Embodiment three
Fig. 3 shows the concrete structure block diagram of the gate control system simulator that the embodiment of the present invention three provides, and for convenience of explanation, illustrate only the part relevant to the embodiment of the present invention.This gate control system simulator 3 comprises: configuration information acquiring unit 31, system signal generation unit 32 and system signal transmitting element 33.
Wherein, configuration information acquiring unit 31, for reading the configuration information pre-set, this configuration information comprises access controller information in the office buildings gate control system of needs simulation, door information, worker information, card image in building;
System signal generation unit 32, for the configuration information read according to configuration information acquiring unit 31, and in conjunction with the commissioning requirements generation system signal of user;
System signal transmitting element 33, the system signal generated for transmitting system signal generation unit 32, to gate control system monitoring terminal, is debugged system signal is sent to Third party system by gate control system monitoring terminal.
The gate control system simulator that the embodiment of the present invention provides can be applied in the embodiment of the method one of aforementioned correspondence, and details, see the description of above-described embodiment one, do not repeat them here.
Embodiment four
Fig. 4 shows the concrete structure block diagram of the gate control system monitor terminal that the embodiment of the present invention four provides, and for convenience of explanation, illustrate only the part relevant to the embodiment of the present invention.This gate control system monitor terminal 4 comprises: system signal reception unit 41 and system signal retransmission unit 42.
Wherein, system signal reception unit 41, for the system signal that receiving gate access control system simulator sends, this system signal is that gate control system simulator is according to the configuration information pre-set, and to generate in conjunction with the commissioning requirements of user, this configuration information comprises worker information, card image in access controller information in the office buildings gate control system of needs simulation, door information, building;
System signal retransmission unit 42, the system signal received for repeater system signal receiving unit 41 is debugged to Third party system.
Further, gate control system monitoring terminal 4 also comprises:
Animation broadcast unit, the information that the system signal received for representing system signal reception unit 41 with the form of animation comprises.
Further, gate control system monitoring terminal 4 also comprises:
Third party's request reception unit, for receiving third party's request that Third party system sends;
Subscription data requesting processing, if be subscription data request for the third party's request received by third party's request reception unit, then from system signal, extract corresponding data encapsulation according to this subscription data request and become Packet Generation to Third party system;
Request list generation unit, for adding in subscription data request list by this subscription data request;
Anti-subscription data request unit, if be anti-subscription data request for the third party's request received by third party's request reception unit, then delete subscription data request corresponding with this anti-subscription data request in subscribe request list according to this anti-subscription data request;
Control command requesting processing, if be control command request for the third party's request received by third party's request reception unit, then forward and change control command request to gate inhibition's simulator, to generate new system signal by gate inhibition's simulator according to this control command request, then forward this new system signal to Third party system by gate inhibition's simulator.
The gate control system monitor terminal that the embodiment of the present invention provides can be applied in the embodiment of the method two of aforementioned correspondence, and details, see the description of above-described embodiment two, do not repeat them here.
Embodiment five
Fig. 5 shows the concrete structure block diagram of the debug system of the office buildings gate control system that the embodiment of the present invention five provides, and for convenience of explanation, illustrate only the part relevant to the embodiment of the present invention.The debug system 5 of this office buildings gate control system comprises the gate control system simulator 3 in embodiment three, the gate control system monitor terminal 4 in embodiment four and Third party system 51.Wherein, gate control system simulator 3 is connected with gate control system monitor terminal 4, and gate control system monitor terminal 4 is connected with Third party system 5.Concrete, connected by the communications protocol connected mode of TCP/IP between gate control system simulator 3 and gate control system monitor terminal 4, the communications protocol connected mode also by TCP/IP between gate control system monitor terminal 4 with Third party system 5 is connected.
The debug system that the present embodiment provides, gate control system simulator office buildings gate control system that is virtually reality like reality generates system signal, and send this system signal to gate control system monitor terminal, forward this system signal to Third party system by gate control system monitor terminal, Third party system carries out the debugging of office buildings gate control system according to this system signal.Due to the real equipment environment without the need to building office buildings gate control system, avoid the defect that prior art needs to build equipment debugging environment in kind, can the system signal of display simulation intuitively, have that equipment investment is few, the construction cycle is short, debugging is convenient and arbitrarily can produce the advantage that a large amount of system signal carries out debugging.
It should be noted that in said system embodiment, included unit is carry out dividing according to function logic, but is not limited to above-mentioned division, as long as can realize corresponding function; In addition, the concrete title of each functional unit, also just for the ease of mutual differentiation, is not limited to protection scope of the present invention.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, all any amendments done within the spirit and principles in the present invention, equivalent replacement and improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. an adjustment method for office buildings gate control system, is characterized in that, described method comprises:
The system signal that gate control system monitoring terminal receiving gate access control system simulator sends, described system signal is that gate control system simulator is according to the configuration information pre-set, and to generate in conjunction with the commissioning requirements of user, described configuration information comprises worker information, card image in access controller information in the office buildings gate control system of needs simulation, door information, building;
Gate control system monitoring terminal forwards described system signal and debugs to Third party system.
2. the method for claim 1, is characterized in that, after the system signal that described gate control system monitoring terminal receiving gate access control system simulator sends, also comprises:
Gate control system monitoring terminal represents with the form of animation the information that described system signal comprises.
3. the method for claim 1, is characterized in that, forwards described system signal to after Third party system is debugged, also comprise at described gate control system monitoring terminal:
Gate control system monitoring terminal receives third party's request that Third party system sends;
If described third party request is subscription data request, then gate control system monitoring terminal extracts corresponding data encapsulation according to described subscription data request and becomes Packet Generation to Third party system from described system signal.
4. method as claimed in claim 3, is characterized in that, forwards described system signal to after Third party system is debugged, also comprise at described gate control system monitoring terminal:
Described subscription data request adds in subscription data request list by gate control system monitoring terminal;
After described gate control system monitoring terminal receives third party's request of Third party system transmission, also comprise:
If described third party's request is anti-subscription data request, then gate control system monitoring terminal deletes subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request.
5. method as claimed in claim 3, is characterized in that, after described gate control system monitoring terminal receives third party's request of Third party system transmission, also comprises:
If described third party's request is control command request, then gate control system monitoring terminal forwards described control command request to gate inhibition's simulator, to generate new system signal by gate inhibition's simulator according to described control command request, then forward described new system signal to Third party system by gate inhibition's simulator.
6. a gate control system simulator, is characterized in that, described gate control system simulator comprises:
Configuration information acquiring unit, for reading the configuration information pre-set, described configuration information comprises access controller information in the office buildings gate control system of needs simulation, door information, worker information, card image in building;
System signal generation unit, for according to described configuration information, and in conjunction with the commissioning requirements generation system signal of user;
System signal transmitting element, for sending described system signal to gate control system monitoring terminal, debugs described system signal is sent to Third party system by gate control system monitoring terminal.
7. a gate control system monitoring terminal, is characterized in that, described gate control system monitoring terminal comprises:
System signal reception unit, for the system signal that receiving gate access control system simulator sends, described system signal is that gate control system simulator is according to the configuration information pre-set, and to generate in conjunction with the commissioning requirements of user, described configuration information comprises worker information, card image in access controller information in the office buildings gate control system of needs simulation, door information, building;
System signal retransmission unit, debugs to Third party system for forwarding described system signal.
8. gate control system monitoring terminal as claimed in claim 7, it is characterized in that, described gate control system monitoring terminal also comprises:
Animation broadcast unit, for representing the information that described system signal comprises with the form of animation.
9. gate control system monitoring terminal as claimed in claim 7, it is characterized in that, described gate control system monitoring terminal also comprises:
Third party's request reception unit, for receiving third party's request that Third party system sends;
Subscription data requesting processing, if described third party request is subscription data request, then extracts corresponding data encapsulation according to described subscription data request and becomes Packet Generation to Third party system from described system signal;
Request list generation unit, for adding in subscription data request list by described subscription data request;
Anti-subscription data request unit, if described third party request is anti-subscription data request, then deletes subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request;
Control command requesting processing, if described third party's request is control command request, then forward described control command request to gate inhibition's simulator, to generate new system signal by gate inhibition's simulator according to described control command request, then forward described new system signal to Third party system by gate inhibition's simulator.
10. the debug system of an office buildings gate control system, it is characterized in that, described debug system comprises Third party system, gate control system simulator as claimed in claim 6 and the gate control system monitoring terminal as described in any one of claim 7 to 9, described gate control system simulator is connected with described gate control system monitoring terminal, and described gate control system monitoring terminal is connected with described Third party system.
CN201310392733.XA 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system Expired - Fee Related CN103500475B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310392733.XA CN103500475B (en) 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310392733.XA CN103500475B (en) 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system

Publications (2)

Publication Number Publication Date
CN103500475A CN103500475A (en) 2014-01-08
CN103500475B true CN103500475B (en) 2015-08-19

Family

ID=49865678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310392733.XA Expired - Fee Related CN103500475B (en) 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system

Country Status (1)

Country Link
CN (1) CN103500475B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243707A (en) * 2015-09-22 2016-01-13 苏州工业园区职业技术学院 Staged automatic entrance guard control device
CN106228642A (en) * 2016-07-15 2016-12-14 颜芳俊 A kind of intelligent door lock system and control method thereof
CN108376453A (en) * 2018-02-28 2018-08-07 张梦雅 Intelligent anti-theft alarm system for office building
CN109871325B (en) * 2019-01-31 2022-11-04 广州视声智能股份有限公司 KNX remote debugging method and system
CN110706392B (en) * 2019-10-14 2021-10-26 重庆紫光华山智安科技有限公司 Security platform test method and device, storage medium and server
CN111290351A (en) * 2020-01-21 2020-06-16 深圳市雷赛软件技术有限公司 Driver management method, system, computer equipment and storage medium
CN111951456B (en) * 2020-08-25 2022-06-21 合肥优恩物联网科技有限公司 Internet of things control access control system based on mobile phone app
CN112415907B (en) * 2020-11-26 2022-03-29 珠海格力电器股份有限公司 Building equipment remote debugging control method and device and computer equipment
CN112991598A (en) * 2021-02-23 2021-06-18 深圳市欣横纵技术股份有限公司 Automatic card swiping device of access control system
CN113160534A (en) * 2021-03-02 2021-07-23 广州朗国电子科技有限公司 Method, equipment and storage medium for alarming abnormity of intelligent access control system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030151493A1 (en) * 2002-02-13 2003-08-14 Swisscom Ag Access control system, access control method and devices suitable therefor
CN102034290A (en) * 2010-12-21 2011-04-27 汉王科技股份有限公司 Access control method and device
CN102646295A (en) * 2011-02-21 2012-08-22 中国移动通信集团江苏有限公司 Intelligent residential community security system and customizing service realizing method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030151493A1 (en) * 2002-02-13 2003-08-14 Swisscom Ag Access control system, access control method and devices suitable therefor
CN102034290A (en) * 2010-12-21 2011-04-27 汉王科技股份有限公司 Access control method and device
CN102646295A (en) * 2011-02-21 2012-08-22 中国移动通信集团江苏有限公司 Intelligent residential community security system and customizing service realizing method thereof

Also Published As

Publication number Publication date
CN103500475A (en) 2014-01-08

Similar Documents

Publication Publication Date Title
CN103500475B (en) A kind of adjustment method, system of office buildings gate control system
US10809753B2 (en) Real-time simulator and controller of power system using distributed data streaming server
WO2015106605A1 (en) Method for testing station level of intelligent substation
CN107580054A (en) Industrial equipment Reverse Turning Control method and system based on Internet of Things
CN105391586B (en) A kind of method and system of fault locating analysis
CN110851320A (en) Server downtime supervision method, system, terminal and storage medium
CN104126182A (en) Systems and methods of remote communication
CN113533887B (en) Intelligent debugging method and system for power distribution terminal
CN103533084A (en) Real-time DMS (device management system) of B/S (browser/server) framework and method thereof
CN104836699A (en) Equipment state processing method and equipment state processing system
CN104216361A (en) State monitoring system for secondary device
CN102083091A (en) Network management alarm managing method and system, and alarm collecting server
CN103955360A (en) Configuration system and control method of vehicle-mounted monitoring device
CN106936780B (en) A kind of method for monitoring network and system
CN105553743A (en) Log obtaining method, system, first network device and third network device
CN104503405A (en) Monitoring method, device and system based on SCADA (Supervisory Control And Data Acquisition) system
CN105743695A (en) Monitoring method and system based on IEC 104 protocol
CN105217389A (en) The method and system of elevator spare part telemanagement
CN108829072A (en) The control system of sterile pharmaceutical equipment
CN109213657A (en) A kind of grid operation data cloud storage device
CN117234673A (en) Data processing method, system and electronic equipment
CN110733037B (en) Signal processing method and device, storage medium and processor
CN107748672A (en) Secondary remote interface integrated management approach based on IEC61850 sites protection model
KR102406905B1 (en) Edge HMI System Based on Computing Using Industrial IoT Platform
CN101971562B (en) Method, device and system for controlling automatic running process performance

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150819

Termination date: 20190902