CN103469829B - 一种海上风电基础结构的防冲刷装置 - Google Patents

一种海上风电基础结构的防冲刷装置 Download PDF

Info

Publication number
CN103469829B
CN103469829B CN201310465331.8A CN201310465331A CN103469829B CN 103469829 B CN103469829 B CN 103469829B CN 201310465331 A CN201310465331 A CN 201310465331A CN 103469829 B CN103469829 B CN 103469829B
Authority
CN
China
Prior art keywords
skirtboard
flow guiding
guiding device
diameter
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310465331.8A
Other languages
English (en)
Other versions
CN103469829A (zh
Inventor
孙文
刘超
张洪龙
张平
张积乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Original Assignee
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Electric Power Engineering Consulting Institute Corp Ltd filed Critical Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority to CN201310465331.8A priority Critical patent/CN103469829B/zh
Publication of CN103469829A publication Critical patent/CN103469829A/zh
Application granted granted Critical
Publication of CN103469829B publication Critical patent/CN103469829B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

本发明公开了一种海上风电基础结构的防冲刷装置,包括锥形导流装置,锥形导流装置设在桩的外围且位于泥线处,锥形导流装置的下方设有裙板,所述裙板设置在海床土内。锥形导流装置为锥形帽,锥形导流装置的坡度为3:1。桩的直径不大于2m时,裙板的高度为2.5倍桩的直径,桩的直径大于2m时,裙板高度为1.5倍桩的直径,裙板的半径与冲刷坑的半径相等,裙板的高度与冲刷坑的深度相等。本发明与传统方法相比具有下述优点:1.不需要定期检查和维护;2.增加的结构成本较小,可忽略不计;3.防冲刷效果好,结构的动力特性不会在服役期间发生变化。

Description

一种海上风电基础结构的防冲刷装置
技术领域
本发明涉及一种海上风电基础结构的防冲刷装置。
背景技术
海上风电基础结构的主要形式是桩基结构,海流会造成桩基础冲刷,在桩的周围形成圆形的冲刷坑,导致桩的竖向和横向承载力降低。这也是海洋石油平台的常见问题。
为了减小冲刷对结构的影响,一直以来,主要采用在桩周围抛石或增加桩与土的接触长度,使冲刷后桩与土的接触长度等于设计桩长。
抛石方法是将石块装入铁丝笼内,并抛入海中,使其在桩的周围形成一堵石墙,当冲刷形成冲刷坑时,石笼自然下沉填补被冲刷的海床土。由于海水腐蚀作用,铁丝笼在使用一段时间后将发生破坏,导致石块散落而被海水冲走,再次形成冲刷坑。因此,抛石方法尽管简单,但需要定期检查,一旦新的冲刷坑形成,则需再次抛石。
增加桩长的方法尽管可行,但结构成本和施工成本都将有较大的增加,且冲刷前后结构的动力特性会有一定的变化。不仅如此,由于打桩的困难,增加桩长可能导致打桩深度达不到设计要求。
因此,现有防冲刷的方法存在一定的不足。
发明内容
为解决现有技术存在的不足,本发明公开了一种海上风电基础结构的防冲刷装置,本装置通过锥形导流装置与裙板结构的组合,减小了水流与桩壁撞击后的反射速度,从而减缓了海床土的泥沙启动,同时,采用裙板保护桩周土,以免桩周土被冲刷。
为实现上述目的,本发明的具体方案如下:
一种海上风电基础结构的防冲刷装置,包括锥形导流装置,锥形导流装置设在桩的外围且位于泥线处,锥形导流装置的下方设有裙板,所述裙板设置在海床土内。
所述锥形导流装置为锥形帽。
所述锥形导流装置的斜度为3:1。
所述裙板的半径计算公式为:
式中:r为裙板的半径,D为桩的直径,S为冲刷坑的深度,为海床土的摩擦角。
所述桩的直径不大于2m时,裙板的高度为2.5倍桩的直径,桩的直径大于2m时,裙板高度为1.5倍桩的直径。
所述锥形导流装置的半径、裙板的半径及桩的直径之间的关系是:R-r=0.2D。
其中,R为锥形导流装置的半径,r为裙板的半径;D为桩的直径。
所述裙板的半径与冲刷坑的半径相等。
所述裙板的高度与冲刷坑的深度相等。
锥形帽的作用是避免水流在桩前形成马蹄形涡,从而避免水流速度的急剧变化造成泥沙启动,裙板的作用则是保护桩周土的流失。
锥形帽的斜度为3:1,裙板的半径r按(1)式计算,锥形帽的半径R大于裙板的半径,R-r=0.2D。对于直径不大于2m的桩,其裙板的高度为2.5D,否则,裙板高度为1.5D。
本发明的有益效果:
本发明将锥形导流装置与裙板结构组合,减小了水流与桩壁撞击后的反射速度,从而减缓了海床土的泥沙启动,同时,采用裙板保护桩周土,以免桩周土被冲刷。本发明与传统方法相比具有下述优点:
1.不需要定期检查和维护。
2.增加的结构成本较小,可忽略不计。
3.防冲刷效果好,结构的动力特性不会在服役期间发生变化。
附图说明
图1防冲刷结构立面图;
图2防冲刷结构的平面图;
图中,1锥形帽,2裙板,3桩。
具体实施方式:
下面结合附图对本发明进行详细说明:
如图1所示,一种海上风电基础结构的防冲刷装置,包括锥形导流装置,锥形导流装置设在桩3的外围且位于泥线处,锥形导流装置的下方设有裙板2,所述裙板2设置在海床土内。
所述锥形导流装置为锥形帽1。
所述锥形导流装置的斜度为3:1。
所述裙板2的半径计算公式为:
式中:r为裙板2的半径,D为桩3的直径,S为冲刷坑的深度,为海床土的摩擦角。
所述桩3的直径不大于2m时,裙板2的高度为2.5倍桩3的直径,桩3的直径大于2m时,裙板2高度为1.5倍桩3的直径。
所述锥形导流装置的半径、裙板2的半径及桩3的直径之间的关系是:R-r=0.2D。
其中,R为锥形导流装置的半径,r为裙板2的半径;D为桩3的直径。
所述裙板2的半径与冲刷坑的半径相等。
所述裙板2的高度与冲刷坑的深度相等。
锥形帽1的作用是避免水流在桩3前形成马蹄形涡,从而避免水流速度的急剧变化造成泥沙启动,裙板2的作用则是保护桩3周土的流失。
锥形帽1的斜度为3:1,裙板2的半径r按(1)式计算,锥形帽1的半径R大于裙板2的半径,R-r=0.2D。对于直径不大于2m的桩3,其裙板2的高度为2.5D,否则,裙板2高度为1.5D。
本发明将锥形导流装置与裙板2结构的组合,减小了水流与桩壁撞击后的反射速度,从而减缓了海床土的泥沙启动,同时,采用裙板保护桩周土,以免桩周土被冲刷。

Claims (3)

1.一种海上风电基础结构的防冲刷装置,其特征是,包括锥形导流装置,锥形导流装置设在桩的外围且位于泥线处,锥形导流装置的下方设有裙板,所述裙板设置在海床土内;
所述锥形导流装置的斜度为3:1;
所述裙板的半径计算公式为:
式中:r为裙板的半径,D为桩的直径,S为冲刷坑的深度,为海床土的摩擦角;
所述锥形导流装置为锥形帽;
所述桩的直径不大于2m时,裙板的高度为2.5倍桩的直径,桩的直径大于2m时,裙板高度为1.5倍桩的直径;
所述锥形导流装置的半径、裙板的半径及桩的直径之间的关系是:R-r=0.2D
其中,R为锥形导流装置的半径,r为裙板的半径;D为桩的直径。
2.如权利要求1所述的一种海上风电基础结构的防冲刷装置,其特征是,所述裙板的半径与冲刷坑的半径相等。
3.如权利要求1所述的一种海上风电基础结构的防冲刷装置,其特征是,所述裙板的高度与冲刷坑的深度相等。
CN201310465331.8A 2013-09-30 2013-09-30 一种海上风电基础结构的防冲刷装置 Active CN103469829B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310465331.8A CN103469829B (zh) 2013-09-30 2013-09-30 一种海上风电基础结构的防冲刷装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310465331.8A CN103469829B (zh) 2013-09-30 2013-09-30 一种海上风电基础结构的防冲刷装置

Publications (2)

Publication Number Publication Date
CN103469829A CN103469829A (zh) 2013-12-25
CN103469829B true CN103469829B (zh) 2016-02-10

Family

ID=49794858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310465331.8A Active CN103469829B (zh) 2013-09-30 2013-09-30 一种海上风电基础结构的防冲刷装置

Country Status (1)

Country Link
CN (1) CN103469829B (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812159A (zh) * 2017-03-14 2017-06-09 天津大学 一种海上风电单桩基础防冲刷套筒
CN109372006B (zh) * 2018-11-27 2023-11-10 中国电建集团华东勘测设计研究院有限公司 海上风机基础防冲刷保护结构及其施工方法
CN110080265B (zh) * 2019-04-29 2021-04-27 河海大学 一种适用于中等水深的注浆式重力锚桩基础
CN112922015A (zh) * 2021-01-22 2021-06-08 上海电气风电集团股份有限公司 一种海上风机单桩基础及风机
CN114351752B (zh) * 2022-01-17 2022-09-23 中国海洋大学 一种可自适应海上风电桩基冲刷坑形貌的支撑装置
CN114508130A (zh) * 2022-03-17 2022-05-17 福州大学 海上风机防冲刷结构及其设置方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202265837U (zh) * 2011-10-21 2012-06-06 天津大学 一种海上风电机组单桩基础
CN102493478A (zh) * 2011-12-16 2012-06-13 浙江海洋学院 一种新型重力式海上风电基础装置
CN103195052A (zh) * 2013-03-27 2013-07-10 天津市市政工程设计研究院 一种用于高浓度盐溶液腐蚀环境的灌注桩及其施工方法
CN203487564U (zh) * 2013-09-30 2014-03-19 山东电力工程咨询院有限公司 一种海上风电基础结构的防冲刷装置

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
PL2354535T3 (pl) * 2009-12-29 2012-12-31 Kyowa Co Ltd Sposób konstruowania fundamentu dla wiatrowego układu do wytwarzania energii

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202265837U (zh) * 2011-10-21 2012-06-06 天津大学 一种海上风电机组单桩基础
CN102493478A (zh) * 2011-12-16 2012-06-13 浙江海洋学院 一种新型重力式海上风电基础装置
CN103195052A (zh) * 2013-03-27 2013-07-10 天津市市政工程设计研究院 一种用于高浓度盐溶液腐蚀环境的灌注桩及其施工方法
CN203487564U (zh) * 2013-09-30 2014-03-19 山东电力工程咨询院有限公司 一种海上风电基础结构的防冲刷装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《海水冲刷效应对海上风机桩基承载性能的影响分析》;薛九天等;《建筑科学》;20120930;第28卷;第84-88页 *

Also Published As

Publication number Publication date
CN103469829A (zh) 2013-12-25

Similar Documents

Publication Publication Date Title
CN103469829B (zh) 一种海上风电基础结构的防冲刷装置
CN203487564U (zh) 一种海上风电基础结构的防冲刷装置
CN104805854A (zh) 一种潮汐环境下深水超长钢板桩围堰施工方法
CN104196026A (zh) 水中桥梁临时工程用钢管桩拔除方法
JP3230883U (ja) 洋上風力発電用組み合せ単杭基礎構造
CN204370372U (zh) 废旧轮胎耐冲刷生态护堤装置
CN107794954A (zh) 一种抗浮泄水泄压结构
CN206956832U (zh) 一种漂浮式海水取水装置
CN205444232U (zh) 一种锚杆-重力式渗水挡土墙
TWI457488B (zh) A caudal - type breakwater with a circular arc
CN214697746U (zh) 一种基于空化效应反循环的孔底清渣装置
CN201738284U (zh) 一种带有透水阻滑板的防浪墙
CN211172112U (zh) 一种矿山爆破的减震装置
CN204626445U (zh) 一种带钢质翼板的桶形基础
CN204370459U (zh) 高灵敏度土深基坑支护基坑外降水系统
CN203475411U (zh) 疏干井结合气压劈裂加固吹填土地基的结构
JP2013087554A (ja) 液状化対策構造及び液状化対策工法
CN201770969U (zh) 一种水库堤坝
CN203097753U (zh) 快穿透隔水导管管鞋
CN204097976U (zh) 一种消力池
CN204940201U (zh) 一种高桩码头的施工结构
CN205667187U (zh) 一种应用于砀山酥梨早春防冻设施中的供水系统
CN202090335U (zh) 一种双向对穿孔管桩
CN202482847U (zh) 一种星状对穿孔锥形管桩
CN104179158B (zh) 一种消力池

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant