CN103422565B - Construction method for waterlogging removing of outdoor cable chute - Google Patents

Construction method for waterlogging removing of outdoor cable chute Download PDF

Info

Publication number
CN103422565B
CN103422565B CN201310376642.7A CN201310376642A CN103422565B CN 103422565 B CN103422565 B CN 103422565B CN 201310376642 A CN201310376642 A CN 201310376642A CN 103422565 B CN103422565 B CN 103422565B
Authority
CN
China
Prior art keywords
aqueduct
water
water conduits
unilateral gate
drain hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310376642.7A
Other languages
Chinese (zh)
Other versions
CN103422565A (en
Inventor
华维军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Tianjin Electric Power Transmission and Transformation Engineering Corp
Original Assignee
State Grid Corp of China SGCC
Tianjin Electric Power Transmission and Transformation Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Tianjin Electric Power Transmission and Transformation Engineering Corp filed Critical State Grid Corp of China SGCC
Priority to CN201310376642.7A priority Critical patent/CN103422565B/en
Publication of CN103422565A publication Critical patent/CN103422565A/en
Application granted granted Critical
Publication of CN103422565B publication Critical patent/CN103422565B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Barrages (AREA)

Abstract

The invention relates to a construction method for waterlogging removing of an outdoor cable chute. The method comprises the steps of 1, setting the inner bottom face of the outdoor cable chute to be a slope and setting draining holes in the bottom of the side wall of the cable chute with lower slope side; 2, mounting water conduits on the draining holes, communicating the water conduits with the mounting positions of the draining holes, sleeving seal pads at the connecting positions between the water conduits and the draining holes and radially mounting screens in the water conduits; 3, connecting the other ends of the water conduits with an adjacent rainwater well by pipelines; and 4, mounting check valves on the connecting positions between the water conduits and the rainwater well in a hinging mode, wherein the check valves are opened when water flows flow from the water conduits to the rainwater well, otherwise, the check valves are closed. According to the method, after the water flows flow into the rainwater well, the check valves are rotated in a swinging mode to be reset to connect with openings of the water conduits in a pressing mode, so backflow of water flows is avoided, the possibility that external water permeates into the cable chute is also prevented due to the seal pads at the contacting positions between the draining holes and the water conduits and creeping of small animals such as mice can be prevented by the design of the screens in the water conduits.

Description

A kind of for the construction method of outside cable ditch except ponding
Technical field
The invention belongs to drainage and construction method field, especially a kind of for the construction method of outside cable ditch except ponding.
Background technology
Cable run is the important component part of urban power network, day by day perfect along with city function, and the requirement that urban aerial line enters ground is more and more outstanding.In recent years, newly-built road has all built conduit line, cable duct bank the same period, and the cable passable space network be jointly made up of them provides safeguard for urban development from now on.As long as the oversheath quality of cable is good, lays and also do not damage, in cable trench, a small amount of ponding can not have too large impact to cable, if but ponding is too much, cable long period of soaking, in water, can have a strong impact on Exterior cable insulating properties and operation stability, causes power grid accident.
At present, solve the method that the method for cable trench water collecting adopts suction pump usually, but suction pump cost is higher, seriously improve electric power and to speedily carry out rescue work cost, and submersible pump need can complete by multiple electric elements, subelement is comparatively accurate, once damage, maintenance cost is higher.
Through retrieval, find one section of patent document relevant to present patent application content, publication number is that 202545206U Chinese patent discloses a kind of device measuring cable trench water collecting.This utility model comprises water pumper, inductor and delay switch, and water pumper and inductor are cascaded, and delay switch is in parallel with inductor.The utility model has the advantage of: 1. can discharge moisture unnecessary in cable trench timely; 2. the existence of delay switch can ensure that the water in cable trench still can allow water pumper work a period of time again after inductor open circuit, extends working cycles.
Through contrast, there is relatively big difference in the technical scheme of above patent and present patent application.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art part, provide a kind of easy and simple to handle and effectively avoid cable be dipped in water for outside cable ditch except the construction method of ponding.
The present invention solves its technical problem and takes following technical scheme to realize:
For the construction method of outside cable ditch except ponding, the steps include:
(1) be set to domatic at outside cable ditch inner bottom surface, drain hole is set at the cable trench sidewall bottom of domatic lower side;
(2) on above-mentioned drain hole, aqueduct is installed, aqueduct is communicated with drain hole installation site, aqueduct and drain hole link position are set with sealing mat, radial installation screen cloth in aqueduct;
(3) be connected by pipeline between the aqueduct other end with contiguous catch-basin;
(4) cut with scissors on aqueduct and catch-basin link position and fill unilateral gate, current from penstock flow to catch-basin time, this unilateral gate open, otherwise, unilateral gate close.
And the (1) described domatic gradient of step is 0.3%.
And described unilateral gate rotation angle is 10 ~ 45 °.
And, the aqueduct mouth of pipe place contacted with described unilateral gate is provided with sealing rubber pad.
Advantage of the present invention and good effect are:
The present invention adopts and domatic cable trench current is carried out water conservancy diversion, when the water yield after water conservancy diversion arrives drain hole liquid level, namely current flow through aqueduct from drain hole and enter catch-basin, and the rotation angle of unilateral gate is drawn by calculating and repetition test, after current flow into catch-basin, unilateral gate rotation return crimps with the aqueduct mouth of pipe, thus avoid flow backwards, and the sealing mat on drain hole and drainage tube contact position also prevent the possibility that outside moisture infiltrates cable trench, in aqueduct, the design of screen cloth it also avoid climbing into of the toys such as mouse simultaneously, improve cable trench safety factor.
Detailed description of the invention
Below by specific embodiment, the invention will be further described, and following examples are descriptive, is not determinate, can not limit protection scope of the present invention with this.
Embodiment 1
For the construction method of outside cable ditch except ponding, the steps include:
(1) be set to domatic at outside cable ditch inner bottom surface, the gradient is 0.3%, arranges drain hole at the cable trench sidewall bottom of domatic lower side;
(2) on above-mentioned drain hole, aqueduct is installed, aqueduct is communicated with drain hole installation site, aqueduct and drain hole link position are set with sealing mat, radial installation screen cloth in aqueduct;
(3) be connected by pipeline between the aqueduct other end with contiguous catch-basin;
(4) cut with scissors on aqueduct and catch-basin link position and fill unilateral gate, current from penstock flow to catch-basin time, this unilateral gate open, otherwise, unilateral gate is closed, and unilateral gate rotation angle is 30 °, and the aqueduct mouth of pipe place contacted with described unilateral gate is provided with sealing rubber pad.
Embodiment 2
For the construction method of outside cable ditch except ponding, the steps include:
(1) be set to domatic at outside cable ditch inner bottom surface, the gradient is 0.3%, arranges drain hole at the cable trench sidewall bottom of domatic lower side;
(2) on above-mentioned drain hole, aqueduct is installed, aqueduct is communicated with drain hole installation site, aqueduct and drain hole link position are set with sealing mat, radial installation screen cloth in aqueduct;
(3) be connected by pipeline between the aqueduct other end with contiguous catch-basin;
(4) cut with scissors on aqueduct and catch-basin link position and fill unilateral gate, current from penstock flow to catch-basin time, this unilateral gate open, otherwise, unilateral gate is closed, and unilateral gate rotation angle is 10 °, and the aqueduct mouth of pipe place contacted with described unilateral gate is provided with sealing rubber pad.
Embodiment 3
For the construction method of outside cable ditch except ponding, the steps include:
(1) be set to domatic at outside cable ditch inner bottom surface, the gradient is 0.3%, arranges drain hole at the cable trench sidewall bottom of domatic lower side;
(2) on above-mentioned drain hole, aqueduct is installed, aqueduct is communicated with drain hole installation site, aqueduct and drain hole link position are set with sealing mat, radial installation screen cloth in aqueduct;
(3) be connected by pipeline between the aqueduct other end with contiguous catch-basin;
(4) cut with scissors on aqueduct and catch-basin link position and fill unilateral gate, current from penstock flow to catch-basin time, this unilateral gate open, otherwise, unilateral gate is closed, and unilateral gate rotation angle is 45 °, and the aqueduct mouth of pipe place contacted with described unilateral gate is provided with sealing rubber pad.

Claims (2)

1., for the construction method of outside cable ditch except ponding, it is characterized in that: the steps include:
(1) be set to domatic at outside cable ditch inner bottom surface, drain hole is set at the cable trench sidewall bottom of domatic lower side;
(2) on above-mentioned drain hole, aqueduct is installed, aqueduct is communicated with drain hole installation site, aqueduct and drain hole link position are set with sealing mat, radial installation screen cloth in aqueduct;
(3) be connected by pipeline between the aqueduct other end with contiguous catch-basin;
(4) cut with scissors on aqueduct and catch-basin link position and fill unilateral gate, current from penstock flow to catch-basin time, this unilateral gate is opened, otherwise unilateral gate is closed, and the (1) described domatic gradient of step is 0.3%, and described unilateral gate rotation angle is 10 ~ 45 °.
2. according to claim 1 for the construction method of outside cable ditch except ponding, it is characterized in that: the aqueduct mouth of pipe place contacted with described unilateral gate is provided with sealing rubber pad.
CN201310376642.7A 2013-08-26 2013-08-26 Construction method for waterlogging removing of outdoor cable chute Active CN103422565B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310376642.7A CN103422565B (en) 2013-08-26 2013-08-26 Construction method for waterlogging removing of outdoor cable chute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310376642.7A CN103422565B (en) 2013-08-26 2013-08-26 Construction method for waterlogging removing of outdoor cable chute

Publications (2)

Publication Number Publication Date
CN103422565A CN103422565A (en) 2013-12-04
CN103422565B true CN103422565B (en) 2015-07-15

Family

ID=49647908

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310376642.7A Active CN103422565B (en) 2013-08-26 2013-08-26 Construction method for waterlogging removing of outdoor cable chute

Country Status (1)

Country Link
CN (1) CN103422565B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610608A (en) * 2018-12-17 2019-04-12 江苏中电科电力建设有限公司 A kind of cable duct water-proof skid-proof construction method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866790B (en) * 2014-03-26 2016-08-24 中国能源建设集团广东省电力设计研究院有限公司 Ground beam type raceway groove
CN104358277A (en) * 2014-10-29 2015-02-18 上海市政工程设计研究总院(集团)有限公司 Waterproof treating structure for cable trench penetrating through external wall
CN105319660A (en) * 2015-11-12 2016-02-10 国网辽宁省电力有限公司辽阳供电公司 A down-leading optical cable protection device and protection method
CN109440793A (en) * 2018-10-11 2019-03-08 北京中科中电电力工程管理有限公司 A kind of power equipment cable ditch water discharge construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4207038A1 (en) * 1992-03-06 1993-09-23 Mueller Hans Connection to existing main drain by new pipe - where seal is formed by inverting resin soaked packing into joint and holding under pressure until hardened
CN1389009A (en) * 2000-08-07 2003-01-01 芦森工业株式会社 Method and structure for laying communication cable in underground line, and members used for laying
CN101019286A (en) * 2004-03-12 2007-08-15 维也纳渠道污水处理技术有限责任公司 Cable laying configuration
CN201241323Y (en) * 2008-07-02 2009-05-20 贵阳铝镁设计研究院 Outside cable ditch water discharge structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4207038A1 (en) * 1992-03-06 1993-09-23 Mueller Hans Connection to existing main drain by new pipe - where seal is formed by inverting resin soaked packing into joint and holding under pressure until hardened
CN1389009A (en) * 2000-08-07 2003-01-01 芦森工业株式会社 Method and structure for laying communication cable in underground line, and members used for laying
CN101019286A (en) * 2004-03-12 2007-08-15 维也纳渠道污水处理技术有限责任公司 Cable laying configuration
CN201241323Y (en) * 2008-07-02 2009-05-20 贵阳铝镁设计研究院 Outside cable ditch water discharge structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610608A (en) * 2018-12-17 2019-04-12 江苏中电科电力建设有限公司 A kind of cable duct water-proof skid-proof construction method

Also Published As

Publication number Publication date
CN103422565A (en) 2013-12-04

Similar Documents

Publication Publication Date Title
CN103422565B (en) Construction method for waterlogging removing of outdoor cable chute
CN106638681B (en) A kind of pipe gallery
CN205153099U (en) Rainwater flow discarding device
CN207959443U (en) A kind of anti-waterlogging drainage arrangement in city
CN205369377U (en) Automatic abandon class, retaining, overflow integration rainwater collection system
CN203878608U (en) Underground utility tunnel structure
CN203878651U (en) Vertical deep rainwater storage and collection system
CN202390883U (en) Rainwater collecting and utilizing system
CN203008100U (en) Drainage network of barrier-free drainage facility
CN204326110U (en) A kind of inspection well cover of not easily ponding
CN106592687A (en) Rainwater collection system for container-type movable house
CN204435529U (en) United villa subsurface stormwater concentrates discharge structure
CN103366309A (en) LID (low-impact development)-based urban rainwater utilization scale determination method
CN203768881U (en) Water seepage draining device for corridors of mountain and dam body
CN202755439U (en) Building pipeline sewage cut-off device
CN205296616U (en) A class device is abandoned to riser rainwater that falls
CN206503226U (en) A kind of anti-inspection shaft ponding dredger in city
CN204125968U (en) The anti-water collecting device of a kind of cable shaft
CN203654439U (en) Integrated-type rainwater discarding system
CN206267184U (en) A kind of draining pump merges the pipe gallery for utilizing
CN208395840U (en) A kind of preventative water draw-off of basement sump
CN207130751U (en) Water guide pipe network device for dredging underground water around underground building
CN205224093U (en) Novel valve well
CN207484624U (en) A kind of double-layer drainage pipe duct of rain sewage diversion
CN204645066U (en) Dewatering installation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant