CN103331572A - Once forming of die forging crane wheel - Google Patents

Once forming of die forging crane wheel Download PDF

Info

Publication number
CN103331572A
CN103331572A CN 201310126102 CN201310126102A CN103331572A CN 103331572 A CN103331572 A CN 103331572A CN 201310126102 CN201310126102 CN 201310126102 CN 201310126102 A CN201310126102 A CN 201310126102A CN 103331572 A CN103331572 A CN 103331572A
Authority
CN
China
Prior art keywords
wheel
steel
heating
warehouse
furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201310126102
Other languages
Chinese (zh)
Inventor
韩景轩
王国强
李华庆
宋迎旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN NORTH CHINA LIFTING HOOK CO Ltd
Original Assignee
HENAN NORTH CHINA LIFTING HOOK CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN NORTH CHINA LIFTING HOOK CO Ltd filed Critical HENAN NORTH CHINA LIFTING HOOK CO Ltd
Priority to CN 201310126102 priority Critical patent/CN103331572A/en
Publication of CN103331572A publication Critical patent/CN103331572A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Forging (AREA)

Abstract

The invention provides a once forming fabrication technology of a die forging crane wheel, which comprises the steps of heating steel, oxidizing, entering a forming die, conducting blanking on the steel with a numerical-control horizontal sawing machine, allowing the steel to enter a heating furnace, heating the steel to be about 1200 DEG C, allowing the steel to be discharged from the furnace, removing oxide skins with a high-pressure water gun, entering the forming die directly, fabricating and forming all structures except wheel grooves and a shaft hole within 30 seconds with a megaton forging machine, accomplishing upsetting, returning to the furnace for heating, and entering the die. The technology adopts the technical scheme that with the adoption of the advanced technology, the production procedures can be decreased, the production cost can be lowered greatly, and the production efficiency can be improved greatly.

Description

Die forging crane wheel once-forming
Technical field
The present invention relates to a kind of crane locomotive wheel production Technology.Especially can the first mate reduce production costs and enhance productivity.
Background technology
Present domestic die forging crane locomotive wheel production technology all needs post bake and wheel race to be shaped in forging process, its technological process of production mostly be blanking, heating, pier slightly, heating, descaling again, go into die forming, punching, heat treatment, trimming, go into roughcast warehouse, roughing, modified, fine finishining, finished product warehouse-in, have in addition also need three heating.This just certainly will cause, and production cost height, efficient are low etc. to be unfavorable for that producer and user are competing in current intense market competition.
Summary of the invention
In order to overcome in the existing technological process of production production cost height, the inefficient deficiency that heating again and roughing cause, the invention provides a kind of production Technology, this technology can not only reduce production process, also can significantly reduce production costs and significantly enhance productivity.
Based on above-mentioned purpose, technical problem solved by the invention realizes by the following technical solutions:
A kind of preparation technology of die forging crane wheel once-forming, step of preparation process of the present invention is:
1) steel heating, oxidation, enters shaping dies; Steel are come out of the stove after utilizing the laggard heating furnace of numerical control horizontal sawing machine blanking to be heated to about 1200 ℃, utilize after the giant descaling directly into shaping dies, utilize ten thousand tons of forging presses in 30 seconds, the structure except wheel race and axis hole all to be made shaping, finish jumping-up, melt down heating, go into mould;
2) roller groove, roughing, fine finishining; Utilize the milling train roller groove after going out shaping dies, finish the operation that needs process roughing just can finish in the traditional handicraft in 120 seconds, namely crane wheel race is shaped and also keeps 3-5mm allowance so that modified back fine finishining;
3) towards axis hole, heat treatment; The crane wheel all is shaped behind the axis hole, advances heat-treatment furnace and carries out the formation that positive temper suppresses the inside wheel net carbide and eliminate internal stress, to obtain the good interior tissue of wheel and to improve its toughness;
4) warehouse-in, modified, fine finishining, check, warehouse-in again; After the wheel modulation, further carry out the blank warehouse-in, carry out, after modified, the check, enter warehouse for finished product.
The technical scheme that the present invention has done has adopted advanced technology, and this technology can not only reduce production process, also can significantly reduce production costs and significantly enhance productivity.
Description of drawings
Fig. 1 is process chart of the present invention;
Fig. 2 is the front view of the crane wheel finished product organigram made of the present invention;
Fig. 3 is the crane wheel body structural representation that the present invention makes;
The specific embodiment
Below by Figure of description, further set forth the present invention;
According to Fig. 1, Fig. 2, shown in Figure 3, steel are come out of the stove after utilizing the laggard heating furnace of numerical control horizontal sawing machine blanking to be heated to about 1200 ℃, utilize after the giant descaling directly into shaping dies, utilize ten thousand tons of forging presses in 30 seconds, the structure except wheel race and axis hole all to be made shaping, finish slightly, melt down heating, go into mould; Utilize the milling train roller groove behind the shaping dies, finish the operation that needs process roughing just can finish in the traditional handicraft in 120 seconds, namely crane wheel race is shaped and also keeps 3-5mm allowance so that modified back fine finishining; The crane wheel all is shaped behind the axis hole, advances heat-treatment furnace and carries out the formation that positive temper suppresses the inside wheel net carbide and eliminate internal stress, to obtain the good interior tissue of wheel and to improve its toughness; After the wheel modulation, further carry out the blank warehouse-in, carry out, after modified, the check, enter warehouse for finished product; The car wheel structure of final once-forming comprises race 1, axis hole 2, technology groove 3, wheel face 4, fabrication hole 5.
The above only is preferred embodiment of the present invention, not in order to limiting the present invention, all any modifications of doing within the spirit and principles in the present invention, is equal to and replaces and improvement etc., all should be included within protection scope of the present invention.

Claims (1)

1. the preparation technology of a die forging crane wheel once-forming is characterized in that step of preparation process of the present invention is:
1) steel heating, oxidation, enters shaping dies; Steel are come out of the stove after utilizing the laggard heating furnace of numerical control horizontal sawing machine blanking to be heated to about 1200 ℃, utilize after the giant descaling directly into shaping dies, utilize ten thousand tons of forging presses in 30 seconds, the structure except wheel race and axis hole all to be made shaping, finish jumping-up, melt down heating, go into mould;
2) roller groove, roughing, fine finishining; Utilize the milling train roller groove after going out shaping dies, finish the operation that needs process roughing just can finish in the traditional handicraft in 120 seconds, namely crane wheel race is shaped and also keeps 3-5mm allowance so that modified back fine finishining;
3) towards axis hole, heat treatment; The crane wheel all is shaped behind the axis hole, advances heat-treatment furnace and carries out the formation that positive temper suppresses the inside wheel net carbide and eliminate internal stress, to obtain the good interior tissue of wheel and to improve its toughness;
4) warehouse-in, modified, fine finishining, check, warehouse-in again; After the wheel modulation, further carry out the blank warehouse-in, carry out, after modified, the check, enter warehouse for finished product.
CN 201310126102 2013-04-12 2013-04-12 Once forming of die forging crane wheel Pending CN103331572A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201310126102 CN103331572A (en) 2013-04-12 2013-04-12 Once forming of die forging crane wheel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201310126102 CN103331572A (en) 2013-04-12 2013-04-12 Once forming of die forging crane wheel

Publications (1)

Publication Number Publication Date
CN103331572A true CN103331572A (en) 2013-10-02

Family

ID=49239812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201310126102 Pending CN103331572A (en) 2013-04-12 2013-04-12 Once forming of die forging crane wheel

Country Status (1)

Country Link
CN (1) CN103331572A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103624206A (en) * 2013-12-09 2014-03-12 无锡透平叶片有限公司 Method for removing oxide scales from surface of stainless steel blade forge piece
CN103753138A (en) * 2013-12-26 2014-04-30 马钢(集团)控股有限公司 Production method of railway wheels
CN106002111A (en) * 2016-08-14 2016-10-12 河南省矿山起重机有限公司 Crane single-beam walking wheel forging technology
CN110142362A (en) * 2019-05-28 2019-08-20 中冶重工(唐山)有限公司 The manufacturing process of lifting equipment wheel forging
CN110142361A (en) * 2019-05-28 2019-08-20 中冶重工(唐山)有限公司 The forging method of lifting equipment wheel forging

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103624206A (en) * 2013-12-09 2014-03-12 无锡透平叶片有限公司 Method for removing oxide scales from surface of stainless steel blade forge piece
CN103753138A (en) * 2013-12-26 2014-04-30 马钢(集团)控股有限公司 Production method of railway wheels
CN106002111A (en) * 2016-08-14 2016-10-12 河南省矿山起重机有限公司 Crane single-beam walking wheel forging technology
CN106002111B (en) * 2016-08-14 2018-04-17 河南省矿山起重机有限公司 A kind of crane single-beam traveling wheel forging technology
CN110142362A (en) * 2019-05-28 2019-08-20 中冶重工(唐山)有限公司 The manufacturing process of lifting equipment wheel forging
CN110142361A (en) * 2019-05-28 2019-08-20 中冶重工(唐山)有限公司 The forging method of lifting equipment wheel forging

Similar Documents

Publication Publication Date Title
CN102319992B (en) Method for manufacturing aluminum alloy die forging
CN103331572A (en) Once forming of die forging crane wheel
CN104907471A (en) Supporting wheel closed forging process and forging die
CN103706743B (en) Die-forging forming process of titanium-alloy forged drum piece
CN105642805B (en) The preparation method of housing
CN104015004A (en) Method for manufacturing aluminum alloy hub
CN103668027A (en) Quasi beta forging process for TC25 titanium alloy
CN102989986A (en) Forging technology of large TC4 alloy drum forged piece
CN103121075B (en) Hot forging method for transmission shaft yoke with horizontal yoke part
CN103990946A (en) Manufacturing method for H-shaped aluminum alloy hub
CN103008521A (en) Forming die for conic forgings and forming method thereof
CN101947633A (en) Die forging process and special die for final stage blade of large half-RPM (Revolution per Minute) nuclear turbine
CN104139147A (en) Forging method of SB564 UNS N06690 alloy large-scale internal T-shaped annular forge piece blank
CN104139279A (en) Manufacturing process for inner-trapezoid-groove ring piece
CN104191181A (en) Magnesium alloy wheel forging-spinning composite forming method
CN203265502U (en) Hot forging device for transmission shaft joint fork with horizontal fork part
CN104148428A (en) Cold extrusion forming method of axisymmetric pull rod joint part
CN101618500A (en) Production process of cycloidal gear of speed reducer
CN106623466A (en) Nuclear main pump shell hot extrusion forming technology
CN102179464B (en) Process for forming generator claw pole of vehicle
CN103464977B (en) A kind of manufacture method of irregular arm
CN102989989B (en) Forging process of heavy truck steering knuckle
CN102909298B (en) Forming method of forge piece with large torsional flange and spacer flange as well as forming mold
CN103706745A (en) Manufacturing method of damping shaft sleeve
CN109822021A (en) Rolloff forming method of C-shaped section forging

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131002