CN103306302A - Shafting load preadjusting method of metered spring base - Google Patents
Shafting load preadjusting method of metered spring base Download PDFInfo
- Publication number
- CN103306302A CN103306302A CN2012100578243A CN201210057824A CN103306302A CN 103306302 A CN103306302 A CN 103306302A CN 2012100578243 A CN2012100578243 A CN 2012100578243A CN 201210057824 A CN201210057824 A CN 201210057824A CN 103306302 A CN103306302 A CN 103306302A
- Authority
- CN
- China
- Prior art keywords
- bearing
- load
- spring
- elevation
- absolute altitude
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Measurement Of Mechanical Vibrations Or Ultrasonic Waves (AREA)
Abstract
The invention relates to a shafting load preadjusting method of a metered spring base. The method sequentially comprises the following steps of (1) collecting the elevation hi of a rigid base bearing and a spring with the rigid Ki of a spring base corresponding to the bearing; (2) obtaining a relation between a bearing load and the elevation hi at a constant speed under the rigid base by adopting a transfer matrix method; (3) obtaining the stroke of the spring; (4) solving a reynolds equation by adopting a finite element method so as to obtain the floating amount of a shaft neck under a bearing load condition; (5) obtaining the elevation of the bearing; (6) replacing hi by use of the elevation of the bearing according to the f(hi) obtained in the step (2) so as to obtain an iterated bearing load; (7) returning to the steps (3)-(7) in due time; (8) obtaining the real load and practical elevation of the bearing at a constant speed under the spring base; and (9) obtaining the preadjusting amount delta of the elevation of the bearing. The method provided by the invention can be used for effectively improving the stability of the bearing and reducing the low-frequency vibration of the bearing and is wide in application prospect.
Description
Technical field
The present invention relates to a kind of axle that counts spring foundation is the load pre-adaptation method, and particularly relating to a kind of fault diagnosis of Power Machinery Engineering power plant equipment and the axle that counts spring foundation of processing technology field is the load pre-adaptation method.
Background technology
Along with increase and the manufacturing development of electricity needs, the Turbo-generator Set single-machine capacity is increasing, the support post on conventional basis bear because of axle be that the dead load of the dynamic load that brings such as remaining mass unbalance and unit body is also increasing.Adopt the nuclear power Turbo-generator Set of saturated vapour acting, in order to export same power, it is through-flow and long-pending much larger than conventional power plant that the nuclear power Turbo-generator Set needs, and more increased the load of support post.If adopt conventional basis, will cause support post quite thick, make civil engineering cost increase, but the equipment arrangement space is dwindled; If the employing flexible foundation then can make monoblock basic platform and institute's installed device and bottom foundation framework break away from the power coupling, and then simplify ground basic stress situation, reduce basic column size, increase installation space, and save the high thick platform of cost.The spring vibration isolation device that damper is installed simultaneously can also be decayed because of the high amplitude of crossing that produces in earthquake and the unit running process, and protection equipment does not suffer damage.Therefore, Turbo-generator Set adapted spring foundation becomes a kind of development trend gradually, and a lot of countries are also adopting the spring vibration isolation basis as the preferred option in the international generating set tender standard manual.
Along with the construction of introducing unit, China successively also uses spring foundation at gulf, field nuclear power station 2 * 1060MW, mountain range Australia nuclear power station 2 * 1000MW, Dabie Mountain, Huang gang power plant 2 * 600MW, duck river mouth, the Henan 2 * 350MW of power plant, more than 40 units such as the 2 * 350MW of Hefei two power plant, the 2 * 200MW of Beijing No.1 Heat and Power Plant, in addition also sunshine power plant, Taishan Electric Power Plant, decide also to have used spring foundation on the steam feed pump of power plant such as continent power plant, three phases of Waigaoqiao Bonded Zone, power plant, state Huaning sea, this has all shown the popularization of present spring foundation.Yet up to now, China relatively lags behind to the research of spring foundation, and its technology is grasped neither be very ripe, does not still have special design, installation and operating specification at the Turbo-generator Set spring foundation.
The greatest problem that Turbo-generator Set adapted spring unit brings supports the dynamic stiffness variation of (comprising rigidity and damping etc.) exactly, the shaft system of unit dynamic analysis that is the conventional concrete basis can be done rigid treatment to the basis, and the shaft system of unit dynamic analysis of adapted spring foundation then must be considered the influence of soil rigidity and damping.Therefore, probing into the axle that counts spring foundation is the load pre-adaptation method, installs with the shaft system of unit that instructs the adapted spring foundation, just has important theoretical meaning and more practical value.
Summary of the invention
It is the load pre-adaptation method that the technical problem to be solved in the present invention provides a kind of axle that counts spring foundation that improves bearing stability.
For solving the problems of the technologies described above, a kind of axle that counts spring foundation of the present invention is the load pre-adaptation method, may further comprise the steps successively:
(1) gather rigid foundation bearing absolute altitude h, and the stiffness K on bearing corresponding spring basis
The i spring, i=1,2 ... I, I is the number of middle (center) bearing for axle;
(2) adopt transfer matrix method, obtain under the rigid foundation constant speed operating mode lower bearing load
With absolute altitude h
iBetween relation;
(4) adopt Finite Element, by finding the solution Reynolds equation, obtain bearing load
Under the operating mode, the floatation volume of axle journal
(6) according to f (h in the step (2)
i), use the bearing absolute altitude
Substitute h
i, obtain the bearing load of iteration
(8) when
Obtain under the spring foundation real load of constant speed operating mode lower bearing
And actual elevation
(9) obtain the pre-adjustment amount Δ of bearing absolute altitude;
Install under the operating mode than static state, the influence that Turbo-generator Set is floated by basic telescopic spring and axle journal, its axle under operation condition is that the absolute altitude situation will take place than obvious variation, and then causes that axle is redistributing of load.How to predict that this variable quantity just becomes particularly important to realize a pre-adjustment that is load.Adopt the inventive method can effectively improve bearing stability, reduce the bearing low frequency vibration, be with a wide range of applications.
Description of drawings
Fig. 1 is horizontal low frequency vibration figure before No. 11 bearings of No. 1 unit of gulf, field nuclear power station are optimized.
Fig. 2 is vertical low frequency vibration figure before No. 11 bearings of No. 1 unit of gulf, field nuclear power station are optimized.
Fig. 3 is horizontal low frequency vibration figure after No. 11 bearing optimization of No. 1 unit of gulf, field nuclear power station.
Fig. 4 is vertical low frequency vibration figure after No. 11 bearing optimization of No. 1 unit of gulf, field nuclear power station.
The specific embodiment
The present invention is further detailed explanation below in conjunction with drawings and Examples.
The present invention may further comprise the steps successively:
(1) gathers rigid foundation bearing absolute altitude h
i, and the stiffness K on bearing corresponding spring basis
The i spring, i=1,2 ... I, I is the number of middle (center) bearing for axle;
(2) adopt transfer matrix method, obtain under the rigid foundation constant speed operating mode lower bearing load
With absolute altitude h
iBetween relation;
(3) obtain the stroke of spring
(4) adopt Finite Element, by finding the solution Reynolds equation, obtain bearing load
Under the operating mode, the floatation volume of axle journal
(6) according to f (h in the step (2)
i), use the bearing absolute altitude
Substitute h
i, obtain the bearing load of iteration
(8) when
Obtain under the spring foundation real load of constant speed operating mode lower bearing
And actual elevation
(9) obtain the pre-adjustment amount Δ of bearing absolute altitude;
Utilize the present invention in the T103 of No. 1 unit of gulf, field nuclear power station maintenance, 13 spring bearings are advanced theoretical analysis and calculation, thinking needs to break through the relevant installation code that manufactory provides, and in the T103 overhaul, No. 10, No. 11 bearing absolute altitudes are adjusted, that is: (1) No. 10 bearing absolute altitude reduces 0.1mm; (2) according to the bearing absolute altitude, the shaft coupling deviation between No. 10 and No. 11 bearings is adjusted into 0.255mm.The maintenance back starts to be found: this is to have adjusted this unit not enough problem of No. 11 bearing stabilities with regard to exist always since putting into operation that solved.This bearing low frequency vibration tendency chart of field measurement is seen Fig. 1 to figure four.The present invention is worth similar engineering to be used for reference, and is with a wide range of applications.
Claims (1)
1. an axle that counts spring foundation is the load pre-adaptation method, may further comprise the steps successively:
(1) gathers rigid foundation bearing absolute altitude h
i, and the stiffness K on bearing corresponding spring basis
The i spring, i=1,2 ... I, I is the number of middle (center) bearing for axle;
(2) adopt transfer matrix method, obtain under the rigid foundation constant speed operating mode lower bearing load
With absolute altitude h
iBetween relation;
(4) adopt Finite Element, by finding the solution Reynolds equation, obtain bearing load
Under the operating mode, the floatation volume of axle journal
(6) according to f (h in the step (2)
i), use the bearing absolute altitude
Substitute h
i, obtain the bearing load of iteration
(8) when
Obtain under the spring foundation real load of constant speed operating mode lower bearing
And actual elevation
(9) obtain the pre-adjustment amount Δ of bearing absolute altitude;
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100578243A CN103306302A (en) | 2012-03-07 | 2012-03-07 | Shafting load preadjusting method of metered spring base |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100578243A CN103306302A (en) | 2012-03-07 | 2012-03-07 | Shafting load preadjusting method of metered spring base |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103306302A true CN103306302A (en) | 2013-09-18 |
Family
ID=49131988
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100578243A Pending CN103306302A (en) | 2012-03-07 | 2012-03-07 | Shafting load preadjusting method of metered spring base |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103306302A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107916960A (en) * | 2017-12-12 | 2018-04-17 | 中广核工程有限公司 | Nuclear power turbine-generator unit dual-gripper spring discharges and locking logical method and system |
CN112439852A (en) * | 2019-08-28 | 2021-03-05 | 上海中国弹簧制造有限公司 | Spring hot-pressing method |
CN112464529A (en) * | 2020-11-16 | 2021-03-09 | 西安热工研究院有限公司 | Load distribution real-time calculation method under running state of flexible support steam turbine generator unit |
CN115758061A (en) * | 2023-01-10 | 2023-03-07 | 西南交通大学 | Track irregularity fine adjustment method based on adjacent sleeper coupling analytic calculation |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3960008A (en) * | 1974-12-12 | 1976-06-01 | Goble George G | Pile capacity testing means |
-
2012
- 2012-03-07 CN CN2012100578243A patent/CN103306302A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3960008A (en) * | 1974-12-12 | 1976-06-01 | Goble George G | Pile capacity testing means |
Non-Patent Citations (2)
Title |
---|
何国安等: "计入弹簧基础的1060MW核电机组轴承载荷灵敏度分析", 《机械工程师》 * |
刘荣强等: "轴承标高对多跨轴系振动及稳定性的影响", 《哈尔滨工业大学学报》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107916960A (en) * | 2017-12-12 | 2018-04-17 | 中广核工程有限公司 | Nuclear power turbine-generator unit dual-gripper spring discharges and locking logical method and system |
CN112439852A (en) * | 2019-08-28 | 2021-03-05 | 上海中国弹簧制造有限公司 | Spring hot-pressing method |
CN112439852B (en) * | 2019-08-28 | 2023-02-03 | 上海中国弹簧制造有限公司 | Spring hot-pressing method |
CN112464529A (en) * | 2020-11-16 | 2021-03-09 | 西安热工研究院有限公司 | Load distribution real-time calculation method under running state of flexible support steam turbine generator unit |
CN115758061A (en) * | 2023-01-10 | 2023-03-07 | 西南交通大学 | Track irregularity fine adjustment method based on adjacent sleeper coupling analytic calculation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Zhang et al. | Transient vibration analysis of unit-plant structure for hydropower station in sudden load increasing process | |
CN204458973U (en) | A kind of simple liquid damping TMD | |
CN206329666U (en) | Piezoelectric type self energizing MR damper | |
CN103470737B (en) | The intelligent vibration damping device of wind turbine gearbox | |
CN103306302A (en) | Shafting load preadjusting method of metered spring base | |
CN104088757B (en) | A kind of wind energy, ocean wave energy composite generating set | |
CN204551516U (en) | A kind of steam turbine generator spring vibration-isolated foundation | |
Wang et al. | Flexible multibody dynamics modelling of point-absorber wave energy converters | |
CN206686016U (en) | A kind of motor of vibration and noise reducing | |
CN103572857A (en) | Electromagnetic tuned mass damper and design method thereof | |
CN102619361B (en) | Building structure system of turbo generator set arranged at high position | |
CN201696220U (en) | Vertical axis wind generating set for communication tower frame | |
CN106088169A (en) | Multiple degrees of freedom CYCLIC LOADING device for offshore wind turbine foundation laboratory test research | |
Jia et al. | A wave energy converter based on a zero-pressure-angle mechanism for self-powered applications in near-zero energy sea-crossing bridges | |
CN202280565U (en) | Lifting type hydroelectric generating set | |
CN201772009U (en) | Isolating device | |
CN203604543U (en) | Vibration reduction structure of wind driven generator | |
CN105576673B (en) | A kind of forced power oscillation suppressing method and system based on E STATCOM | |
Chang et al. | Soil response around Donghai offshore wind turbine foundation, China | |
CN203613669U (en) | Electromagnetic tuned mass damper | |
CN203146222U (en) | Vertical shaft lever bucket-type stacked wind energy power producer | |
CN105756985A (en) | Testing platform for electric system | |
Bian et al. | Wind turbine on-line monitoring system based on vibration mechanics | |
CN205207033U (en) | Generating set start -up system | |
Mohamed et al. | Structural Dynamic Behavior of Turbo Generator Foundation Connected with Passive Supplemental Damping Devices |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130918 |