CN103452368A - Slurry accident pool and construction method thereof - Google Patents
Slurry accident pool and construction method thereof Download PDFInfo
- Publication number
- CN103452368A CN103452368A CN2013104112923A CN201310411292A CN103452368A CN 103452368 A CN103452368 A CN 103452368A CN 2013104112923 A CN2013104112923 A CN 2013104112923A CN 201310411292 A CN201310411292 A CN 201310411292A CN 103452368 A CN103452368 A CN 103452368A
- Authority
- CN
- China
- Prior art keywords
- pool
- slope
- slurry
- wall
- pond
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
The invention discloses a slurry accident pool and a construction method thereof. The slurry accident pool is constructed below the ground elevation plus or minus 0.00 of the ground, and comprises a pool bottom and pool walls, wherein one pool wall is provided with a slope for allowing a slurry material cleaning device to move to the pool bottom from the ground at the pool opening of the slurry accident pool. According to the invention, the slurry accident pool is constructed below the ground line, and a passage for the cleaning device to move in is arranged on one side wall of the slurry accident pool, so that the problems that solid materials are difficult to take out after depositing in the slurry accident pool and a large quantity of human resources, financial resources, material resources and time are consumed in the cleaning process of the materials are effectively solved, the cleaning efficiency of the materials depositing in the slurry accident pool is greatly enhanced, and further the conveying efficiency of a slurry pipeline is enhanced.
Description
Technical field
The present invention relates to slurry and deposit technical field, relate to more specifically a kind of novel slurry accident pool and mode of construction thereof, especially relate to a kind of ore pulp accident pool and mode of construction thereof for the iron ore concentrate pipeline transportation.
Background technology
In the transportation of current slurry pipeline, slurry body tends to because overflow and defeated leakage occur in various production accidents, therefore prior art generally will be built the slurry accident pool when carrying out Slurry Pipeline Transportation, especially in the iron ore concentrate pipeline transportation, the construction of slurry accident pool is very necessary, this slurry accident pool is for collecting in time slurry pipeline because of accident overflow or the defeated slurry spilt, especially ore pulp.This slurry accident pool of the prior art as shown in Figures 1 and 2, it is built in the absolute altitude on ground 1 ± more than 0, and structure as shown in Figures 1 and 2, protrudes from the rectangle steel reinforced concrete pool on ground, comprise at the bottom of pond 3 and pool wall 2, at the bottom of pond, 3 are built on ground 1.In the transportation of slurry pipeline, slurry can flow in the slurry accident pool shown in accompanying drawing 1 due to various production accidents, in the course of time, slurry material 4 in the slurry accident pool just runs up to certain amount, need to be cleared up it, if removed not in time, will affect the operating efficiency of slurry accident pool, once just the slurry solid accumulation in accident pool can not be brought into play its effect after expiring again.In view of the structural texture of slurry accident pool shown in accompanying drawing in prior art 1 and accompanying drawing 2, often adopt three kinds of methods to be cleared up the slurry material 4 deposited in the slurry accident pool: (1) hangs in loader in the slurry accident pool and is cleared up with crane; (2) under the condition allowed at orographic condition, set up support, loader is cleared up in support drives the slurry accident pool into; (3) the slurry accident pool being opened to an openning allowing loader from the sidewall of its protrusion enters.These three kinds of the prior art exist following problem to the deposition material method of being cleared up in the slurry accident pool: (1) hangs in loader in accident pool while being cleared up with crane, cleaning will be all a larger cost payout each time, because the usage charges of a crane just approach ten thousand yuan, but also needing the wait crane to march into the arena, this mode tends to expend plenty of time and financial resources; (2) adopt and to set up support and make loader drive the mode of accident pool into along support, need to make in advance support and be installed according to topographic features, after finishing using, also need to be removed, and support also needs to be kept properly while not using, not only increased the manufacturing cost of support, and also can produce the labour cost of great number in its installation, demolishing process, and cause cost of production to increase, also can there is potential safety hazard; (3) accident pool is opened to the manner of cleaning up that an openning allowing loader enters, because the slurry accident pool is generally concrete structure, need destroy original structure when opening openning, and the curing time that concrete need be longer when recovering, during this period of time, the slurry accident pool can not be used, even after recovering, also there will be drainage at accident pool openning seam crossing, cause this manner of cleaning up to have a strong impact on the application life of slurry accident pool, and reduced production efficiency.Therefore in this slurry accident pool, the cleaning problem of deposition slurry material has become technical barrier urgently to be resolved hurrily in the Slurry Pipeline Transportation process.
Summary of the invention
The present invention is based on above-mentioned technical problem, proposition a kind of brand-new slurry accident pool structure and the mode of construction of innovation, by building the slurry accident pool and offer cleaning equipment at the sidewall of slurry accident pool and sail passage into below ground line, effectively solved the problem that need expend a large amount of manpowers, financial resources, material resources and time when being difficult to taking-up in the prior art in the slurry accident pool after the solid material precipitation and clearing up these materials, greatly improve the cleaning efficiency of material precipitation in the slurry accident pool, and then improved Slurry Pipeline Transportation efficiency.
It is as follows that the present invention solves the problems of the technologies described above taked technical scheme:
A kind of slurry accident pool, described slurry accident pool is built in the terrace absolute altitude on ground ± below 0.00, comprises at the bottom of pond 3 and pool wall 2, and on described pool wall 2, being provided with can be for slurry material cleaning plant slope 5 of 3 at the bottom of pond is sailed on slurry accident pool Chi Kou ground into.
Further, according to slurry accident pool of the present invention, wherein said slope 5 is arranged at the inboard of described pool wall 2, and the top on slope 5 extends to the pool wall end face, and the bottom on slope 5 extends to the pond basal surface.
Further according to slurry accident pool of the present invention, wherein said slope 5 is arranged at the outside of described pool wall 2, the middle part of described pool wall 2 offers breach, stretch out to build from described breach passage is arranged, described slope 5 is built in described passage, the end face of the top on slope 5, the end face of passage and pool wall is in the same level position, and the bottom on slope 5 extends to the surface at the bottom of pond.
Further, according to slurry accident pool of the present invention, the width on wherein said slope 5 is 3-4 rice, and the height on slope is consistent with the height of pool wall, and described slope 5 is 20-40 ° with respect to the angle of inclination of pond basal surface.
Further, according to slurry accident pool of the present invention, the width on wherein said slope 5 is 3 meters, is highly 3 meters, with respect to the angle of inclination of pond basal surface, is 30 °.
Further according to slurry accident pool of the present invention, wherein said slurry accident pool is the rectangle form pool structure, comprise the one side pond at the bottom of 3 and the four sides pool wall 2, at the bottom of described pond 3 and pool wall 2 all adopt the wall body structure of concreting, on a pool wall therein, adopt concrete pouring structure to build described slope 5.
A kind of construction method of slurry accident pool comprises the following steps:
1), at the following excavation pit in terrace absolute altitude ± 0.00, the excavation of foundation pit degree of depth is 3-4 rice, horizontal dimension meets size at the bottom of slurry accident pool pond;
2), at the bottom of the built-in pulping body accident pool of described foundation ditch pond and the body of wall of pool wall, and with the described body of wall of pouring concrete;
3), a pool wall place builds the slope that connects slurry accident pool Chi Kou ground and pond basal surface with concreting therein;
4), backfill between the pool wall body of wall of slurry accident pool and excavation pit surrounding.
Further, according to above-mentioned construction method, it is characterized in that, wherein said step 3) specifically comprises:
1), offer 4 meters breach that left and right is wide on the body of wall of pool wall;
2), build approximately 2 meters of length, the height passage consistent with pool wall to the pool wall outside from described breach;
3), in described passage, with concreting, build the described slope of gradient between 20-40 °, the top, slope extends to Chi Kou ground in passage, and the bottom, slope extends to the pond basal surface in breach.
Further, according to above-mentioned construction method, it is characterized in that, wherein said step 3) specifically comprises:
Along the body of wall middle inside of a pool wall wherein with concreting build width at 3-4 rice, gradient on the slope of 20-40 °, the top, slope extends to the pool wall end face, the bottom on slope extends to the pond basal surface.
Further, according to above-mentioned construction method, it is characterized in that, the width on wherein said slope is 3 meters, and height is consistent with the pool wall height, with respect to the gradient of pond basal surface, is 30 ° of angles.
At least can reach following technique effect by technical scheme of the present invention:
1), by the structure of slurry accident pool of the present invention, can directly loader be driven in accident pool and carry out the ore pulp cleaning, avoided using and hung use, setting support or, in the accident pool upper shed, to greatly reduce the ore pulp cleaning up cost, and then reduced the transportation expenses of slurry pipeline;
2), by the structure of slurry accident pool of the present invention, loader can drive at any time in accident pool and carry out the ore pulp cleaning, make the cleaning of accident pool more conveniently, saved the stand-by period, the allocation and transportation time, repaired the accident pool time, greatly improved cleaning efficiency;
3), the construction method of slurry accident pool of the present invention is simple, replicability is strong.
The accompanying drawing explanation
The plan structure figure that accompanying drawing 1 is slurry accident pool in prior art;
Accompanying drawing 2 is that slurry accident pool shown in accompanying drawing 1 is along the sectional view of A-A line;
The plan structure figure of the slurry accident pool that accompanying drawing 3 is first embodiment of the invention;
Accompanying drawing 4 is that slurry accident pool shown in accompanying drawing 3 is along the sectional view of A-A line;
The plan structure figure of the slurry accident pool that accompanying drawing 5 is second embodiment of the invention;
Accompanying drawing 6 is that slurry accident pool shown in accompanying drawing 5 is along the sectional view of A-A line;
In figure, the implication of each Reference numeral is:
1-ground; The 2-pool wall; At the bottom of the 3-pond; 4-slurry material; The 5-slope.
The specific embodiment
Below in conjunction with accompanying drawing, technical scheme of the present invention is described in detail, so that those skilled in the art can more clearly understand the solution of the present invention, but does not therefore limit the scope of the invention.
The whole rectangle form pool structure for the terrace absolute altitude that is built in ground 1 ± below 0.00 of the slurry accident pool of innovative design of the present invention, comprise the one side pond at the bottom of 3 and the four sides pool wall 2, at the bottom of described pond 3 and pool wall 2 all adopt the wall body structure of concreting, pool wall 2 height are 3 meters, be preferably dimensioned to be 8m * 12m at the bottom of pond, on pool wall 2 therein of innovation, being provided with can be for loader slope 5 of 3 at the bottom of pond is sailed on Chi Ding ground into, described slope 5 is concrete pouring structure, top flushes with the ground of accident pool opening, bottom extends at the bottom of pond 3 surface, described slope 5 is 20-40 ° with respect to the tilt angle theta of pond basal surface, be preferably 30 °, at the bottom of whole concrete and pond, pool wall is built one and is built, the width on slope is more than 3 meters, be preferably between 3-4 rice, thereby the loader of slurry material can be by this slope 5 from the bottom of the ground line of slurry accident pool Chi Kou be directly opened the pond in the slurry accident pool 3 in the cleaning accident pool, thereby the deposition slurry material in accident pool is cleared up.
The building course of described slurry accident pool is:
At first at the rectangle form pool of 1 time excavation earthward of terrace absolute altitude ± below 0.00, cutting depth is slurry accident pool desired height, is generally 3 meters left and right, and the rectangle form pool size meets the size of 8m * 12m at the bottom of general slurry accident pool pond;
At the bottom of the build process of then pressing the slurry accident pool is built pond and the body of wall of pool wall, and, with at the bottom of the pouring concrete pond and the body of wall of pool wall, be poured onto terrace absolute altitude ± 0.00;
Then a pool wall place build to connect the ramp structure at the bottom of accident pool Chi Kou ground and pond with concreting therein, for loader at the bottom of pond is sailed on Chi Ding ground into;
Between the last pool wall body of wall at accident pool and excavation pit surrounding, backfill is to be protected body of wall.
Innovation of the present invention is the slurry accident pool is built in to below ground, build and the material cleaning plants such as loader can be opened into the passage at the bottom of the accident pool pond by accident pool Chi Kou ground therein simultaneously, described passage preferably adopts the ramp structure at the bottom of connection pool mouth and pond, further there are two kinds of set-up modes on described slope, for the first embodiment as shown in accompanying drawing 3-accompanying drawing 4, described slope 5 is positioned at the outside of pool wall 2, the top on slope 5 and lip are in the same level position, the bottom, slope extends to the pond basal surface, the width on described slope is preferably 3 meters, height is consistent with the pool wall height, be preferably 3 meters, Slope Facies is 30 ° for the angle θ of pond basal surface, the whole concrete pouring structure that adopts in slope, concrete construction method is, at first offer 4 meters breach that left and right is wide on the pool wall body of wall of building, then build the passage of length 2 meters left and right from described breach to the pool wall outside, finally in described passage, with concreting, build the slope of gradient θ 30 ° of left and right, the top, slope extends to Chi Kou ground in passage, at the bottom of the bottom, slope transits to the pond in breach, in accident pool, the slurry material deposits to a certain degree like this, loader just can carry out by the slope in passage the material cleaning in accident pool is sailed on ground into.
Accompanying drawing 5-accompanying drawing 6 provides the structure that arranges of slope of the present invention the second embodiment, in this embodiment, described slope 5 is positioned at the inboard of pool wall 2, the top on same slope 5 and lip are in the same level position, the bottom, slope extends to the pond basal surface, the width on described slope is preferably 3 meters, height is consistent with the pool wall height, be preferably 3 meters, Slope Facies is 30 ° for the angle θ of pond basal surface, the whole concrete pouring structure that adopts in slope, concrete construction method is: the body of wall middle inside along a constructed wherein pool wall is built width at 3 meters with concreting, the gradient is on the slope of 30 ° of left and right, the slope end face flushes with the pool wall end face, at the bottom of the bottom, slope extends to pond, whole ramp structure is positioned at slurry accident pool inside, in accident pool, the slurry material deposits to a certain degree like this, loader just can carry out along slope the material cleaning in accident pool is sailed on ground into.
The present invention is by being built in the slurry accident pool below ground and arranging and the material cleaning plants such as loader can be opened into the passage at the bottom of pond therein, can directly loader be sailed in accident pool and be cleared up, be very easy to the on-site cleanup work to deposition slurry material in the slurry accident pool, and can not produce extra charge, do not need accident pool is destroyed and punches simultaneously, save human and material resources, greatly improved production efficiency.
Only below that the preferred embodiment of the present invention is described; technical scheme of the present invention is not limited to this; the any known distortion that those skilled in the art do on the basis of major technique of the present invention design all belongs to the claimed technology category of the present invention, and the concrete protection domain of the present invention is as the criterion with the record of claims.
Claims (10)
1. a slurry accident pool, it is characterized in that, described slurry accident pool is built in the terrace absolute altitude on ground ± below 0.00, (3) and pool wall (2) at the bottom of comprising pond, on described pool wall (2), being provided with can be for slurry material cleaning plant slope (5) of (3) at the bottom of pond is sailed on slurry accident pool Chi Kou ground into.
2. slurry accident pool according to claim 1, is characterized in that, wherein said slope (5) are arranged at the inboard of described pool wall (2), and the top of slope (5) extends to the pool wall end face, and the bottom of slope (5) extends to the pond basal surface.
3. slurry accident pool according to claim 1, it is characterized in that, wherein said slope (5) is arranged at the outside of described pool wall (2), the middle part of described pool wall (2) offers breach, stretch out to build from described breach passage is arranged, described slope (5) is built in described passage, and the end face of the top of slope (5), the end face of passage and pool wall is in the same level position, and the bottom of slope (5) extends to the surface at the bottom of pond.
4. according to the described slurry accident pool of claim 2 or 3, it is characterized in that, the width of wherein said slope (5) is 3-4 rice, and the height on slope is consistent with the height of pool wall, and described slope (5) are 20-40 ° with respect to the angle of inclination of pond basal surface.
5. slurry accident pool according to claim 4, is characterized in that, the width of wherein said slope (5) is 3 meters, is highly 3 meters, with respect to the angle of inclination of pond basal surface, is 30 °.
6. slurry accident pool according to claim 4, it is characterized in that, wherein said slurry accident pool is the rectangle form pool structure, comprise at the bottom of the one side pond (3) and pool wall (2) on four sides, at the bottom of described pond, (3) and pool wall (2) all adopt the wall body structure of concreting, on a pool wall therein, adopt concrete pouring structure to build described slope (5).
7. the construction method of a slurry accident pool, is characterized in that, comprises the following steps:
(1) at the following excavation pit in terrace absolute altitude ± 0.00, the excavation of foundation pit degree of depth is 3-4 rice, and horizontal dimension meets size at the bottom of slurry accident pool pond;
(2) at the bottom of the built-in pulping body accident pool of described foundation ditch pond and the body of wall of pool wall, and with the described body of wall of pouring concrete;
(3) a pool wall place builds the slope that connects slurry accident pool Chi Kou ground and pond basal surface with concreting therein;
(4) backfill between the pool wall body of wall of slurry accident pool and excavation pit surrounding.
8. construction method according to claim 7, is characterized in that, wherein said step (3) specifically comprises:
(1) offer 4 meters breach that left and right is wide on the body of wall of pool wall;
(2) build approximately 2 meters of length, the height passage consistent with pool wall to the pool wall outside from described breach;
(3) build the described slope of gradient between 20-40 ° with concreting in described passage, the top, slope extends to Chi Kou ground in passage, and the bottom, slope extends to the pond basal surface in breach.
9. construction method according to claim 7, it is characterized in that, wherein said step (3) specifically comprises: along the body of wall middle inside of a pool wall wherein with concreting build width at 3-4 rice, gradient the slope at 20-40 °, the top, slope extends to the pool wall end face, and the bottom on slope extends to the pond basal surface.
10. construction method according to claim 8 or claim 9, is characterized in that, the width on wherein said slope is 3 meters, and height is consistent with the pool wall height, with respect to the gradient of pond basal surface, is 30 ° of angles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310411292.3A CN103452368B (en) | 2013-09-11 | 2013-09-11 | A kind of slurry accident pool and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310411292.3A CN103452368B (en) | 2013-09-11 | 2013-09-11 | A kind of slurry accident pool and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103452368A true CN103452368A (en) | 2013-12-18 |
CN103452368B CN103452368B (en) | 2016-01-20 |
Family
ID=49735161
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310411292.3A Active CN103452368B (en) | 2013-09-11 | 2013-09-11 | A kind of slurry accident pool and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103452368B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108980620A (en) * | 2018-09-13 | 2018-12-11 | 铜陵有色金属集团股份有限公司金冠铜业分公司 | The reuse water system of ore dressing |
CN111939604A (en) * | 2020-07-13 | 2020-11-17 | 广东韶钢工程技术有限公司 | Ship-shaped slag-water separation device and using method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2635319Y (en) * | 2003-04-18 | 2004-08-25 | 聂伟璋 | Slurry material precipitating pool |
JP2010106501A (en) * | 2008-10-29 | 2010-05-13 | Takenaka Komuten Co Ltd | Construction method of low-temperature storage tank |
CN201704965U (en) * | 2010-05-26 | 2011-01-12 | 云南大红山管道有限公司 | Device capable of making loading machine directly enter accident pool |
CN101979781A (en) * | 2010-09-28 | 2011-02-23 | 中国石油集团川庆钻探工程有限公司 | Method for constructing petroleum drilling waste slurry curing tank |
CN102061709A (en) * | 2010-12-15 | 2011-05-18 | 河海大学 | Engineering machinery construction channel in debris flow state alluvial soil area |
CN202347653U (en) * | 2011-11-28 | 2012-07-25 | 广东新大禹环境工程有限公司 | Buried type waste water collecting device |
CN203452433U (en) * | 2013-09-11 | 2014-02-26 | 云南大红山管道有限公司 | Slurry accident pool |
-
2013
- 2013-09-11 CN CN201310411292.3A patent/CN103452368B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2635319Y (en) * | 2003-04-18 | 2004-08-25 | 聂伟璋 | Slurry material precipitating pool |
JP2010106501A (en) * | 2008-10-29 | 2010-05-13 | Takenaka Komuten Co Ltd | Construction method of low-temperature storage tank |
CN201704965U (en) * | 2010-05-26 | 2011-01-12 | 云南大红山管道有限公司 | Device capable of making loading machine directly enter accident pool |
CN101979781A (en) * | 2010-09-28 | 2011-02-23 | 中国石油集团川庆钻探工程有限公司 | Method for constructing petroleum drilling waste slurry curing tank |
CN102061709A (en) * | 2010-12-15 | 2011-05-18 | 河海大学 | Engineering machinery construction channel in debris flow state alluvial soil area |
CN202347653U (en) * | 2011-11-28 | 2012-07-25 | 广东新大禹环境工程有限公司 | Buried type waste water collecting device |
CN203452433U (en) * | 2013-09-11 | 2014-02-26 | 云南大红山管道有限公司 | Slurry accident pool |
Non-Patent Citations (1)
Title |
---|
刘文帆 等: "石化企业事故污水池的设置", 《广州化工》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108980620A (en) * | 2018-09-13 | 2018-12-11 | 铜陵有色金属集团股份有限公司金冠铜业分公司 | The reuse water system of ore dressing |
CN111939604A (en) * | 2020-07-13 | 2020-11-17 | 广东韶钢工程技术有限公司 | Ship-shaped slag-water separation device and using method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN103452368B (en) | 2016-01-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107938692B (en) | Drainage and recharging construction method and structure | |
CN108505805B (en) | Large cast-in-situ water pool with expansion reinforcing belt for crack control and construction method thereof | |
CN106088530A (en) | Large area method for constructing terrace | |
CN109736884B (en) | Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure | |
CN110374068B (en) | Construction method of drain hole of bottom plate of sluice stilling pool capable of preventing blockage | |
CN109610263A (en) | A kind of construction method of fabricated construction sidewalk | |
CN105804089A (en) | Locally-deepened supporting and protecting system used after original deep foundation pit is constructed and construction method of system | |
CN113235601A (en) | Deep foundation pit construction risk control structure and method for collapsible loess adjacent building | |
CN111519734B (en) | Silt dredging method for river channel hidden culvert | |
CN118110193A (en) | Whole-process construction method for large-diameter open caisson on land in complex geology | |
CN103452368B (en) | A kind of slurry accident pool and construction method thereof | |
CN112195943B (en) | Construction method of underwater concrete water-proof wall | |
CN109056879A (en) | A kind of riverway sludge cleaning plant and construction method | |
CN112176954A (en) | Construction method for newly excavated channel | |
CN210151748U (en) | Foundation pit water collection surface drainage dewatering system | |
CN203452433U (en) | Slurry accident pool | |
WO2017193226A1 (en) | Apparatus for controlling hydrostatic pressure under foundation base | |
CN105089143B (en) | Method and device for setting highway desilting basin | |
CN107974875B (en) | High-speed railway foundation reinforcing structure with lossless candela function and construction method | |
CN206503069U (en) | trestle drainage system | |
CN201644490U (en) | Concrete pouring waste treatment and recovery system | |
CN212956838U (en) | Super high-rise construction floor water interception structure | |
CN208949951U (en) | A kind of riverway sludge cleaning plant | |
CN211368952U (en) | Hidden rainwater collection device | |
CN113700111A (en) | Construction method of rainwater permeation, drainage and reuse integrated system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |