CN103323184B - High-speed transplanter box parts airtight test device - Google Patents

High-speed transplanter box parts airtight test device Download PDF

Info

Publication number
CN103323184B
CN103323184B CN201310250735.5A CN201310250735A CN103323184B CN 103323184 B CN103323184 B CN 103323184B CN 201310250735 A CN201310250735 A CN 201310250735A CN 103323184 B CN103323184 B CN 103323184B
Authority
CN
China
Prior art keywords
casing
built
jig
speed transplanter
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310250735.5A
Other languages
Chinese (zh)
Other versions
CN103323184A (en
Inventor
田先民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI XIE CHANG HUO NING INDUSTRY DEVELOPMENT Co Ltd
Original Assignee
SHANGHAI XIE CHANG HUO NING INDUSTRY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI XIE CHANG HUO NING INDUSTRY DEVELOPMENT Co Ltd filed Critical SHANGHAI XIE CHANG HUO NING INDUSTRY DEVELOPMENT Co Ltd
Priority to CN201310250735.5A priority Critical patent/CN103323184B/en
Publication of CN103323184A publication Critical patent/CN103323184A/en
Application granted granted Critical
Publication of CN103323184B publication Critical patent/CN103323184B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

The invention discloses a kind of high-speed transplanter box parts airtight test device.Comprise several sealing clamp and sealing detent mechanism, described sealing clamp and sealing detent mechanism form built-up jig, clamp high-speed transplanter casing and seal the aperture of high-speed transplanter casing, be placed on and leak hunting in liquid casing, one of them sealing clamp is provided with air intake opening, another sealing detent mechanism is provided with exhausr port; Described air intake opening and air inlet stop valve UNICOM, described exhausr port and discharge line valve UNICOM.Be provided with in the described liquid casing that leaks hunting and erect two parallel guide rails, described built-up jig is provided with lifting angle sheave, and the piston pushing mechanism being built up in top is fixedly connected with built-up jig.Be provided with stand above the described liquid casing that leaks hunting, stand be respectively equipped with electric control unit, pneumatic control unit.The present invention tests simple and fast, realistic operating environment, have employed the positive compression testing device consistent with dynamically pressure value 6mpa, makes the environment detected closer to dynamic value.

Description

High-speed transplanter box parts airtight test device
Technical field
The present invention relates to the monomer mechanical field in traditional industry, particularly a kind of high-speed transplanter box parts airtight test device.
Background technology
High-speed transplanter is the type with high-tech content, has comfortable, high efficiency advantage, and have the trend of driving and riding car compared with legged type.High-speed transplanter has the types such as 4,5,6,8,10 row, and line number is more, and efficiency is higher, and price is high.General use 6 row type, engine is between 7-12 horsepower, and cost performance is comparatively suitable.
The effect of high-speed rice transplanter and common seedling transplanter contrasts, and result shows the advantage that high-speed transplanter has volume increase, increases income, work efficiency is fast, and it is lower than common seedling transplanter to hinder root rate, the maturity stage in advance, volume increase." rice is waste " is jeopardizing world food supply at present; as instrument very important in grain-production; development improves technology and the function of rice transplanter; not only can increase work efficiency, reduce labor intensity; grain quality can also be ensured, reduce production cost, increase economic efficiency, increase grain yield, solve current crisis in food.And high-speed transplanter box parts plays a very important effect when high-speed transplanter high-speed cruising, once casing leaks, the danger that rice transplanter will occur " killing ", the airtight measuring technology of high-speed transplanter box parts becomes the important step of product suggestion for this reason, to detect the leaks of box casting, guarantee the reliability of product.
Traditional airtight method of testing have employed negative pressure method, i.e. vacuum pumping method, testing complex, and practical effect is not good enough, and comparatively dynamic value differs greatly, and does not meet actual operating condition.
Summary of the invention
The object of the invention is to provide a kind of high-speed transplanter box parts airtight test device testing simple and fast, realistic operating environment.
The present invention includes several sealing clamp and sealing detent mechanism, described sealing clamp and sealing detent mechanism form built-up jig, clamp high-speed transplanter casing and seal the aperture of high-speed transplanter casing, be placed on and leak hunting in liquid casing, one of them sealing clamp is provided with air intake opening, another sealing detent mechanism is provided with exhausr port; Described air intake opening and air inlet stop valve UNICOM, described exhausr port and discharge line valve UNICOM.Described left side sealing clamp is provided with on the left of high-speed transplanter casing, described intermediate seal fixture is provided with in the middle part of high-speed transplanter casing, sealing clamp above being provided with on the upside of high-speed transplanter casing, on the right side of high-speed transplanter casing, be provided with right side sealing detent mechanism, below high-speed transplanter casing, be provided with lower side seals detent mechanism.Be provided with in the described liquid casing that leaks hunting and erect two parallel guide rails, described built-up jig is provided with lifting angle sheave, and the piston pushing mechanism be built up in above built-up jig is fixedly connected with built-up jig.Be provided with stand above the described liquid casing that leaks hunting, stand be respectively equipped with electric control unit, pneumatic control unit.Electric control unit comprises general supply, fuse, the first via is starting switch, pressure switch, and time relay time delay is broken contact, time relay coil, second tunnel is the instantaneous normally opened contact of the time relay, warning lamp, and the 3rd tunnel is working table lamp switch, portable lamp, the first via, the second road and the 3rd tunnel are in parallel, and break contact, time relay coil of Switching Power Supply, electromagnetic valve coil and time relay time delay is in parallel; In pneumatic control unit, pressurized air is divided into two tunnels by total air intake opening: a road is through reduction valve, tensimeter, air inlet stop valve, pressure switch, built-up jig, discharge line valve, and leak hunting exhausr port; Second tunnel controls exhausr port through the cylinder of solenoid valve reversal valve, upper one-way speed-regulating valve, piston pushing mechanism, lower one-way speed-regulating valve, air pressure.
Piston pushing mechanism in the present invention: make easy and simple to handle laborsaving using pressurized air as power, cylinder is had to drive built-up jig to be dipped in side leakage liquid, it has pressure switch to control, detect in built-up jig and whether have air pressure, and whether air pressure is arranging in scope, plays one and prevent not open air inlet stop valve to leak hunting and air pressure that other reasons causes is not arranging the idle error prevention device of scope inner carrier pushing mechanism.Have employed the positive compression testing device consistent with dynamically pressure value 6mpa, make the environment detected closer to dynamic value.
Accompanying drawing explanation
Fig. 1 high-speed transplanter box parts test device for air tightness front view.
Fig. 2 high-speed transplanter box parts test device for air tightness side view.
Fig. 3 high-speed transplanter box parts test device for air tightness stand figure.
Fig. 4 high-speed transplanter box parts test device for air tightness built-up jig mechanism map.
Fig. 5 high-speed transplanter box parts test device for air tightness electrical schematic diagram.
Fig. 6 high-speed transplanter box parts test device for air tightness pneumatic schematic diagram.
1. total air intake opening 3. piston pushing mechanism 4. general supply 5. stand 6. high-speed transplanter box parts 7. built-up jig 8. of the warning lamp 2. sealing clamp 22. intermediate seal fixture 23. that to leak hunting on the left of fluid box 9. tap hole 10. built-up jig air intake opening 11. electric control unit 12. starting switch 13. pneumatic control unit 14. reduction valve 15. tensimeter 16. pressure switch 17. Switching Power Supply 18. fixture discharge line valve 19. fixture air inlet stop valve 21. seals detent mechanism 25. lower side seals detent mechanism 31 on the right side of sealing clamp 24. above and is elevated angle sheave 32 guide rail 39 cylinder, 51 fuses, 53 time relay time delays are broken contact, 54 time relay coils, 56 electromagnetic valve coils, 57 working table lamp switches, 58. portable lamps, 61 solenoid directional control valves, one-way speed-regulating valve on 62, 63 times one-way speed-regulating valves, 64 leak hunting exhausr port, 65 air pressure control exhausr port.
Embodiment
The present invention includes several sealing clamp and sealing detent mechanism, described sealing clamp and sealing detent mechanism form built-up jig 7, clamp high-speed transplanter box parts 6 and seal the aperture of high-speed transplanter box parts 6, be placed on and leak hunting in liquid casing 8, one of them sealing clamp is provided with air intake opening 10, another sealing detent mechanism is provided with exhausr port; Described air intake opening and air inlet stop valve 19 UNICOM, described exhausr port and discharge line valve UNICOM 18.Described left side sealing clamp 21 is provided with on the left of high-speed transplanter box parts 6, described intermediate seal fixture 22 is provided with in the middle part of high-speed transplanter box parts 6, sealing clamp 23 above being provided with on the upside of high-speed transplanter box parts 6, on the right side of high-speed transplanter box parts 6, be provided with right side sealing detent mechanism 24, below high-speed transplanter box parts 6, be provided with lower side seals detent mechanism 25.Be provided with in the described liquid casing 8 that leaks hunting and erect two parallel guide rails 32, described built-up jig is provided with four lifting angle sheaves 31, and the piston pushing mechanism 3 be built up in above built-up jig is fixedly connected with built-up jig.Be provided with tap hole 9 below the described liquid casing 8 that leaks hunting, top is provided with stand 5, stand 5 is respectively equipped with electric control unit 11, pneumatic control unit 13.
Electric control unit 11 comprises general supply 4, fuse 51, starting switch 12, pressure switch 16, time relay time delay is broken contact 53, time relay coil 54, the instantaneous normally opened contact 55 of the time relay, warning lamp 1, Switching Power Supply 17, electromagnetic valve coil 56, working table lamp switch 57, working table lamp 58.Press starting switch 12, time relay coil 54 obtains electric by the time delay break contact 53 of starting switch 12 and pressure switch 16 and the time relay, pressure switch 16 is just closed under built-up jig is connected with compressed-air actuated situation, so just ensure could start under built-up jig is connected with compressed-air actuated situation, now the instantaneous normally opened contact 55 of the time relay closes, to starting switch 12 self-insurance, the time relay starts timing, warning lamp 1 glimmers, Switching Power Supply 17 obtains electric work, for electromagnetic valve coil 56 is powered, setting-up time disconnects to the time delay break contact 53 of the time relay, time relay coil 54 dead electricity, the instantaneous normally opened contact 55 of the time relay disconnects, warning lamp 1 stops flicker, Switching Power Supply 17 dead electricity, electromagnetic valve coil 56 dead electricity, electrical equipment all resets, get ready for starting next time.
Pneumatic control unit 13 comprises reduction valve 14, tensimeter 15, air inlet stop valve 19, pressure switch 16, discharge line valve 18, solenoid directional control valve 61, upper one-way speed-regulating valve 62, lower one-way speed-regulating valve 63, the cylinder 31 of piston pushing mechanism, electromagnetic valve coil 64.Pressurized air is divided into two tunnels by total air intake opening 2: a road is through reduction valve 14, tensimeter 15, air inlet stop valve 19, built-up jig, discharge line valve 18, and leak hunting exhausr port 64; Second tunnel is through the cylinder 31 of solenoid valve reversal valve 61, upper one-way speed-regulating valve 62, lower one-way speed-regulating valve 63, piston pushing mechanism, and air pressure controls exhausr port 65.Reduction valve 14 is that adjustment enters built-up jig test gas pressure (before work, pressure being transferred to required value).Close air inlet stop valve 19, open discharge line valve 18, workpiece is loaded onto in built-up jig, close discharge line valve 18, open air inlet stop valve 19, for built-up jig inflation, pressure switch 16 detection system pressure is that startup is got ready simultaneously, press starting switch 12, electromagnetic valve coil 14 obtains electric, solenoid valve commutation gas circuit is by upper one-way speed-regulating valve 62, lower one-way speed-regulating valve 63 makes cylinder 39 work, piston promotes built-up jig and moves downward, upper one-way speed-regulating valve 62, lower one-way speed-regulating valve 63 is adjusting cylinders 39 movement velocitys, make its at the uniform velocity easy motion, setting-up time is to electromagnetic valve coil 64 dead electricity, solenoid valve return piston promotes built-up jig and moves upward, move to clamping position, whole circulation terminates.
Described stand 5 is respectively equipped with: electrical control unit 11, pneumatic control unit 13, reduction valve 14, tensimeter 15, pressure switch 16, Switching Power Supply 17, fixture air inlet stop valve 18, fixture discharge line valve 19, electrical control unit 11 are connected with tensimeter 15 with starting switch 12, pneumatic control unit 13 respectively by wire, pneumatic control unit 13 is connected with piston pushing mechanism 3 respectively by gas circuit, and pressure switch 16 is connected with pneumatic control unit 13 with electrical control unit 11.
Built-up jig in the present invention: built-up jig air intake opening 10 hydraulic quick coupler makes replacing product quick and convenient, and this fixture product has: PT000 is serial, PT100 is serial, PR181 is serial, PR159 is serial, 5T01 is serial.This fixture can reach 5-6 to the sealing surface of workpiece, so the right side adopts in fixture: right side sealing detent mechanism 24, adopt below: lower side seals connects detent mechanism 25, adopt above: sealing clamp 23 above, the right side adopts: left side sealing clamp 21.Middle for not interfering other location so adopt: intermediate seal fixture 22, make fixture operation convenient like this, cost of manufacture is low.
The liquid that leaks hunting in the present invention: because the material major part of high-speed transplanter box parts is ironcasting, be very easy to get rusty, so the requirement to the liquid that leaks hunting: one is antirust, two liquid are as clear as crystal, and three want garbage energy automatically to precipitate.What in the liquid that leaks hunting in the present invention, solvent adopted in industrial pure water tap water is chloride too high, and solute adopts semi-synthetic cuttings liquid, with the percentage by weight proportioning of 5%.Making to leak hunting, liquid is as clear as crystal, the automatic sedimentation function of rubbish is good, rust-preventing characteristic well generally can keep a week.
Feature of the present invention: detect data admission pressures, continue air pressure, the dwell time presets, freely, result understands fast in operation, and test is correct, mistake proofing front, detection means science.
principle of work
1 operation prepares:
Open source of the gas, inspection measuring pressure≤5.5kg/cm2, closes built-up jig gas admittance valve, opens built-up jig vent valve, opening power, arrange the dwell time.
2 methods of operating
To detect a certain part of high-speed transplanter casing, the lower side seals be placed on by measured piece on built-up jig 7 connects on detent mechanism 25, and sealing connects on detent mechanism 24 on the right side of being close to the right, operation left side sealed clamping structure 21, be that it clamps left, operate sealed clamping structure 23 above simultaneously, compress downwards, operation intermediate seal clamp system 22, seals the side leakage mouth of centre.Close built-up jig vent valve 18, open built-up jig gas admittance valve 19, if simultaneously pressure switch 16 starts to detect air pressure "Yes" "No" in built-up jig automatically arranging arrange in scope just can starting switch 12 in scope, if just do not started arranging starting switch 12 in scope.Starting switch 12, warning lamp 1 glimmers, electrical control unit 12 works, dwell time starts timing, pneumatic control unit 13 works, piston pushing mechanism 3 is started working, promotion built-up jig moves downward, and is that its built-up jig 7 is immersed in together with workpiece and leaks hunting in liquid, the leak condition of observation period workpiece, after dwell time arrives, electrical control unit 11 controls pneumatic control unit 13, makes piston pushing mechanism 3 drive built-up jig 7 to move upward, and arrives the position of clamping, pull down workpiece, whole airtight test procedure terminates.

Claims (2)

1. high-speed transplanter box parts airtight test device, it is characterized in that: comprise several sealing clamp and sealing detent mechanism, described sealing clamp and sealing detent mechanism form built-up jig, clamp high-speed transplanter casing and seal the aperture of high-speed transplanter casing, be placed on and leak hunting in liquid casing, one of them sealing clamp is provided with air intake opening, another sealing detent mechanism is provided with exhausr port; Described air intake opening and air inlet stop valve UNICOM, described exhausr port and discharge line valve UNICOM; Left side sealing clamp is provided with on the left of high-speed transplanter casing, intermediate seal fixture is provided with in the middle part of high-speed transplanter casing, sealing clamp above being provided with on the upside of high-speed transplanter casing, on the right side of high-speed transplanter casing, be provided with right side sealing detent mechanism, below high-speed transplanter casing, be provided with lower side seals detent mechanism; Be provided with in the described liquid casing that leaks hunting and erect two parallel guide rails, described built-up jig is provided with lifting angle sheave, and the piston pushing mechanism be built up in above built-up jig is fixedly connected with built-up jig; Stand is provided with above the described liquid casing that leaks hunting, described stand is respectively equipped with electric control unit, pneumatic control unit, electric control unit comprises general supply, fuse, the first via is starting switch, contact and time relay coil are broken in pressure switch, time relay time delay, second tunnel is the instantaneous normally opened contact of the time relay and warning lamp, 3rd tunnel is working table lamp switch and portable lamp, the first via, the second road and the 3rd tunnel are in parallel, and break contact, time relay coil of Switching Power Supply, electromagnetic valve coil and time relay time delay is in parallel; In pneumatic control unit, pressurized air is divided into two tunnels by total air intake opening: a road is through reduction valve, tensimeter, air inlet stop valve, pressure switch, built-up jig, discharge line valve, and leak hunting exhausr port; Second tunnel controls exhausr port through the cylinder of solenoid valve reversal valve, upper one-way speed-regulating valve, piston pushing mechanism, lower one-way speed-regulating valve, air pressure.
2. high-speed transplanter box parts airtight test device according to claim 1, is characterized in that: in the liquid that leaks hunting, solvent adopts industrial pure water, and solute adopts semi-synthetic cuttings liquid, with the percentage by weight proportioning of 5%.
CN201310250735.5A 2013-06-21 2013-06-21 High-speed transplanter box parts airtight test device Expired - Fee Related CN103323184B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310250735.5A CN103323184B (en) 2013-06-21 2013-06-21 High-speed transplanter box parts airtight test device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310250735.5A CN103323184B (en) 2013-06-21 2013-06-21 High-speed transplanter box parts airtight test device

Publications (2)

Publication Number Publication Date
CN103323184A CN103323184A (en) 2013-09-25
CN103323184B true CN103323184B (en) 2016-03-16

Family

ID=49192075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310250735.5A Expired - Fee Related CN103323184B (en) 2013-06-21 2013-06-21 High-speed transplanter box parts airtight test device

Country Status (1)

Country Link
CN (1) CN103323184B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105043678B (en) * 2015-09-09 2018-04-03 浙江施克汽车配件有限公司 A kind of air-tightness detection device
CN117101248B (en) * 2023-10-23 2023-12-29 启东威诺冶金机械设备有限公司 Sealing detection device for stop valve

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3207732B2 (en) * 1995-11-20 2001-09-10 ダイハツ工業株式会社 Fuel tank airtightness test equipment
JP2010032391A (en) * 2008-07-29 2010-02-12 Kurita Water Ind Ltd Sealability testing device of joint of pipe made of bonded synthetic resin, and sealability test method of joint of pipe made of bonded synthetic resin using the device
CN201413224Y (en) * 2009-06-16 2010-02-24 浙江景宁洁净钢管有限公司 Steel tube seamless checkout gear
CN201795904U (en) * 2010-09-07 2011-04-13 重庆长安新兴汽车配件有限责任公司 Oil tank air tightness detector
CN203385530U (en) * 2013-06-21 2014-01-08 上海协昌霍宁实业发展有限公司 Airtightness testing apparatus for box part of high-speed rice transplanter

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3207732B2 (en) * 1995-11-20 2001-09-10 ダイハツ工業株式会社 Fuel tank airtightness test equipment
JP2010032391A (en) * 2008-07-29 2010-02-12 Kurita Water Ind Ltd Sealability testing device of joint of pipe made of bonded synthetic resin, and sealability test method of joint of pipe made of bonded synthetic resin using the device
CN201413224Y (en) * 2009-06-16 2010-02-24 浙江景宁洁净钢管有限公司 Steel tube seamless checkout gear
CN201795904U (en) * 2010-09-07 2011-04-13 重庆长安新兴汽车配件有限责任公司 Oil tank air tightness detector
CN203385530U (en) * 2013-06-21 2014-01-08 上海协昌霍宁实业发展有限公司 Airtightness testing apparatus for box part of high-speed rice transplanter

Also Published As

Publication number Publication date
CN103323184A (en) 2013-09-25

Similar Documents

Publication Publication Date Title
CN203894011U (en) Air tightness detection apparatus of automotive intake hose
CN204255581U (en) A kind of enmgine exhaust air-tightness detection device
CN201364226Y (en) Hydraulic tester for testing air tightness of pipeline connecting pieces
CN203298937U (en) Valve test pressure source
CN201506705U (en) Liquid filling device
CN203283422U (en) Vacuum heat-sealing mechanism for automatic vacuum package machine
CN204831703U (en) ABS solenoid valve seals accredited testing organization
CN103323184B (en) High-speed transplanter box parts airtight test device
CN205808649U (en) Bottled water leak tester
CN202210013U (en) Bend pipe airtightness testing machine
CN103234714B (en) A kind of high-capacity dynamical lithium-ion explosion-proof valve leak-testing apparatus and detection method thereof
CN208313722U (en) A kind of U heat exchange pressure testing device
CN203385530U (en) Airtightness testing apparatus for box part of high-speed rice transplanter
CN202673653U (en) Air compressor vacuum pump overall performance experimental table
CN207050924U (en) A kind of end cap structure for pressure test
CN205183181U (en) Machine is examined to automatic gas tightness helium of square power battery
CN204115978U (en) The pump housing air-tightness detection device of urea volume pump
CN202631200U (en) Air-tightness inspection equipment
CN102749177B (en) Submerged air leakage test device for bicycle front fork casts
CN202710259U (en) Pressure testing machine for testing water pressure of valves used on water pipeline
CN106768679A (en) A kind of turbocharger waterway sealing propertytest system and method
CN211121832U (en) Dry type automatic leakage detector for diesel engine body
CN201819780U (en) Pressure detection equipment for container
CN2903951Y (en) Air inlet pipe blasting tester for automobile engine
CN203719845U (en) Helium detection device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160316