CN103485285A - 一种系杆拱桥刚性吊杆的更换方法 - Google Patents

一种系杆拱桥刚性吊杆的更换方法 Download PDF

Info

Publication number
CN103485285A
CN103485285A CN201310387192.1A CN201310387192A CN103485285A CN 103485285 A CN103485285 A CN 103485285A CN 201310387192 A CN201310387192 A CN 201310387192A CN 103485285 A CN103485285 A CN 103485285A
Authority
CN
China
Prior art keywords
bearing pin
hanger
suspension rod
pin
lifting eye
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310387192.1A
Other languages
English (en)
Other versions
CN103485285B (zh
Inventor
胡锋
王统宁
唐国斌
张会礼
张理
梁柯峰
李洪波
杜红静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Provincial Highway Survey and Design Co., Ltd.
Original Assignee
HENAN PROVINCIAL TRANSPORTATION RESEARCH INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN PROVINCIAL TRANSPORTATION RESEARCH INSTITUTE Co Ltd filed Critical HENAN PROVINCIAL TRANSPORTATION RESEARCH INSTITUTE Co Ltd
Priority to CN201310387192.1A priority Critical patent/CN103485285B/zh
Publication of CN103485285A publication Critical patent/CN103485285A/zh
Application granted granted Critical
Publication of CN103485285B publication Critical patent/CN103485285B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种系杆拱桥刚性吊杆的更换方法,吊杆更换的施工过程分为如下步骤:(1)设置临时吊杆平台;临时吊杆平台包括吊杆和销铰,吊杆的上下两端分别与拱肋和横梁连接,所述横梁上连接有锚固耳板,所述锚固耳板上连接有销铰,所述销铰与吊杆的下端连接;其传力途径为桥面板→横梁→锚固耳板→销铰→吊杆→拱肋,(2)吊装临时纵梁即贝雷梁;(3)提升临时吊杆,使原吊杆处于无应力状态;本发明具有以下特点:1.不需在原结构上钻孔,避免对结构的损害,便于吊杆更换施工;2.吊杆下端可随桥面一起水平位移,改善吊杆受力状况,避免吊杆护套破损和钢丝受力不均匀;3.便于后期吊杆更换。

Description

一种系杆拱桥刚性吊杆的更换方法
技术领域
本发明涉及系杆拱桥吊杆更换技术领域,具体涉及一种采用销接式吊杆更换刚性吊杆的方法。
背景技术
系杆拱桥具有结构合理、受力明确、竖向刚度大等优点,这种桥型不但技术经济指标先进,造价经济,同时桥型美观,反映出力与美的统一,结构形式与环境的和谐。系杆拱桥中的吊杆将纵梁和横梁系统悬挂在拱肋之下,是主要的受拉构件,桥面荷载通过吊杆和桥面系将作用力传递至拱肋上。由于传统吊杆在锚固体系、索体结构、防腐方案等方面的缺陷,致使其过早产生损伤,吊杆的主要病害有防护结构失效、钢丝或钢绞线锈蚀、上下锚具不能发挥作用及吊杆断裂等。
系杆拱桥的吊杆根据其构造分为刚性吊杆和柔性吊杆。刚性吊杆通常采用钢筋混凝土或预应力混凝土制作,吊杆两端钢筋分别与拱肋和横梁钢筋焊接,这种连接方式为吊杆的更换带来诸多不便。当采用传统的更换方法时,需要在拱肋和横梁上同时钻孔,这对原结构的损伤较大,尤其当横梁出现病害较多时,可能导致横梁出现破坏。 
发明内容
本发明的目的在于提供一种系杆拱桥刚性吊杆的更换方法,避免对结构的损害,改善吊杆受力状况,便于后期吊杆更换。
本发明的技术方案是: 
一种系杆拱桥刚性吊杆的更换方法,吊杆更换的施工过程分为如下步骤:
(1)设置临时吊杆平台;临时吊杆平台包括吊杆和销铰,吊杆的上下两端分别与拱肋和横梁连接,所述横梁上连接有锚固耳板,所述锚固耳板上连接有销铰,所述销铰与吊杆的下端连接;其传力途径为桥面板→横梁→锚固耳板→销铰→吊杆→拱肋,
(2)吊装临时纵梁即贝雷梁;
(3)提升临时吊杆,使原吊杆处于无应力状态;
(4)拆除原吊杆;
(5)在拱肋正确位置钻孔,并设锚下平台;
(6)在横梁上安装插耳式铰;
(7)安装新吊杆;
(8)调整新吊杆;通过调整新吊杆长度,使其达到正常使用受力状态;
(9)完成吊杆更换,拆除临时设施。
所述锚固耳板包括上连接板,所述上连接板与销铰连接。
所述锚固耳板还包括下连接板、螺纹杆和螺纹钢锚具,所述上连接板和下连接板之间通过螺纹杆和螺纹钢锚具连接。
所述销铰包括吊耳、吊耳座和销轴,吊耳、吊耳座之间通过销轴连接,吊耳与吊杆的下端固定连接,吊耳座与上连接板固定连接。
所述吊耳座焊接在上连接板上。
所述的吊耳座的设计参数包括板宽B、板厚δ、板孔的顶距A1、板孔的底距A2、边距A3、孔直径D、孔与销轴的间隙e:
(1)验算吊耳座的横截面强度
Figure 602212DEST_PATH_IMAGE001
公式中,An为销孔边至吊耳座的截面积An=2A3×δ,F为销轴传递至吊耳的拉力;f为钢材强度设计值,该验算可避免吊耳座发生净截面受拉破坏;
(2)验算吊耳座的孔壁承压强度
Figure 245683DEST_PATH_IMAGE002
式中,
Figure 580849DEST_PATH_IMAGE003
为参照普通螺栓连接的承压强度取值,F为销轴传递至吊耳的拉力,D为吊耳座的孔的内径,δ为板厚,该验算可以防止出现孔道的挤压破坏。
所述销轴用于连接吊杆和吊耳座,其参数包括销轴的直径d、F为销轴承受的吊杆拉力,对销轴强度进行验算:
(1)验算销轴的抗剪强度
Figure 12835DEST_PATH_IMAGE004
式中,fe为钢材抗剪强度设计值,ne为销轴的剪切面数,通过该式的验算可防止销轴发生剪切破坏;
(2)验算销轴的抗弯强度
Figure 29332DEST_PATH_IMAGE005
式中,M为销轴承受的弯矩,M=FL/4,L为销轴的计算跨度,W1为销轴截面的抵抗矩,
Figure 527310DEST_PATH_IMAGE006
,通过该式的验算可防止销轴发生弯曲破坏。
所述吊杆的上端连接有张拉端锚环,张拉端锚环上端密封连接有压盖。
张拉端锚环的外侧设有保护的上防护罩。
本发明提出采用销接式吊杆更换传统刚性吊杆的方法,解决新吊杆与横梁的锚固问题。该方法不仅施工简便,而且可以改善吊杆的受力,同时便于后期吊杆更换。
本发明具有以下特点:1.不需在原结构上钻孔,避免对结构的损害,便于吊杆更换施工;2.吊杆下端可随桥面一起水平位移,改善吊杆受力状况,避免吊杆护套破损和钢丝受力不均匀;3.便于后期吊杆更换。
本发明的技术经济效果:
1. 不需在原结构上钻孔,避免对结构的损害,便于吊杆更换施工。
2. 吊杆下端可随桥面一起水平位移,改善吊杆受力状况,避免吊杆护套破损和钢丝受力不均匀。
3. 便于后期吊杆的更换。
附图说明
图1是本发明的销接式吊杆结构体系的横桥向图;
图2是本发明的销接式吊杆结构体系的纵桥向图;
图3是销铰的几何尺寸图;
图4是采用临时纵梁和临时吊杆示意图。
图注说明:上防护罩1,压盖2,张拉端锚环3,锚具垫板4,吊杆5,浇筑的环氧砂浆6,约束环7,减震器8,拱肋9,防水装置10,不锈钢护套11,防锈钢管12,下防护罩13,固定端锚杯螺母14,吊耳15,销轴16,精轧螺纹杆17,精轧螺纹钢锚具18,上连接板19,下连接板20,横梁21,锚固耳板22,临时吊杆23、临时纵梁(贝雷梁)24、钢垫板25、防锈油脂26,外螺纹27,吊耳座28。
具体实施方式
如图1、2所示,本发明包括吊杆5,吊杆5的上下两端分别与拱肋9、横梁21连接。
吊杆5的外侧面涂有防锈油脂26,吊杆5的露在外的部分的外侧还设有不锈钢护套11以及防锈钢管12。
吊杆5的上端连接有张拉端锚环3,张拉端锚环3的上端连接有密封张拉端锚环3上端的压盖2,张拉端锚环3的外侧设有保护的上防护罩1。拱肋9的上侧面固定连接有锚具垫板4,上防护罩1固定连接在锚具垫板4上。吊杆5的外侧还连接有约束环7。在吊杆5和拱肋9之间设有减震器8,拱肋9和吊杆5连接处的最下端设有防水装置10。锚具垫板4和拱肋9之间浇筑有环氧砂浆6。
本发明采用一种销接式吊杆结构体系,通过锚固耳板22与桥面横梁21相连,在锚固耳板22上做销铰,实现桥面结构与吊杆5的铰接。销铰连接在锚固耳板22上。
本发明包括锚固耳板22和销铰;锚固耳板22由上连接板19、下连接板20、精轧螺纹杆17和精轧螺纹钢锚具18构成。
销铰由吊耳15、吊耳座28和销轴16构成。
具体结构为:
横梁21上连接有锚固耳板22,锚固耳板22的上下两端分别连接有上连接板19、下连接板20,上连接板19、下连接板20之间通过精轧螺纹杆17以及精轧螺纹钢锚具18紧固连接。在上连接板19上焊接有吊耳座28,吊耳座28连接吊耳15,吊耳座28和吊耳15之间通过销轴16连接。吊耳15的上端设有外螺纹,吊杆5的下端也设有外螺纹27。吊耳15的上端和吊杆5的下端之间通过固定端锚杯螺母14连接在一起。在固定端锚杯螺母14以及吊耳15的外侧还设有起防护作用的下防护罩13。下防护罩13的下端焊接在上连接板19上。
销接式吊杆结构体系由锚固耳板和销铰构成,其传力途径为桥面板→横梁→锚固耳板→销铰→吊杆→拱肋,传力明确顺畅。
如图3所示,图3为销铰的几何尺寸图。根据设计吊杆5张拉力F和设计参数,对吊耳座28的横截面强度、孔壁承压强度及销轴16的抗剪、抗弯强度分别进行验算。
吊耳座28焊接于锚固耳板22的上连接板19上,其设计参数包括板宽B、板厚δ、板孔的顶距A 1、板孔的底距A 2、边距A 3、孔直径D、孔与销轴的间隙e,设计方法为:
(1)吊耳座28横截面强度
Figure 298957DEST_PATH_IMAGE001
式中,F为销轴16传递至吊耳座28的拉力;f为为钢材强度设计值,A n为销孔边至吊耳座28的截面积An=2A3×δ,该验算可避免吊耳座28发生净截面受拉破坏。
(2)吊耳座28孔壁承压强度
Figure 249595DEST_PATH_IMAGE002
式中,
Figure 319051DEST_PATH_IMAGE003
为参照普通螺栓连接的承压强度取值,D为吊耳座的孔的内径,δ为板厚,该验算可以防止出现孔道的挤压破坏。
所述销轴16用于连接吊杆5和吊耳座28,其设计参数包括销轴16的直径d、销轴16的计算跨度L,设计方法为:
(1)销轴16的抗剪强度
Figure 671535DEST_PATH_IMAGE004
式中,F为销轴16承受的吊杆拉力,f e为钢材抗剪强度设计值,n e为销轴16的剪切面数,d为销轴直径,通过该式的验算可防止销轴16发生剪切破坏。
(2)销轴16的抗弯强度
式中,M为销轴16承受的弯矩,M=FL/4,F为销轴承受的吊杆拉力,L为销轴16的计算跨度,W 1为销轴16截面的抵抗矩,
Figure 52018DEST_PATH_IMAGE006
,通过该式的验算可防止销轴16发生弯曲破坏。
吊杆5更换的施工过程分为如下:
(1)设置临时吊杆平台;
(2)如图4所示,吊装临时纵梁24(贝雷梁),横梁21下方连接有钢垫板25;
(3)提升临时吊杆23,使原吊杆处于无应力状态;
(4)拆除原吊杆;
(5)在拱肋9的正确位置钻孔,并设锚下平台;
(6)在横梁21上安装锚固耳板22;
(7)安装新吊杆5;
(8)调整新吊杆5,通过调整新吊杆5长度,使其达到正常使用受力状态;
(9)完成吊杆更换,拆除临时设施。

Claims (10)

1.一种系杆拱桥刚性吊杆的更换方法,其特征在于:吊杆更换的施工过程分为如下步骤:
(1)设置临时吊杆平台;临时吊杆平台包括吊杆和销铰,吊杆的上下两端分别与拱肋和横梁连接,所述横梁上连接有锚固耳板,所述锚固耳板上连接有销铰,所述销铰与吊杆的下端连接;其传力途径为桥面板→横梁→锚固耳板→销铰→吊杆→拱肋,
(2)吊装临时纵梁即贝雷梁;
(3)提升临时吊杆,使原吊杆处于无应力状态;
(4)拆除原吊杆;
(5)在拱肋正确位置钻孔,并设锚下平台;
(6)在横梁上安装插耳式铰;
(7)安装新吊杆;
(8)调整新吊杆;通过调整新吊杆长度,使其达到正常使用受力状态;
(9)完成吊杆更换,拆除临时设施。
2.根据权利要求1所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述锚固耳板包括上连接板,所述上连接板与销铰连接。
3.根据权利要求2所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述锚固耳板还包括下连接板、螺纹杆和螺纹钢锚具,所述上连接板和下连接板之间通过螺纹杆和螺纹钢锚具连接。
4.根据权利要求1-3任一条所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述销铰包括吊耳、吊耳座和销轴,吊耳、吊耳座之间通过销轴连接,吊耳与吊杆的下端固定连接,吊耳座与上连接板固定连接。
5.根据权利要求4所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述吊耳座焊接在上连接板上。
6.根据权利要求4所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述的吊耳座的设计参数包括板宽B、板厚δ、板孔的顶距A 1、板孔的底距A 2、边距A 3、孔直径D、孔与销轴的间隙e
(1)验算吊耳座的横截面强度
Figure 2013103871921100001DEST_PATH_IMAGE001
公式中,A n为销孔边至吊耳座的截面积An=2A3×δF为销轴传递至吊耳的拉力;f为钢材强度设计值,该验算可避免吊耳座发生净截面受拉破坏;
(2)验算吊耳座的孔壁承压强度
Figure 771727DEST_PATH_IMAGE002
式中,为参照普通螺栓连接的承压强度取值,F为销轴传递至吊耳的拉力,D为吊耳座的孔的内径,δ为板厚,该验算可以防止出现孔道的挤压破坏。
7.根据权利要求4所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述销轴用于连接吊杆和吊耳座,其参数包括销轴的直径dF为销轴承受的吊杆拉力,对销轴强度进行验算:
(1)验算销轴的抗剪强度
式中,f e为钢材抗剪强度设计值,n e为销轴的剪切面数,通过该式的验算可防止销轴发生剪切破坏;
(2)验算销轴的抗弯强度
Figure DEST_PATH_IMAGE005
式中,M为销轴承受的弯矩,M=FL/4,L为销轴的计算跨度,W 1为销轴截面的抵抗矩,
Figure 995215DEST_PATH_IMAGE006
,通过该式的验算可防止销轴发生弯曲破坏。
8.根据权利要求6所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述销轴用于连接吊杆和吊耳座,其参数包括销轴的直径dF为销轴承受的吊杆拉力,对销轴强度进行验算:
(1)验算销轴的抗剪强度
Figure 965051DEST_PATH_IMAGE004
式中,f e为钢材抗剪强度设计值,n e为销轴的剪切面数,通过该式的验算可防止销轴发生剪切破坏;
(2)验算销轴的抗弯强度
Figure 377578DEST_PATH_IMAGE005
式中,M为销轴承受的弯矩,M=FL/4,L为销轴的计算跨度,W 1为销轴截面的抵抗矩,
Figure 343260DEST_PATH_IMAGE006
,通过该式的验算可防止销轴发生弯曲破坏。
9.根据权利要求1-3任一条所述的系杆拱桥刚性吊杆的更换方法,其特征在于:所述吊杆的上端连接有张拉端锚环,张拉端锚环上端密封连接有压盖。
10.根据权利要求1-3任一条所述的系杆拱桥刚性吊杆的更换方法,其特征在于:张拉端锚环的外侧设有保护的上防护罩。
CN201310387192.1A 2013-08-30 2013-08-30 一种系杆拱桥刚性吊杆的更换方法 Active CN103485285B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310387192.1A CN103485285B (zh) 2013-08-30 2013-08-30 一种系杆拱桥刚性吊杆的更换方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310387192.1A CN103485285B (zh) 2013-08-30 2013-08-30 一种系杆拱桥刚性吊杆的更换方法

Publications (2)

Publication Number Publication Date
CN103485285A true CN103485285A (zh) 2014-01-01
CN103485285B CN103485285B (zh) 2016-08-24

Family

ID=49825840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310387192.1A Active CN103485285B (zh) 2013-08-30 2013-08-30 一种系杆拱桥刚性吊杆的更换方法

Country Status (1)

Country Link
CN (1) CN103485285B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612052A (zh) * 2015-02-04 2015-05-13 河南省交通规划勘察设计院有限责任公司 用于桥梁拱肋吊杆的锚固装置
CN105002836A (zh) * 2015-07-27 2015-10-28 丁洪华 一种原位快速更换拱桥系杆的施工方法
CN105113429A (zh) * 2015-08-27 2015-12-02 中国市政工程华北设计研究总院有限公司 一种系杆拱桥吊杆更换方法
CN105507167A (zh) * 2015-12-30 2016-04-20 杭州市市政工程集团有限公司 一种系杆拱桥plc同步张拉更换吊杆的施工方法
CN107663831A (zh) * 2017-11-13 2018-02-06 湖南省交通规划勘察设计院有限公司 一种拉吊索锚固结构件及拉吊索更换方法
CN108797381A (zh) * 2017-04-26 2018-11-13 武汉二航路桥特种工程有限责任公司 一种吊杆拆除更换方法
CN111074746A (zh) * 2019-12-31 2020-04-28 中交路桥华南工程有限公司 拱桥及其吊杆锚固结构
CN114592420A (zh) * 2022-03-15 2022-06-07 广西交科集团有限公司 一种简易更换吊杆的吊杆系统及更换吊杆的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2637552Y (zh) * 2003-08-21 2004-09-01 江苏法尔胜新日制铁缆索有限公司 吊杆或斜拉索用高密封性能锚具总成
US20070124876A1 (en) * 2005-12-01 2007-06-07 Tao Jian R Self-anchored suspension bridge
CN102286942A (zh) * 2011-08-23 2011-12-21 河海大学 系杆拱桥吊杆更换装置
CN102797219A (zh) * 2012-08-10 2012-11-28 柳州欧维姆机械股份有限公司 一种方便更换的拱桥吊杆组件及其用于更换吊杆的方法
CN202936720U (zh) * 2012-08-10 2013-05-15 柳州欧维姆机械股份有限公司 一种方便更换的拱桥吊杆组件

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2637552Y (zh) * 2003-08-21 2004-09-01 江苏法尔胜新日制铁缆索有限公司 吊杆或斜拉索用高密封性能锚具总成
US20070124876A1 (en) * 2005-12-01 2007-06-07 Tao Jian R Self-anchored suspension bridge
CN102286942A (zh) * 2011-08-23 2011-12-21 河海大学 系杆拱桥吊杆更换装置
CN102797219A (zh) * 2012-08-10 2012-11-28 柳州欧维姆机械股份有限公司 一种方便更换的拱桥吊杆组件及其用于更换吊杆的方法
CN202936720U (zh) * 2012-08-10 2013-05-15 柳州欧维姆机械股份有限公司 一种方便更换的拱桥吊杆组件

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张幼军: "《拱桥吊杆更换施工方案研究》", 《科技信息》, no. 11, 31 December 2009 (2009-12-31) *
闫鲁生: "《沙河大桥维修加固工程的施工工艺》", 《漯河职业技术学院学报》, vol. 8, no. 2, 31 March 2009 (2009-03-31), pages 71 - 72 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612052A (zh) * 2015-02-04 2015-05-13 河南省交通规划勘察设计院有限责任公司 用于桥梁拱肋吊杆的锚固装置
CN105002836A (zh) * 2015-07-27 2015-10-28 丁洪华 一种原位快速更换拱桥系杆的施工方法
CN105002836B (zh) * 2015-07-27 2017-01-25 丁洪华 一种原位快速更换拱桥系杆的施工方法
CN105113429A (zh) * 2015-08-27 2015-12-02 中国市政工程华北设计研究总院有限公司 一种系杆拱桥吊杆更换方法
CN105507167A (zh) * 2015-12-30 2016-04-20 杭州市市政工程集团有限公司 一种系杆拱桥plc同步张拉更换吊杆的施工方法
CN108797381A (zh) * 2017-04-26 2018-11-13 武汉二航路桥特种工程有限责任公司 一种吊杆拆除更换方法
CN107663831A (zh) * 2017-11-13 2018-02-06 湖南省交通规划勘察设计院有限公司 一种拉吊索锚固结构件及拉吊索更换方法
CN111074746A (zh) * 2019-12-31 2020-04-28 中交路桥华南工程有限公司 拱桥及其吊杆锚固结构
CN114592420A (zh) * 2022-03-15 2022-06-07 广西交科集团有限公司 一种简易更换吊杆的吊杆系统及更换吊杆的施工方法

Also Published As

Publication number Publication date
CN103485285B (zh) 2016-08-24

Similar Documents

Publication Publication Date Title
CN103485285A (zh) 一种系杆拱桥刚性吊杆的更换方法
CN105863145B (zh) 张弦结构、张弦梁和建筑
CN205188797U (zh) 一种混凝土系杆拱桥吊杆下锚端连接结构
CN102864742B (zh) 一种斜拉桥先滑后固型组合钢锚箱锚固装置及其施工方法
CN101570961B (zh) 一种对桥梁断裂主梁的加固方法
CN203546625U (zh) 系杆拱桥刚性吊杆的更换装置
CN103898834B (zh) 一种钢管混凝土组合梁与桁架式索塔斜拉桥及其施工方法
CN106884371B (zh) 一种变截面梁与悬索组合桥梁结构体系
CN104631320A (zh) 单洞双锚系统的隧道锚
CN105586826B (zh) 一种混凝土系杆拱桥吊杆下锚端连接结构及其施工方法
CN104088375A (zh) 一种屈曲约束钢筋构造
CN104947589A (zh) 多股成品索式锚碇预应力锚固装置及其施工方法
ITUB20159737A1 (it) Giunto meccanico di collegamento antisismico
CN208250889U (zh) 一种拱桥吊杆结构
CN103410090A (zh) 一种主动加固砼系杆拱桥的吊杆锚固构造及其施工方法
CN105569265A (zh) 无粘结钢绞线预应力减小梁截面高度技术
CN106049527B (zh) 明挖法可修复三拱三索地铁车站结构
MXPA05009322A (es) Perno para cable.
CN208733618U (zh) 一种地连墙和主体结构的锚固结构
CN108797381B (zh) 一种吊杆拆除更换方法
CN207537889U (zh) 大跨径盖梁、横梁施工底模支撑模架
CN104088401A (zh) 一种防屈曲钢筋构造
KR20160082643A (ko) 묶음대각철근을 활용한 병렬 전단벽의 연결보
CN108442230B (zh) 一种拱桥吊杆结构
CN207032036U (zh) 一种可换式锚碇预应力锚固装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Hu Feng

Inventor after: Li Dazhi

Inventor after: Liu Dan

Inventor after: Wang Jing

Inventor after: Wang Yukun

Inventor after: Yin Ying

Inventor after: Wang Jibo

Inventor after: Wang Tongning

Inventor after: Tang Guobin

Inventor after: Li Yulei

Inventor after: Meng Fenglin

Inventor after: Li Xuechao

Inventor after: Zhao Jie

Inventor after: Ding Guangyong

Inventor after: Du Haili

Inventor before: Hu Feng

Inventor before: Wang Tongning

Inventor before: Tang Guobin

Inventor before: Zhang Huili

Inventor before: Zhang Li

Inventor before: Liang Kefeng

Inventor before: Li Hongbo

Inventor before: Du Hongjing

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20170217

Address after: 450006 Henan City, Zhengzhou Province, No. 27 navigation road, No. 219

Patentee after: Henan Provincial Highway Survey and Design Co., Ltd.

Address before: 450006 Henan City, Zhengzhou Province, No. 27 navigation road, No. 219

Patentee before: Henan Provincial Transportation Research Institute Co., Ltd.

CB03 Change of inventor or designer information

Inventor after: Hu Feng

Inventor after: Li Dazhi

Inventor after: Liu Dan

Inventor after: Wang Jing

Inventor after: Wang Yushen

Inventor after: Yin Ying

Inventor after: Wang Jibo

Inventor after: Wang Tongning

Inventor after: Tang Guobin

Inventor after: Li Yulei

Inventor after: Meng Fenglin

Inventor after: Li Xuechao

Inventor after: Zhao Jie

Inventor after: Ding Guangyong

Inventor after: Du Haili

Inventor before: Hu Feng

Inventor before: Li Dazhi

Inventor before: Liu Dan

Inventor before: Wang Jing

Inventor before: Wang Yukun

Inventor before: Yin Ying

Inventor before: Wang Jibo

Inventor before: Wang Tongning

Inventor before: Tang Guobin

Inventor before: Li Yulei

Inventor before: Meng Fenglin

Inventor before: Li Xuechao

Inventor before: Zhao Jie

Inventor before: Ding Guangyong

Inventor before: Du Haili

CB03 Change of inventor or designer information