CN103352472A - Construction method of deep water pile foundation without steel pile casings - Google Patents

Construction method of deep water pile foundation without steel pile casings Download PDF

Info

Publication number
CN103352472A
CN103352472A CN2013102828163A CN201310282816A CN103352472A CN 103352472 A CN103352472 A CN 103352472A CN 2013102828163 A CN2013102828163 A CN 2013102828163A CN 201310282816 A CN201310282816 A CN 201310282816A CN 103352472 A CN103352472 A CN 103352472A
Authority
CN
China
Prior art keywords
steel
cofferdam
pile
steel pipe
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102828163A
Other languages
Chinese (zh)
Inventor
张鹏飞
祝长春
陈洪敏
罗本洪
裴剑铃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN2013102828163A priority Critical patent/CN103352472A/en
Publication of CN103352472A publication Critical patent/CN103352472A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a construction method of a deep water pile foundation without steel pile casings. The construction method comprises the following steps that (1) a covering layer and sludge on a riverbed at a pier position are cleaned, and rock of the riverbed is completely exposed; (2) a steel cofferdam is placed downwards at the pier position; (3) underwater bottom sealing concrete is poured in the steel cofferdam, and pouring is paused when the bottom sealing concrete is poured by 50cm lower than a preset height; (4) after the bottom sealing concrete reaches the design strength, water in the steel cofferdam is completely pumped out, lofting of bored pile positions is conducted in the steel cofferdam, and meanwhile lofting of steel pipe pile positions used for setting-up of a drilling platform is conducted; (5) drill guide steel pile casings with the height of 150cm are installed at the bored pile positions, steel pipe piles are installed at the steel pipe pile positions, the scale height of the top of each steel pipe pile is arranged in the mode that the top of each steel pipe pile is flush with the top of the steel cofferdam, and then the remaining portion, with the height of 50 cm, of the bottom sealing concrete is poured; (6) lower supporting is conducted by the steel pipe piles and the steel cofferdam, and the drilling platform is set up; (7) drilling machines are placed in position to conduct drilling.

Description

A kind of Construction of Deep-water Pile method without the steel casing
Technical field
The present invention relates to a kind of Deep-Water Bored Pile job practices, be specifically related to a kind of large bridge Construction of Deep-water Pile technology of utilizing steel cofferdam.
Background technology
In deep water, all adopt at present full casing form in the bored pile, with the steel casing as the construction auxiliary part, mouth will insert the Riverbed certain depth at the bottom of specifically being arranged as the steel casing, the top mouth will surface more than 4~6m, and the major function of steel casing is the container for drilling machine platform support waterborne, rig guiding, borehole wall-protection, maintenance head height, concrete form.Generally speaking, nearly tens of the drilled piles of a pier position, each position needs a steel casing, especially in the profundal zone construction, needs the length of steel casing very long, and therefore this job practices need to expend great deal of steel, and cost is very high, and complicated construction technique.
Summary of the invention
The object of the present invention is to provide a kind of Construction of Deep-water Pile method without the steel casing, to save steel casing cost, reduce numerous and diverse working procedure.
Technical scheme of the present invention is as follows:
A kind of Construction of Deep-water Pile method without the steel casing is characterized in that, may further comprise the steps:
(1) at first with the covering layer on the riverbed, place, pier position and mud cleaning, make its riverbed expose rock fully;
(2) transfer steel cofferdam at place, pier position;
(3) build bottom concrete under water in steel cofferdam, bottom concrete is poured into from predetermined altitude also during poor 50cm, and time-out is built;
(4) after bottom concrete reaches design strength, water in the steel cofferdam is drained, setting-out goes out the drilled pile position in the cofferdam, and simultaneously setting-out goes out the stake position be used to the steel pipe pile of setting up drilling platform;
(5) the drill bit guiding steel casing of high 150cm is installed in described drilled pile position, described drill bit guiding steel casing diameter is than the design stake large 20~40cm in footpath; Steel pipe pile is installed in the steel pipe pile position, and high the setting with the top, cofferdam of steel pipe pile top mark flushes; Then build the high bottom concrete of remaining 50cm;
(6) utilize described steel pipe pile and cofferdam wall to make lower support, set up drilling platform;
(7) the rig drilling construction that carries out in place.
The present invention arranges one and only has the high drill bit guiding steel casing of 150cm in each position, and because drill bit guiding steel casing only play the guiding role, need not consider stressedly, therefore can adopt the Steel Thin-Wall casing of wall thickness δ 1.2cm, thereby the present invention can save great deal of steel, and construction technology is simple.
The present invention is particularly useful for following execution conditions: stake method construction behind (1) first weir; (2) therefore naked rock or riverbed shallow overburden do not need steel cylinder-wall protecting function; (3) adopt the double-wall steel cofferdam construction low pile cap, pile crown flushes with bottom concrete, does not therefore need the steel casing to make the inner concrete container.
Description of drawings
Fig. 1 is the piling plan of a kind of embodiment of the present invention
Fig. 2 is the drilling construction view of an embodiment of the present invention.
The specific embodiment
Below in conjunction with Fig. 1 and Fig. 2, method of the present invention is elaborated.Implementation step of the present invention is as follows:
(1), at first the pier position is located covering layer and mud cleaning on the riverbed 1, made the riverbed 1 at place, pier position expose rock fully.Covering layer and mud are cleaned out, and concrete does not mix with earth in the time of can guaranteeing the cofferdam back cover, thereby improves the bottom concrete quality; The stake hole wall is without dirt bed in the time of can guaranteeing to hole, thereby guarantees the stability of hole wall.
(2), transfer steel cofferdam 2 at place, pier position.Steel cofferdam can be transferred according to on-the-spot natural conditions, existing boats and ships and the rational form of structure of selection of mechanical equipment.
(3), in steel cofferdam 2, build bottom concrete 3 under water, bottom concrete 3 is poured into from predetermined altitude also during poor 50cm, time-out is built.
It is integrated poured that described bottom concrete can adopt " vertical many tremie methods " to carry out.Described " vertical many tremie methods " namely vertically put into the steel conduit that a plurality of internal diameters are 200~300mm in the cofferdam, the pipe end is connected to the funnel of certain capacity far from bottom surface, cofferdam 30~40mm at the conduit top, at funnel neck ball plug, and fasten with rope.The full Sheng fallen into the larger concrete of degree in the funnel, cuts off rope when building, simultaneously rapidly constantly to the funnel penetration concrete, interior bulb stopper, the empty G﹠W of conduit this moment discharged by the pipe end by the concrete gravity extruding all, moment, concrete is built at bottom, cofferdam heap, makes outer closure isolation in the cofferdam.
(4), after bottom concrete reaches design strength, water in the steel cofferdam is drained, setting-out goes out drilled pile position 4 in the cofferdam, simultaneously setting-out goes out be used to the steel pipe pile position 5 of setting up drilling platform.Generally speaking, 5 bit quantity of steel pipe pile of going out of setting-out can equate with the drilled pile bit quantity.Among the embodiment as shown in Figure 2,4 of drilled piles and steel pipe pile position 5 respectively have 26.
(5), the drill bit guiding steel casing 6 of high 150cm is installed in described drilled pile position, drill bit guiding steel casing 6 diameters are than the design stake large 20~40cm in footpath; Steel pipe pile 7 is installed in the steel pipe pile position, and high the setting with the top, cofferdam of the top mark of steel pipe pile 7 flushes; Then build the high bottom concrete of remaining 50cm, drill bit guiding steel casing 6 and steel pipe pile 7 parts are embedded in the bottom concrete, fixed.Because drill bit guiding steel casing 6 only play the guiding role, need not consider stressedly, therefore can adopt the Steel Thin-Wall casing of wall thickness δ 1.2cm.
(6), utilize described steel pipe pile 7 and cofferdam wall to make lower support, set up drilling platform 8.
(7), finish putting up platform after, rig 9 drilling constructions that carry out in place.
Bore process adopts method of air lifting reverse circulation clear water drilling construction.Gas lift reverse circulation creeps into has the advantages such as chip removal ability is strong, drilling efficiency is high, bit life is long, hole quality is good.For satisfying height of water level in the gas lift reverse circulation construction cofferdam, sidewall in described cofferdam is provided with the valve of through hole and control through hole switch, open valve during drilling construction, can make the inside and outside UNICOM in cofferdam, in order to avoid cause anti-circulation to extract out in the cofferdam behind the water, cause in the excessive and cofferdam of the inside and outside water-head in cofferdam water level to hang down and to satisfy the required water pressure of gaslift.Because omnidistance for creeping into the rock stratum, employing method of air lifting reverse circulation clear water drilling construction can greatly reduce the pollution to water environment.

Claims (6)

1. the Construction of Deep-water Pile method without the steel casing is characterized in that, may further comprise the steps:
(1) at first with the covering layer on the riverbed, place, pier position and mud cleaning, make its riverbed expose rock fully;
(2) transfer steel cofferdam at place, pier position;
(3) build bottom concrete under water in steel cofferdam, bottom concrete is poured into from predetermined altitude also during poor 50cm, and time-out is built;
(4) after bottom concrete reaches design strength, water in the steel cofferdam is drained, setting-out goes out the drilled pile position in the cofferdam, and simultaneously setting-out goes out be used to the steel pipe pile position of setting up drilling platform;
(5) the drill bit guiding steel casing of high 150cm is installed in described drilled pile position, described drill bit guiding steel casing diameter is than the design stake large 20~40cm in footpath; Steel pipe pile is installed in the steel pipe pile position, and high the setting with the top, cofferdam of steel pipe pile top mark flushes; Then build the high bottom concrete of remaining 50cm;
(6) utilize described steel pipe pile and cofferdam wall to make lower support, set up drilling platform;
(7) the rig drilling construction that carries out in place.
2. method according to claim 1, it is characterized in that: in the described step (4), the steel pipe pile bit quantity that setting-out goes out equates with the drilled pile bit quantity.
3. method according to claim 1 is characterized in that: the wall thickness of described drill bit guiding steel casing is 1.2cm.
4. method according to claim 1 is characterized in that: described bottom concrete adopts " vertical many tremie methods " to carry out integrated poured.
5. method according to claim 1 is characterized in that: drilling construction employing method of air lifting reverse circulation clear water drilling construction.
6. method according to claim 1, it is characterized in that: the sidewall in described cofferdam is provided with through hole and valve, makes the inside and outside UNICOM in cofferdam.
CN2013102828163A 2013-07-06 2013-07-06 Construction method of deep water pile foundation without steel pile casings Pending CN103352472A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102828163A CN103352472A (en) 2013-07-06 2013-07-06 Construction method of deep water pile foundation without steel pile casings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102828163A CN103352472A (en) 2013-07-06 2013-07-06 Construction method of deep water pile foundation without steel pile casings

Publications (1)

Publication Number Publication Date
CN103352472A true CN103352472A (en) 2013-10-16

Family

ID=49308880

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102828163A Pending CN103352472A (en) 2013-07-06 2013-07-06 Construction method of deep water pile foundation without steel pile casings

Country Status (1)

Country Link
CN (1) CN103352472A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628511A (en) * 2013-12-17 2014-03-12 中铁大桥局集团第四工程有限公司 Setting-out plumbing method for pile foundation casing
CN105257215A (en) * 2015-10-06 2016-01-20 中交第四公路工程局有限公司 Method for performing in-water pile foundation hole drilling by large-diameter reverse circulation roller cone drilling
CN109868805A (en) * 2019-02-28 2019-06-11 天津大学 Steel pile casting formula heavy-tamping method underwater reinforced construction method
CN110080684A (en) * 2019-05-08 2019-08-02 永康微唯智能科技有限公司 A kind of support protecting apptss of drilled pile
CN113006056A (en) * 2021-03-23 2021-06-22 蒙城安路蓝海交通投资有限公司 Deepwater pile foundation construction method
CN115324086A (en) * 2022-07-29 2022-11-11 中交路桥建设有限公司 Cofferdam and drilling platform integrated system and application construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19533014A1 (en) * 1995-09-07 1997-03-13 Holzmann Philipp Ag Sheet pile wall construction method
CN1837510A (en) * 2006-04-07 2006-09-27 上海市政工程设计研究总院 Steel pipe pile cofferdam and method for manufacturing the same
CN101200898A (en) * 2007-12-04 2008-06-18 中铁大桥局股份有限公司 Construction method of drilling pile base for bare rock and shallow overburden
CN101696578A (en) * 2009-09-28 2010-04-21 中铁八局集团第一工程有限公司 Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway
CN102021901A (en) * 2010-10-28 2011-04-20 中铁十三局集团有限公司 Method for putting up steel pipe pile platform of abrupt slope bare rock
CN201981543U (en) * 2011-01-25 2011-09-21 中交一公局厦门工程有限公司 Hasp-free steel pipe pile foundation pit bracing sealing-up cofferdam structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19533014A1 (en) * 1995-09-07 1997-03-13 Holzmann Philipp Ag Sheet pile wall construction method
CN1837510A (en) * 2006-04-07 2006-09-27 上海市政工程设计研究总院 Steel pipe pile cofferdam and method for manufacturing the same
CN101200898A (en) * 2007-12-04 2008-06-18 中铁大桥局股份有限公司 Construction method of drilling pile base for bare rock and shallow overburden
CN101696578A (en) * 2009-09-28 2010-04-21 中铁八局集团第一工程有限公司 Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway
CN102021901A (en) * 2010-10-28 2011-04-20 中铁十三局集团有限公司 Method for putting up steel pipe pile platform of abrupt slope bare rock
CN201981543U (en) * 2011-01-25 2011-09-21 中交一公局厦门工程有限公司 Hasp-free steel pipe pile foundation pit bracing sealing-up cofferdam structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
唐斌华等: ""无钢护筒清水钻深水桩基施工技术简介"", 《公路交通技术》 *
杨基好: ""异型开放式有刃脚双壁钢围堰施工技术"", 《安徽建筑》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628511A (en) * 2013-12-17 2014-03-12 中铁大桥局集团第四工程有限公司 Setting-out plumbing method for pile foundation casing
CN103628511B (en) * 2013-12-17 2015-07-08 中铁大桥局集团第四工程有限公司 Setting-out plumbing method for pile foundation casing
CN105257215A (en) * 2015-10-06 2016-01-20 中交第四公路工程局有限公司 Method for performing in-water pile foundation hole drilling by large-diameter reverse circulation roller cone drilling
CN105257215B (en) * 2015-10-06 2017-07-07 中交第四公路工程局有限公司 A kind of method of use Large Diameter Reverse circulation roller boring water-filling pile foundation drilling
CN109868805A (en) * 2019-02-28 2019-06-11 天津大学 Steel pile casting formula heavy-tamping method underwater reinforced construction method
CN110080684A (en) * 2019-05-08 2019-08-02 永康微唯智能科技有限公司 A kind of support protecting apptss of drilled pile
CN113006056A (en) * 2021-03-23 2021-06-22 蒙城安路蓝海交通投资有限公司 Deepwater pile foundation construction method
CN115324086A (en) * 2022-07-29 2022-11-11 中交路桥建设有限公司 Cofferdam and drilling platform integrated system and application construction method thereof

Similar Documents

Publication Publication Date Title
US20210292987A1 (en) Construction method for pouring concrete in karst cave
CN103352472A (en) Construction method of deep water pile foundation without steel pile casings
CN105569560B (en) A full set of tubular type long auger stake machine and the method for utilizing the ram machine construction
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
NO871255L (en) PROCEDURE FOR THE DEVELOPMENT OF OIL AND / OR GAS FIELDS FOR THE SEA, AND THE FOUNDATION FOR A DRILL AND / OR PRODUCTION PLATFORM FOR THE SEA.
CN110158582A (en) A method of trestle steel pipe pile is set on intectate riverbed
CN102071645B (en) Bridge bored pile hole wall opening protection method
CN107654206A (en) One kind drilling antipriming and water-stopping method
CN102433878A (en) Post-grouting device and construction method for pipe pile foundation
CN106638717A (en) Construction method for foundation buoyancy resistance
CN104563126B (en) A kind of churning driven bored pile construction method
CN114215049A (en) Construction method for main steel casing of bored pile under deep water foundation and bare rock environment
CN104762981A (en) Hole forming method of precipitation well
CN205382483U (en) Drilling bored concrete pile drilling equipment in deep water sand boulder bed riverbed
CN110241731A (en) A method of forming rock-socketed pile foundation in seabed
CN201459749U (en) Stable structure for construction platform of deep water steel pipe pile
CN106480876A (en) A kind of inclined hole steel pipe piles set into rock construction
CN106088123A (en) A kind of sand geology steel tube well fall water level device and construction method thereof
CN114045854A (en) Bridge pile foundation composite construction method under complex geological condition
CN202247897U (en) Post-grouting device for pipe pile foundation
CN101545259A (en) Device and method for non-underwater concreting by using drilled pile
CN104278680A (en) Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method
CN103669347B (en) Underwater anchor rod construction method
CN103835240A (en) Buoyancy tank type deepwater pile group bridge abutment construction platform and construction method thereof
CN101349059A (en) New technique of long screw driller for press pouring reinforced concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 100027, Beijing, Dongcheng District, East Street, No. 9 east ring Plaza, block A, Luqiao building, eight floor

Applicant after: Road & Bridge International Co., Ltd.

Applicant after: ROAD AND BRIDGE EAST CHINA ENGINEERING CO., LTD.

Address before: 100027, Beijing, Dongcheng District, East Street, No. 9 east ring Plaza, block A, Luqiao building, eight floor

Applicant before: Road & Bridge International Co., Ltd.

Applicant before: Road & Bridge East China Engineering Co., Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131016