CN103266772B - Curing method used for highway engineering construction concrete in winter - Google Patents

Curing method used for highway engineering construction concrete in winter Download PDF

Info

Publication number
CN103266772B
CN103266772B CN201310185404.8A CN201310185404A CN103266772B CN 103266772 B CN103266772 B CN 103266772B CN 201310185404 A CN201310185404 A CN 201310185404A CN 103266772 B CN103266772 B CN 103266772B
Authority
CN
China
Prior art keywords
concrete
temperature
health
strength
mist vapour
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310185404.8A
Other languages
Chinese (zh)
Other versions
CN103266772A (en
Inventor
李英勇
薛志超
杨秀生
曹佩荣
李秀贤
王同福
高晋
张继明
吕龙
曹海船
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG HENGJIAN ENGINEERING SUPERVISION AND CONSULTING Co Ltd
Original Assignee
SHANDONG HENGJIAN ENGINEERING SUPERVISION AND CONSULTING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG HENGJIAN ENGINEERING SUPERVISION AND CONSULTING Co Ltd filed Critical SHANDONG HENGJIAN ENGINEERING SUPERVISION AND CONSULTING Co Ltd
Priority to CN201310185404.8A priority Critical patent/CN103266772B/en
Publication of CN103266772A publication Critical patent/CN103266772A/en
Application granted granted Critical
Publication of CN103266772B publication Critical patent/CN103266772B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a curing method used for highway engineering construction concrete in winter. The curing method comprises arranging a pressure boiler and a box girder precast pedestal; arranging a main pipe line which is communicated with the pressure boiler on the bilateral sides of the box girder precast pedestal; binding box girder rebar and installing a box girder formwork; pre-embedding thermometer holes and pouring concrete; arranging a curing shed moving support; installing a branch pipe line and a fog steam nozzle; covering a canvas insulation layer on the curing shed moving support; and performing still-stand period, temperature-rise period, constant temperature period and temperature-fall period curing. According to the curing method used for the highway engineering construction concrete in winter, water vapor is formed into fog to cure the concrete under no pressure or small pressure and the fog steam temperature is controlled at about 30 DEG C to enable the strength of cement concrete to be improved under the condition of constant temperature and humidity to be beneficial to the formation of hydration products that crystallization is complete and crystal materials are uniform, so that the temperature difference of the concrete surface and the environment caused by the removal of the insulation layer is redued, concrete cracks can be prevented, and the later strength and durability of components are guaranteed.

Description

A kind of for the concrete maintenance process of highway engineering construction in winter
Technical field
The present invention relates to a kind of concrete maintenance process, specifically, relate to a kind of for the concrete maintenance process of highway engineering construction in winter, belong to Construction Technology field.
Background technology
The concrete teletostage maintenance of Current Highway engineering mainly contains regenerative process, steam heating and construction " heating house method ".Wherein regenerative process: be applicable to below ground engineering or structure is not suitable for more than ground concrete maintenance.Steam heating: when adopting Portland cement, curing temperature is no more than 80 DEG C; When adopting portland slag cement, curing temperature can reach 85 DEG C.Construction " heating house method ": require that temperature of shed is not less than 5 DEG C, and should keep certain humidity, should have the safety prevention measure of anti-gas poisoning of preventing fires.
Require in existing " highway bridge and culvert construction technique normalizing " (JTG/T F50-2011) that the curing temperature scope of steam heating is no more than 80 DEG C (85 DEG C), do not provide optimum temperature-controlled zones, usually temperature is controlled at 70-80 DEG C in practice of construction, hydrated cementitious is very fast, early age strength of concrete is high, but because the growth of hydrated product crystalline substance material is fast, crystallization is thick, later strength is often caused to rise slowly, also the durability of works is had influence on, after maintenance insulation layer and template are removed in succession, surface temperature of concrete differs larger with environment temperature like this, higher to the requirement of removing rear concrete surface covering and heat insulating, easily there is crack in concrete surface, still need to carry out covering and heat insulating to concrete surface, need to continue to adopt in construction " heating house method " construction often to use briquet stove heating, carbon dioxide content in brooder will be caused to raise, cause the early stage carbonization of concrete, concrete structure durability is had a negative impact.
Summary of the invention
Technical problem to be solved by this invention is for above-mentioned Problems existing, there is provided a kind of for the concrete maintenance process of highway engineering construction in winter, very little on late strength of concrete impact, avoid High-temperature Curing and terminate thermal cracking that rear concrete component internal-external temperature difference causes and shrinkage crack.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: a kind of for the concrete maintenance process of highway engineering construction in winter, it is characterized in that: described maintenance process comprises the following steps:
Arrange pressure boiler and prefabricated box-beam pedestal at precasting yard, lay main pipeline in the both sides of prefabricated box-beam pedestal, main pipeline is communicated with pressure boiler;
Colligation case beam steel, install bin beam forms;
Pre-buried thermometer hole, concreting: the metal sleeve of pre-buried length 10 ~ 15cm on reinforcing bar, time pre-buried, colligation is on the reinforcing bar of beam slab, is put in each 1 place of 0L, 1/4L, 1/2L, 3/4L, L place of beam body web, base plate, top board, and be numbered in order, concreting;
Arrange shed traversing carriage: after concreting, shed support is set around beam body, highly exceeds the end face 10 ± 2cm of beam body, length 20 ± 2cm larger than the length of beam body, width 10 ± 2cm larger than the widest part of beam body;
Branch pipe(tube) and mist vapour nozzle are installed: several branch pipe(tube)s are straight up set on main pipeline, spacing≤4 meter of adjacent branch pipe(tube), the end of branch pipe(tube) is provided with mist vapour nozzle, the Way out of mist vapour nozzle becomes miter angle obliquely, distance between the outer wall of mist vapour nozzle and beam body is 1 ± 0.1 meter, and main pipeline thermal insulation material wraps up;
Shed support covers canvas insulation layer, and canvas lower edge compresses;
Pressure boiler conveying mist vapour carries out health step, and health step comprises quietly puts stage, temperature rise period, constant temperature stage and temperature-fall period:
Describedly quietly put the stage: the quiet time of putting of wet concrete is 2 ~ 4 hours; The quiet time of putting of harsh concrete is 1 hour; The concrete in static time of putting being mixed with retarding additive is 4 ~ 6 hours;
The described temperature rise period: conveying mist vapour heats up, and beam surface programming rate controls within 10 DEG C/h, and the heating up time is 2 ~ 3 hours;
In the described constant temperature stage: prestressed concrete health temperature remains on 30 DEG C, treat that concrete crushing strength reaches 100% of design strength, enter temperature-fall period;
Described temperature-fall period: cooling rate is not more than 5 DEG C/h, controls health temperature by Valve controlling water vapour spray volume;
Remove insulation layer, concrete strength reach design strength 100% and curing age remove when reaching seven days, remove shed support.
The present invention adopts above technical scheme, compared with prior art, there is following effect: traditional steam curing is changed into the health of mist vapour, by pipeline to concreting ground, without under pressure or very little pressure, steam is nebulized health concrete, reduce the temperature of steam, mist stripping temperature controls at about 30 DEG C, test specimen entity proper temperature, decrease the crackle and liter that occur because concrete local temperature is too high, lower the temperature too fast, make cement concrete at constant temperature, intensity is increased under humidity constant state, be conducive to forming perfect crystalline, the uniform hydrated product of brilliant material, and the concrete surface brought after reducing dismounting insulation layer and ambient temperature differences, can prevent concrete from occurring crack, and be conducive to forming perfect crystalline, the uniform hydrated product of brilliant material, ensure that later strength and the durability of component.
Meanwhile, whole health process does not introduce carbon dioxide, reduces carbonation of concrete degree, decreases the discharge of pollutant.
Below in conjunction with drawings and Examples, the present invention is described in further detail.
Accompanying drawing explanation
Accompanying drawing 1 is the apparatus structure schematic diagram of maintenance process in the embodiment of the present invention;
Accompanying drawing 2 be in accompanying drawing 1 A-A to structural representation;
In figure,
1-pressure boiler, 2-prefabricated box-beam pedestal, 3-main pipeline, 4-mist vapour conveyance conduit, 5-shed support, 6-beam body, 7-branch pipe(tube), 8-mist vapour nozzle.
Detailed description of the invention
Embodiment, a kind of for the concrete maintenance process of highway engineering construction in winter, for prefabricated case beam health, comprise the following steps:
The first step: set up pressure boiler 1 at precasting yard, i.e. steam heating boiler, lay main pipeline 3 in the both sides of prefabricated box-beam pedestal 2, main pipeline 3 is communicated with pressure boiler 1 by mist vapour conveyance conduit 4, and main pipeline 3 adopts the pvc pipe of 5cm;
Second step: colligation case beam steel, install bin beam forms;
Second step: pre-buried thermometer hole metal sleeve, concreting: the metal sleeve of pre-buried internal diameter 12mm, long 10 ~ 15cm on reinforcing bar, time pre-buried, colligation is on the reinforcing bar of beam slab, be put in each 1 place of 0L, 1/4L, 1/2L, 3/4L, L place of beam body 6 web, base plate, top board, and be numbered in order, concreting;
3rd step: arrange shed traversing carriage: after concreting, shed support 5 is set around beam body 6, shed support 5 adopts φ 20 reinforcement welding to form, highly exceed the end face 10 ± 2cm of beam body 6, length 20 ± 2cm larger than the length of beam body 6, width 10 ± 2cm larger than the widest part of beam body 6;
4th step: install branch pipe(tube) and mist vapour nozzle: be provided with branch pipe(tube) 7 straight up on main pipeline 3, branch pipe(tube) 7 adopts the pvc pipe of 2cm, spacing≤4 meter of adjacent branch pipe(tube) 7, the end of branch pipe(tube) 7 is provided with mist vapour nozzle 8, the Way out of mist vapour nozzle 8 becomes miter angle obliquely, distance between mist vapour nozzle 8 and the outer wall of beam body 6 is 1 ± 0.1 meter, and to prevent mist vapour from directly blowing on concrete, main pipeline 3, mist vapour conveyance conduit 4 wrap up with thermal insulation material;
5th step: cover canvas insulation layer on shed support 5, canvas lower edge steel pipe, reinforcing bar compress, and prevent ventilative;
6th step: pressure boiler 1, namely steam heating boiler conveying mist vapour carries out health step;
Health step divides four-stage, quietly puts the stage: wet concrete is 2 ~ 4 hours; Harsh concrete is 1 hour, the concrete being mixed with retarding additive is 4 ~ 6 hours, quiet temperature of putting should not lower than 10 DEG C, this one-phase mainly makes cement in concrete have a more abundant hydration time, concrete forms some strength, with the resistance of Concrete Structure to temperature rise period Structural Disintegration, avoid occurring crack and loose phenomenon in component surface during the maintenance of mist vapour.This is very important for the swelling of elimination concrete in intensification;
Temperature rise period: conveying mist vapour heats up, and beam surface programming rate controls within 10 DEG C/h, and the heating up time is 2 ~ 3 hours, this one-phase, hydrated reaction of cement is accelerated, and forms some strength gradually, and concrete generation heat expansion is out of shape, and inside and outside the temperature difference can produce thermal stresses;
In the constant temperature stage: prestressed concrete health temperature remains on 30 DEG C, treat that concrete strength reaches 100%, after can lower the temperature, under identical curing condition, the intensity of concrete test block is concrete strength;
Temperature-fall period: cooling rate is not more than 5 DEG C/h, controls health temperature by Valve controlling water vapour spray volume, with prevent concrete surface and internal difference in temperature excessive and produce crack, and fill in mist vapour health record;
Control the concrete temperature 10 DEG C-30 DEG C in 7d after building, heating-cooling speed measurement per hour temperature, thermometer stops and is not less than 3 minutes in pipe, then takes out and writes down temperature.To component, namely within during the health of case beam constant temperature every 2 hours, carry out a temperature survey and record, set up health temperature and detect account.By test room, compressive strength inspection is carried out to test block, reach 100% design strength rear and allow to lower the temperature.
7th step: concrete strength reach design strength 100% and curing age when reaching seven days, remove insulation layer, remove shed support 5.
Health effect:
Intensity rebound test is carried out by concrete structure low temperature micro-carbon mist vapour method being carried out to health in winter, result is all qualified in and even, surperficial any crack, low temperature micro-carbon mist vapour regimen controls mist stripping temperature at about 30 DEG C, test specimen entity proper temperature, avoid the too high easy generation fine cracks of vapor (steam) temperature and the too fast phenomenon of heating-cooling occurs, cement concrete is made to increase intensity under constant temperature, humidity constant state, be conducive to forming perfect crystalline, the uniform hydrated product of brilliant material, ensure that later strength and the durability of component.
Test:
In the speed construction of blue or green Lingao, for analyzing the health of low temperature micro-carbon mist vapour to the impact of concrete strength, the feasibility of checking low temperature micro-carbon mist vapour health, carry out following contrast test according to maintenance process of the present invention:
Getting C30 precast plate concrete mix, to carry out test block prefabricated, under being positioned over 75 DEG C of steam curing conditions and 30 DEG C of mist vapour health-preserving conditions respectively, carry out concrete strength compression test the length of time to 3d, 5d, 7d, 14d, 28d respectively, under different condition, concrete crushing strength (MPa) comparing result is as following table:
Health-preserving condition/length of time 3d 5d 7d 14d 28d
75 DEG C of steam curings 28.2 31.8 33.2 37.2 41.6
The health of 30 DEG C of mist vapour 21.5 26.2 28.4 35.2 41.2
Experimental data illustrates, 75 DEG C of steam curings, due to higher temperature, improve the hydration rate of concrete cement, and concrete hydration reaction is comparatively fast corresponding, and early age strength of concrete promotes very fast, but later strength increasess slowly; Under 30 DEG C of mist vapour health-preserving conditions, concrete test block intensity increases relatively slow in early days, and later stage concrete strength is substantially identical with under 75 DEG C of steam curing conditions.
Low temperature (30 DEG C) health is very little on late strength of concrete impact, helps avoid High-temperature Curing simultaneously and terminates thermal cracking that rear concrete component internal-external temperature difference causes and shrinkage crack, contribute to alleviating the early stage carbonization of concrete easily occurred in general health.
The micro-carbon health-preserving method of low temperature mist vapour that this health-preserving method is discussed is equally applicable to the health of the position winter construction such as cast-in-situ box girder, precast hollow slab, bent cap and pier stud.
Those skilled in the art will recognize that; above-mentioned detailed description of the invention is exemplary; to enable those skilled in the art better understand content of the present invention; should not be understood as limiting the scope of the invention; as long as according to the improvement that technical solution of the present invention is done, all fall into protection scope of the present invention.

Claims (1)

1. for the concrete maintenance process of highway engineering construction in winter, it is characterized in that: described maintenance process comprises the following steps:
The first step: set up pressure boiler (1) at precasting yard, i.e. steam heating boiler, lay main pipeline (3) in the both sides of prefabricated box-beam pedestal (2), main pipeline (3) is communicated with pressure boiler (1) by mist vapour conveyance conduit (4), and main pipeline (3) adopts the pvc pipe of 5cm;
Second step: colligation case beam steel, install bin beam forms;
Second step: pre-buried thermometer hole metal sleeve, concreting: the metal sleeve of pre-buried internal diameter 12mm, long 10 ~ 15cm on reinforcing bar, time pre-buried, colligation is on the reinforcing bar of beam slab, be put in each 1 place of 0L, 1/4L, 1/2L, 3/4L, L place of beam body (6) web, base plate, top board, and be numbered in order, concreting;
3rd step: arrange shed traversing carriage: after concreting, shed support (5) is set around beam body (6), shed support (5) adopts φ 20 reinforcement welding to form, highly exceed the end face 10 ± 2cm of beam body (6), length 20 ± 2cm larger than the length of beam body (6), width 10 ± 2cm larger than the widest part of beam body (6);
4th step: install branch pipe(tube) and mist vapour nozzle: be provided with branch pipe(tube) (7) straight up on main pipeline (3), branch pipe(tube) (7) adopts the pvc pipe of 2cm, spacing≤4 meter of adjacent branch pipe(tube) (7), the end of branch pipe(tube) (7) is provided with mist vapour nozzle (8), the Way out of mist vapour nozzle (8) becomes miter angle obliquely, distance between the outer wall of mist vapour nozzle (8) and beam body (6) is 1 ± 0.1 meter, to prevent mist vapour from directly blowing on concrete, main pipeline (3), mist vapour conveyance conduit (4) wrap up with thermal insulation material;
5th step: at shed support (5) upper covering canvas insulation layer, canvas lower edge steel pipe, reinforcing bar compress, and prevent ventilative;
6th step: pressure boiler (1) conveying mist vapour carries out health step;
Health step divides four-stage, quietly puts the stage: wet concrete is 2 ~ 4 hours; Harsh concrete is 1 hour, the concrete being mixed with retarding additive is 4 ~ 6 hours, quiet temperature of putting should not lower than 10 DEG C, this one-phase mainly makes cement in concrete have a more abundant hydration time, concrete forms some strength, with the resistance of Concrete Structure to temperature rise period Structural Disintegration, avoid occurring crack and loose phenomenon in component surface during the maintenance of mist vapour;
Temperature rise period: conveying mist vapour heats up, and beam surface programming rate controls within 10 DEG C/h, and the heating up time is 2 ~ 3 hours, this one-phase, hydrated reaction of cement is accelerated, and forms some strength gradually, and concrete generation heat expansion is out of shape, and inside and outside the temperature difference can produce thermal stresses;
In the constant temperature stage: prestressed concrete health temperature remains on 30 DEG C, treat that concrete strength reaches 100%, after can lower the temperature, under identical curing condition, the intensity of concrete test block is concrete strength;
Temperature-fall period: cooling rate is not more than 5 DEG C/h, controls health temperature by Valve controlling water vapour spray volume, with prevent concrete surface and internal difference in temperature excessive and produce crack, and fill in mist vapour health record;
Control the concrete temperature 10 DEG C-30 DEG C in 7d after building, heating-cooling speed measurement per hour temperature, thermometer stops and is not less than 3 minutes in pipe, then take out and write down temperature, to component, namely within during the health of case beam constant temperature every 2 hours, carry out a temperature survey and record, set up health temperature and detect account, by test room, compressive strength inspection is carried out to test block, reach 100% design strength rear and allow to lower the temperature;
7th step: concrete strength reach design strength 100% and curing age when reaching seven days, remove insulation layer, remove shed support (5);
Under 30 DEG C of mist vapour health-preserving conditions, 3d, 5d, 7d, 14d, 28d age concrete compressive strength is 21.5MPa, 26.2MPa, 28.4MPa, 35.2MPa, 41.2MPa.
CN201310185404.8A 2013-05-20 2013-05-20 Curing method used for highway engineering construction concrete in winter Expired - Fee Related CN103266772B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310185404.8A CN103266772B (en) 2013-05-20 2013-05-20 Curing method used for highway engineering construction concrete in winter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310185404.8A CN103266772B (en) 2013-05-20 2013-05-20 Curing method used for highway engineering construction concrete in winter

Publications (2)

Publication Number Publication Date
CN103266772A CN103266772A (en) 2013-08-28
CN103266772B true CN103266772B (en) 2015-07-22

Family

ID=49010426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310185404.8A Expired - Fee Related CN103266772B (en) 2013-05-20 2013-05-20 Curing method used for highway engineering construction concrete in winter

Country Status (1)

Country Link
CN (1) CN103266772B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385528B (en) * 2016-09-18 2019-06-28 山东省交通科学研究院 A kind of application method of low temperature season pier stud concrete heat-insulating health preserving equipment
CN107877681A (en) * 2017-10-30 2018-04-06 山东高速轨道设备材料有限公司 A kind of Maintenance in Winter method of concrete component
CN108018779A (en) * 2017-11-30 2018-05-11 苏交科集团股份有限公司 Concrete construction method under a kind of low temperature difference environment
CN107916793A (en) * 2017-12-20 2018-04-17 宁波二十冶建设有限公司 A kind of cold weather concrete curing means
CN108978472B (en) * 2018-07-05 2020-03-31 中交二航局第二工程有限公司 Maintenance method suitable for winter construction of hanging basket suspension casting box girder in strong wind area
CN109024284A (en) * 2018-07-09 2018-12-18 贵州新联爆破工程集团有限公司 A kind of cored slab simply supported beam casting concrete cooling device
CN109551621A (en) * 2018-10-09 2019-04-02 中建市政工程有限公司 Water-saving maintenance method and maintenance device for precast beam
CN109571735A (en) * 2019-02-22 2019-04-05 云南建投第十建设有限公司 Green bio low-voltage high-temperature steam press maintenance system
CN110181669A (en) * 2019-05-27 2019-08-30 中国十七冶集团有限公司 Using solar energy cyclic steam to the construction method of beam slab winter health
CN110499790A (en) * 2019-07-26 2019-11-26 国网辽宁省电力有限公司鞍山供电公司 A kind of detection device of winter iron tower foundation construction concrete critical intensity
CN111364731B (en) * 2020-03-14 2021-07-13 深圳市第一建筑工程有限公司 Reinforced concrete ground seamless construction device and method
CN113001772A (en) * 2021-02-22 2021-06-22 中电建十一局工程有限公司 Winter heat preservation construction method for concrete precast beam
CN113309106A (en) * 2021-06-07 2021-08-27 中国水利水电第九工程局有限公司 Dam concrete construction method in low-temperature season in high-altitude cold region
CN113370367B (en) * 2021-06-29 2022-05-13 保利长大工程有限公司 Combined UHPC (ultra high performance polycarbonate) curing method
CN113719144A (en) * 2021-07-13 2021-11-30 中铁十九局集团有限公司 Method for construction and maintenance of beam body in winter
CN115097875A (en) * 2022-05-20 2022-09-23 湖南科技大学 Carbon fiber electric heating-based concrete structure prestressed pipeline temperature control system and control method

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338129A (en) * 1995-06-13 1996-12-24 Takiuchi Kasetsu Kk Concrete curing form and method of concrete curing
CN1830644A (en) * 2006-04-17 2006-09-13 上海隧道工程股份有限公司 Cast-in-place box girder low-temperature steam maintenance operating method
CN2915446Y (en) * 2006-05-31 2007-06-27 郑祖元 Standard maintenance apparatus for cement concrete test piece
CN2920608Y (en) * 2006-06-27 2007-07-11 深圳市建筑科学研究院 Concrete curing box
CN101244607A (en) * 2008-03-17 2008-08-20 中铁二局股份有限公司 Precast beam maintaining apparatus and maintaining method
CN201232359Y (en) * 2008-06-13 2009-05-06 中建三局第二建设工程有限责任公司 Internal dispersion and external accumulation concrete moisture retention and temperature control maintaining system
CN101791823A (en) * 2010-03-25 2010-08-04 淮海工学院 Fast curing method of concrete members
EP1090892B1 (en) * 1998-06-04 2011-01-19 Denki Kagaku Kogyo Kabushiki Kaisha High-temperature, high-pressure underwater concrete product curing device and curing method for concrete product using the curing device
CN201837056U (en) * 2010-10-26 2011-05-18 中铁十三局集团有限公司 Nested warm air furnace
CN202162884U (en) * 2011-07-26 2012-03-14 中铁一局集团有限公司 Sliding type box girder precast maintenance tent
CN202391147U (en) * 2011-11-24 2012-08-22 天津二十冶建设有限公司 Greenhouse for concrete construction in winter
JP2012233309A (en) * 2011-04-28 2012-11-29 Kajima Corp Concrete curing method and device
CN202826031U (en) * 2012-10-17 2013-03-27 中建三局第一建设工程有限责任公司 Steam generator for road maintenance

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338129A (en) * 1995-06-13 1996-12-24 Takiuchi Kasetsu Kk Concrete curing form and method of concrete curing
EP1090892B1 (en) * 1998-06-04 2011-01-19 Denki Kagaku Kogyo Kabushiki Kaisha High-temperature, high-pressure underwater concrete product curing device and curing method for concrete product using the curing device
CN1830644A (en) * 2006-04-17 2006-09-13 上海隧道工程股份有限公司 Cast-in-place box girder low-temperature steam maintenance operating method
CN2915446Y (en) * 2006-05-31 2007-06-27 郑祖元 Standard maintenance apparatus for cement concrete test piece
CN2920608Y (en) * 2006-06-27 2007-07-11 深圳市建筑科学研究院 Concrete curing box
CN101244607A (en) * 2008-03-17 2008-08-20 中铁二局股份有限公司 Precast beam maintaining apparatus and maintaining method
CN201232359Y (en) * 2008-06-13 2009-05-06 中建三局第二建设工程有限责任公司 Internal dispersion and external accumulation concrete moisture retention and temperature control maintaining system
CN101791823A (en) * 2010-03-25 2010-08-04 淮海工学院 Fast curing method of concrete members
CN201837056U (en) * 2010-10-26 2011-05-18 中铁十三局集团有限公司 Nested warm air furnace
JP2012233309A (en) * 2011-04-28 2012-11-29 Kajima Corp Concrete curing method and device
CN202162884U (en) * 2011-07-26 2012-03-14 中铁一局集团有限公司 Sliding type box girder precast maintenance tent
CN202391147U (en) * 2011-11-24 2012-08-22 天津二十冶建设有限公司 Greenhouse for concrete construction in winter
CN202826031U (en) * 2012-10-17 2013-03-27 中建三局第一建设工程有限责任公司 Steam generator for road maintenance

Also Published As

Publication number Publication date
CN103266772A (en) 2013-08-28

Similar Documents

Publication Publication Date Title
CN103266772B (en) Curing method used for highway engineering construction concrete in winter
CN105133615B (en) Circulating cooling water temperature-control construction method for mass concrete in large temperature difference environments of Qinghai-Tibet plateau areas
CN101413251B (en) 0 type block anti-cracking construction method of high pier large across creeping formwork
CN104278598A (en) Self-compacting bituminous concrete waterproof seal and construction method thereof
CN104264678A (en) Mass concrete cracking proof construction technology
CN102011492B (en) Method for controlling occurrence of cracks on mass concrete structure
CN102619329B (en) Expansion restraint construction method for post-pouring belt
CN102661154A (en) Double-layer structural concrete for lining tunnel under condition of terrestrial heat erosion and construction method of double-layer structural concrete
CN105822068A (en) Ultra-long thin wall concrete wall pouring and maintenance method under high temperature environment
CN102182316A (en) Building method for controlling temperature cracks of masonry
CN216196782U (en) Single-layer multi-loop water cooling system for super-thick large-volume concrete
CN207646954U (en) Cast-in-place concrete compound external mold plate body system
CN207159822U (en) A kind of bridge pier mass concrete temperature regulating device
CN110578300A (en) Large-volume concrete pouring process for special-shaped bridge pier column
CN104264675A (en) Method for controlling mass concrete quality of high-rise building foundation
CN104652280A (en) One-time continuous forming and pouring method for ultralong post-poured fish ridge wall and ultralong fish ridge wall
CN113774957B (en) Open-cut cast-in-place tunnel main structure concrete anti-cracking construction method
CN103805723B (en) Blast-furnace hot-air pipeline transposition section refractory brick comes off quick prosthetic appliance and method
Imaykin et al. Perfecting technology of winter concreting of cast-in-situ columns
Cheng Mass Concrete Crack Control Technology
CN207144522U (en) Large volume ultra-long concrete teletostage jointless construction conserves structure
CN115387372A (en) Construction method for preventing concrete cracks
CN204421587U (en) Zinc oxide settling bin top arcuate cast template
CN113217033B (en) Construction method of anti-impact wear-resistant concrete of bottom plate of hydraulic tunnel
CN109537626A (en) A kind of control cracking method of subway station concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Li Yingyong

Inventor after: Cao Haichuan

Inventor after: Xue Zhichao

Inventor after: Yang Xiusheng

Inventor after: Cao Peirong

Inventor after: Li Xiuxian

Inventor after: Wang Tongfu

Inventor after: Gao Jin

Inventor after: Zhang Jiming

Inventor after: Lv Long

Inventor before: Li Yingyong

Inventor before: Xue Zhichao

Inventor before: Yang Jingxin

Inventor before: Cao Peirong

Inventor before: Chen Baoqiang

Inventor before: Gao Jin

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LI YINGYONG XUE ZHICHAO YANG JINGXIN CAO PEIRONG CHEN BAOQIANG GAO JIN TO: LI YINGYONG XUE ZHICHAO YANG XIUSHENG CAO PEIRONG LI XIUXIAN WANG TONGFU GAO JIN ZHANG JIMING LV LONG CAO HAICHUAN

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150722

Termination date: 20180520

CF01 Termination of patent right due to non-payment of annual fee