CN103277125A - 带钢板连接的锁脚小导管 - Google Patents

带钢板连接的锁脚小导管 Download PDF

Info

Publication number
CN103277125A
CN103277125A CN2013102500394A CN201310250039A CN103277125A CN 103277125 A CN103277125 A CN 103277125A CN 2013102500394 A CN2013102500394 A CN 2013102500394A CN 201310250039 A CN201310250039 A CN 201310250039A CN 103277125 A CN103277125 A CN 103277125A
Authority
CN
China
Prior art keywords
lock pin
steel plate
ductule
lock
feet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102500394A
Other languages
English (en)
Other versions
CN103277125B (zh
Inventor
张星江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
The Yunnan investment group Yunling Construction Co. Ltd.
Original Assignee
YUNNAN YUNLING EXPRESSWAY BRIDGE CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN YUNLING EXPRESSWAY BRIDGE CONSTRUCTION CO Ltd filed Critical YUNNAN YUNLING EXPRESSWAY BRIDGE CONSTRUCTION CO Ltd
Priority to CN201310250039.4A priority Critical patent/CN103277125B/zh
Publication of CN103277125A publication Critical patent/CN103277125A/zh
Application granted granted Critical
Publication of CN103277125B publication Critical patent/CN103277125B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种带钢板连接的锁脚小导管,其特征在于一块穿有两个对称圆洞的锁脚钢板,焊接在需要锁脚的工字钢上;身上钻有注浆孔的锁脚小导管,穿过锁脚钢板的圆洞打进围岩里;在锁脚小导管外露的头上套一个钢筋限位圈,作为锁脚钢板与锁脚小导管焊接固定的连接物。本发明能使围岩与锁脚小导管紧密连接,以及锁脚小导管与初期支护中的工字钢牢固连接,达到控制收敛、控制拱顶和地面整体下沉的目的;构件可以工厂化加工制作,钢板和工字钢可以在隧道外提前焊接在一起,减少了洞内的施工时间,提高了施工进度和工程质量,改善了洞内的施工环境;安全可靠,操作简便,兼顾了在安全、质量、进度、经济效益、社会效益等方面的要求。

Description

带钢板连接的锁脚小导管
技术领域
本发明涉及一种隧道初期支护的构件,尤其是带钢板连接的锁脚小导管。
背景技术
在软弱围岩隧道施工过程中,预防和处治隧道过大变形甚至塌方尤为重要。为此,隧道建设者们在长期的理论研究和工程实践中总结出了一些预防和处治软弱围岩隧道过大变形的工程措施,取得了一些显著的成绩,如注浆加固软弱围岩体、提高初期支护刚度、增设长锚杆及锁脚锚杆等。锁脚锚杆是近几年发展起来的一项新技术,由于其简单易行、经济、效果明显,大大地提高了施工效率,省去了其他辅助施工措施,节约了人力、物力。尤其在地层软弱、地层含水量大、拱脚积水的条件下, 锁脚锚杆的增设对控制收敛严重、拱顶和地面整体下沉效果非常明显。
但锁脚锚杆在施工中也存在问题,一是锁脚锚杆基本成水平角,选用砂浆锚杆施工时,水平孔灌浆很难灌满,施工很不便,故大部分采用锚固剂锚杆,而锚固剂锚杆虽然施厂方法简单,辅助设施投入少,但质量难以保证。二是锁脚锚杆与初期支护中的工字钢连接不牢固,因接触面积小,经常采用点焊连接,质量难以保证,稍有外力就造成连接处焊点脱落而失去支撑、锁脚的作用。
发明内容
针对现有技术中的不足,本发明提供一种带钢板连接的锁脚小导管,能使围岩与锁脚小导管紧密连接,以及锁脚小导管与初期支护中的工字钢牢固连接。
为实现上述目的本发明所采用的技术方案是:
一种带钢板连接的锁脚小导管,由两根锁脚小导管、一块锁脚钢板和两个限位圈组成。其特征在于,一块穿有两个对称圆洞的锁脚钢板,焊接在需要锁脚的工字钢上;身上钻有注浆孔的锁脚小导管,穿过锁脚钢板的圆洞打进围岩里;在锁脚小导管外露的头上套一个钢筋限位圈,作为锁脚钢板与锁脚小导管焊接固定的连接物。
所述的锁脚钢板为一块刚度足够的矩形钢板,以矩形钢板长边为对称轴,对称的钻两个直径比锁脚小导管大的圆洞,两个圆洞净间距要大于工字钢的腿宽度,把钢板按对称位置焊在需要锁脚的工字钢上。
所述的锁脚小导管为一根材料为无缝钢管的空心管,锁脚小导管的前端做成尖楔状,便于打插入孔中或直接打入,身上按梅花形钻小孔作为注浆孔;安装好需要锁脚的工字钢后,采用钻孔设备穿过锁脚钢板的圆洞,在围岩上以下倾方式钻直径大于锁脚小导管、深度与锁脚小导管长度相当的圆孔,成孔后安设锁脚小导管。
所述的限位圈为一个以小型号的钢筋加工成直径稍大于锁脚小导管外径的圆圈,套在锁脚小导管外露的头上,并作为矩形钢板与锁脚小导管焊接固定的连接物。
围岩与锁脚小导管通过注浆紧密连接,锁脚小导管与初期支护中的工字钢通过锁脚钢板采用焊接方式牢固连接,形成一个整体,共同受力,让拱顶围岩的垂直力和水平力都能传递到拱脚的围岩,约束初期支护在水平和垂直方向的变形,达到控制收敛、拱顶和地面整体下沉的目的。
本发明的有益效果是:
(1)能使围岩与锁脚小导管紧密连接,以及锁脚小导管与初期支护中的工字钢牢固连接,达到控制收敛、控制拱顶和地面整体下沉的目的;
(2)构件可以工厂化加工制作,钢板和工字钢可以在隧道外提前焊接在一起,减少了洞内的施工时间,提高了施工进度和工程质量,改善了洞内的施工环境;
(3)安全可靠,操作简便,兼顾了在安全、质量、进度、经济效益、社会效益等方面的要求。
附图说明
图1为本发明整体结构示意图;
图2为本发明钢板结构示意图;
图3为本发明小导管结构示意图;
图4为本发明钢筋圈结构示意图;
图中:1-工字钢,2-锁脚钢板,3-锁脚小导管,4-限位圈,5-圆洞,6-注浆孔。
具体实施方式
下面结合附图1-4对本发明作进一步说明。
在图1-3中,一种带钢板连接的锁脚小导管,由两根锁脚小导管3、一块锁脚钢板2和两个限位圈4组成。其特征在于,一块穿有两个对称圆洞5的锁脚钢板2,焊接在需要锁脚的工字钢1上;身上钻有注浆孔6的锁脚小导管3,穿过锁脚钢板2的圆洞5打进围岩里;在锁脚小导管3外露的头上套一个钢筋限位圈4,作为锁脚钢板2与锁脚小导管3焊接固定的连接物。
在图1中,所述的工字钢1为隧道初期支护中的工字钢。
在图2中,所述的锁脚钢板2为一块刚度足够的矩形钢板,长度为a,宽度为b,以矩形钢板长边为对称轴,对称的钻两个直径为Φ1的圆洞5,Φ1比锁脚小导管3的外径大,两个圆洞5的净间距为a2,a2要大于工字钢1的腿宽度,把锁脚钢板2按对称位置焊在需要锁脚的工字钢1上。
在图3中,所述的锁脚小导管3为一根材料为无缝钢管的空心管,锁脚小导管3的前端做成尖楔状,便于打插入孔中或直接打入,身上按梅花形钻小孔作为注浆孔6;安装好需要锁脚的工字钢1后,采用钻孔设备穿过锁脚钢板2的圆洞5,在围岩上以下倾方式钻直径大于锁脚小导管、深度与锁脚小导管长度L相当的圆孔,成孔后安设锁脚小导管3。
在图4中,所述的限位圈4为一个以小型号的钢筋加工成直径为Φ2的圆圈,Φ2稍大于锁脚小导管外径,限位圈4套在锁脚小导管3外露的头上,并作为锁脚钢板2与锁脚小导管3焊接固定的连接物。

Claims (4)

1.一种带钢板连接的锁脚小导管,由两根锁脚小导管、一块锁脚钢板和两个限位圈组成。其特征在于,一块穿有两个对称圆洞的锁脚钢板,焊接在需要锁脚的工字钢上;身上钻有注浆孔的锁脚小导管,穿过锁脚钢板的圆洞打进围岩里;在锁脚小导管外露的头上套一个钢筋限位圈,作为锁脚钢板与锁脚小导管焊接固定的连接物。
2.根据权利要求1所述的带钢板连接的锁脚小导管,其特征在于所述的锁脚钢板为一块刚度足够的矩形钢板,以矩形钢板长边为对称轴,对称的钻两个直径比锁脚小导管大的圆洞,两个圆洞净间距要大于工字钢的腿宽度,把钢板按对称位置焊在需要锁脚的工字钢上。
3.根据权利要求1所述的带钢板连接的锁脚小导管,其特征在于所述的锁脚小导管为一根材料为无缝钢管的空心管,锁脚小导管的前端做成尖楔状,便于打插入孔中或直接打入,身上按梅花形钻小孔作为注浆孔;安装好需要锁脚的工字钢后,采用钻孔设备穿过锁脚钢板的圆洞,在围岩上以下倾方式钻直径大于锁脚小导管、深度与锁脚小导管长度相当的圆孔,成孔后安设锁脚小导管。
4.根据权利要求1所述的带钢板连接的锁脚小导管,其特征在于所述的钢筋限位圈为一个以小型号的钢筋加工成直径稍大于锁脚小导管外径的圆圈,套在锁脚小导管外露的头上,并作为矩形钢板与锁脚小导管焊接固定的连接物。
CN201310250039.4A 2013-06-21 2013-06-21 带钢板连接的锁脚小导管 Active CN103277125B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310250039.4A CN103277125B (zh) 2013-06-21 2013-06-21 带钢板连接的锁脚小导管

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310250039.4A CN103277125B (zh) 2013-06-21 2013-06-21 带钢板连接的锁脚小导管

Publications (2)

Publication Number Publication Date
CN103277125A true CN103277125A (zh) 2013-09-04
CN103277125B CN103277125B (zh) 2016-03-23

Family

ID=49059729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310250039.4A Active CN103277125B (zh) 2013-06-21 2013-06-21 带钢板连接的锁脚小导管

Country Status (1)

Country Link
CN (1) CN103277125B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234724A (zh) * 2014-09-29 2014-12-24 中铁五局(集团)有限公司 一种用于隧道锁脚锚管精准定位并与钢架成为一体的装置
CN105134258A (zh) * 2015-08-14 2015-12-09 中国建筑土木建设有限公司 全风化ⅵ级围岩隧道多台阶管棚锁脚施工方法
CN106979024A (zh) * 2017-04-27 2017-07-25 中铁十局集团第四工程有限公司 一种固定隧道钢支撑与锁脚的施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005344346A (ja) * 2004-06-02 2005-12-15 Japan Railway Construction Transport & Technology Agency 鋼管打設工法
CN101852083A (zh) * 2010-04-16 2010-10-06 中国科学院武汉岩土力学研究所 大变形易冒落破碎松散巷道的快速支护方法及装置
CN102678134A (zh) * 2012-05-18 2012-09-19 中铁十二局集团第二工程有限公司 迈式管棚处理风积砂质黄土隧道塌陷下沉侵限施工方法
CN203394555U (zh) * 2013-06-21 2014-01-15 云南云岭高速公路桥梁工程有限公司 带钢板连接的锁脚小导管

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005344346A (ja) * 2004-06-02 2005-12-15 Japan Railway Construction Transport & Technology Agency 鋼管打設工法
CN101852083A (zh) * 2010-04-16 2010-10-06 中国科学院武汉岩土力学研究所 大变形易冒落破碎松散巷道的快速支护方法及装置
CN102678134A (zh) * 2012-05-18 2012-09-19 中铁十二局集团第二工程有限公司 迈式管棚处理风积砂质黄土隧道塌陷下沉侵限施工方法
CN203394555U (zh) * 2013-06-21 2014-01-15 云南云岭高速公路桥梁工程有限公司 带钢板连接的锁脚小导管

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨明槐: "锁脚小导管注浆在隧道Ⅳ、Ⅴ级围岩施工中的应用", 《石家庄铁路工程职业技术学院学报》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234724A (zh) * 2014-09-29 2014-12-24 中铁五局(集团)有限公司 一种用于隧道锁脚锚管精准定位并与钢架成为一体的装置
CN105134258A (zh) * 2015-08-14 2015-12-09 中国建筑土木建设有限公司 全风化ⅵ级围岩隧道多台阶管棚锁脚施工方法
CN106979024A (zh) * 2017-04-27 2017-07-25 中铁十局集团第四工程有限公司 一种固定隧道钢支撑与锁脚的施工方法
CN106979024B (zh) * 2017-04-27 2019-02-01 中铁十一局集团第四工程有限公司 一种固定隧道钢支撑与锁脚的施工方法

Also Published As

Publication number Publication date
CN103277125B (zh) 2016-03-23

Similar Documents

Publication Publication Date Title
CN203756182U (zh) 一种应用于软弱岩质区域浅埋公路隧道的支护结构
CN204552783U (zh) 一种黄土隧道竖向变形控制结构
CN109024651B (zh) 一种钢管混凝土混合桩基及施工方法
CN203394555U (zh) 带钢板连接的锁脚小导管
CN102797478A (zh) 分布式抗剪阻滑钢筋混凝土桩防治软岩巷道底鼓方法
CN103277125A (zh) 带钢板连接的锁脚小导管
CN202628123U (zh) 大断面断层破碎带隧道突泥处理结构
CN206467667U (zh) 一种采用膨胀式固定钢筋网片的桩间挂网喷锚围护结构
CN109209443A (zh) 一种破碎围岩隧道结构的修建方法
CN102518451A (zh) 一种黄土含水地质硐室喷射混凝土支护施工方法
CN104141500A (zh) 一种板结砂砾石地层洞室施工方法
CN205152983U (zh) 地下空间施工的地层预加固处理结构
CN202644519U (zh) 钻孔灌注桩钢筋笼防上浮专用固定卡
CN204551549U (zh) 盖挖逆作法基坑中钢管立柱与桩基、底板纵梁的连接节点
CN106284366A (zh) 外拉式拉森钢板桩加固方法
CN210317344U (zh) 一种隧道钢管拱初期支护结构
CN204174638U (zh) 地下建筑物加固结构
CN204738819U (zh) 隧道用非扰动型塌腔支护结构
CN103410529A (zh) 一种用于软弱围岩的隧道支撑拱脚加固结构及施工方法
CN203583501U (zh) 一种抵抗岩体滑动的深层抗剪装置
CN205938203U (zh) 一种沿山体外弧面敷设供水管的转弯支撑结构
CN210369864U (zh) 一种外脚手架法兰盘连墙件
CN209212270U (zh) 钢管排水锁脚桩
CN206419043U (zh) 一种隧道换拱施工支撑结构
CN207405615U (zh) 一种渠式切割水泥土连续墙组合工形预制桩的支护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 650224, No. 226, alliance road, Panlong District, Yunnan, Kunming

Applicant after: Yunling, Yunnan expressway construction Group Co., Ltd

Address before: 650224, No. 226, alliance road, Panlong District, Yunnan, Kunming

Applicant before: Yunnan Yunling Expressway Bridge Construction Co., Ltd.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 650224, No. 226, alliance road, Panlong District, Yunnan, Kunming

Patentee after: The Yunnan investment group Yunling Construction Co. Ltd.

Address before: 650224, No. 226, alliance road, Panlong District, Yunnan, Kunming

Patentee before: Yunling, Yunnan expressway construction Group Co., Ltd