CN103326472A - Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit - Google Patents

Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit Download PDF

Info

Publication number
CN103326472A
CN103326472A CN2013102911692A CN201310291169A CN103326472A CN 103326472 A CN103326472 A CN 103326472A CN 2013102911692 A CN2013102911692 A CN 2013102911692A CN 201310291169 A CN201310291169 A CN 201310291169A CN 103326472 A CN103326472 A CN 103326472A
Authority
CN
China
Prior art keywords
station
intelligent
wall
information
information sharing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102911692A
Other languages
Chinese (zh)
Inventor
张凌
黄滇生
文华
何永东
胡祖伟
杨晴
张志生
孔令匀
杨文波
何光树
王德智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dali Power Supply Bureau Of Yunnan Power Grid Corp
Yunnan Electric Power Experimental Research Institute Group Co Ltd of Electric Power Research Institute
Kunming Enersun Technology Co Ltd
Original Assignee
Dali Power Supply Bureau Of Yunnan Power Grid Corp
Yunnan Electric Power Experimental Research Institute Group Co Ltd of Electric Power Research Institute
Kunming Enersun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dali Power Supply Bureau Of Yunnan Power Grid Corp, Yunnan Electric Power Experimental Research Institute Group Co Ltd of Electric Power Research Institute, Kunming Enersun Technology Co Ltd filed Critical Dali Power Supply Bureau Of Yunnan Power Grid Corp
Priority to CN2013102911692A priority Critical patent/CN103326472A/en
Publication of CN103326472A publication Critical patent/CN103326472A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses an information sharing and interoperating method for intelligent electrical devices of an intelligent substation operation cockpit. The information shearing and interoperating method is used for realizing information sharing and interoperability between the intelligent electrical appliances in a digital transformer substation according to a layered distribution way. The realizing process of the information sharing and interoperating method is as follows: dividing the electrical appliance of the intelligent power station into a station control layer, a partition layer and a process layer. The information sharing and interoperating method for the intelligent electrical devices of the intelligent substation operation cockpit has the advantages that seamless communication protocol standards based on the new-generation transformer substation are IEC (International Electrotechnical Commission) 61850 standards; and the information sharing and interoperability between the intelligent electrical appliances in the digital transformer substation are realized according to a layered distribution way.

Description

Intelligence power transformation operation driving cabin intelligent electric facility information Share and interoperability method
Technical field
The present invention relates to the automatic control of transformer station, database technology, IEC61850 communication protocol, GOOSE communication protocol, layer distributed management mode, particularly intelligent electric facility information Share and interoperability method method.
Background technology
In today of the develop rapidly of intelligent substation technology and equipment operation management content generation great change, the business such as power transformation operation fail to combine closely with technical development, seriously restricted the lifting of substation operation level, power transformation operation strides forward extremely urgent to intellectuality.
Foundation breaks traditions, height integration, information sharing, running be efficiently based on the power transformation operation " driving cabin " of intellectualized technology, promote power transformation operation management work march toward intellectuality, informationization, lean by " driving cabin " comprehensively, make intelligent substation really become " the strong node " of intelligent grid.
The construction of intelligent substation operation driving cabin depends on the interoperability between sharing of intelligent electric facility information in the station and the intelligent electric equipment, at present, these device datas share and the interoperability of equipment not enough accurately, in time, comprehensively, reliable.
Summary of the invention
Intelligence power transformation operation driving cabin intelligent electric facility information Share and interoperability method, seamless communication consensus standard based on transformer station of new generation is the IEC61850 standard, realizes information sharing and the interoperability of intelligent electric equipment room in the digital transformer substation by layered distribution type.Realization flow of the present invention is as follows:
The Intelligent Power Station electric equipment is divided into station level, wall, three layers of process layers:
(1), station level is by monitoring host computer, operator station, these electric equipments of engineer station form; Wherein:
1. monitoring host computer, by various operating systems, Database Systems and application software consist of, and effect is collection, processing, storage, display data, realizes that the panorama of all intelligent electric equipment in the station is showed and monitoring;
2. operator station comprises Substation Operating system and application software, from the host schedules data, to realize operation monitoring and the control of transformer station;
3. the engineer station by the system maintenance librarian use, possesses state-detection, parameter detecting, these functions of data modification to station equipment;
(2), wall comprises relaying protection and protective device, these smart machines of measure and control device, wherein:
1. wall and station level adopt the IEC61850-8-1 protocol communication;
2. adopt different cell devices according to different electric pressures;
The wall collection and process once, the parameter information of secondary device, state information; And the communication standard that these information exchanges are excessively certain transmits;
(3), process layer comprises the Big Dipper, GPS, switch twisted-pair feeder equipment is realized the communication of station level and wall isomery equipment, wherein:
1. the sample information of wall and process layer comprehensive intelligent terminal adopts the IEC61850-9-2 protocol communication, and the GOOSE information of wall and process layer comprehensive intelligent terminal adopts the GOOSE protocol communication;
2. adopt star-like fiber optic network framework, research and development merge cells, the two-in-one process layer comprehensive intelligent terminal of intelligent terminal, the collection of the signals such as the collection of realization digital sampled signal and switch tool, the outdoor group screen of process terminal is installed on the switch next door on the spot.
The invention has the advantages that, be the IEC61850 standard based on the seamless communication consensus standard of transformer station of new generation, realizes information sharing and the interoperability of intelligent electric equipment room in the digital transformer substation by layered distribution type.
Further set forth content of the present invention below in conjunction with drawings and Examples.
Description of drawings
Fig. 1 is the inventive method structural representation.
Embodiment
Intelligence power transformation operation driving cabin intelligent electric facility information Share and interoperability method, seamless communication consensus standard based on transformer station of new generation is the IEC61850 standard, realizes information sharing and the interoperability of intelligent electric equipment room in the digital transformer substation by layered distribution type.Its realization flow is as follows:
The Intelligent Power Station electric equipment is divided into station level, wall, three layers of process layers:
(1), station level is by monitoring host computer, operator station, these electric equipments of engineer station form; Wherein:
1. monitoring host computer, by various operating systems, Database Systems and application software consist of, and effect is collection, processing, storage, display data, realizes that the panorama of all intelligent electric equipment in the station is showed and monitoring;
2. operator station comprises Substation Operating system and application software, from the host schedules data, to realize operation monitoring and the control of transformer station;
3. the engineer station by the system maintenance librarian use, possesses state-detection, parameter detecting, these functions of data modification to station equipment;
(2), wall comprises relaying protection and protective device, these smart machines of measure and control device, wherein:
1. wall and station level adopt the IEC61850-8-1 protocol communication;
2. adopt different cell devices according to different electric pressures;
The wall collection and process once, the parameter information of secondary device, state information; And the communication standard that these information exchanges are excessively certain transmits;
(3), process layer comprises the Big Dipper, GPS, switch twisted-pair feeder equipment is realized the communication of station level and wall isomery equipment, wherein:
1. the sample information of wall and process layer comprehensive intelligent terminal adopts the IEC61850-9-2 protocol communication, and the GOOSE information of wall and process layer comprehensive intelligent terminal adopts the GOOSE protocol communication;
2. adopt star-like fiber optic network framework, research and development merge cells, the two-in-one process layer comprehensive intelligent terminal of intelligent terminal, the collection of the signals such as the collection of realization digital sampled signal and switch tool, the outdoor group screen of process terminal is installed on the switch next door on the spot.

Claims (1)

1. intelligent power transformation operation driving cabin intelligent electric facility information Share and interoperability method is characterized in that, realizes information sharing and the interoperability of intelligent electric equipment room in the digital transformer substation by layered distribution type; Its realization flow is as follows:
The Intelligent Power Station electric equipment is divided into station level, wall, three layers of process layers:
(1), station level is by monitoring host computer, operator station, these electric equipments of engineer station form; Wherein:
1) monitoring host computer, by various operating systems, Database Systems and application software consist of, and effect is collection, processing, storage, display data, realizes that the panorama of all intelligent electric equipment in the station is showed and monitoring;
2) operator station comprises Substation Operating system and application software, from the host schedules data, to realize operation monitoring and the control of transformer station;
3) engineer station by the system maintenance librarian use, possesses state-detection, parameter detecting, these functions of data modification to station equipment;
(2), wall comprises relaying protection and protective device, these smart machines of measure and control device, wherein:
1) wall and station level adopt the IEC61850-8-1 protocol communication;
2) adopt different cell devices according to different electric pressures;
3) the wall collection and process once, the parameter information of secondary device, state information; And the communication standard that these information exchanges are excessively certain transmits;
(3), process layer comprises the Big Dipper, GPS, switch twisted-pair feeder equipment is realized the communication of station level and wall isomery equipment, wherein:
1) sample information of wall and process layer comprehensive intelligent terminal adopts the IEC61850-9-2 protocol communication, and the GOOSE information of wall and process layer comprehensive intelligent terminal adopts the GOOSE protocol communication;
2) adopt star-like fiber optic network framework, research and development merge cells, the two-in-one process layer comprehensive intelligent terminal of intelligent terminal, the collection of the signals such as the collection of realization digital sampled signal and switch tool, the outdoor group screen of process terminal is installed on the switch next door on the spot.
CN2013102911692A 2013-07-11 2013-07-11 Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit Pending CN103326472A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102911692A CN103326472A (en) 2013-07-11 2013-07-11 Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102911692A CN103326472A (en) 2013-07-11 2013-07-11 Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit

Publications (1)

Publication Number Publication Date
CN103326472A true CN103326472A (en) 2013-09-25

Family

ID=49195073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102911692A Pending CN103326472A (en) 2013-07-11 2013-07-11 Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit

Country Status (1)

Country Link
CN (1) CN103326472A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103679561A (en) * 2013-12-24 2014-03-26 云南电力调度控制中心 Display system structure of power dispatching operation cockpit and realizing method thereof
CN104238497A (en) * 2014-08-11 2014-12-24 广东电网公司电力科学研究院 Power grid across-business integrated remote regulation and control system
CN104660709A (en) * 2015-03-12 2015-05-27 国家电网公司 Domestic data acquisition system based on IEC61850 and working method of domestic data acquisition system
CN105242593A (en) * 2015-09-21 2016-01-13 中国南方电网有限责任公司 Automatic interconnection system for IOT (Internet of Things) intelligent secondary equipment
CN107546778A (en) * 2017-08-21 2018-01-05 许继集团有限公司 A kind of power station intelligence in-situ control system and method based on IEC61850 standards

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101789624A (en) * 2009-12-09 2010-07-28 中国电力科学研究院 Centralized digital transformer substation system

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101789624A (en) * 2009-12-09 2010-07-28 中国电力科学研究院 Centralized digital transformer substation system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
周勇等: "智能化变电站的系统结构及应用", 《大众用电》 *
邱爱兵: "35 kV 变电站综合自动化系统的设计与实践", 《电气时代》 *
郑华珍等: "110 kV 数字化变电站综合自动化系统的智能化改造", 《电气时代》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103679561A (en) * 2013-12-24 2014-03-26 云南电力调度控制中心 Display system structure of power dispatching operation cockpit and realizing method thereof
CN103679561B (en) * 2013-12-24 2017-01-04 云南电力调度控制中心 A kind of power scheduling runs display system architecture and its implementation of driving cabin
CN104238497A (en) * 2014-08-11 2014-12-24 广东电网公司电力科学研究院 Power grid across-business integrated remote regulation and control system
CN104660709A (en) * 2015-03-12 2015-05-27 国家电网公司 Domestic data acquisition system based on IEC61850 and working method of domestic data acquisition system
CN104660709B (en) * 2015-03-12 2017-10-31 国家电网公司 A kind of electricity consumption data acquisition system and its method of work based on IEC61850
CN105242593A (en) * 2015-09-21 2016-01-13 中国南方电网有限责任公司 Automatic interconnection system for IOT (Internet of Things) intelligent secondary equipment
CN107546778A (en) * 2017-08-21 2018-01-05 许继集团有限公司 A kind of power station intelligence in-situ control system and method based on IEC61850 standards
CN107546778B (en) * 2017-08-21 2020-02-21 许继集团有限公司 Hydropower station intelligent in-situ control system and method based on IEC61850 standard

Similar Documents

Publication Publication Date Title
CN102255389B (en) Method for implementing intensive intelligent substation based on intelligent power grid system
CN103414251A (en) Substation network communication simulation system based on IEC 61850
CN106532935B (en) For carrying out the method and its system of secondary system of intelligent substation fault diagnosis
CN102447305B (en) Topological anti-misoperation system for power grid
CN103366312A (en) Intelligent transformer substation cloud system
CN105071532A (en) Transformer station automatic system
CN103326472A (en) Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit
CN104410169A (en) Intelligent and online area monitoring system and implementation method thereof
CN203233236U (en) Digital protection, measurement and control integrated device
CN102306955B (en) Residential distribution automation system
CN103401316A (en) Integrated type monitoring and processing method for state data of intelligent power network equipment
CN104319886A (en) Power grid wide area protection and control system
CN203104116U (en) Unattended remote monitoring device for power transformation facilities
CN102832708B (en) Intelligent transformer substation based on integrated multi-stage server framework
CN202276196U (en) Intelligent monitoring terminal device of intelligent switchhouse
CN102868218A (en) Transition method for improving monitoring system in intelligent improvement of ordinary transformer substation
CN204089191U (en) Power distribution network multiple target is collaborative from the major clique system that becomes
CN203278060U (en) Intelligent box-type substation
CN205265371U (en) Transformer substation's long -range fortune dimension management and control device
CN105024454A (en) Transformer substation secondary equipment monitoring system
CN104537571A (en) GIS-based power dispatching data graphical display method
CN103545805A (en) Modeling-based railway power supply arm monitoring method
CN103439938A (en) Small hydropower station control system
CN101651361A (en) Integrated automation system of substation
CN203840058U (en) Substation secondary equipment monitoring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130925