CN103266899A - Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall - Google Patents

Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall Download PDF

Info

Publication number
CN103266899A
CN103266899A CN2013102130359A CN201310213035A CN103266899A CN 103266899 A CN103266899 A CN 103266899A CN 2013102130359 A CN2013102130359 A CN 2013102130359A CN 201310213035 A CN201310213035 A CN 201310213035A CN 103266899 A CN103266899 A CN 103266899A
Authority
CN
China
Prior art keywords
roadway
concrete
continuous wall
wall
floor heave
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102130359A
Other languages
Chinese (zh)
Inventor
蒋宇静
王刚
吴学震
张学朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN2013102130359A priority Critical patent/CN103266899A/en
Publication of CN103266899A publication Critical patent/CN103266899A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a method for controlling floor heave deformation of a soft rock roadway by means of an anchor pile continuous wall. The method for controlling the floor heave deformation of the soft rock roadway by means of the anchor pile continuous wall comprises the flowing steps that a, a roadway base plate is dug according to a given central line and a given height, wall structure grooves are vertically dug downwards along two walls, and then a round pile pit is dug downwards on the bottom of each groove; b, I-steel is inserted into the round pile pits after the round pile pits are dug, concrete is poured into the pipe pits, a rectangular reinforcing cage which is tied in advance is placed in each groove, bar-mat reinforcement is paved on the bottom surface of the roadway, two sides of the bar-mat reinforcement are connected with reinforcing steel bars of the reinforced concrete walls, the walls are poured with concrete, and finally concrete is sprayed on the bottom surface of the roadway; c, the length of the roadway base plate is controlled according to need and the step a and the step b are repeated until the anchor pile continuous wall is constructed. The method for controlling the floor heave deformation of the soft rock roadway by means of the anchor pile continuous wall has the advantages that a slip line of deformation and crack of a surrounding rock can be effectively cut off, the surrounding rock is prevented from moving and sliding, and the floor heave degree is reduced. The method for controlling the floor heave deformation of the soft rock roadway by means of the anchor pile continuous wall is particularly suitable for being used for managing wide-range floor heave disasters of coal mining roadways under the extreme conditions of high stress, high expansion, extremely soft rocks and the like.

Description

The method of anchoring pile diaphragm wall control soft-rock tunnel pucking distortion
Technical field
The present invention relates to the soft rock roadway support method, relate in particular to a kind of method of utilizing the distortion of anchoring pile diaphragm wall control soft-rock tunnel pucking.
Background technology
The pucking deformation failure is the ubiquitous mode of failure of coal mine roadway, and particularly outstanding in soft-rock tunnel, violent pucking distortion can cause the unstability of whole tunnel, reduce the tunnel useful area, influence the normal use in tunnel, increase maintenance and drop into, even can cause serious accident.
At present, the method for improvement soft-rock tunnel pucking has a variety of, plays anchor pole and closed steel bracket etc. as arch of the anti-end, floor grouting, base plate.For low stress or the not too soft situation of lithology, said method can effectively be controlled the distortion of country rock pucking.But under heavily stressed or dead-soft rock condition, rheology distortion or shearing slip distortion very easily take place in the roadway floor rock mass, and said method can not effectively be controlled the pucking deformation failure in this tunnel, and it is unreliable to exist safety to go up, economically irrational problem.
According to mechanical analysis as can be known, cut off the skid wire that surrouding rock deformation is broken by diaphragm wall, can stop country rock motion and slippage, thereby reduce tunnel pucking degree.Yet when traditional diaphragm wall was used for coal mine roadway, its rigidity and insufficient strength can not be born huge pressure from surrounding rock; When adopting reinforced concrete wall, as Chinese patent 2012103070011, because constructional difficulties, the body of wall height is restricted, and can't be deep into roadway floor and stablize the rock stratum, is difficult to obtain satisfied effect.
Summary of the invention
The objective of the invention is to address the above problem by the fit applications of steel sheet pile and reinforced concrete wall, the method for a kind of anchoring pile diaphragm wall control soft-rock tunnel pucking distortion is provided.
Its technical solution is:
The method of a kind of anchoring pile diaphragm wall control soft-rock tunnel pucking distortion comprises the following steps:
A, the form that cooperates artificial pick to dig with pneumatic pick by given center line and dig roadway floor highly clearly, are dug out the wall construction groove along two walls, the degree of depth 600 ~ 1000mm, width 350 ~ 500mm straight down; Dig out the circular stake hole that the degree of depth is 700 ~ 1200mm, diameter 250 ~ 400mm at bottom land downwards every 800 ~ 1200mm then;
After b, excavation are finished, the circular stake that the vertical insertion of i iron is dug is in advance cheated, to the interior concreting in stake hole, and vibration compacting, after treating that concrete has certain intensity, the rectangle reinforcing cage of colligation is in advance put into groove, be connected with the reinforcing bar of reinforced concrete wall at bottom surface, tunnel laying steel mesh reinforcement and with its both sides, using the poured concrete wall body then, is the concrete of 150 ~ 250mm at bottom surface, tunnel spray thickness at last;
C, handle the length of roadway floor as required, repeating step a, b finish until the anchoring pile construction of diaphragm wall.
Described rectangle reinforcing cage comprises main muscle and stirrup, and main muscle arranges that vertically each body of wall comprises 6 ~ 10 main muscle, and the stirrup disposition interval is 200 ~ 400mm.
Described i iron, length are wall construction gash depth and stake hole degree of depth sum, can change waste and old steel rail etc. into according to the colliery current material.
The present invention compared with prior art, the advantage and the beneficial effect that have comprise:
(1) in the process in excavation wall construction groove and circular stake hole, the stress of primary rock obtains certain release, has reduced the soft rock roadway support difficulty; (2) anchoring pile is deep into roadway floor and stablizes the rock stratum, and the diaphragm wall structure then can stop country rock to the rheology distortion of bottom, tunnel, both in conjunction with using, improved the rigidity of body of wall, and can effectively cut off the skid wire that surrouding rock deformation is broken, stop country rock motion and slippage, thereby reduce the pucking degree; (3) form an integral body with the anchoring pile diaphragm wall after the concrete setting of the steel mesh reinforcement of roadway floor laying and injection, its pressure from surrounding rock of bearing can be delivered to the base slab stability rock stratum, thereby it is stable to keep roadway floor, is specially adapted to the improvement of pucking distortion on a large scale disaster in stope of coal mines tunnel under the extreme conditions such as heavily stressed, high expansion and dead-soft rock.
Description of drawings
The invention will be further described below in conjunction with accompanying drawing and the specific embodiment:
Fig. 1 is structure section schematic diagram of the present invention;
Fig. 2 is the schematic top plan view of Fig. 1;
Fig. 3 is rectangle reinforcing cage arrangement of reinforcement.
Marginal data, 1-diaphragm wall, 2-steel sheet pile, 3-sprayed mortar, 4-steel mesh reinforcement, 5-i iron, 6-master's muscle, 7-stirrup.
Description of drawings
As illustrated in fig. 1 and 2, the method for a kind of anchoring pile diaphragm wall control of the present invention soft-rock tunnel pucking distortion is characterized in that comprising the following steps:
A, cooperate the form of manually digging with pick with pneumatic pick, by given center line and dig roadway floor highly clearly, dig out continuous groove straight down along the two side, tunnel, be used for settling diaphragm wall 1, degree of depth 750mm, width 400mm; Then at bottom land every 1000mm, digging out the degree of depth downwards is 750mm, diameter is the circular stake hole of 350mm, is used for settling steel sheet pile 2;
After b, excavation are finished, be the circular stake hole that the i iron 5 vertical insertions of 1500mm are dug in advance with length, to the interior concreting (can mix a certain amount of accelerating admixture) in stake hole, and vibration compacting, guarantee that i iron is wrapped up fully by concrete, after treating that concrete has certain intensity, the rectangle reinforcing cage of colligation is in advance put into groove, be connected with the reinforcing bar of reinforced concrete wall at bottom surface, tunnel laying steel mesh reinforcement 4 and with its both sides, use the poured concrete wall body then, at bottom surface, tunnel construction sprayed mortar 3, thickness is 150mm at last;
C, handle the length of roadway floor as required, repeating step a, b finish until the anchoring pile construction of diaphragm wall.
Described rectangle reinforcing cage comprises main muscle 6 and stirrup 7 as shown in Figure 3, and main muscle 6 arranges that vertically each body of wall comprises six main muscle, and stirrup 7 disposition intervals are 300mm.The model of described i iron 5 adopts 25a, can change waste and old steel rail etc. into according to the colliery current material.
The above embodiment is a kind of of the more preferably concrete embodiment of the present invention, and the common variation that those skilled in the art carries out in the technical solution of the present invention scope and replacement all should be included in protection scope of the present invention.

Claims (3)

1. the method for anchoring pile diaphragm wall control soft-rock tunnel pucking distortion is characterized in that comprising the following steps:
A, the form that cooperates artificial pick to dig with pneumatic pick by given center line and dig roadway floor highly clearly, are dug out the wall construction groove along two walls, the degree of depth 600 ~ 1000mm, width 350 ~ 500mm straight down; Dig out the circular stake hole that the degree of depth is 700 ~ 1200mm, diameter 250 ~ 400mm at bottom land downwards every 800 ~ 1200mm then;
After b, excavation are finished, the circular stake that the vertical insertion of i iron is dug is in advance cheated, to the interior concreting in stake hole, and vibration compacting, after treating that concrete has certain intensity, the rectangle reinforcing cage of colligation is in advance put into groove, be connected with the reinforcing bar of reinforced concrete wall at bottom surface, tunnel laying steel mesh reinforcement and with its both sides, using the poured concrete wall body then, is the concrete of 150 ~ 250mm at bottom surface, tunnel spray thickness at last;
C, handle the length of roadway floor as required, repeating step a, b finish until the anchoring pile construction of diaphragm wall.
2. the method for a kind of anchoring pile diaphragm wall control soft-rock tunnel pucking as claimed in claim 1 distortion is characterized in that described rectangle reinforcing cage, comprise main muscle and stirrup, main muscle arranges that vertically each body of wall comprises 6 ~ 10 main muscle, and the stirrup disposition interval is 200 ~ 400mm.
3. the method for a kind of anchoring pile diaphragm wall control soft-rock tunnel pucking as claimed in claim 1 distortion is characterized in that, described i iron, and length is wall construction gash depth and stake hole degree of depth sum, can change waste and old steel rail etc. into according to the colliery current material.
CN2013102130359A 2013-05-31 2013-05-31 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall Pending CN103266899A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102130359A CN103266899A (en) 2013-05-31 2013-05-31 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102130359A CN103266899A (en) 2013-05-31 2013-05-31 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall

Publications (1)

Publication Number Publication Date
CN103266899A true CN103266899A (en) 2013-08-28

Family

ID=49010553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102130359A Pending CN103266899A (en) 2013-05-31 2013-05-31 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall

Country Status (1)

Country Link
CN (1) CN103266899A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590840A (en) * 2013-11-29 2014-02-19 王威 Floor grouting method
CN103628898A (en) * 2013-11-15 2014-03-12 山东科技大学 Continuous wall supporting method for preventing floor heaving of roadway
CN105484757A (en) * 2015-12-18 2016-04-13 中国神华能源股份有限公司 Method and structure for treating bottom heaving of fully-mechanized mining face gate roadway
CN115964902A (en) * 2023-03-16 2023-04-14 太原理工大学 Method for determining high-stress large-section soft rock bottom plate fracture area and controlling bottom heave

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4699547A (en) * 1985-03-15 1987-10-13 Seegmiller Ben L Mine truss structures and method
DE3820700A1 (en) * 1988-06-18 1989-12-21 Ruhrkohle Ag Compound anchor support system
CN101509383A (en) * 2009-03-24 2009-08-19 徐州工程学院 Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique
CN101915108A (en) * 2010-06-22 2010-12-15 中国矿业大学 Method for controlling floor heave of dynamic pressure tunnel
CN101886545B (en) * 2010-07-05 2011-11-30 北京科技大学 Method for treating bottom heave of soft rock roadway by using micro broken stone pipe cast pile
CN102444407A (en) * 2011-12-12 2012-05-09 中铁二局股份有限公司 Construction deformation control method for lower step of high crustal stress weak surrounding rock tunnel
CN101839140B (en) * 2010-03-31 2012-05-23 中国矿业大学 Method for reinforcing roadway floor by grouting
CN102797480A (en) * 2012-08-27 2012-11-28 中国矿业大学 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4699547A (en) * 1985-03-15 1987-10-13 Seegmiller Ben L Mine truss structures and method
DE3820700A1 (en) * 1988-06-18 1989-12-21 Ruhrkohle Ag Compound anchor support system
CN101509383A (en) * 2009-03-24 2009-08-19 徐州工程学院 Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique
CN101839140B (en) * 2010-03-31 2012-05-23 中国矿业大学 Method for reinforcing roadway floor by grouting
CN101915108A (en) * 2010-06-22 2010-12-15 中国矿业大学 Method for controlling floor heave of dynamic pressure tunnel
CN101886545B (en) * 2010-07-05 2011-11-30 北京科技大学 Method for treating bottom heave of soft rock roadway by using micro broken stone pipe cast pile
CN102444407A (en) * 2011-12-12 2012-05-09 中铁二局股份有限公司 Construction deformation control method for lower step of high crustal stress weak surrounding rock tunnel
CN102797480A (en) * 2012-08-27 2012-11-28 中国矿业大学 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628898A (en) * 2013-11-15 2014-03-12 山东科技大学 Continuous wall supporting method for preventing floor heaving of roadway
CN103628898B (en) * 2013-11-15 2016-01-20 山东科技大学 A kind of for preventing the diaphragm wall supporting method of Floor Heave in Roadway
CN103590840A (en) * 2013-11-29 2014-02-19 王威 Floor grouting method
CN105484757A (en) * 2015-12-18 2016-04-13 中国神华能源股份有限公司 Method and structure for treating bottom heaving of fully-mechanized mining face gate roadway
CN115964902A (en) * 2023-03-16 2023-04-14 太原理工大学 Method for determining high-stress large-section soft rock bottom plate fracture area and controlling bottom heave
CN115964902B (en) * 2023-03-16 2023-05-16 太原理工大学 Determination and bottom drum treatment method for high-stress large-section soft rock bottom plate fracture area

Similar Documents

Publication Publication Date Title
CN103469939B (en) Masonry infilled wall and main body flexible connection anti-seismic structure and construction method thereof
KR101022382B1 (en) Precast horizontality tubular roof and tunnel construction method using the same
CN107201908B (en) Construction method for deep-buried central ditch of tunnel in severe cold region
CN105239586B (en) Method for supporting foundation pit by adopting support structure
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN207406349U (en) Tunnel Base reinforcing construction
CN104195911A (en) Widened embankment structure with beside-water cliff high retaining wall fill section and construction method of widened embankment structure
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN103939113B (en) A kind of outstanding rail construction trolley
CN203729324U (en) Anchor rod lattice type retaining wall structure
CN203782684U (en) Anti-skid pile provided with crossbeam
CN103397656A (en) Embedded type joist pile plank structure
CN105569726A (en) Gob-side entry retaining method for GFRP (Glass Fiber Reinforced Polymer) tube concrete pier stud and gangue concrete wall
CN103266899A (en) Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN106193047B (en) Big width base pit stand construction
CN106321113A (en) Laneway space frame structure for goaf penetration and supporting method of lane space frame structure
CN104018490A (en) Z-shaped rectangular-section anti-skidding pile and construction method thereof
CN203285452U (en) Anchor pile continuous wall controlling floor heave deformation of soft rock roadway
CN103161474B (en) Construction method of down hole interchange roadway
CN204059125U (en) One suspended wall height barricade embankment near water section Widening Embankment structure
CN206956744U (en) A kind of compound retaining structure of curb
CN102828506A (en) Ultra-deep large-section square support pile and construction method thereof
CN201605588U (en) Structure for reinforcing and fixing slope surface of prestress anchoring frame beam
CN202181908U (en) Expanding soft rock roadway waterproof supporting combined structure
CN202881775U (en) Counter-arc shape sleeper for managing roadway heaving floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130828