CN103292035B - Construction method of underground pipe jacking - Google Patents

Construction method of underground pipe jacking Download PDF

Info

Publication number
CN103292035B
CN103292035B CN201310198767.5A CN201310198767A CN103292035B CN 103292035 B CN103292035 B CN 103292035B CN 201310198767 A CN201310198767 A CN 201310198767A CN 103292035 B CN103292035 B CN 103292035B
Authority
CN
China
Prior art keywords
pipeline
jacking
length
tubing
control point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310198767.5A
Other languages
Chinese (zh)
Other versions
CN103292035A (en
Inventor
王淑保
谭福生
赵玉波
刘玉科
张淑贤
马炜锋
张彦龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201310198767.5A priority Critical patent/CN103292035B/en
Publication of CN103292035A publication Critical patent/CN103292035A/en
Application granted granted Critical
Publication of CN103292035B publication Critical patent/CN103292035B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a construction method of underground pipe jacking. The construction method includes a) arranging control points at end points of each road segment in a same straight line; b) producing and arranging a working well; c) mounting a guide rail and a jacking device; d) mounting a point unit, and allowing extension of the pointed direction of the point unit to be located in same plane with the straight where the control points located; e) mounting an orientation unit, hoisting two first-segment pipelines, allowing the orientation unit to receive the oriented direction from the point unit, starting the jacking device to jack the two first-segment pipelines in opposite directions, and excavating at the front ends of the first-segment pipelines; f) hoisting a pipeline, connecting the pipeline with a front pipeline, allowing the orientation unit to receive the pointed direction of the point unit, starting the jacking device to jack the pipeline in the opposite direction, and excavating at the front ends of the first-segment pipelines; g) repeating step f till the pipeline is mounted completely, and allowing the pipeline to be a joint unit between the two first-segment pipelines.

Description

A kind of method of construction of underground pipe-driving
Technical field
The present invention relates to underground pipeline construction method, specifically, relate to the method for construction of the two-way jacking of a kind of underground pipe-driving.
Background technique
Under ground piping is laid on underground for carrying the pipeline of gas, liquid or solid, such as underground intake pipe, waste pipe, gas pipe or telecommunication cable pipe etc.In the process of laying under ground piping, the traffic fortress in city may be in, cannot carry out digging direct-buried and truss built on stilts by time, adopt pipe-jacking technology more.
Pipe-jacking technology is a kind of no-dig technique driving formula pipelaying techniques.Do not need to excavate ground, ground structure and underground utility can be passed through, do not need to block traffic, little on the impact arround construction.Fig. 1 is schematic diagram, shows the method for construction of push pipe in prior art.As shown in Figure 1, the initial point position of pipeline is determined before construction, perpendicular to floor manufacture active well 100 and received well 200, in active well 100, arrange reacting wall 110 etc., the jacking device 300 such as jack 310, top iron 320 is installed, lifting pipeline 400, jack 300 promotes pipeline 400 through soil layer, adopt artificial or machinery to cut the earth in the front end of pipeline 400 simultaneously, pipeline 400 is headed into one by one, until in top to received well 200.Fig. 2 shows the reinforcing mode between the pipeline of push pipe in prior art.As shown in Figure 2, produce mismatch for avoiding pipeline 400 jointing in jack-in process or cause pipeline 400 to drift about because soil is partially soft, the interface of two pipelines 400 is alignd, is fixed to inside the interface of two pipelines 400 with the semicircular interior packing 10 of welded steel plate, adopt bolt 20 to be fixed.When pipeline 400 jacking completes, dismountable interior packing 10.Usually, the T bar collar is adopted to reinforce at pipe joint place.And, in the process of jacking, the direct of travel of pipeline be determined, if find deviation, should rectify a deviation in time.
The shortcoming of the method is, the distance of the unidirectional jacking of push pipe is limited, and especially artificial push pipe length is no more than in the common distance of 100 meters usually, otherwise can cause that the skew of push pipe is large or push pipe is damaged, and the construction period is long.
Summary of the invention
The present invention makes to solve the problem.Specifically, the object of the invention is to, the method of construction of the two-way jacking of a kind of underground pipe-driving is provided, in the common distance of unidirectional push pipe jacking, or the length in the section of laying push pipe is within the scope of the double length of the common distance of unidirectional push pipe jacking, bilateral excavation active well, two-way jacking operation simultaneously, and accurately control jacking precision, pipeline is accurately docked.
To achieve these goals, the invention provides the method for construction of the two-way jacking of a kind of underground pipe-driving, the method comprises: a) section is divided into two sections, and arrange control point at the end points place of each segmentation, described control point is located on the same line; B) make active well at the described control point place at two ends, section and arrange described active well; C) mounting guide rail and jacking device in described active well; D) in described active well, install sensing unit, the extension of the assigned direction of described sensing unit and the straight line residing for described control point are positioned at same vertical plane; E) on the top of first length of tubing, directed element is installed, two described first length of tubing are lifted on described guide rail, described directed element receives the assigned direction of described sensing unit, start described jacking device and make two first length of tubing jackings in opposite directions, and cut the earth in the front end of described first length of tubing; F) lift pipeline, described pipeline with it front pipeline connects, and described directed element receives the assigned direction of described sensing unit, starts described jacking device and makes pipeline jacking in opposite directions, and cuts the earth in described first length of tubing front end; G) step f is repeated) complete to described Pipe installing, make between described two first length of tubing and be connected unit.
Preferably, described jacking device comprises jack and top iron.
In addition, preferably, described sensing unit is laser theodolite, and described directed element is laser pick-off target.
From description above with put into practice, in the common distance of unidirectional push pipe jacking, or treat that jacking road section length is in the length of common distance twice of unidirectional push pipe jacking, two active wells are excavated at the two ends in section, middle jacking from two ends simultaneously to section, both can guarantee the jacking quality of pipeline, can speed of application have been improved again, reduce the engineering time.In addition, by pointing to the positioning action of unit and directed element, pipeline can be made to dock accurately.
Accompanying drawing explanation
Fig. 1 is schematic diagram, shows the method for construction of push pipe in prior art;
Fig. 2 shows the reinforcing mode between the pipeline of push pipe in prior art;
Fig. 3 is schematic diagram, shows the method for construction of the two-way jacking of underground pipe-driving of the present invention; And
Fig. 4 is the finishing stage schematic diagram of the method for construction descending the two-way jacking of push pipe as shown in Figure 3.
Embodiment
The embodiment of the method for construction of the two-way jacking of underground pipe-driving of the present invention is described below with reference to the accompanying drawings.Those of ordinary skill in the art can recognize, when without departing from the spirit and scope of the present invention, can revise by various different mode to described embodiment.Therefore, accompanying drawing is illustrative with being described in essence, instead of for limiting the protection domain of claim.In addition, in this manual, identical reference character represents same or analogous part.
Below by the method for construction of the two-way jacking of a kind of underground pipe-driving described in description one embodiment of the present of invention.Fig. 3 is schematic diagram, shows the method for construction of the two-way jacking of underground pipe-driving of the present invention.Fig. 4 is the finishing stage schematic diagram of the method for construction of the two-way jacking of underground pipe-driving shown in Fig. 3.
As shown in Figure 3, first according to the starting point A of the section AB of push pipe to be laid and the position of initial point B and spacing, the section AB of push pipe to be laid is divided into AC section and the segmentation of two, BD section, the length in AC section and BD section is all less than or equal to the maximum normal travel distance of the unidirectional laying of push pipe, at the end points place of each segmentation, control point A, C, D and B are set, A, C, D, B are located on the same line at control point, and middle distance between two control points C, D is the distance between normal two pipelines 400.
Active well 100 is made near control point A, the B at the AB two ends, section of push pipe to be laid.Here, refer near control point on the bearing of trend of straight line residing for control point.The degree of depth of active well 100 will meet the elevation demand of pipeline 400, arranges two active wells 100 respectively, in active well 100, make reacting wall 110 etc.Then, mounting guide rail 700 and jacking device 300 in two active wells 100; When mounting guide rail 700, adopt level instrument to check and approve the elevation of guide rail 700, avoid the elevation affecting pipeline 400.Jacking device 300 comprises jack 310 and top iron 320.In two active wells 100, the sensing extension of assigned direction of unit 500 of installation sensing unit 500, two and the straight line residing for control point A, C, D, B are positioned at same vertical plane respectively.
On the top of two first length of tubing 400, directed element 600 is installed, two first length of tubing 400 are lifted on the guide rail 700 in active well 100, now, the straight line that the axis of pipeline 400 and two point on the extension of the assigned direction of unit 500 and ground residing for control point A, C, D, B is positioned at same vertical plane.Directed element 600 receives the assigned direction pointing to unit 500, starts jacking device 300, makes first length of tubing 400 jacking in opposite directions in two active wells 100, and cut the earth in the front end of first length of tubing 400.If directed element 600 does not receive the assigned direction pointing to unit 500, jacking direction should be adjusted in time, carry out correction of deviation.Preferably, pointing to unit 500 is laser theodolites, and directed element 600 is laser pick-off targets.Be installed in active well 100 by two laser theodolites, two laser pick-off targets be installed to the top of first length of tubing 400, the laser spots that laser theodolite is launched lays respectively at the same position of laser pick-off target corresponding with it, such as target center place.Further, the axis of the laser alignment that two laser theodolites are launched overlaps, and is positioned at same vertical plane with the straight line residing for the axis of first length of tubing 400 and control point A, C, D, B.If deviation occurs in the position of laser spots, then illustrate that the jacking direction of first length of tubing 400 is departed from, should rectify a deviation in time.
Lifting pipeline 400, and be connected at the jointing of pipeline 400 front pipeline 400 with it, now, the straight line that the axis of pipeline 400 and two point on the extension of the assigned direction of unit 500 and ground residing for control point A, C, D, B is positioned at same vertical plane.Directed element 600 receives the assigned direction pointing to unit 500, and startup jacking device 300 makes pipeline 400 jacking in opposite directions in two active wells 100, and cuts the earth in first length of tubing 400 front end.In like manner, if directed element 600 does not receive the assigned direction pointing to unit 500, jacking direction should be adjusted in time, carry out correction of deviation.As shown in Figure 4, first length of tubing 400 in two active wells 100 is pushed to C, D place, control point, be connected between two first length of tubing 400, now, whole pipelines 400 installs, and the pipeline 400 between whole section AB is through, the jacking device in migration active well 100, and carry out backfill, the construction of the two-way jacking of underground pipe-driving completes.
From description above with put into practice, in the common distance of unidirectional push pipe jacking, or treat that jacking road section length is in the length of common distance twice of unidirectional push pipe jacking, two active wells are excavated at the two ends in section, middle jacking from two ends simultaneously to section, both can guarantee the jacking quality of pipeline, can speed of application have been improved again, reduce the engineering time.In addition, by pointing to the positioning action of unit and directed element, pipeline can be made to dock accurately.
The method of construction of the two-way jacking of underground pipe-driving of the present invention is described in an illustrative manner above with reference to accompanying drawing.But, it will be appreciated by those skilled in the art that for said method, various improvement and combination can also be made on the basis not departing from content of the present invention.Therefore, protection scope of the present invention should be determined by the content of appending claims.

Claims (2)

1. a method of construction for the two-way jacking of underground pipe-driving, comprising:
A) section is divided into two sections, arrange control point at the end points place of each segmentation, described control point is located on the same line;
B) make active well at the described control point place at two ends, section and arrange described active well;
C) in described active well, reacting wall is made, and mounting guide rail and jacking device; Wherein, level instrument is adopted to check and approve the elevation of guide rail;
D) in described active well, install sensing unit, described sensing unit is laser theodolite, and the extension of its assigned direction and the straight line residing for described control point are positioned at same vertical plane;
E) on the top of first length of tubing, directed element is installed, two described first length of tubing are lifted on described guide rail, described directed element receives the assigned direction of described sensing unit, start described jacking device and make two first length of tubing jackings in opposite directions, and cut the earth in the front end of described first length of tubing; Wherein, described directed element is laser pick-off target, and the axis of laser alignment that two laser theodolites are launched overlaps, and is positioned at same vertical plane with the straight line residing for the axis of first length of tubing and control point;
F) lift pipeline, described pipeline with it front pipeline connects, and described directed element receives the assigned direction of described sensing unit, starts described jacking device and makes pipeline jacking in opposite directions, and cuts the earth in described first length of tubing front end;
G) step f is repeated) complete to described Pipe installing, make between two first length of tubing and be connected unit.
2. the method for construction of the two-way jacking of a kind of underground pipe-driving as claimed in claim 1, wherein, described jacking device comprises jack and top iron.
CN201310198767.5A 2013-05-24 2013-05-24 Construction method of underground pipe jacking Active CN103292035B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310198767.5A CN103292035B (en) 2013-05-24 2013-05-24 Construction method of underground pipe jacking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310198767.5A CN103292035B (en) 2013-05-24 2013-05-24 Construction method of underground pipe jacking

Publications (2)

Publication Number Publication Date
CN103292035A CN103292035A (en) 2013-09-11
CN103292035B true CN103292035B (en) 2015-06-10

Family

ID=49093372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310198767.5A Active CN103292035B (en) 2013-05-24 2013-05-24 Construction method of underground pipe jacking

Country Status (1)

Country Link
CN (1) CN103292035B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110925489A (en) * 2019-12-12 2020-03-27 贵州建工集团第一建筑工程有限责任公司 Opposite jacking and butt joint construction method for finished pipes

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104565534B (en) * 2014-11-24 2017-06-06 余澄玉 A kind of method that component is laid in weak soil
CN104763436B (en) * 2015-03-09 2016-08-17 中国地质大学(武汉) A kind of push-bench method of reseptance under high hydraulic pressure complex geological condition and device
CN105114698A (en) * 2015-09-08 2015-12-02 广东省建筑工程集团有限公司 River opposite jacking butt joint construction process and specially-produced head
CN105403203B (en) * 2015-12-22 2018-02-16 中铁上海工程局集团有限公司 A kind of long range straight line push pipe center simply controls measuring system and method
CN106122589B (en) * 2016-07-02 2018-05-01 天鸿建设集团有限公司 A kind of earth pressure balance method
CN106369223B (en) * 2016-10-31 2018-04-10 中铁二十局集团第五工程有限公司 A kind of silt stratum pipe jacking construction method
CN106402490B (en) * 2016-10-31 2018-04-10 中铁二十局集团第五工程有限公司 Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN106764055B (en) * 2017-01-09 2019-02-01 中建四局第三建筑工程有限公司 Push pipe sight alignment construction
CN106988751B (en) * 2017-04-07 2019-11-01 广东盛际工程咨询有限公司 Small diameter tube drainage pipeline push pipe equipment and pipe jacking construction method
CN107269288A (en) * 2017-08-11 2017-10-20 曹丽召 The non-explosion water mill of hard stone section push pipe bores two-way drilling construction method
CN108194703B (en) * 2018-02-11 2023-06-20 北京建工土木工程有限公司 Correction construction system and correction method for construction jacking pipe
CN108953759B (en) * 2018-06-27 2020-01-21 广东管博管道技术科技有限公司 Self-balancing bidirectional pipe replacement and repair method and device
CN109056806A (en) * 2018-09-04 2018-12-21 深圳市深水水务咨询有限公司 A kind of construction method and its construction for underground type sewage plant
CN110541966B (en) * 2019-08-27 2024-03-26 北京住总集团有限责任公司 Auxiliary equipment for jacking pipe joint in narrow space and application method thereof
CN111306357B (en) * 2020-02-14 2022-06-24 上海市基础工程集团有限公司 Construction method for steel top pipe to penetrate foundation stratum based on temporary sleeve butt joint
CN111810712A (en) * 2020-07-17 2020-10-23 中铁十二局集团有限公司 Push pipe starting construction method for bent pipeline
CN112253844B (en) * 2020-09-29 2022-04-22 北京政平建设投资集团有限公司 Self-monitoring guide rail
CN112267889B (en) * 2020-10-26 2023-02-28 中铁八局集团第一工程有限公司 Construction method for penetrating through filling material of molten cavity
CN112761647A (en) * 2020-12-30 2021-05-07 西安市政设计研究院有限公司 Support-free underground excavation and pushing construction method for rectangular large-section comprehensive pipe gallery
CN112797227B (en) * 2021-01-05 2022-06-24 安徽省新路建设工程集团有限责任公司 Ultra-long distance pipe jacking structure in complex environment and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU898203A1 (en) * 1980-04-25 1982-01-15 Войсковая Часть 74242 Hopper for tubes
CN101788082A (en) * 2009-12-21 2010-07-28 上海市第一市政工程有限公司 Construction method for abutting jack pipe underground
CN102261517A (en) * 2011-07-13 2011-11-30 中国建筑第二工程局有限公司 Method for installing prestressed steel cylinder concrete pipe in narrow space in casing pipe

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU898203A1 (en) * 1980-04-25 1982-01-15 Войсковая Часть 74242 Hopper for tubes
CN101788082A (en) * 2009-12-21 2010-07-28 上海市第一市政工程有限公司 Construction method for abutting jack pipe underground
CN102261517A (en) * 2011-07-13 2011-11-30 中国建筑第二工程局有限公司 Method for installing prestressed steel cylinder concrete pipe in narrow space in casing pipe

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王显根等.顶管质量通病.《市政工程施工质量检验》.高等教育出版社,2007,等326页. *
顶管工程施工方案;惠阳建筑工程总公司惠阳区内环路西段一期工程项目部;《豆丁》;20121125;第19-24页 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110925489A (en) * 2019-12-12 2020-03-27 贵州建工集团第一建筑工程有限责任公司 Opposite jacking and butt joint construction method for finished pipes

Also Published As

Publication number Publication date
CN103292035A (en) 2013-09-11

Similar Documents

Publication Publication Date Title
CN103292035B (en) Construction method of underground pipe jacking
CN106369223B (en) A kind of silt stratum pipe jacking construction method
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
Bieniawski et al. Critical assessment of RMR-based tunnel design practices: A practical engineer’s approach
CN102032393B (en) Small-bore long distance curved pipe jacking method
CN102691294B (en) Construction method of underground continuous wall
CN101684669B (en) Submersed type inspection well construction method
CN103322989A (en) Measuring device and method of dynamic real-time measurement of position and posture of pipe pushing jack
CN108916467A (en) Heavy caliber sigmoid curve pipe jacking construction method
CN103114599B (en) Deep basal pit sealing dewatering device and construction method thereof
CN105696550B (en) A kind of three axes agitating pile construction method of additional reinforcement continuous wall trench underground
CN101701646B (en) Method for slurry-water balance type pipe-pulling construction of underground pipeline
CN205822220U (en) A kind of assembled open caisson
CN106894422B (en) Complex environment deep foundation pit supporting construction method
CN203422091U (en) Device for dynamically measuring positions and attitudes of push bench in real time
CN104032743B (en) Steel pile casting under deep water, torrent and inclined rock base condition transfers inserted to play method
CN103628509B (en) Inner and outer pipes for bearing capacity of pile foundation test adopts double-tube structure and the construction method of unlike material
CN105546213B (en) A kind of flexible composite pipe rapid construction device and construction method
CN101798823B (en) Construction method of performing remote deviation rectification by passageway method
CN105672351A (en) Construction method of buckling type prefabricated ribbed reinforced concrete comprehensive pipe gallery structure
CN109119943A (en) System of laying optimization method of the cable at push pipe both ends
CN103644370B (en) Buried pipeline construction method with self-regulating function
CN110173229A (en) One kind being used for the anti-well off-angle drilling plugging device of oil-gas pipeline and method for blocking
CN108978679A (en) A kind of method that cable tunnel is constructed in high water level region

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant