- CN103362114A CN103362114A CN2013103386860A CN201310338686A CN103362114A CN 103362114 A CN103362114 A CN 103362114A CN 2013103386860 A CN2013103386860 A CN 2013103386860A CN 201310338686 A CN201310338686 A CN 201310338686A CN 103362114 A CN103362114 A CN 103362114A
- Authority
- CN
- China
- Prior art keywords
- settlement
- fiber grating
- soil
- tube
- measuring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002689 soil Substances 0.000 title claims abstract description 43
- 238000012544 monitoring process Methods 0.000 title claims abstract description 21
- 238000000034 method Methods 0.000 title claims abstract description 11
- 239000000835 fiber Substances 0.000 claims abstract description 46
- 238000006073 displacement reaction Methods 0.000 claims abstract description 34
- 238000005259 measurement Methods 0.000 claims abstract description 26
- 238000000691 measurement method Methods 0.000 claims abstract description 15
- 239000011083 cement mortar Substances 0.000 claims abstract description 8
- 230000003287 optical effect Effects 0.000 claims abstract description 5
- 239000000463 material Substances 0.000 claims description 8
- 239000002002 slurry Substances 0.000 claims description 6
- 238000005260 corrosion Methods 0.000 claims description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 5
- 238000005553 drilling Methods 0.000 claims description 4
- 238000000576 coating method Methods 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000013307 optical fiber Substances 0.000 description 3
- 239000000523 sample Substances 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000004804 winding Methods 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 1
- 238000013480 data collection Methods 0.000 description 1
- 230000008021 deposition Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 238000011010 flushing procedure Methods 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000004062 sedimentation Methods 0.000 description 1
- 229910001220 stainless steel Inorganic materials 0.000 description 1
- 239000010935 stainless steel Substances 0.000 description 1
- 238000013517 stratification Methods 0.000 description 1
Images
Landscapes
- Testing Or Calibration Of Command Recording Devices (AREA)
- Length Measuring Devices By Optical Means (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310338686.0A CN103362114B (zh) | 2013-08-06 | 2013-08-06 | 一种监测土体分层沉降的测量方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310338686.0A CN103362114B (zh) | 2013-08-06 | 2013-08-06 | 一种监测土体分层沉降的测量方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103362114A true CN103362114A (zh) | 2013-10-23 |
CN103362114B CN103362114B (zh) | 2015-11-04 |
Family
ID=49364320
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310338686.0A Active CN103362114B (zh) | 2013-08-06 | 2013-08-06 | 一种监测土体分层沉降的测量方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103362114B (zh) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104501773A (zh) * | 2014-12-16 | 2015-04-08 | 河海大学 | 一种水工建筑物竖向变形监测装置及方法 |
CN105089702A (zh) * | 2015-08-27 | 2015-11-25 | 江苏省交通规划设计院股份有限公司 | 一种可大规模高精度在线监测盾构隧道错台的系统及方法 |
CN105424910A (zh) * | 2015-12-11 | 2016-03-23 | 天津城建大学 | 一种土体分层沉降测量装置 |
CN106918323A (zh) * | 2017-03-29 | 2017-07-04 | 中铁十四局集团有限公司 | 土体沉降传感器及土体沉降监测系统 |
CN106918322A (zh) * | 2017-03-24 | 2017-07-04 | 中南大学 | 一种深层岩体或土体水平及竖向变形联合测试方法 |
CN108086283A (zh) * | 2017-12-22 | 2018-05-29 | 深圳工云科技有限公司 | 拉线式沉降观测系统 |
CN109403300A (zh) * | 2018-12-12 | 2019-03-01 | 中国矿业大学(北京) | 一种双层土体沉降监测系统及其安装方法 |
CN109631832A (zh) * | 2018-12-10 | 2019-04-16 | 中交天津港湾工程研究院有限公司 | 一种土体分层沉降量监测方法 |
CN109655001A (zh) * | 2019-02-03 | 2019-04-19 | 南京吉欧地下空间科技有限公司 | 一种原位监测土体侧向位移的装置及其使用方法 |
CN110057734A (zh) * | 2019-05-22 | 2019-07-26 | 南京林业大学 | 一种用于分层测量泥浆中砂粒沉降规律的插入式试验装置及测量方法 |
CN112482343A (zh) * | 2020-11-06 | 2021-03-12 | 中交第四航务工程勘察设计院有限公司 | 一种土体分层沉降自动监测装置及方法 |
CN115450267A (zh) * | 2022-06-07 | 2022-12-09 | 中国葛洲坝集团勘测设计有限公司 | 一种土石坝沉降管接力安装埋设结构及其方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2685821Y (zh) * | 2004-02-16 | 2005-03-16 | 长沙金码高科技实业有限公司 | 分层沉降仪 |
JP4551436B2 (ja) * | 2007-11-27 | 2010-09-29 | 株式会社 Nncエンジニアリング | 既設井戸ケーシングパイプの底部除去工法並びに既設井戸の再生工法 |
CN102012225A (zh) * | 2010-09-28 | 2011-04-13 | 黎剑华 | 高等级公路软基光纤监测系统 |
CN102221332A (zh) * | 2011-04-01 | 2011-10-19 | 西安科技大学 | 松散地层的光纤光栅多点传感装置及监测系统与监测方法 |
CN202119406U (zh) * | 2011-07-05 | 2012-01-18 | 电子科技大学 | 光纤光栅沉降传感器 |
CN202265815U (zh) * | 2011-10-20 | 2012-06-06 | 中铁西北科学研究院有限公司 | 自动化多点组合式沉降观测仪 |
-
2013
- 2013-08-06 CN CN201310338686.0A patent/CN103362114B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2685821Y (zh) * | 2004-02-16 | 2005-03-16 | 长沙金码高科技实业有限公司 | 分层沉降仪 |
JP4551436B2 (ja) * | 2007-11-27 | 2010-09-29 | 株式会社 Nncエンジニアリング | 既設井戸ケーシングパイプの底部除去工法並びに既設井戸の再生工法 |
CN102012225A (zh) * | 2010-09-28 | 2011-04-13 | 黎剑华 | 高等级公路软基光纤监测系统 |
CN102221332A (zh) * | 2011-04-01 | 2011-10-19 | 西安科技大学 | 松散地层的光纤光栅多点传感装置及监测系统与监测方法 |
CN202119406U (zh) * | 2011-07-05 | 2012-01-18 | 电子科技大学 | 光纤光栅沉降传感器 |
CN202265815U (zh) * | 2011-10-20 | 2012-06-06 | 中铁西北科学研究院有限公司 | 自动化多点组合式沉降观测仪 |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104501773A (zh) * | 2014-12-16 | 2015-04-08 | 河海大学 | 一种水工建筑物竖向变形监测装置及方法 |
CN105089702A (zh) * | 2015-08-27 | 2015-11-25 | 江苏省交通规划设计院股份有限公司 | 一种可大规模高精度在线监测盾构隧道错台的系统及方法 |
CN105424910A (zh) * | 2015-12-11 | 2016-03-23 | 天津城建大学 | 一种土体分层沉降测量装置 |
CN105424910B (zh) * | 2015-12-11 | 2017-05-03 | 天津城建大学 | 一种土体分层沉降测量装置 |
CN106918322A (zh) * | 2017-03-24 | 2017-07-04 | 中南大学 | 一种深层岩体或土体水平及竖向变形联合测试方法 |
CN106918323A (zh) * | 2017-03-29 | 2017-07-04 | 中铁十四局集团有限公司 | 土体沉降传感器及土体沉降监测系统 |
CN108086283A (zh) * | 2017-12-22 | 2018-05-29 | 深圳工云科技有限公司 | 拉线式沉降观测系统 |
CN108086283B (zh) * | 2017-12-22 | 2023-12-12 | 深圳工云科技有限公司 | 拉线式沉降观测系统 |
CN109631832A (zh) * | 2018-12-10 | 2019-04-16 | 中交天津港湾工程研究院有限公司 | 一种土体分层沉降量监测方法 |
CN109403300A (zh) * | 2018-12-12 | 2019-03-01 | 中国矿业大学(北京) | 一种双层土体沉降监测系统及其安装方法 |
CN109655001A (zh) * | 2019-02-03 | 2019-04-19 | 南京吉欧地下空间科技有限公司 | 一种原位监测土体侧向位移的装置及其使用方法 |
CN109655001B (zh) * | 2019-02-03 | 2024-05-24 | 南京吉欧地下空间科技有限公司 | 一种原位监测土体侧向位移的装置及其使用方法 |
CN110057734A (zh) * | 2019-05-22 | 2019-07-26 | 南京林业大学 | 一种用于分层测量泥浆中砂粒沉降规律的插入式试验装置及测量方法 |
CN110057734B (zh) * | 2019-05-22 | 2024-03-12 | 南京林业大学 | 一种用于分层测量泥浆中砂粒沉降规律的插入式试验装置及测量方法 |
CN112482343A (zh) * | 2020-11-06 | 2021-03-12 | 中交第四航务工程勘察设计院有限公司 | 一种土体分层沉降自动监测装置及方法 |
CN112482343B (zh) * | 2020-11-06 | 2025-02-11 | 中交第四航务工程勘察设计院有限公司 | 一种土体分层沉降自动监测装置及方法 |
CN115450267A (zh) * | 2022-06-07 | 2022-12-09 | 中国葛洲坝集团勘测设计有限公司 | 一种土石坝沉降管接力安装埋设结构及其方法 |
CN115450267B (zh) * | 2022-06-07 | 2023-10-27 | 中国葛洲坝集团勘测设计有限公司 | 一种土石坝沉降管接力安装埋设结构及其方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103362114B (zh) | 2015-11-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103362114B (zh) | 一种监测土体分层沉降的测量方法 | |
CN104280167B (zh) | 岩体工程单孔多点光纤光栅空心包体三维应力测试装置 | |
CN204479060U (zh) | 一种路基稳定性观测系统 | |
CN106092042A (zh) | 一种基于光纤光栅传感技术的软土地基沉降传感器 | |
CN102162234A (zh) | 一种岩土体表面位移实时监测装置及监测方法 | |
CN102269578A (zh) | 空间结构竖向变形测量装置 | |
CN103644892A (zh) | 一种深基坑土体分层沉降测量装置及测量方法 | |
CN110207655A (zh) | 路基沉降监测用沉降计及监测方法 | |
CN108195349A (zh) | 一种磁阻电测沉降仪 | |
CN106643649B (zh) | 一种土体深层沉降和孔隙水压力测量装置及测量方法 | |
CN205785182U (zh) | 一种基于光纤光栅传感技术的软土地基沉降传感器 | |
CN204085751U (zh) | 岩体工程单孔多点光纤光栅空心包体三维应力测试装置 | |
CN103994753B (zh) | 用于黄土填料高填方路堤的分层沉降装置及测量方法 | |
CN102102358B (zh) | 无线传导式水压仪量测地基深层沉降变形的方法 | |
CN107100213A (zh) | 桥梁群桩施工对邻近隧道的土体扰动监测系统及监测方法 | |
CN209877948U (zh) | 土体分层沉降和水平位移复合测量装置及系统 | |
CN109682347B (zh) | 一种膨胀土遇水过程中不同深度处膨胀量的量测方法 | |
CN115265477A (zh) | 高土石坝上游堆石区沉降监测方法 | |
CN201876257U (zh) | 超大量程大坝坝基沉降仪 | |
CN110284436A (zh) | 一种用于地下暗涵工程的沉降变形观测点及施工方法 | |
CN206459650U (zh) | 一种磁致沉降仪 | |
CN207832168U (zh) | 一种填筑体分层沉降监测装置 | |
CN103411649A (zh) | 传热桥式冲淤传感器及其制作安装方法 | |
CN206479166U (zh) | 一种土体深层沉降和孔隙水压力测量装置 | |
CN207277308U (zh) | 桥梁群桩施工对邻近隧道的土体扰动监测系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20160509 Address after: 510000, room 10, 101 Grand View Park Road, Huangcun village, Guangdong, Guangzhou, Tianhe District Patentee after: GUANGDONG ZHIAN CONSTRUCTION ENGINEERING TECHNOLOGY CO., LTD. Address before: 222000 Jiangsu Institute of civil engineering, Huaihai Institute of Techology, Cangwu, Sinpo Road, No. 59, Zhang Zhendong, Patentee before: Huaihai Institute of Technology |
|
TR01 | Transfer of patent right |
Effective date of registration: 20190912 Address after: 518000 Dalang Street Peak Community, Longhua District, Shenzhen City, Guangdong Province Patentee after: Shenzhen City Anwulian Technology Co., Ltd. Address before: 510000, room 10, 101 Grand View Park Road, Huangcun village, Guangdong, Guangzhou, Tianhe District Patentee before: GUANGDONG ZHIAN CONSTRUCTION ENGINEERING TECHNOLOGY CO., LTD. |
|
TR01 | Transfer of patent right |