CN103394546B - Production method for longitudinal welded pipe - Google Patents

Production method for longitudinal welded pipe Download PDF

Info

Publication number
CN103394546B
CN103394546B CN201310366055.XA CN201310366055A CN103394546B CN 103394546 B CN103394546 B CN 103394546B CN 201310366055 A CN201310366055 A CN 201310366055A CN 103394546 B CN103394546 B CN 103394546B
Authority
CN
China
Prior art keywords
welding
pipe
online
production method
submerged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310366055.XA
Other languages
Chinese (zh)
Other versions
CN103394546A (en
Inventor
刘占增
万国胜
龚涛
王剑
张毅
郭胜鸿
高峰
黄志军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Co Ltd
Original Assignee
Wuhan Iron and Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Corp filed Critical Wuhan Iron and Steel Group Corp
Priority to CN201310366055.XA priority Critical patent/CN103394546B/en
Publication of CN103394546A publication Critical patent/CN103394546A/en
Application granted granted Critical
Publication of CN103394546B publication Critical patent/CN103394546B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Arc Welding In General (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

A disclosed production method for a longitudinal welded pipe successively comprises the following steps of hot-rolled coil decoiling, shearing and butt welding, looping, edge milling, coil flaw detection, cage roll forming, on-line pipe blank prewelding, welding of end tabs to pipe ends, on-line internal welding by employing submerged arc welding, on-line external welding by employing submerged arc welding, sizing and saw cutting, end tab removing, blowing and sweeping of welding slags, pipe end grinding, X-ray, expanding, chamfering, water pressing, ultrasonic flaw detection, X-ray, magnetic powder flaw detection, length measuring and weighing, mark spraying and warehousing. Practice proves that the production method of the longitudinal welded pipe is simple in operation and high in production efficiency.

Description

ERW production method
Technical field
The invention belongs to ERW production technical field, specifically refer to a kind of ERW production method.
Background technology
Straight-line joint submerged arc welding tube production technology is very ripe in China, and its weld properties is excellent and thus extensively promoted higher than body.Traditional straight-line joint submerged arc welding tube pipe-making method has JCOE and UOE, and which kind of method is all by shaping by forming machine for individual hot rolled plate of cut lengths, then carries out submerged arc welding and produces.
Traditional straight-line joint submerged arc welding tube pipe-making method, its raw material can only choose individual hot rolled plate, or hot rolled coil is carried out out flat, cut into single steel plate, and can not directly use hot rolled coil to carry out online formation rolling, the serious production efficiency that have impact on welded tube.
The patent No. is the production method that 200710033068.X granted patent discloses a kind of large straight-line joint submerged arc welding tube, it adopts the continuous row-roll forming process of coiled strip, online prewelding, then off-line automatic submerged arc welding is utilized to carry out interior weldering and the outside weld of welded tube, expanding, hydraulic pressure, Non-Destructive Testing, thus realize the High-efficient Production of large straight-line joint submerged arc welding tube product.Although the more traditional submerged-arc welded (SAW) pipe of this production method is produced and improve certain production efficiency, it still adopts off-line automatic submerged arc welding to carry out interior weldering and the outside weld of welded tube, submerged-arc welding produce be still single welded tube by propping up a welding processing, have impact on production efficiency.
In addition, the patent No. be 201110003728.6 granted patent describe a kind of straight-line joint submerged arc welding tube manufacture method, its key step comprises that steel band uncoiling, docking, plate edge machined, shaping, on-line continuous prewelding, Pipe Cutting, Lincoln weld are astute and able, finishing, it is characterized in that: described forming step adopts the forming method of alternating-current resistance welded tube, and the forming method of alternating-current resistance welded tube is continuous bend method, circular arc bending method or combination forming method.This manufacture method provides multiple forming method, but still adopts off-line submerged-arc welded (SAW) pipe to produce, and have impact on the production efficiency of welded tube.
Summary of the invention
Object of the present invention will provide a kind of simple to operate exactly, the ERW production method that production efficiency is high.
For achieving the above object, ERW production method of the present invention, its special character is: it comprises the following steps successively: hot rolled coil uncoiling, shears butt welding, kink, milling limit, plate body is detected a flaw, row-roll forming process, online pipe prewelding, tube head weldering run-on tab, weldering in submerged-arc welding is online, the online outside weld of submerged-arc welding, scale sawing, removes run-on tab, and welding slag purges, pipe end polishing, X-ray, expanding, chamfered edge, hydraulic pressure, ultrasonic examination, X-ray, magnetic powder inspection, surveys long weighing, spray mark warehouse-in.
Further, described shearing butt welding refers to hot rolled coil crop, back-end crop, and then the end of reel of last volume and the volume head of a rear volume carry out butt welding, and the hot rolled coil of same specification is connected together.
Further, in described submerged-arc welding is online during weldering, internal welding machine be arranged on prewelding and shaping between, internal welding machine stretches in pipe, and welding head is motionless, is welded by the on-line operation of welded tube pipe, in welding process, first prewelding, rear interior weldering.
Also preferably, during the online outside weld of submerged-arc welding, outside weld seat in the plane is put fixing, is welded by the on-line operation of welded tube pipe.
ERW production method of the present invention, adopt hot rolled coil as welded tube forming raw material, first hot rolled coil is carried out uncoiling, to hot rolled coil crop, back-end crop, then the volume head of the end of reel of last volume and a rear volume is carried out butt welding, the hot rolled coil of same specification is connected together; Hot rolled plate after uncoiling enters large-scale kink, can play the effect of the storage of raw materials and buffering; Hot rolled plate carries out milling limit, plate body flaw detection by edge milling machines, enters row-roll forming process unit, and utilizing row-roll forming process to make raw material continuously shaped is pipe; Online prewelding, tube head weldering run-on tab are carried out to pipe, stretches into submerged arc internal welding machine in shaping pipe flared end and carry out weldering online, then carry out the online outside weld of submerged-arc welding, scale sawing; Remove run-on tab to first welded tube, welding slag purging, pipe end polishing, then carry out ultrasonic examination, x-ray inspection; Welded Pipe carries out expanding, carries out chamfered edge to pipe end, and water inlet press carries out pressure test; Carry out ultrasonic examination, x-ray inspection, magnetic powder inspection afterwards; Finally survey long weighing, by qualified welded tube spray mark warehouse-in.
Feature of the present invention is: adopt hot rolled coil as raw material, decrease hot rolled coil is carried out out flat, the process of cutting, reduce production cost, simultaneously, adopt row-roll forming process+online prewelding+online submerged-arc welding process, make welded tube forming, prewelding, submerged-arc welding realizes continuous online production, substantially increase the production efficiency of straight-line joint submerged arc welding tube, in addition, production method of the present invention only needs when carrying out first production at shaping pipe top welding run-on tab, run-on tab is removed when carrying out finishing process to first welded tube, welding run-on tab is greatly reduced relative to prior art, arc-extinguishing plate and run-on tab of going out, the technique of arc-extinguishing plate, further increase production efficiency.
Detailed description of the invention
Below in conjunction with specific embodiment, ERW production method of the present invention is described in further detail.
A kind of production technology of Φ 323.9 × 8.7mm ERW, comprises the following steps:
To choose broadening be the hot rolled coil of 1020mm is raw material, and first hot rolled coil is carried out uncoiling, to hot rolled coil crop 2m, back-end crop 2m, then the end of reel of last volume and the volume head of a rear volume carry out butt welding, and the hot rolled coil of same specification is connected together; Hot rolled plate after uncoiling enters large-scale kink, and large-scale kink plays the effect of the storage of raw materials and buffering; Hot rolled plate carries out milling limit, plate body flaw detection by edge milling machines, enters row-roll forming process unit, and utilizing row-roll forming process to make raw material continuously shaped is pipe; Online prewelding is carried out to pipe, then tube head weldering run-on tab, weldering in submerged-arc welding is online, the online outside weld of submerged-arc welding; Wherein, in submerged-arc welding is online during weldering, internal welding machine be arranged on prewelding and shaping between, internal welding machine stretches in pipe, and welding head is motionless, is welded by the on-line operation of welded tube pipe, in welding process, first prewelding, rear interior weldering; During the online outside weld of submerged-arc welding, outside weld seat in the plane is put fixing, is welded by the on-line operation of welded tube pipe; Carry out online scale sawing again, cut lengths is 12m; Remove run-on tab, carry out welding slag purging, pipe end polishing, then carry out ultrasonic examination, x-ray inspection; Welded Pipe carries out expanding, carries out chamfered edge to pipe end, and water inlet press carries out pressure test; Carry out ultrasonic examination, x-ray inspection, magnetic powder inspection afterwards; Finally survey long weighing, by qualified welded tube spray mark warehouse-in.

Claims (3)

1. an ERW production method, is characterized in that: it comprises the following steps successively: hot rolled coil uncoiling, shears butt welding, kink, milling limit, plate body is detected a flaw, row-roll forming process, online pipe prewelding, tube head weldering run-on tab, weldering in submerged-arc welding is online, the online outside weld of submerged-arc welding, scale sawing, remove run-on tab, welding slag purging, pipe end polishing, X-ray, expanding, chamfered edge, hydraulic pressure, ultrasonic examination, X-ray, magnetic powder inspection, surveys long weighing, spray mark warehouse-in; Wherein, described shearing butt welding refers to hot rolled coil crop, back-end crop, and then the end of reel of last volume and the volume head of a rear volume carry out butt welding, and the hot rolled coil of same specification is connected together.
2. ERW production method according to claim 1, is characterized in that: in described submerged-arc welding is online during weldering, internal welding machine stretches in pipe, and welding head is motionless, is welded by the on-line operation of welded tube pipe, in welding process, and first prewelding, rear interior weldering.
3. ERW production method according to claim 1 and 2, is characterized in that: during the online outside weld of submerged-arc welding, outside weld seat in the plane is put fixing, is welded by the on-line operation of welded tube pipe.
CN201310366055.XA 2013-08-21 2013-08-21 Production method for longitudinal welded pipe Expired - Fee Related CN103394546B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310366055.XA CN103394546B (en) 2013-08-21 2013-08-21 Production method for longitudinal welded pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310366055.XA CN103394546B (en) 2013-08-21 2013-08-21 Production method for longitudinal welded pipe

Publications (2)

Publication Number Publication Date
CN103394546A CN103394546A (en) 2013-11-20
CN103394546B true CN103394546B (en) 2015-06-03

Family

ID=49558373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310366055.XA Expired - Fee Related CN103394546B (en) 2013-08-21 2013-08-21 Production method for longitudinal welded pipe

Country Status (1)

Country Link
CN (1) CN103394546B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105880809B (en) * 2014-11-14 2018-06-12 宋国栋 Middle steel pipes with straight upward multi-wire submerged-arc Welding and the bonding pad roll used online
CN104999277B (en) * 2015-07-13 2017-03-22 天津钢管集团股份有限公司 Production method of anticorrosion wear-resistant stainless steel HFW welding pipe with outer diameter of 108-660.4mm
CN105382545A (en) * 2015-12-11 2016-03-09 河北沧海核装备科技股份有限公司 Production equipment and technique for plate-strip dual-use continuous production straight-slit submerged-arc welded pipes
CN106239168A (en) * 2016-08-01 2016-12-21 葫芦岛市钢管工业有限公司 A kind of pre-soldering method of the ERW for LSAW steel pipe's production
CN113118230B (en) * 2021-04-21 2023-05-12 中冶赛迪技术研究中心有限公司 Composite technology for producing closed section steel through hot roll bending
CN116167396A (en) * 2023-01-09 2023-05-26 太原重工股份有限公司 Material tracking method for straight welded pipe

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1490097A (en) * 2002-10-15 2004-04-21 赵春友 Production of steel pipes with straight central seaming and primary shaping, final shaping and welder
CN1781655A (en) * 2005-09-30 2006-06-07 番禺珠江钢管有限公司 Process for producing welded pipe
CN101214511A (en) * 2007-12-29 2008-07-09 番禺珠江钢管有限公司 Large straight-line joint submerged arc welding tube fast production process
CN102000716A (en) * 2010-11-30 2011-04-06 大连三高科技发展有限公司 Production line of major diameter straight welded pipe
CN102274871A (en) * 2011-08-02 2011-12-14 太原华科信冶金成套设备有限公司 Method and equipment for producing longitudinal submerged arc welded pipe
CN102294571A (en) * 2010-06-25 2011-12-28 上海月月潮钢管制造有限公司 Method for manufacturing high-temperature and high-pressure steel pipe
CN102294553A (en) * 2011-07-21 2011-12-28 北京工业大学 Magnesium alloy brazing filler metal containing rare-earth element Er and preparation method thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59113921A (en) * 1982-12-20 1984-06-30 Nisshin Steel Co Ltd Double square tube and its manufacturing device
JP2692542B2 (en) * 1993-09-03 1997-12-17 住友金属工業株式会社 Pipe welding method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1490097A (en) * 2002-10-15 2004-04-21 赵春友 Production of steel pipes with straight central seaming and primary shaping, final shaping and welder
CN1781655A (en) * 2005-09-30 2006-06-07 番禺珠江钢管有限公司 Process for producing welded pipe
CN101214511A (en) * 2007-12-29 2008-07-09 番禺珠江钢管有限公司 Large straight-line joint submerged arc welding tube fast production process
CN102294571A (en) * 2010-06-25 2011-12-28 上海月月潮钢管制造有限公司 Method for manufacturing high-temperature and high-pressure steel pipe
CN102000716A (en) * 2010-11-30 2011-04-06 大连三高科技发展有限公司 Production line of major diameter straight welded pipe
CN102294553A (en) * 2011-07-21 2011-12-28 北京工业大学 Magnesium alloy brazing filler metal containing rare-earth element Er and preparation method thereof
CN102274871A (en) * 2011-08-02 2011-12-14 太原华科信冶金成套设备有限公司 Method and equipment for producing longitudinal submerged arc welded pipe

Also Published As

Publication number Publication date
CN103394546A (en) 2013-11-20

Similar Documents

Publication Publication Date Title
CN103394546B (en) Production method for longitudinal welded pipe
CN103341522B (en) The production method of thick-walled titanium welded tube and forming machine
CN106541253A (en) A kind of production technology of steel pipe
CN102172814B (en) Method for manufacturing longitudinal submerged arc welded pipe
CN102699107B (en) Cold roll forming method of thin-walled and high-strength square steel tube
CN107263031A (en) Cylinder is without pre-bending edge rolling moulding process
CN105817840A (en) Machining and producing process of seamless steel pipe
CN103143587B (en) The welding band-leading being applicable to compact cold strip mill improves the device and method of lumber recovery
CN103357697B (en) Manufacturing technology of longitudinal submerged arc welded pipe
US9266161B2 (en) Production line of large diameter longitudinal welded pipe
CN102581566A (en) Sleeve rolling process
CN105127236A (en) Manufacturing method for special-shaped steel pipes special for logistics shelves
CN101767123A (en) Process and equipment for producing aluminum-cladding copper pipe
CN108453475B (en) Production process of press-fit steel ring
CN103084427B (en) Manufacturing method of hardenability steel tube
CN202162537U (en) High-frequency straight welded pipe production line
CN104384678A (en) Novel welding technology of SSAW (Spirally Submerged Arc Welding) pipe
CN101386041B (en) Cold roll forming technique of large-sized curve type steel tube
CN104439949A (en) Lengthened welded steel tube manufacturing method
CN113043020B (en) Stainless steel pipe production device and production method
CN104439672A (en) High frequency prewelding technology of longitudinal submerged arc welded pipe
CN201596691U (en) Equipment for producing aluminum covered copper tubes
CN104476122A (en) Preparation method for welded steel pipe for boiler
CN104999277A (en) Production method of anticorrosion wear-resistant stainless steel HFW welding pipe with outer diameter of 108-660.4mm
CN101190444B (en) Method for manufacturing titanium or titanium alloy tube of 12 to 16 meters

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170720

Address after: 430083, Hubei Wuhan Qingshan District Factory No. 2 Gate joint stock company organs

Patentee after: Wuhan iron and Steel Company Limited

Address before: 430080 Hubei, Wuhan, Wuchang Friendship Road, No. 999, block A, floor 15

Patentee before: Wuhan Iron & Steel (Group) Corp.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150603

Termination date: 20190821

CF01 Termination of patent right due to non-payment of annual fee