CN103345870B - A kind of transformer intelligent simulation device - Google Patents

A kind of transformer intelligent simulation device Download PDF

Info

Publication number
CN103345870B
CN103345870B CN201310296247.8A CN201310296247A CN103345870B CN 103345870 B CN103345870 B CN 103345870B CN 201310296247 A CN201310296247 A CN 201310296247A CN 103345870 B CN103345870 B CN 103345870B
Authority
CN
China
Prior art keywords
module
relay
resistance
control module
fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310296247.8A
Other languages
Chinese (zh)
Other versions
CN103345870A (en
Inventor
张长营
姜凤宗
夏振雨
陈铮
徐光举
支长义
张军照
朱立位
尹雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU PROVINCIAL POWER Co VOCATIONAL SKILLS TRAINING BASE
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Lianyungang Power Supply Co of Jiangsu Electric Power Co
Original Assignee
JIANGSU PROVINCIAL POWER Co VOCATIONAL SKILLS TRAINING BASE
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Lianyungang Power Supply Co of Jiangsu Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU PROVINCIAL POWER Co VOCATIONAL SKILLS TRAINING BASE, State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Lianyungang Power Supply Co of Jiangsu Electric Power Co filed Critical JIANGSU PROVINCIAL POWER Co VOCATIONAL SKILLS TRAINING BASE
Priority to CN201310296247.8A priority Critical patent/CN103345870B/en
Publication of CN103345870A publication Critical patent/CN103345870A/en
Application granted granted Critical
Publication of CN103345870B publication Critical patent/CN103345870B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The invention discloses a kind of transformer intelligent simulation device, comprise host computer, communication conversion and control module, wireless data transceiver module, fault simulator, programmable power supply module, p-wire Intelligent Measurement module, testing tool module and power module; Described host computer is connected with communication conversion and control module, wireless data transceiver module respectively; Communication conversion and control module is connected between two with fault simulator, programmable power supply module, communication conversion and control module controls the duty of fault simulator, programmable power supply module, meanwhile, the data that communication conversion and control module receives fault simulator, programmable power supply module is uploaded; Wireless data transceiver module is connected between two with p-wire Intelligent Measurement module, testing tool module, wherein can carry out data transmission between the two arbitrarily; Power module is connected with other module, for it provides power supply; The invention provides that a kind of security is high, good reliability, functional diversities, intelligentized transformer intelligent simulation device.

Description

A kind of transformer intelligent simulation device
Technical field
The invention belongs to technical field of electric equipment, particularly a kind of transformer intelligent simulation device.
Background technology
Both at home and abroad to teaching and the Training Methodology of transformer associative skills, be only limitted to the explanation of transformer principle at present and anatomic observation is carried out to a certain type transformer, can not reproduce the contingent phenomenon of the failure of Transformer, simultaneously because the transformer of training is once selected, in the test of transformer correlated performance and test, as long as the electrical specification of transformer own does not change, test data has uniqueness, cannot realize carrying out personalization test examination to multidigit student, this training method is unfavorable for understanding and the study of student, denounce in teaching practice a lot of.In order to improve student's practical operation technical ability and maintenance, maintenance and measuring technology level, improve existing teaching and training method imperative.
Need carry out dielectric voltage withstand test, insulation resistance test, direct current resistance test, volume test, no-load voltage ratio and be connected the testing experiments such as group during the electric parameter of transformer when delivery test occurs with normal operation and fault detects, to test the danger when actual carrying out larger for such test such as dielectric voltage withstand, technical requirement is also higher, does not generally all carry out such test in laboratory environments; Insulation resistance test, in actual tests, cannot simulate multiple insulation characterisitic, and use real transformer as subjects, test data is single, and Parameters variation when transformer fault occurs cannot be simulated; Direct current resistance and transformer capacity parameter embody different test resistance values on different transformer, and resistance value is simulated from milliohm to tens Ou Buyi; No-load voltage ratio and connection group cannot load virtual voltage and realize no-load voltage ratio test.For above transformer test Problems existing, simulation and training is carried out to existing transformer there is certain real necessity.
In actual field teaching, normally move a certain model substation transformer of practical application to Training Room, student is allowed to carry out test training, after real training transformer puts in place, all kinds of parameter is all invariable, student is difficult to Judging fault state and fault type from the change of transformer parameter, is unfavorable for very much teaching and examination.Therefore, for the ease of teaching and examination, reduce danger during operation, need to improve existing transformer actual training device.
Summary of the invention
The object of the present invention is to provide that a kind of security is high, good reliability, functional diversities, intelligentized transformer intelligent simulation device, to meet the demand of transformer test teaching and training.
The technical solution realizing the object of the invention is: a kind of transformer intelligent simulation device, comprises host computer, communication conversion and control module, wireless data transceiver module, fault simulator, programmable power supply module, p-wire Intelligent Measurement module, testing tool module and power module; Described host computer is connected with communication conversion and control module, wireless data transceiver module respectively, by host computer command to communication conversion and control module and wireless data transceiver module, meanwhile, host computer receives the signal of communication conversion and control module and wireless data transceiver module passback; Communication conversion and control module is connected between two with fault simulator, programmable power supply module, communication conversion and control module controls the duty of fault simulator, programmable power supply module, meanwhile, the data that communication conversion and control module receives fault simulator, programmable power supply module is uploaded; Wireless data transceiver module is connected between two with p-wire Intelligent Measurement module, testing tool module, wherein can carry out data transmission between the two arbitrarily; Power module is connected with above-mentioned each module, for it provides power supply.
The present invention compared with prior art, its remarkable advantage is: a kind of transformer intelligent simulation device of the present invention fundamentally solves a transformer training technique difficult problem, by the operating most common failure of computer installation real transformer, transformer fault is reappeared, contribute to student and have more deep understanding to transformer principle, student is enable to experience various fault truly, more realistically close to on-the-spot truth, the understanding of student to transformer ' s type Related product can be strengthened, more student is made to understand method for designing and the implementation of different device for transformer, transformer training facilitation and deepization more can be made, teaching on transformer training apparatus and result of training are strengthened greatly, the technical merit of station personnel can be improved further, thus improve reliability and the power supplying efficiency of power supply, it is high that a kind of transformer intelligent simulation device of the present invention has security, good reliability, functional diversities, intelligentized feature.
Below in conjunction with accompanying drawing, the present invention is described in further detail.
Accompanying drawing explanation
Fig. 1 is the theory diagram of a kind of transformer intelligent simulation device of the present invention.
Fig. 2 is the high-pressure side circuit diagram of direct current resistance test simulation module in a kind of transformer intelligent simulation device of the present invention.
Fig. 3 is the lower-voltage circuit figure of direct current resistance test simulation module in a kind of transformer intelligent simulation device of the present invention.
Fig. 4 is volume test analog module circuit diagram in a kind of transformer intelligent simulation device of the present invention.
Fig. 5 is transformer insulated test simulation module circuit diagram in a kind of transformer intelligent simulation device of the present invention.
Fig. 6 is no-load voltage ratio test simulation module circuit diagram in a kind of transformer intelligent simulation device of the present invention.
Embodiment
A kind of transformer intelligent simulation device of the present invention, comprises host computer, communication conversion and control module, wireless data transceiver module, fault simulator, programmable power supply module, p-wire Intelligent Measurement module, testing tool module and power module; Described host computer is connected with communication conversion and control module, wireless data transceiver module respectively, by host computer command to communication conversion and control module and wireless data transceiver module, meanwhile, host computer receives the signal of communication conversion and control module and wireless data transceiver module passback; Communication conversion and control module is connected between two with fault simulator, programmable power supply module, communication conversion and control module controls the duty of fault simulator, programmable power supply module, meanwhile, the data that communication conversion and control module receives fault simulator, programmable power supply module is uploaded; Wireless data transceiver module is connected between two with p-wire Intelligent Measurement module, testing tool module, wherein can carry out data transmission between the two arbitrarily; Power module is connected with other module, for it provides power supply.
Described communication conversion and control module comprises communication module, control module and FPGA module, and communication module is link control module and FPGA module successively, and communication module is transferred to control module by after host computer instruction transformation, and control module controls the output of FPGA module.
Described wireless data transceiver module, p-wire Intelligent Measurement module and testing tool module all comprise control module, A/D modular converter, zigbee module, and control module is connected with A/D modular converter, zigbee module.
Described fault simulator comprises fault simulation communication module, main control module, FCM fault control module and fault simulation module; Fault simulation communication module connects main control module, FCM fault control module and fault simulation module successively, and fault simulation communication module is by Signal transmissions to main control module, and main control module controls the switching of fault simulation module by FCM fault control module.
Described fault simulation module comprises transformer insulated test simulation module, direct current resistance test simulation module, volume test analog module, no-load voltage ratio test simulation module and position of tapping switch detection module.
Described direct current resistance test simulation module comprises the first resistance R1, second resistance R2, 3rd resistance R3, 4th resistance R4, 5th resistance R5, 6th resistance R6, 7th resistance R7, 8th resistance R8, 9th resistance R9, tenth resistance R10, 11 resistance R11, 12 resistance R12, 13 resistance R13, 14 resistance R14, 15 resistance R15, 16 resistance R16, 17 resistance R17, 18 resistance R18, 19 resistance R19, 20 resistance R20, 21 resistance R21, 22 resistance R22, 23 resistance R23, 24 resistance R24, 25 resistance R25, 26 resistance R26, 27 resistance R27, 28 resistance R28, 29 resistance R29, 30 resistance R30, 31 resistance R31, 32 resistance R32, 33 resistance R33, 34 resistance R34, 35 resistance R35, 36 resistance R36, 37 resistance R37, 38 resistance R38, 39 resistance R39, 40 resistance R40, 41 resistance R41, 42 resistance R42, 43 resistance R43, 44 resistance R44, 45 resistance R45, 46 resistance R46, 47 resistance R47, 48 resistance R48, 49 resistance R49, 50 resistance R50, 51 resistance R51, 53 resistance R53, 54 resistance R54, 55 resistance R55, 57 resistance R57, 58 resistance R58, 59 resistance R59, first relay J 1, second relay J 2, 3rd relay J 3, 4th relay J 4, 5th relay J 5, 6th relay J 6, 7th relay J 7, 8th relay J 8, 9th relay J 9, tenth relay J 10, 11 relay J 11, 12 relay J 12, 13 relay J 13, 14 relay J 14, 15 relay J 15, 16 relay J 16, 17 relay J 17, 18 relay J 18, 19 relay J 19, 20 relay J 20, 21 relay J 21, 22 relay J 22, 23 relay J 23, 24 relay J 24, 25 relay J 25, 26 relay J 26, 27 relay J 27, 28 relay J 28, 29 relay J 29, 30 relay J 30, 31 relay J 31, 32 relay J 32, 33 relay J 33, 34 relay J 34, 35 relay J 35, 36 relay J 36, 37 relay J 37, 38 relay J 38, 39 relay J 39, 40 relay J 40, 41 relay J 41, 42 relay J 42, 43 relay J 43, 44 relay J 44, 45 relay J 45, 46 relay J 46, 47 relay J 47, 48 relay J 48, 49 relay J 49, 50 relay J 50, 51 relay J 51, 52 relay J 52, 53 relay J 53, 54 relay J 54, 55 relay J 55, 56 relay J 56, 57 relay J 57, 58 relay J 58, 59 relay J 59, 60 relay J 60, 61 relay J 61, first fuse FU1, second fuse FU2, 3rd fuse FU3, first slide rheostat RP1, second slide rheostat RP2 and the 3rd slide rheostat RP3, high-pressure side A phase is connected with one end of the 55 relay J 55, the other end of the 55 relay J 55 is connected with one end of the first fuse FU1, the other end of the first fuse FU1 is connected with one end of the first relay J 1, simultaneously, the other end of the first fuse FU1 respectively with the second relay J 2, 3rd relay J 3, 13 relay J 13, 14 relay J 14, 15 relay J 15, 16 relay J 16, 31 relay J 31, 32 relay J 32, 33 relay J 33, 46 relay J 46, 47 relay J 47, one end of 48 relay J 48 is connected, the other end of the first relay J 1 is connected with one end of the first resistance R1, the other end of the first resistance R1 is connected with one end of the second resistance R2, simultaneously, the other end of the first resistance R1 is connected with the other end of the second relay J 2, the other end of the second resistance R2 is connected with one end of the 3rd resistance R3, simultaneously, the other end of the second resistance R2 is connected with the other end of the 3rd relay J 3, one end of the other end the 4th resistance R4 of the 3rd resistance R3 is connected, simultaneously, the other end of the 3rd resistance R3 respectively with the tenth relay J 10, one end of 25 relay J 25 is connected, the other end of the 4th resistance R4 is connected with one end of the 5th resistance R5, simultaneously, the other end of the 4th resistance R4 is connected with the other end of the tenth relay J 10, the other end of the 14 relay J 14 is connected with one end of the 16 resistance R16, the other end of the 16 resistance R16 is connected with one end of the 17 resistance R17, simultaneously, the other end of the 16 resistance R16 is connected with the other end of the 13 relay J 13, the other end of the 17 resistance R17 is connected with one end of the 18 resistance R18, simultaneously, the other end of the 17 resistance R17 is connected with the other end of the 15 relay J 15, the other end of the 18 resistance R18 is connected with one end of the 19 resistance R19, the other end of the 18 resistance R18 is connected with the other end of the 16 relay J 16 simultaneously, the other end of the 19 resistance R19 is connected with one end of the 26 relay J 26, simultaneously, the other end of the 19 resistance R19 is connected with the other end of the 25 relay J 25, the other end of the 31 relay J 31 is connected with one end of the 28 resistance R28, the other end of the 28 resistance R28 is connected with one end of the 29 resistance R29, simultaneously, the other end of the 28 resistance R28 respectively with the other end of the 26 relay J 26, the other end of the 32 relay J 32 is connected, the other end of the 29 resistance R29 is connected with one end of the 30 resistance R30, simultaneously, the other end of the 29 resistance R29 respectively with the other end of the 33 relay J 33, one end of 40 relay J 40 is connected, the other end of the 30 resistance R30 is connected with one end of the 31 resistance R31, the other end of the 31 resistance R31 is connected with one end of the 32 resistance R32, the other end of the 32 resistance R32 is connected with one end of the 33 resistance R33, simultaneously, the other end of the 32 resistance R32 is connected with the other end of the 40 relay J 40, the other end of the 33 resistance R33 is connected with one end of the 34 resistance R34, simultaneously, the other end of the 33 resistance R33 is connected with the other end of the 5th resistance R5, the other end of the 46 relay J 46 is connected with one end of the 49 resistance R49, the other end of the 49 resistance R49 is connected with one end of the 50 resistance R50, simultaneously, the other end of the 49 resistance R49 is connected with the other end of the 47 relay J 47, the other end of the 50 resistance R50 is connected with one end of the 51 resistance R51, simultaneously, the other end of the 50 resistance R50 respectively with the other end of the 48 relay J 48, one end of 43 relay J 43 is connected, the other end of the 51 resistance R51 is connected with the other end of the 43 relay J 43, simultaneously, the other end of the 51 resistance R51 is connected with the other end of the 34 resistance R34, the circuit that high-pressure side B phase, C phase connect is identical with the circuit that A phase connects, and wherein, the other end of the 51 resistance R51 is connected with the other end of the 55 resistance R55, the other end of the 59 resistance R59 respectively, low-pressure side a phase is connected with one end of the 58 relay J 58, the other end of the 58 relay J 58 is connected with one end of the first slide rheostat RP1, low-pressure side b phase is connected with one end of the 59 relay J 59, the other end of the 59 relay J 59 is connected with one end of the second slide rheostat RP2, low-pressure side c phase is connected with one end of the 60 relay J 60, the other end of the 60 relay J 60 is connected with one end of the 3rd slide rheostat RP3, low-pressure side N phase is connected with one end of the 61 relay J 61, the other end of the 61 relay J 61 is respectively at the other end of the first slide rheostat RP1, the other end of the second slide rheostat RP2, the other end of the 3rd slide rheostat RP3 is connected.
Described volume test analog module comprises the 61 resistance R61, 62 resistance R62, 63 resistance R63, 64 resistance R64, 65 resistance R65, 66 resistance R66, 67 resistance R67, 68 resistance R68, 69 resistance R69, 70 resistance R70, 71 resistance R71, 72 resistance R72, 73 resistance R73, 74 resistance R74, 75 resistance R75, 76 resistance R76, 77 resistance R77, 78 resistance R78, 79 resistance R79, 80 resistance R80, 81 resistance R81, 62 relay J 62, 63 relay J 63, 64 relay J 64, 65 relay J 65, 66 relay J 66, 67 relay J 67, 68 relay J 68, 69 relay J 69, 70 relay J 70, 71 relay J 71, 72 relay J 72, 73 relay J 73, 74 relay J 74, 75 relay J 75, 76 relay J 76, 77 relay J 77, 78 relay J 78, 79 relay J 79, 80 relay J 80, 81 relay J 81, 82 relay J 82, 83 relay J 83, 84 relay J 84, 85 relay J 85, high-pressure side A phase is connected with one end of the 62 relay J 62, and high-pressure side B phase is connected with one end of the 63 relay J 63, and high-pressure side C phase is connected with one end of the 64 relay J 64, volume test analog module is provided with seven identical relay control module, relay control module comprises the 65 relay J the 65, the 66 relay J the 66, the 67 relay J the 67, the 61 resistance R61, the 62 resistance R62, the 63 resistance R63, wherein, one end of 65 relay J 65 is connected with one end of the 61 resistance R61, one end of 66 relay J 66 is connected with one end of the 62 resistance R62, and one end of the 67 relay J 67 is connected with one end of the 63 resistance R63, the other end of the 62 relay J 62 is connected with the other end of the 65 relay J 65, the other end of the 63 relay J 63 is connected with the other end of the 66 relay J 66, the other end of the 63 relay J 63 is connected with the other end of the 67 relay J 67, and in volume test analog module, the other end of all resistance is connected.
Described transformer insulated test simulation module comprises the 82 resistance R82, 83 resistance R83, 86 relay J 86, 87 relay J 87, high-pressure side terminal is connected with one end of the 82 resistance R82, the other end of the 82 resistance R82 is connected with one end of the 83 resistance R83, the other end of the 83 resistance R83 is connected with one end of the 86 relay J 86, simultaneously, the other end of the 83 resistance R83 is connected with one end of the 87 relay J 87, the other end of the 86 relay J 86 is connected with low-pressure side terminal, the other end of the 87 relay J 87 is connected with transformer case.
Described no-load voltage ratio test simulation module comprises the 88 relay J 88, 89 relay J 89, 90 relay J 90, 91 relay J 91, 92 relay J 92, 93 relay J 93, 94 relay J 94, high-pressure side A phase is connected with one end of the 88 relay J 88, the other end of the 88 relay J 88 is connected with the input end U phase of programmable power supply module, the output terminal U phase of programmable power supply module is connected with one end of the 91 relay J 91, the other end of the 91 relay J 91 is connected with a phase of low-pressure side, high-pressure side B phase is connected with one end of the 89 relay J 89, the other end of the 89 relay J 89 is connected with the input end V phase of programmable power supply module, the output terminal V phase of programmable power supply module is connected with one end of the 92 relay J 92, and the other end of the 92 relay J 92 is connected with the b phase of low-pressure side, high-pressure side C phase is connected with one end of the 90 relay J 90, the other end of the 90 relay J 90 is connected with the input end W phase of programmable power supply module, the output terminal W phase of programmable power supply module is connected with one end of the 93 relay J 93, and the other end of the 93 relay J 93 is connected with the c phase of low-pressure side, low-pressure side N phase is connected with one end of the 94 relay J 94, and the other end of the 94 relay J 94 is connected with the output terminal Un phase of programmable power supply module.
Below in conjunction with embodiment, further detailed description is done to the present invention:
Described host computer is a kind of general computing machine, mainly realizes operation and the controlling functions of various software, and host computer and communication conversion and control mould carry out communication by wireless network.
Described communication conversion and control module comprises RS485 communication module, single-chip microcomputer, fpga chip, when communication conversion and control module sends data, communication conversion and control module receives the data command frame of host computer transmission by RS485 communication module, RS485 communication module by data frame transfer to single-chip microcomputer, the Frame received is sent to fpga chip by parallel port by single-chip microcomputer, the data that single-chip microcomputer is sent by internal conversion by fpga chip, be forwarded to different serial communication interfaces, thus realize the data retransmission of single serial ports to Multi-serial port, complete controlling functions.When communication conversion and control module receives data, the data that in communication conversion and control module, fpga chip serial ports reception fault simulation module and programmable power supply module are uploaded, send the data to single-chip microcomputer through conversion communication, single-chip microcomputer passes through RS485 communication module by data upload to host computer; Communication conversion and control module achieves and sets up standby control multiple devices function.
Described wireless data transceiver module, p-wire Intelligent Measurement module and testing tool module all comprise control module, A/D modular converter, zigbee module, control module connects A/D modular converter respectively successively, zigbee module is connected, control module selects LPC1313 processor control module, A/D modular converter selects the A/D converter AD760 of 18, and zigbee module selects CC2480 chip; Wireless data receipt modules is a kind of receive data by wireless device based on ZigBee technology, the IP address of specific baud rate and institute's group network is transmitted by setting data, can make to form a wireless network between host computer, equipment, testing tool three, realize in network the mutual of data and information between each point; P-wire Intelligent Measurement module a kind ofly whether accesses to instrument test line the equipment that Intelligent Measurement and judgement are carried out in test point and on-position, adopts LPC1313 processor single-chip microcomputer and ZigBee technology to realize the intelligent decision of wiring position and the mutual of testing result information; Testing tool module is transformer commissioning test dependence test instrument analog machine used, and outward appearance is consistent with true instrument with method of operating, but test data is virtual value set as required.
Described fault simulator comprises RS485 fault simulation communication module, main control module, FCM fault control module and fault simulation module; RS485 fault simulation communication module is connected with communication conversion and control module, the RS485 communication between communication conversion and control module and main control module is realized by RS485 fault simulation communication module, realize the reception of fault verification order, main control module realizes fault simulation module by FCM fault control module and switches, fault simulation module, according to the instruction of FCM fault control module, realizes the switching of the mode of connection.
Described programmable power supply module is a kind of high-accuracy virtual load power supply, produces independently voltage, provide no-load voltage ratio required voltage to transformer by Single-chip Controlling, and transformer voltage ratio test function is achieved, without the need to the electric power loads consumption of reality.
Workflow of the present invention illustrates:
1, host computer is by wireless network communication, through communication conversion and control module, controls fault simulator, arranges some most common failures of transformer.
2, host computer is by wireless network communication, through communication conversion and control module, controls the voltage output value of programmable power supply, reaches the object of no-load voltage ratio functional realiey.
3, host computer is by Zigbee Wireless Data Transmission, through wireless data transceiver module, command adapted thereto is issued to p-wire Intelligent Measurement module, p-wire Intelligent Measurement module passes through Zigbee Wireless Data Transmission testing result testing result, carries out information interaction with host computer and testing tool module.
4, host computer is by Zigbee Wireless Data Transmission, and through wireless data transceiver module, issue command adapted thereto and data to testing tool module, testing tool carries out corresponding display according to data.

Claims (1)

1. a transformer intelligent simulation device, is characterized in that, comprises host computer, communication conversion and control module, wireless data transceiver module, fault simulator, programmable power supply module, p-wire Intelligent Measurement module, testing tool module and power module, described host computer is connected with communication conversion and control module, wireless data transceiver module respectively, by host computer command to communication conversion and control module and wireless data transceiver module, meanwhile, host computer receives the signal of communication conversion and control module and wireless data transceiver module passback, communication conversion and control module is connected between two with fault simulator, programmable power supply module, communication conversion and control module controls the duty of fault simulator, programmable power supply module, meanwhile, the data that communication conversion and control module receives fault simulator, programmable power supply module is uploaded, wireless data transceiver module is connected between two with p-wire Intelligent Measurement module, testing tool module, wherein can carry out data transmission between the two arbitrarily, power module is connected with above-mentioned each module, for it provides power supply, described communication conversion and control module comprises communication module, control module and FPGA module, and communication module is link control module and FPGA module successively, and communication module is transferred to control module by after host computer instruction transformation, and control module controls the output of FPGA module, described wireless data transceiver module, p-wire Intelligent Measurement module and testing tool module all comprise control module, A/D modular converter, zigbee module, and control module is connected with A/D modular converter, zigbee module, described fault simulator comprises fault simulation communication module, main control module, FCM fault control module and fault simulation module, fault simulation communication module connects main control module, FCM fault control module and fault simulation module successively, and fault simulation communication module is by Signal transmissions to main control module, and main control module controls the switching of fault simulation module by FCM fault control module, described fault simulation module comprises transformer insulated test simulation module, direct current resistance test simulation module, volume test analog module, no-load voltage ratio test simulation module and position of tapping switch detection module, described transformer insulated test simulation module comprises the 82 resistance [R82], 83 resistance [R83], 86 relay [J86], 87 relay [J87], high-pressure side terminal is connected with one end of the 82 resistance [R82], the other end of the 82 resistance [R82] is connected with one end of the 83 resistance [R83], the other end of the 83 resistance [R83] is connected with one end of the 86 relay [J86], simultaneously, the other end of the 83 resistance [R83] is connected with one end of the 87 relay [J87], the other end of the 86 relay [J86] is connected with low-pressure side terminal, the other end of the 87 relay [J87] is connected with transformer case.
CN201310296247.8A 2013-07-15 2013-07-15 A kind of transformer intelligent simulation device Active CN103345870B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310296247.8A CN103345870B (en) 2013-07-15 2013-07-15 A kind of transformer intelligent simulation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310296247.8A CN103345870B (en) 2013-07-15 2013-07-15 A kind of transformer intelligent simulation device

Publications (2)

Publication Number Publication Date
CN103345870A CN103345870A (en) 2013-10-09
CN103345870B true CN103345870B (en) 2015-09-30

Family

ID=49280661

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310296247.8A Active CN103345870B (en) 2013-07-15 2013-07-15 A kind of transformer intelligent simulation device

Country Status (1)

Country Link
CN (1) CN103345870B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105869489A (en) * 2016-06-16 2016-08-17 国网江苏省电力公司职业技能训练基地 Analog transformer
CN107300648B (en) * 2017-06-16 2023-10-17 国家电网公司 Transformer insulation resistance and absorption ratio simulation training device
CN107356829B (en) * 2017-06-16 2024-03-29 国家电网公司 Transformer capacity simulation training device
CN107527529B (en) * 2017-10-09 2023-08-22 贵州电网有限责任公司 Low-voltage side winding characteristic fault simulation device and simulation method of transformer
CN108831234A (en) * 2017-11-29 2018-11-16 国网吉林省电力有限公司培训中心 Mutual inductor electrical test emulates teaching aid
CN108447360A (en) * 2018-03-08 2018-08-24 广西网冠电气有限公司 A kind of three-phase three-wire electric energy meter device for simulating false wiring
CN112396906A (en) * 2020-11-16 2021-02-23 河南能创电子科技有限公司 Comprehensive simulation system for professional post skills and examination of electricity inspection for actual operation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011233557A (en) * 2010-04-23 2011-11-17 Chugoku Electric Power Co Inc:The Simulated transformer and withstand voltage simulated test device
CN202306914U (en) * 2011-10-11 2012-07-04 安徽省电力公司安庆供电公司 Active load circuit device matched with electric-larceny-prevention comprehensive experimental device
CN102831793A (en) * 2012-09-03 2012-12-19 汪泓 Entity simulation training device for high voltage electrical test
CN102930768A (en) * 2012-11-22 2013-02-13 郑州万特电气有限公司 Transformer cooling loop training device
CN202871159U (en) * 2012-09-27 2013-04-10 武汉华大电力自动技术有限责任公司 Power system integrated automated test bed
CN203376911U (en) * 2013-07-15 2014-01-01 国家电网公司 A transformer intelligent simulating apparatus

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8395394B2 (en) * 2008-08-01 2013-03-12 Avo Multi-Amp Corporation System and method for power system component testing

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011233557A (en) * 2010-04-23 2011-11-17 Chugoku Electric Power Co Inc:The Simulated transformer and withstand voltage simulated test device
CN202306914U (en) * 2011-10-11 2012-07-04 安徽省电力公司安庆供电公司 Active load circuit device matched with electric-larceny-prevention comprehensive experimental device
CN102831793A (en) * 2012-09-03 2012-12-19 汪泓 Entity simulation training device for high voltage electrical test
CN202871159U (en) * 2012-09-27 2013-04-10 武汉华大电力自动技术有限责任公司 Power system integrated automated test bed
CN102930768A (en) * 2012-11-22 2013-02-13 郑州万特电气有限公司 Transformer cooling loop training device
CN203376911U (en) * 2013-07-15 2014-01-01 国家电网公司 A transformer intelligent simulating apparatus

Also Published As

Publication number Publication date
CN103345870A (en) 2013-10-09

Similar Documents

Publication Publication Date Title
CN103345870B (en) A kind of transformer intelligent simulation device
CN103345859B (en) Intelligent practical training device based on transformer fault simulation
CN101615357B (en) Electricity meter-reading check charging training device
CN103713214B (en) A kind of intelligent substation relay protection closed loop test system
CN104076693B (en) Flexible direct-current transmission real-time simulation system and simulation method thereof
CN103616591B (en) The simulator of a kind of Intelligent substation merging unit characteristic and emulation mode thereof
CN105070157A (en) Feeder automation simulation training system
CN109582004B (en) Intelligent detection platform
CN103440803A (en) True-voltage simulation-current closed-loop all-true training system for 10kV power distribution device
CN105203870A (en) Intelligent transformer substation secondary equipment integrated test system based on power line communication
CN201465381U (en) Electric power meter reading and charge accounting training device
CN208637023U (en) Wiring check actual training device before high-voltage metering cubicle power transmission
CN207780127U (en) Low-voltage distribution transformer platform district Intelligent power-utilization information system resultant fault simulator
CN201936510U (en) Two-way controlled anti-electricity stealing simulation training device
CN204808712U (en) Feeder automation emulation training system
CN104535853B (en) The distributed testing terminal of LTE radio communication intelligent substation test systems
CN201839095U (en) Intelligent transformer substation testing and simulation system
CN103390362B (en) Transformer intelligent simulation system
CN105680441A (en) Simulated replacement technique-based simulated point-alignment device
CN203376911U (en) A transformer intelligent simulating apparatus
CN203376888U (en) An intelligent practical training apparatus based on transformer fault simulation
CN203520719U (en) 10kV power distribution unit actual voltage simulation current closed-loop all-real training system
CN202285151U (en) Double-path working power supply of integrative experimental device with electricity-theft prevention for simulating working condition of metering of electric energy
CN102867453B (en) Practical training system and practical training control device for low-voltage capacitor box
CN203376912U (en) A transformer intelligent simulation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: JIANGSU ELECTRIC POWER COMPANY LIANYUNGANG POWER S

Free format text: FORMER OWNER: JIANGSU ELECTRIC POWER COMPANY LIANYUNGANG POWER SUPPLY COMPANY OF JIANGSU ELECTRIC POWER COMPANY

Effective date: 20140305

TA01 Transfer of patent application right

Effective date of registration: 20140305

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Jiangsu Electric Power Company

Applicant after: Lianyungang Power Supply Company of Jiangsu Electric Power Company

Applicant after: JIANGSU PROVINCIAL POWER COMPANY VOCATIONAL SKILLS TRAINING BASE

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant before: State Grid Corporation of China

Applicant before: Jiangsu Electric Power Company

Applicant before: Lianyungang Power Supply Company of Jiangsu Electric Power Company

TA01 Transfer of patent application right
C14 Grant of patent or utility model
GR01 Patent grant