CN103280077A - System for managing and controlling power transmission line corridor flammable and explosive source - Google Patents
System for managing and controlling power transmission line corridor flammable and explosive source Download PDFInfo
- Publication number
- CN103280077A CN103280077A CN2013102032657A CN201310203265A CN103280077A CN 103280077 A CN103280077 A CN 103280077A CN 2013102032657 A CN2013102032657 A CN 2013102032657A CN 201310203265 A CN201310203265 A CN 201310203265A CN 103280077 A CN103280077 A CN 103280077A
- Authority
- CN
- China
- Prior art keywords
- video
- server
- control center
- management control
- message management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention discloses a system for managing and controlling a power transmission line corridor flammable and explosive source, which comprises a network camera arranged near the power transmission line corridor flammable and explosive source. The network camera is connected with a video acquisition and storage server; the video acquisition and storage server is connected with a video analysis server; the video analysis server is connected with a message management control center; and the message management control center is connected with the video acquisition and storage server. The system for managing and controlling the power transmission line corridor flammable and explosive source has a reasonable structure, can be used for carrying out automatic identification and active alarm and has good working efficiency.
Description
Technical field
The present invention relates to the dangerous source point managing and control system in a kind of transmission line of electricity corridor.
Background technology
Electric power is the lifeblood of national economy.Transmission line of electricity press the nail reliably working be the basic guarantee of the national economic development; Because transmission line of electricity has a very wide distribution, and usually pass through city and rural area, and along with rapid economy development, the town and country capital construction is more and more frequent, its operation often is subjected to the interference of people's production and construction unit; As various heavy construction apparatuses at power transmission line trousers annex construction operation (crane, cement pump truck etc.) and plant greenhouse film the stable operation of transmission line of electricity has been constituted potential serious threat, often cause the destruction to transmission line of electricity, cause the transmission line of electricity damage, cause large-area power-cuts, not only cause the life and property loss when thing unit, bring serious threat for especially people's daily productive life.
Because transmission line of electricity suffers extraneous destruction to have regular, disguised and paroxysmal characteristics, make the daily tour of power supply department be difficult to the management effect that reaches desirable: and under " three collection five are big " system, circuit O﹠M personnel's configuration shrinkage in size, running personnel workload increases, and the related personnel supervises cement pump truck and tower crane etc. to be increased the workload that transmission line of electricity influences:
Through consulting a large amount of data, relevant expert with consulting firm has done detail statistics to the measure of existing protection transmission line of electricity safe and stable operation, and existing mode is divided into two big classes nothing but:
1, at transmission line of electricity dangerous matter sources spot correlation high-pressure tower the bread and cheese monitoring is installed, the people is carried out for checking live video in the scene of executing.
The problem of Cun Zaiing is like this: mainly be to be taken as the leading factor by the O﹠M personnel, real time monitoring is carried out in the working-yard, through mass data research, the O﹠M personnel dig-in screen will feel tired unusually about 8 minutes; And whether the operation of tube field dangerous matter sources point does not exist hidden danger or when not working, all requires the video signal flow of camera acquisition is transferred to central monitoring position; This transmission mode not only will consume a large amount of communication broadbands, and can cause huge communication cost, the more important thing is and can not play the actual effect that effectively monitors;
2, be stationed the related personnel at the dangerous source point of transmission line of electricity, artificially protect and intervene.
The problem of Cun Zaiing is like this: because people's uncontrollable factor is more, vacuum can occur nursing, more can not hold safe distance exactly, accurately and timely early warning when large-scale apparatuses such as tower crane, cement pump truck have the security threat behavior to take place to transmission line of electricity before.
Summary of the invention
The object of the present invention is to provide a kind of rational in infrastructure, automatically identification, initiatively report to the police, the dangerous source point managing and control system in transmission line of electricity corridor of favorable working performance.
Technical solution of the present invention is:
The dangerous source point managing and control system in a kind of transmission line of electricity corridor, it is characterized in that: comprise being arranged near the IP Camera of the dangerous source point in transmission line of electricity corridor, IP Camera is connected with storage server with video acquisition, video acquisition is connected with video analytics server with storage server, video analytics server is connected with message management control center, and message management control center is connected with storage server with video acquisition; Client is connected with web server and player, and the web server is connected with message management control center, and player is connected with storage server with video acquisition;
Video acquisition and storage server are gathered video and view data from IP Camera, give the video analytics server analysis with view data, video analytics server returns to video acquisition and storage server with the Meta data that analyze, and the while video analytics server will be reported to the police or temporal information is submitted to message management control center; Video acquisition and storage server save as the VS file with video data and Meta data, and be recorded to database, message management control center is recorded to database with warning message, generate the warning picture, and to video acquisition and storage server requests warning video, video acquisition and storage server Query Database read the VS file, the warning video data is sent to message management control center, and message management control center preserves video and new database more;
Client shows: client is to web server request video source information, the web server is from data base querying video frequency source information and return to client, client is given player with video acquisition and storage server address and channel information, player is to video acquisition and storage server requests real-time video, and display video collection and storage server video and the Meta data returned, client is regularly to the up-to-date warning message of web server request, the web server is from the data base querying alert data and return to client, client is upgraded the tabulation of reporting to the police, client is given player with the warning video address, player plays warning video;
Demarcate: client is given web server with nominal data and video information, the web server is saved in database with nominal data, and notification message management control center, message management control center sends the order of restarting video analytics server, when video analytics server starts to message management control center required parameter information, message management control center is from the data base querying parameter information, and returns to video analytics server.
The present invention is rational in infrastructure, can in time grasp transmission line of electricity ruuning situation under O﹠M personnel situation in short supply, no matter still runs errands in office and can both in time check transmission line of electricity ruuning situation, accomplishes to check electric line ruuning situation whenever and wherever possible; Can identify dangerous objects such as tower crane, cement pump truck automatically, before dangerous object was near safe distance, the scene provided sound and light alarm, and the warning picture is sent on O﹠M personnel, proprietor, the construction hand of driver holding equipment; Can in time give the responsible official of relevant departments with problematic circuit active push, if should not obtain removing by the danger source point, this is reported to the police and can remind relevant responsible official always; Change dangerous point into secure source in the very first time, all may be nipped in the bud to the dangerous matter sources of transmission line of electricity; Solve the vacuum of artificial pro-active intervention, under complicated climatic conditions such as bad weather, night, accomplished 24 hours uninterrupted nurse transmission lines of electricity; Improved O﹠M personnel work efficiency, human and material resources, financial resources have been saved, the mode that tradition is solved the transmission line of electricity safe operation is broken fully, passive-type is handled problems to change into initiatively identify adventurous object, thereby further guarantee the safe operation of transmission line of electricity.
Description of drawings
The invention will be further described below in conjunction with drawings and Examples.
Fig. 1 is the structural representation of one embodiment of the invention.
Embodiment
The dangerous source point managing and control system in a kind of transmission line of electricity corridor, comprise and be arranged near the IP Camera of the dangerous source point in transmission line of electricity corridor, IP Camera is connected with storage server (VAM) 1 with video acquisition, video acquisition is connected with video analytics server (VPS) 2 with storage server, video analytics server is connected with message management control center 3, and message management control center is connected with storage server 1 with video acquisition; Client 4 is connected with web server 5 and player, and the web server is connected with message management control center 3, and player 6 is connected with storage server 1 with video acquisition;
Video acquisition and storage server are gathered video and view data from IP Camera, give the video analytics server analysis with view data, video analytics server returns to video acquisition and storage server with the Meta data that analyze, and the while video analytics server will be reported to the police or temporal information is submitted to message management control center; Video acquisition and storage server save as the VS file with video data and Meta data, and be recorded to database (DB) 8, message management control center is recorded to database (DB) 9 with warning message, generate the warning picture, and to video acquisition and storage server requests warning video, video acquisition and storage server Query Database read the VS file, the warning video data is sent to message management control center, and message management control center preserves video and new database more;
Client shows: client is to web server request video source information, the web server is from data base querying video frequency source information and return to client, client is given player with video acquisition and storage server address and channel information, player is to video acquisition and storage server requests real-time video, and display video collection and storage server video and the Meta data returned, client is regularly to the up-to-date warning message of web server request, the web server is from the data base querying alert data and return to client, client is upgraded the tabulation of reporting to the police, client is given player with the warning video address, player plays warning video;
Demarcate: client is given web server with nominal data and video information, the web server is saved in database with nominal data, and notification message management control center, message management control center sends the order of restarting video analytics server, when video analytics server starts to message management control center required parameter information, message management control center is from the data base querying parameter information, and returns to video analytics server.
Claims (1)
1. the dangerous source point managing and control system in a transmission line of electricity corridor, it is characterized in that: comprise being arranged near the IP Camera of the dangerous source point in transmission line of electricity corridor, IP Camera is connected with storage server with video acquisition, video acquisition is connected with video analytics server with storage server, video analytics server is connected with message management control center, and message management control center is connected with storage server with video acquisition; Client is connected with web server and player, and the web server is connected with message management control center, and player is connected with storage server with video acquisition;
Video acquisition and storage server are gathered video and view data from IP Camera, give the video analytics server analysis with view data, video analytics server returns to video acquisition and storage server with the Meta data that analyze, and the while video analytics server will be reported to the police or temporal information is submitted to message management control center; Video acquisition and storage server save as the VS file with video data and Meta data, and be recorded to database, message management control center is recorded to database with warning message, generate the warning picture, and to video acquisition and storage server requests warning video, video acquisition and storage server Query Database read the VS file, the warning video data is sent to message management control center, and message management control center preserves video and new database more;
Client shows: client is to web server request video source information, the web server is from data base querying video frequency source information and return to client, client is given player with video acquisition and storage server address and channel information, player is to video acquisition and storage server requests real-time video, and display video collection and storage server video and the Meta data returned, client is regularly to the up-to-date warning message of web server request, the web server is from the data base querying alert data and return to client, client is upgraded the tabulation of reporting to the police, client is given player with the warning video address, player plays warning video;
Demarcate: client is given web server with nominal data and video information, the web server is saved in database with nominal data, and notification message management control center, message management control center sends the order of restarting video analytics server, when video analytics server starts to message management control center required parameter information, message management control center is from the data base querying parameter information, and returns to video analytics server.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310203265.7A CN103280077B (en) | 2013-05-28 | 2013-05-28 | Power transmission line corridor hazard Identification managing and control system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310203265.7A CN103280077B (en) | 2013-05-28 | 2013-05-28 | Power transmission line corridor hazard Identification managing and control system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103280077A true CN103280077A (en) | 2013-09-04 |
CN103280077B CN103280077B (en) | 2015-10-07 |
Family
ID=49062581
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310203265.7A Active CN103280077B (en) | 2013-05-28 | 2013-05-28 | Power transmission line corridor hazard Identification managing and control system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103280077B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105575065A (en) * | 2015-12-31 | 2016-05-11 | 国网浙江奉化市供电公司 | Accident prevention method and system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1264254A (en) * | 1999-01-21 | 2000-08-23 | 松下电器产业株式会社 | Network type monitoring device |
CN101052123A (en) * | 2006-04-03 | 2007-10-10 | 索尼株式会社 | Monitoring apparatus and method |
CN202067379U (en) * | 2010-11-26 | 2011-12-07 | 上海电力带电作业技术开发有限公司 | Remote wireless video intelligent monitoring prewarning system for electricity transmission line |
WO2012151651A1 (en) * | 2011-05-12 | 2012-11-15 | Solink Corporation | Video analytics system |
CN102980607A (en) * | 2011-09-07 | 2013-03-20 | 辽宁省电力有限公司营口供电公司 | Electric transmission line image identification monitoring system |
CN103096042A (en) * | 2013-02-05 | 2013-05-08 | 泰州市易航软件科技有限公司 | Video monitoring system |
-
2013
- 2013-05-28 CN CN201310203265.7A patent/CN103280077B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1264254A (en) * | 1999-01-21 | 2000-08-23 | 松下电器产业株式会社 | Network type monitoring device |
CN101052123A (en) * | 2006-04-03 | 2007-10-10 | 索尼株式会社 | Monitoring apparatus and method |
CN202067379U (en) * | 2010-11-26 | 2011-12-07 | 上海电力带电作业技术开发有限公司 | Remote wireless video intelligent monitoring prewarning system for electricity transmission line |
WO2012151651A1 (en) * | 2011-05-12 | 2012-11-15 | Solink Corporation | Video analytics system |
CN102980607A (en) * | 2011-09-07 | 2013-03-20 | 辽宁省电力有限公司营口供电公司 | Electric transmission line image identification monitoring system |
CN103096042A (en) * | 2013-02-05 | 2013-05-08 | 泰州市易航软件科技有限公司 | Video monitoring system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105575065A (en) * | 2015-12-31 | 2016-05-11 | 国网浙江奉化市供电公司 | Accident prevention method and system |
Also Published As
Publication number | Publication date |
---|---|
CN103280077B (en) | 2015-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106227132A (en) | A kind of laboratory cloud monitor supervision platform and laboratory monitoring method | |
CN204087400U (en) | perimeter protection warning system | |
CN105262210A (en) | System and method for analysis and early warning of substation network security | |
CN103310574B (en) | The transmission line of electricity hazard Identification managing and control system of potential safety hazard is retrieved for examination by handheld device | |
CN103295355B (en) | Automatically the power transmission line corridor hazard Identification managing and control system of potential safety hazard is identified night | |
CN202373134U (en) | Intelligent urban traffic system | |
CN204389937U (en) | Transit equipment overall process monitoring operation device | |
CN105467936A (en) | Power equipment monitoring system | |
CN203931066U (en) | A kind of warehouse abnormal conditions initiative alarming device | |
CN103280077B (en) | Power transmission line corridor hazard Identification managing and control system | |
CN103337122B (en) | Electric line virtual isolation barrier system | |
CN203275996U (en) | Power transmission line hazard point management and control system capable of seeing potential safety hazard through handheld device | |
CN103280061B (en) | Many protective seams power transmission line corridor hazard Identification managing and control system | |
CN102890172A (en) | Intelligent warning device for metering box | |
CN203279061U (en) | Multi-protection layer power transmission line corridor hazard point management and control system | |
CN202694189U (en) | Intelligent temperature and humidity monitoring and management system for medicine warehouse | |
CN202475650U (en) | Network video monitoring device | |
CN207895653U (en) | A kind of moisture condensation warning device | |
CN203102467U (en) | Henhouse anti-theft alarm device | |
CN201674602U (en) | Video identification system in high-voltage power transmission line online monitoring system | |
CN206133655U (en) | Place name generaI investigation acquisition manager system based on cloud | |
CN204332032U (en) | A kind of road information acquisition system based on mobile terminal | |
CN205049901U (en) | Biological sample storehouse centralized monitoring system | |
CN203327165U (en) | Real-time monitoring system for power plant instruments | |
CN204229489U (en) | A kind of intelligent entrance guard supervisory system based on cloud platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |