CN103500475A - Office building access control system debugging method and system - Google Patents

Office building access control system debugging method and system Download PDF

Info

Publication number
CN103500475A
CN103500475A CN201310392733.XA CN201310392733A CN103500475A CN 103500475 A CN103500475 A CN 103500475A CN 201310392733 A CN201310392733 A CN 201310392733A CN 103500475 A CN103500475 A CN 103500475A
Authority
CN
China
Prior art keywords
gate control
signal
party
request
monitoring terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310392733.XA
Other languages
Chinese (zh)
Other versions
CN103500475B (en
Inventor
宁强
刘永亮
燕晋春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Security and Fire Technology Co Ltd
Original Assignee
China Security and Fire Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Security and Fire Technology Co Ltd filed Critical China Security and Fire Technology Co Ltd
Priority to CN201310392733.XA priority Critical patent/CN103500475B/en
Publication of CN103500475A publication Critical patent/CN103500475A/en
Application granted granted Critical
Publication of CN103500475B publication Critical patent/CN103500475B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention is suitable for the technical field of intelligent office building, and provides an office building access control system debugging method and an office building access control system debugging system. The method comprises the steps that: an access control system simulator reads preset configuration information, wherein the configuration information comprises access control controller information, door information, information of staffs in the building, and card information of the office building access control system requiring simulation; according to the configuration information and combined with user debugging requirements, the access control system simulator generates system signals; the access control system simulator sends the system signals to an access control system monitoring terminal; the access control system monitoring terminal sends the system signals to a third party system for debugging. According to the invention, an office building access control system real equipment environment is not needed. Compared with prior arts, the system and method have the advantages of short development period, less equipment investment, and convenient debugging.

Description

A kind of adjustment method of office buildings gate control system, system
Technical field
The invention belongs to the intelligent building technical field, relate in particular to a kind of adjustment method, system of office buildings gate control system.
Background technology
In the debug process of the remote monitoring terminal of conventional building security door, usually need equipment in kind and the corresponding software systems such as some safety doors, safety door monitoring and controlling system, remote monitoring terminal, then set up debugging enironment.The safety door monitoring and controlling system need to gather the data of each safety door in the office buildings gate control system and the data of cell controller by bus, then these data are processed, and the status information of each safety door is sent to remote monitoring terminal, on the screen of remote monitoring terminal, show.Such debug process has a lot of inconveniences, for example:
1, affect the construction cycle
In the exploitation debug process, if the safety door monitoring and controlling system is directly connected in actual office buildings gate control system, uncertainty due to the Software function test result, may impact the gate control system actual working environment, therefore, for avoiding the impact of test on the real work of office buildings gate control system, the development and testing personnel need to be according to actual conditions, build and debug the physical device system, increased the staff and built the workload of testing the physical device system.In test process, some unpredictable failure problems also may appear in the physical device system, software developer for the hardware system that is ignorant of the office buildings gate control system, solve relevant issues, some unnecessary difficulty and workloads have also been increased, reduce work efficiency, extended the project development cycle.
2, the investment of equipment
In the uniting and adjustment test process, the safety door monitoring and controlling system connects real office buildings gate control system, at least needs the real equipment such as a set of access control equipment and a station server main frame to build actual door access control system environment, to meet the demand for test environment.So, the equipment that the buying debugging needs has increased cost of development.
3, debugging inconvenience
Use true gate control system, all data messages all come from the access control equipment system.Data message is to produce according to the normal rule of moving of gate control system.In the situation that needs are tested various faults, during the gate control system reference performance, be not easy to simulate various fault-signals.And in the situation that while needing gate control system normal operation to be tested, gate control system likely produces fault.This true gate control system can't meet the uncertainty of test environment, for software project development and test job have caused very big inconvenience.In addition, when in the device systems of building, number of devices is less, gate control system can't provide test required mass data information, load capacity that also just can't software system.
Summary of the invention
The embodiment of the present invention provides a kind of adjustment method, system of office buildings gate control system, is intended to solve prior art when carrying out the debugging of office buildings gate control system, the problem that need to build real facility environment.
On the one hand, provide a kind of adjustment method of office buildings gate control system, described method comprises:
The gate control system simulator reads the configuration information set in advance, and described configuration information comprises worker information, the card image in access controller information in the office buildings gate control system of needs simulations, door information, building;
The gate control system simulator is according to described configuration information, and in conjunction with user's commissioning requirements generation system signal;
The gate control system simulator sends described system signal to the gate control system monitoring terminal, by the gate control system monitoring terminal, described system signal is sent to third party's system, is debugged.
On the other hand, provide a kind of adjustment method of office buildings gate control system, described method comprises:
The system signal that gate control system monitoring terminal receiving gate access control system simulator sends, described system signal is that the gate control system simulator is according to the configuration information set in advance, and generate in conjunction with user's commissioning requirements, described configuration information comprises access controller information, door information, interior worker information, the card image of building in the office buildings gate control system of needs simulation;
The gate control system monitoring terminal forwards described system signal to third party's system and is debugged.
Further, after the system signal sent at described gate control system monitoring terminal receiving gate access control system simulator, also comprise:
The gate control system monitoring terminal represents with the form of animation the information that described system signal comprises.
Further, at described gate control system monitoring terminal, forward described system signal after third party's system is debugged, also comprise:
The gate control system monitoring terminal receives third party's request that third party's system sends;
If described third party request is the subscription data request, the gate control system monitoring terminal extracts corresponding data encapsulation according to described subscription data request and becomes Packet Generation to third party's system from described system signal.
Further, at described gate control system monitoring terminal, forward described system signal after third party's system is debugged, also comprise:
The gate control system monitoring terminal adds described subscription data request in the subscription data request list;
After described gate control system monitoring terminal receives third party's request of third party's system transmission, also comprise:
If described third party's request is anti-subscription data request, gate control system monitoring terminal gate control system monitoring terminal is deleted subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request.
Further, after described gate control system monitoring terminal receives third party's request of third party's system transmission, also comprise:
If described third party's request is the control command request, the gate control system monitoring terminal forwards described control command request to gate inhibition's simulator, by gate inhibition's simulator, according to described control command request, to generate new system signal, then forward described new system signal to third party's system by gate inhibition's simulator.
On the one hand, provide a kind of gate control system simulator again, described gate control system simulator comprises:
The configuration information acquiring unit, for reading the configuration information set in advance, described configuration information comprises worker information, the card image in access controller information in the office buildings gate control system of needs simulations, door information, building;
The system signal generation unit, for according to described configuration information, and in conjunction with user's commissioning requirements generation system signal;
The system signal transmitting element, for sending described system signal to the gate control system monitoring terminal, debugged by the gate control system monitoring terminal, described system signal is sent to third party's system.
Another aspect, provide a kind of gate control system monitoring terminal, and described gate control system monitoring terminal comprises:
The system signal receiving element, the system signal sent for receiving gate access control system simulator, described system signal is that the gate control system simulator is according to the configuration information set in advance, and generate in conjunction with user's commissioning requirements, described configuration information comprises access controller information, door information, interior worker information, the card image of building in the office buildings gate control system of needs simulation;
The system signal retransmission unit, debugged for forwarding described system signal to third party's system.
Further, described gate control system monitoring terminal also comprises:
The animation broadcast unit, represent for the form with animation the information that described system signal comprises.
Further, described gate control system monitoring terminal also comprises:
Third party's request reception unit, the third party's request sent for receiving third party's system;
The subscription data requesting processing if be the subscription data request for described third party's request, extract corresponding data encapsulation according to described subscription data request and becomes Packet Generation to third party's system from described system signal;
The request list generation unit, for adding the subscription data request list by described subscription data request;
Anti-subscription data request unit, if be anti-subscription data request for described third party's request, delete subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request;
The control command requesting processing, if be the control command request for described third party's request, forward described control command request to gate inhibition's simulator, by gate inhibition's simulator, according to described control command request, to generate new system signal, then forward described new system signal to third party's system by gate inhibition's simulator.
Again on the one hand, a kind of debug system of office buildings gate control system is provided, described debug system comprises third party's system, gate control system simulator as above and gate control system monitoring terminal as above, described gate control system simulator is connected with described gate control system monitoring terminal, and described gate control system monitoring terminal is connected with described third party's system.
In the embodiment of the present invention, by gate control system simulator office buildings gate control system that is virtually reality like reality, and generation is for the system signal of debugging, by the gate control system monitor terminal, to forward this system signal to third party's system, carried out the debugging of office buildings gate control system according to this system signal by third party's system.Due to the real equipment environment without building the office buildings gate control system, compared to existing technology, have that the construction cycle is short, equipment investment is few and debug advantage easily.
The accompanying drawing explanation
Fig. 1 is the realization flow figure of the adjustment method of the office buildings gate control system that provides of the embodiment of the present invention one;
The realization flow figure of the adjustment method of the office buildings gate control system that Fig. 2 embodiment of the present invention two provides;
Fig. 3 is the structured flowchart of the gate control system simulator that provides of the embodiment of the present invention three;
Fig. 4 is the structured flowchart of the gate control system monitoring terminal that provides of the embodiment of the present invention four;
Fig. 5 is the structured flowchart of the debug system of the office buildings gate control system that provides of the embodiment of the present invention five.
Embodiment
In order to make purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not intended to limit the present invention.
In embodiments of the present invention, by gate control system simulator office buildings gate control system that is virtually reality like reality, and generation is for the system signal of debugging, by the gate control system monitor terminal, to forward this system signal to third party's system, carried out the debugging of office buildings gate control system according to this system signal by third party's system.
Below in conjunction with specific embodiment, realization of the present invention is described in detail:
Embodiment mono-
Fig. 1 shows the realization flow of the adjustment method of the office buildings gate control system that the embodiment of the present invention one provides, and the gate control system simulator side of take describes as example, and details are as follows:
In step S101, the gate control system simulator reads the configuration information set in advance, and configuration information comprises worker information, the card image in access controller information in the office buildings gate control system of needs simulations, door information, building.
In the present embodiment, when moving the debug system of office buildings gate control system for the first time, configuration information can manually add after the debug system operation, also can be before the operation debug system, insert in advance relevant configuration information in configuration database, the connection parameter modification that then will preserve in the configuration file of connection parameter of configuration database becomes corresponding configuration database.While again moving, debug system will directly read corresponding configuration information according to configuration file later, now, if necessary, can connect parameter or additions and deletions configuration information in the Update Table storehouse.It should be noted that, configuration information can be stored in configuration database, can certainly be stored in the form of file in a configuration file, concrete configuration information is stored in which way, be not restricted in the present embodiment, take configuration information at this and describe as example in being stored in configuration database.
The debug system of office buildings gate control system is when operation, can automatically read configuration file, the connection parameter that comprises configuration database in configuration file, as the database name of the IP address of configuration database place main frame, configuration database, database user name, database password etc., the default configuration database is at the machine (127.0.0.1).Also comprise communication port numbers TCPPort in configuration file.Configuration file format is as follows:
; Configuration database
[DataBase]
IP=xxx.xxx.xxx.xxx (as 127.0.0.1) (IP address)
Dbname=xxx(is as BIS) (database name)
Username=xxx(is as sa) (database user name)
Pwd=xxx(is as 123456) (database password)
; The TCP communication port numbers
[TCP]
TCPPort=xxx (as 6000)
If need to revise the connection parameter of configuration database, can revise the configuration of the configuration database of gate inhibition's analogue system, debug system can be by the connection parameter read-in configuration file of revising.
Wherein, configuration information comprises worker information, the card image in access controller information in the office buildings access control system of needs simulations, door information, building.
Office buildings gate inhibition debug system can configure as required and increase worker information and the card image in access controller, door information and the building that need simulation in the gate control system simulator, and can automatically be kept at the relevant information configured in the tables of data that configuration database is corresponding; Also can insert in the tables of data that configuration database is corresponding by the access controller that will need in advance simulation, worker information and the card image in door information and building, realize worker information in access controller, door information and building and the configuration of card image.If had worker information and card image in access controller, door information and building in the configuration database of configuration, debug system can read configuration file, connect parameter according to the configuration database provided in configuration file and connect configuration database, directly from configuration database, read relevant configuration information.
In step S102, the gate control system simulator is according to configuration information, and in conjunction with user's commissioning requirements generation system signal.
In the embodiment of the present invention, the gate control system simulator can be according to configuration information, and generates the needed system signal of debugging office buildings gate control system in conjunction with the commissioning requirements of the user in debug system.
During practical operation, the mode that office buildings gate inhibition debug system needs artificial initialization system signal to generate, debug system is supported the generating mode of three kinds of system signals, is respectively manual input generating mode, logic generating mode and random generating mode.
Wherein, manually input generating mode for system signal manually is set;
The logic generating mode is set logic generation system signal for pressing, periodic signal during this system signal, and the normal operation that can simulate the office buildings gate control system, third party's system can be debugged according to this system signal.For example, according to the uptime section of office buildings gate control system, be on duty in front and a period of time After Hours, produce a large amount of system signals, within other time period, produce at random system signal.And for example, can set the office buildings gate control system at a fixed time (as 9:00) produce fixing system signal (as some safety door simulation is opened) or set the office buildings gate control system every regular time (as one minute), produce constantly the needed system signal of debugging (as opening the door) etc.;
Random generating mode, for random generation system signal, is applied when the general power system capacity in the office buildings gate control system and load debugging.
The system signal of office buildings gate control system can be divided into five aspects:
1), the system management signal, comprise the mode of operation, user's access permission group of authority, system alarm pattern, the door of user's card image etc.;
2), the access controller signal, comprise the online and off-lined signal of access controller;
3), gate signal, comprise that door is normally opened, door is opened extremely, door is normally closed, door is closed extremely, door open overtime, Men Wei opens and door group interlock is controlled etc.;
4), the signal of swiping the card, comprising swipes the card enters with the gate signal of swiping the card out, illegally stick into door and go out gate signal;
5), alerting signal, comprise that door extremely opens that warnings, door are extremely closed warning, opened overtime warning, Men Wei opens warning, illegally sticks into door alarm, illegally blocks the alerting signal such as door alarm.
After generating mode for debug system selecting system signal, debug system can, according to configuration information, generate corresponding system signal in conjunction with concrete commissioning requirements.The generating mode of the system signal of debug system acquiescence is random generating mode.After system signal generates, the gate control system simulator can send to the gate control system monitoring terminal by the system signal of generation.
In step S103, gate control system simulator transmitting system signal, to the gate control system monitoring terminal, is debugged by the gate control system monitoring terminal, this system signal is sent to third party's system.
In the present embodiment, the system signal that the gate control system monitoring terminal will receive from the gate control system simulator is sent to third party's system and is debugged.Simultaneously, the gate control system monitoring terminal can represent with the form of animation the information that this system signal is comprised, such as, the warning message of the action that simulation is opened the door, closed the door, door and user card punching information etc., and be presented on the operation interface of gate control system monitoring terminal display system signals intuitively.In addition, on operation interface, can also see the essential information of this analog gate, as the ,Men address, access controller address under this, with the door title of this door linkage, this mode of operation etc.
The present embodiment, by gate control system simulator office buildings gate control system that is virtually reality like reality, and generate the system signal for debugging, by the gate control system monitor terminal, to forward this system signal to third party's system, carried out the debugging of office buildings gate control system according to this system signal by third party's system.Due to the real equipment environment without building the office buildings gate control system, compared to existing technology, have that the construction cycle is short, equipment investment is few and debug advantage easily.
One of ordinary skill in the art will appreciate that all or part of step realized in the various embodiments described above method is to come the hardware that instruction is relevant to complete by program, corresponding program can be stored in a computer read/write memory medium, described storage medium, as ROM/RAM, disk or CD etc.
Embodiment bis-
Fig. 2 shows the realization flow of the adjustment method of the office buildings gate control system that the embodiment of the present invention two provides, and the gate control system monitoring terminal side of take describes as example, and details are as follows:
In step S201, the system signal that gate control system monitoring terminal receiving gate access control system simulator sends, wherein, system signal is that the gate control system simulator is according to the configuration information set in advance, and generate in conjunction with user's commissioning requirements, this configuration information comprises access controller information, door information, interior worker information, the card image of building in the office buildings gate control system of needs simulation.
As a preferred embodiment of the present invention, the gate control system monitoring terminal represents with the form of animation the information that system signal comprises, such as, the action that the broadcasting simulation is opened the door, closed the door on the operation interface of gate control system monitoring terminal, the warning message of door and user card punching information etc., display system signals intuitively.In addition, on the operation interface of gate control system monitoring terminal, can also see the essential information of this analog gate, as the ,Men address, access controller address under this, with the door title of this door linkage, this mode of operation etc.
In step S202, the gate control system monitoring terminal forwards system signal to the third party's system received and is debugged.
In step S203, the gate control system monitoring terminal receives third party's request that third party's system sends.
In the embodiment of the present invention, third party's system can also be docked by gate control system monitoring terminal and gate control system simulator, the third party that the gate control system monitoring terminal can send according to third party's system asks to send corresponding data to third party's system, to realize the docking debugging between gate control system simulator, gate inhibition's monitor terminal and third party's system.Wherein, third party's system can need to send three kinds of third parties according to debugging asks to the gate control system monitoring terminal, and these three kinds of requests are respectively subscription data request, anti-subscription data request and control command request.
After third party's request is sent out, the third party's system sent request can be received a rreturn value.This rreturn value, for illustrating whether the request of transmission is successfully executed, runs succeeded and returns to successfully sign " 1 ", carries out and unsuccessfully returns to unsuccessfully sign " 0 ".Only having rreturn value is the request that successfully identifies " 1 ", and the gate control system simulator just can be carried out corresponding operation.
During the third party asks to process, the gate control system monitoring terminal, in the process of operation, can check whether receive third party's request that third party's system sends continuously.If receive this third party's request, the gate control system monitoring terminal can check whether this request meets the request format specification, if do not meet the request format specification, system just abandons this request not process, and returns to third party's system request failure; If meet the request format specification, judge the classification that the third party asks, if the subscription data request forwards in step 204; If anti-subscription data request forwards in step 205; If the control command request forwards in step 206.
In step S204, if this third party request is the subscription data request, the gate control system monitoring terminal extracts corresponding data encapsulation according to this subscription data request and becomes Packet Generation to third party's system from system signal.
In the present embodiment, the subscription data request is divided into real time data request and historical data request.The real time data request comprises real-time status (Men Kai or door close), mode of operation, the booking reader's card using information of subscribing to door of subscribing to door, subscribes to warning message, subscribes to access controller presence etc.The historical data request mainly refers to subscribes to some changeless data, as the essential information of the door of gate control system simulator simulation, access controller list etc.After receiving that for the first time real time data pulls subscription, the gate control system simulator can, when coherent signal changes, ceaselessly push relevant information to third party's system of initiating the subscription data request, until third party's system cancels subscriptions.The gate control system simulator, after receiving the historical data request, only can return to a secondary data, because these data are changeless.
Concrete, after gate inhibition's monitor terminal receives the subscription data request, this subscription data request is added in the subscribe request list, and back can be extracted corresponding data encapsulation and be become Packet Generation to third party's system from system signal according to the subscribe request in the subscribe request list.When the system signal of subscribing to changes, gate inhibition's monitor terminal extracts corresponding data encapsulation and becomes packet from the system signal this variation, then is sent to third party's system corresponding in subscription list.Real-time status for door, access controller presence and mode of operation, system signal change refer to when certain signal lasts till certain time point no longer lasting, change has occurred in this signal, as door was to close originally, then door has been opened, now variation has just occurred in the state of door, and for example the mode of operation of certain beginning is often to open, then be arranged to this mode of operation normally closed as required, variation has occurred in the mode of operation of door, certain access controller is online at first for another example, then due to some setting, this controller off-line, for user card punching information and warning message, signal changes and refers to the data-signal that generation is new, as certain user has opened certain door with the card brush, can produce new card using information, and for example the event of illegally swiping the card has occurred in certain time in certain door, now not only can produce card using information, also can produce alert event, that is to say that variation has occurred for card using information and warning message.
In step S205, if the third party who receives request is anti-subscription data request, the gate control system monitoring terminal is deleted the subscription data request corresponding with this anti-subscription data request according to this anti-subscription data request.
In embodiments of the present invention, after the subscription data request that receives the transmission of third party's system, the gate control system monitoring terminal can add this subscription data request in the subscribe request list.Follow-up, after the gate control system monitoring terminal receives the anti-subscription data request corresponding with this subscription data request, can from the subscribe request list, find the subscription data request corresponding with anti-subscription data request, and it is deleted from the subscribe request list.Delete this subscription data request from the subscribe request list after, when the system signal pulled subscription at this subscription data changes, no longer propelling data is to third party's system.Anti-subscription data request is contrary with the subscription data request, that is to say the request of data that cancels subscriptions.After having sent the anti-subscription data request corresponding with the subscription data request, the data subscription request sent will no longer be had an effect, and the third party's system that sends the subscription data request will no longer be received related data.
In step S206, if the third party who receives request is the control command request, the gate control system monitoring terminal forwards this control command request to gate inhibition's simulator, by gate inhibition's simulator, according to this control command request, to generate new system signal, then forward this new system signal to third party's system by gate inhibition's simulator.
In embodiments of the present invention, the gate control system monitoring terminal forwards the control command request to gate inhibition's simulator, requirement by the gate control system simulator according to the control command request, generate new system signal, then the new system signal generated is sent to the gate control system monitoring terminal, last by the gate control system monitoring terminal, the system signal that this is new is forwarded to third party's system and is debugged.It should be noted that: a control command can be controlled and produce a signal, also can control and generate a plurality of signals, but must be the signal of same, as a control command can change the door state (open the door, close the door) of one or more, while controlling a plurality of, can be arranged to different states to different doors as required, as a door is opened, other door is closed, but in the order of this control gate state, can not be in the control gate state, the mode of operation of control gate.
The present embodiment, gate control system monitor terminal receiving gate access control system simulator office buildings gate control system that is virtually reality like reality and the system signal that generates, and forward this system signal to third party's system, carried out the debugging of office buildings gate control system according to this system signal by third party's system.Due to the real equipment environment without building the office buildings gate control system, the defect of having avoided prior art need to build equipment debugging environment in kind, the system signal of display simulation intuitively, have advantages of that equipment investment is few, the construction cycle is short, debugging is convenient and can arbitrarily produce a large amount of system signals to be debugged.
Embodiment tri-
Fig. 3 shows the concrete structure block diagram of the gate control system simulator that the embodiment of the present invention three provides, and for convenience of explanation, only shows the part relevant to the embodiment of the present invention.This gate control system simulator 3 comprises: configuration information acquiring unit 31, system signal generation unit 32 and system signal transmitting element 33.
Wherein, configuration information acquiring unit 31, for reading the configuration information set in advance, this configuration information comprises worker information, the card image in access controller information in the office buildings gate control system of needs simulations, door information, building;
System signal generation unit 32, for the configuration information read according to configuration information acquiring unit 31, and in conjunction with user's commissioning requirements generation system signal;
System signal transmitting element 33, the system signal generated for transmitting system signal generation unit 32, to the gate control system monitoring terminal, is debugged by the gate control system monitoring terminal, system signal is sent to third party's system.
The gate control system simulator that the embodiment of the present invention provides can be applied in the embodiment of the method one of aforementioned correspondence, and details, referring to the description of above-described embodiment one, do not repeat them here.
Embodiment tetra-
Fig. 4 shows the concrete structure block diagram of the gate control system monitor terminal that the embodiment of the present invention four provides, and for convenience of explanation, only shows the part relevant to the embodiment of the present invention.This gate control system monitor terminal 4 comprises: system signal receiving element 41 and system signal retransmission unit 42.
Wherein, system signal receiving element 41, the system signal sent for receiving gate access control system simulator, this system signal is that the gate control system simulator is according to the configuration information set in advance, and generate in conjunction with user's commissioning requirements, this configuration information comprises access controller information, door information, interior worker information, the card image of building in the office buildings gate control system of needs simulation;
System signal retransmission unit 42, the system signal received for repeater system signal receiving unit 41 to third party's system is debugged.
Further, gate control system monitoring terminal 4 also comprises:
The animation broadcast unit, represent for the form with animation the information that system signal that system signal receiving element 41 receives comprises.
Further, gate control system monitoring terminal 4 also comprises:
Third party's request reception unit, the third party's request sent for receiving third party's system;
The subscription data requesting processing, if the third party request received for third party's request reception unit is the subscription data request, according to this subscription data request, extracts corresponding data encapsulation from system signal and become Packet Generation to third party's system;
The request list generation unit, for adding the subscription data request list by this subscription data request;
Anti-subscription data request unit, if the third party request received for third party's request reception unit is anti-subscription data request, according to this anti-subscription data request, delete the subscription data request corresponding with this anti-subscription data request in the subscribe request list;
The control command requesting processing, if the third party request received for third party's request reception unit is the control command request, forward and change the control command request to gate inhibition's simulator, by gate inhibition's simulator, according to this control command request, to generate new system signal, then forward this new system signal to third party's system by gate inhibition's simulator.
The gate control system monitor terminal that the embodiment of the present invention provides can be applied in the embodiment of the method two of aforementioned correspondence, and details, referring to the description of above-described embodiment two, do not repeat them here.
Embodiment five
Fig. 5 shows the concrete structure block diagram of the debug system of the office buildings gate control system that the embodiment of the present invention five provides, and for convenience of explanation, only shows the part relevant to the embodiment of the present invention.The debug system 5 of this office buildings gate control system comprises gate control system simulator 3, the gate control system monitor terminal 4 in embodiment tetra-and the third party's system 51 in embodiment tri-.Wherein, gate control system simulator 3 is connected with gate control system monitor terminal 4, and gate control system monitor terminal 4 is connected with third party's system 5.Concrete, the communications protocol connected mode by TCP/IP between gate control system simulator 3 and gate control system monitor terminal 4 connects, between gate control system monitor terminal 4 and third party's system 5 also the communications protocol connected mode by TCP/IP be connected.
The debug system that the present embodiment provides, gate control system simulator office buildings gate control system that is virtually reality like reality generates the system signal, and send this system signal to the gate control system monitor terminal, forward this system signal to third party's system by the gate control system monitor terminal, third party's system is carried out the debugging of office buildings gate control system according to this system signal.Due to the real equipment environment without building the office buildings gate control system, the defect of having avoided prior art need to build equipment debugging environment in kind, the system signal of display simulation intuitively, have advantages of that equipment investment is few, the construction cycle is short, debugging is convenient and can arbitrarily produce a large amount of system signals to be debugged.
It should be noted that in said system embodiment, included unit is just divided according to function logic, but is not limited to above-mentioned division, as long as can realize corresponding function; In addition, the concrete title of each functional unit also, just for the ease of mutual differentiation, is not limited to protection scope of the present invention.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, all any modifications of doing within the spirit and principles in the present invention, be equal to and replace and improvement etc., within all should being included in protection scope of the present invention.

Claims (11)

1. the adjustment method of an office buildings gate control system, is characterized in that, described method comprises:
The gate control system simulator reads the configuration information set in advance, and described configuration information comprises worker information, the card image in access controller information in the office buildings gate control system of needs simulations, door information, building;
The gate control system simulator is according to described configuration information, and in conjunction with user's commissioning requirements generation system signal;
The gate control system simulator sends described system signal to the gate control system monitoring terminal, by the gate control system monitoring terminal, described system signal is sent to third party's system, is debugged.
2. the adjustment method of an office buildings gate control system, is characterized in that, described method comprises:
The system signal that gate control system monitoring terminal receiving gate access control system simulator sends, described system signal is that the gate control system simulator is according to the configuration information set in advance, and generate in conjunction with user's commissioning requirements, described configuration information comprises access controller information, door information, interior worker information, the card image of building in the office buildings gate control system of needs simulation;
The gate control system monitoring terminal forwards described system signal to third party's system and is debugged.
3. method as claimed in claim 2, is characterized in that, after the system signal sent at described gate control system monitoring terminal receiving gate access control system simulator, also comprises:
The gate control system monitoring terminal represents with the form of animation the information that described system signal comprises.
4. method as claimed in claim 2, is characterized in that, at described gate control system monitoring terminal, forwards described system signal after third party's system is debugged, and also comprises:
The gate control system monitoring terminal receives third party's request that third party's system sends;
If described third party request is the subscription data request, the gate control system monitoring terminal extracts corresponding data encapsulation according to described subscription data request and becomes Packet Generation to third party's system from described system signal.
5. method as claimed in claim 4, is characterized in that, at described gate control system monitoring terminal, forwards described system signal after third party's system is debugged, and also comprises:
The gate control system monitoring terminal adds described subscription data request in the subscription data request list;
After described gate control system monitoring terminal receives third party's request of third party's system transmission, also comprise:
If described third party's request is anti-subscription data request, gate control system monitoring terminal gate control system monitoring terminal is deleted subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request.
6. method as claimed in claim 4, is characterized in that, after described gate control system monitoring terminal receives third party's request of third party's system transmission, also comprises:
If described third party's request is the control command request, the gate control system monitoring terminal forwards described control command request to gate inhibition's simulator, by gate inhibition's simulator, according to described control command request, to generate new system signal, then forward described new system signal to third party's system by gate inhibition's simulator.
7. a gate control system simulator, is characterized in that, described gate control system simulator comprises:
The configuration information acquiring unit, for reading the configuration information set in advance, described configuration information comprises worker information, the card image in access controller information in the office buildings gate control system of needs simulations, door information, building;
The system signal generation unit, for according to described configuration information, and in conjunction with user's commissioning requirements generation system signal;
The system signal transmitting element, for sending described system signal to the gate control system monitoring terminal, debugged by the gate control system monitoring terminal, described system signal is sent to third party's system.
8. a gate control system monitoring terminal, is characterized in that, described gate control system monitoring terminal comprises:
The system signal receiving element, the system signal sent for receiving gate access control system simulator, described system signal is that the gate control system simulator is according to the configuration information set in advance, and generate in conjunction with user's commissioning requirements, described configuration information comprises access controller information, door information, interior worker information, the card image of building in the office buildings gate control system of needs simulation;
The system signal retransmission unit, debugged for forwarding described system signal to third party's system.
9. gate control system monitoring terminal as claimed in claim 8, is characterized in that, described gate control system monitoring terminal also comprises:
The animation broadcast unit, represent for the form with animation the information that described system signal comprises.
10. gate control system monitoring terminal as claimed in claim 8, is characterized in that, described gate control system monitoring terminal also comprises:
Third party's request reception unit, the third party's request sent for receiving third party's system;
The subscription data requesting processing if be the subscription data request for described third party's request, extract corresponding data encapsulation according to described subscription data request and becomes Packet Generation to third party's system from described system signal;
The request list generation unit, for adding the subscription data request list by described subscription data request;
Anti-subscription data request unit, if be anti-subscription data request for described third party's request, delete subscription data request corresponding with described anti-subscription data request in described subscribe request list according to described anti-subscription data request;
The control command requesting processing, if be the control command request for described third party's request, forward described control command request to gate inhibition's simulator, by gate inhibition's simulator, according to described control command request, to generate new system signal, then forward described new system signal to third party's system by gate inhibition's simulator.
11. the debug system of an office buildings gate control system, it is characterized in that, described debug system comprises third party's system, gate control system simulator as claimed in claim 7 and gate control system monitoring terminal as described as claim 8 to 10 any one, described gate control system simulator is connected with described gate control system monitoring terminal, and described gate control system monitoring terminal is connected with described third party's system.
CN201310392733.XA 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system Expired - Fee Related CN103500475B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310392733.XA CN103500475B (en) 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310392733.XA CN103500475B (en) 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system

Publications (2)

Publication Number Publication Date
CN103500475A true CN103500475A (en) 2014-01-08
CN103500475B CN103500475B (en) 2015-08-19

Family

ID=49865678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310392733.XA Expired - Fee Related CN103500475B (en) 2013-09-02 2013-09-02 A kind of adjustment method, system of office buildings gate control system

Country Status (1)

Country Link
CN (1) CN103500475B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243707A (en) * 2015-09-22 2016-01-13 苏州工业园区职业技术学院 Staged automatic entrance guard control device
CN106228642A (en) * 2016-07-15 2016-12-14 颜芳俊 A kind of intelligent door lock system and control method thereof
CN108376453A (en) * 2018-02-28 2018-08-07 张梦雅 Intelligent anti-theft alarm system for office building
CN110706392A (en) * 2019-10-14 2020-01-17 重庆紫光华山智安科技有限公司 Security platform test method and device, storage medium and server
CN112415907A (en) * 2020-11-26 2021-02-26 珠海格力电器股份有限公司 Building equipment remote debugging control method and device and computer equipment

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030151493A1 (en) * 2002-02-13 2003-08-14 Swisscom Ag Access control system, access control method and devices suitable therefor
CN102034290A (en) * 2010-12-21 2011-04-27 汉王科技股份有限公司 Access control method and device
CN102646295A (en) * 2011-02-21 2012-08-22 中国移动通信集团江苏有限公司 Intelligent residential community security system and customizing service realizing method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030151493A1 (en) * 2002-02-13 2003-08-14 Swisscom Ag Access control system, access control method and devices suitable therefor
CN102034290A (en) * 2010-12-21 2011-04-27 汉王科技股份有限公司 Access control method and device
CN102646295A (en) * 2011-02-21 2012-08-22 中国移动通信集团江苏有限公司 Intelligent residential community security system and customizing service realizing method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243707A (en) * 2015-09-22 2016-01-13 苏州工业园区职业技术学院 Staged automatic entrance guard control device
CN106228642A (en) * 2016-07-15 2016-12-14 颜芳俊 A kind of intelligent door lock system and control method thereof
CN108376453A (en) * 2018-02-28 2018-08-07 张梦雅 Intelligent anti-theft alarm system for office building
CN110706392A (en) * 2019-10-14 2020-01-17 重庆紫光华山智安科技有限公司 Security platform test method and device, storage medium and server
CN112415907A (en) * 2020-11-26 2021-02-26 珠海格力电器股份有限公司 Building equipment remote debugging control method and device and computer equipment

Also Published As

Publication number Publication date
CN103500475B (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN103500475B (en) A kind of adjustment method, system of office buildings gate control system
CN105137922B (en) field device management system
DE102006033503A1 (en) Wireless power transmission systems and methods
CN104836699A (en) Equipment state processing method and equipment state processing system
WO2012050734A1 (en) Intelligent interface for a distributed control system
US10809753B2 (en) Real-time simulator and controller of power system using distributed data streaming server
CN104216361A (en) State monitoring system for secondary device
CN104898438A (en) Household electrical appliance control method and apparatus, and terminal
CN105137928A (en) Full-automatic production line data collection method and system thereof
CN103425096A (en) Building automation system
CN105530220B (en) The interface method of two kinds of different agreement system communications is realized based on OPC
KR100586432B1 (en) A remote operating system and method for Water Cooling System of M·TR appling PLC ? DDC System
KR20120110693A (en) Integrated remote monitoring and controlling system extensible to mobile environment
CN106909327A (en) A kind of display control unit for industrial control equipment
CN103997542A (en) Multi-sensor and multi-device monitoring system based on cloud storage
CN108132664B (en) Automatic relay protection information point aligning method suitable for intelligent substation
CN105217389A (en) The method and system of elevator spare part telemanagement
CN105792025A (en) Device information obtaining method and terminal
KR102310507B1 (en) The Operation System and Control Method of Special Protection Systems/Schemes
KR20160129264A (en) Power converting apparatus having function of server
CN108829072A (en) The control system of sterile pharmaceutical equipment
CN205453732U (en) Warning equipment of high in clouds control
KR20140122454A (en) dispatcher training system and its control method
CN103871177A (en) Remote maintenance method of network billing machine
CN103853139A (en) Air conditioner gateway and building centralized control system

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
GR01 Patent grant
C14 Grant of patent or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150819

Termination date: 20190902

CF01 Termination of patent right due to non-payment of annual fee