CN103257292A CN2013101355355A CN201310135535A CN103257292A CN 103257292 A CN103257292 A CN 103257292A CN 2013101355355 A CN2013101355355 A CN 2013101355355A CN 201310135535 A CN201310135535 A CN 201310135535A CN 103257292 A CN103257292 A CN 103257292A
Authority
CN
China
Prior art keywords
insulator
test
test method
carried out
minutes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101355355A
Other languages
Chinese (zh)
Other versions
CN103257292B (en
Inventor
肖嵘
王海峰
邵宇鹰
郑颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI SHINE ENERGY INFO-TECH Co Ltd
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Original Assignee
SHANGHAI SHINE ENERGY INFO-TECH Co Ltd
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI SHINE ENERGY INFO-TECH Co Ltd, State Grid Corp of China SGCC, Shanghai Municipal Electric Power Co filed Critical SHANGHAI SHINE ENERGY INFO-TECH Co Ltd
Priority to CN201310135535.5A priority Critical patent/CN103257292B/en
Publication of CN103257292A publication Critical patent/CN103257292A/en
Application granted granted Critical
Publication of CN103257292B publication Critical patent/CN103257292B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Insulators (AREA)

Abstract

The invention discloses an experimental method for insulator dirt deposition. The experimental method for the insulator dirt deposition comprises the following steps: placing an insulator in a wind tunnel experiment device, starting the wind tunnel experiment device to carry out a blowing test on the insulator, placing the insulator in a fog environment, carrying out a rainfall test on the insulator, carrying out drying on the insulator, collecting dirt on the surface of the insulator, and analyzing an experimental result. The experimental method for the insulator dirt deposition is simple in setting, the experiment is carried by repeating a plurality of procedures, and the experimental result is closer to a true value. Dirt collection is more convenient and more complete. An experiment flow is standard, and the interference of human factors is eliminated.

Description

Insulator contamination test method
Technical field
The present invention relates to a kind of test method, be specifically related to insulator contamination test method.
Background technology
Be suspended in airborne solid or liquid particle and be deposited on insulator surface, form pollution layer.This pollution course is determined by the acting force that filthy particulate is subjected to that mainly the adhesion when also being contacted with insulator surface by filthy particulate is simultaneously determined near insulator.Often be suspended in that filthy particulate has two kinds in the air: the one, make the ultrafine dust (diameter is less than 1 μ m) of Brownian movement with gas molecule, the permanent suspension, smaller to the effect that insulator pollutes; The one, the mineral matter dust, the organic fine particles that fly up from ground, the flue dust of factory's chimney discharging, and the spittle of wave machine and sea wind are carried under one's arms and the salt solution droplet that comes, these filthy particle sizes are bigger, they are subjected to the combined action of gravity, wind pressure and electric field force near insulator, insulator surface is polluted.
When the contamination of insulator was analyzed, currently used method mainly contained, and the one, carry out site test, namely hang different insulator test products at same circuit or current conversion station, advanced certain contamination phase and analyze then, its shortcoming is the influence that is subjected to external environment, and the dispersiveness of data is bigger; The secondth, utilize the calculating that the line element method is arranged, when the analysis air flow stream is crossed insulator surface, umbellate form is to the influence of airflow field, thereby the contamination characteristic of contrast different insulative, this method is fairly simple from operating, only need to calculate to get final product, but the correctness of net result also needs to come secondary proof by test.
Summary of the invention
The object of the present invention is to provide a kind of insulator contamination test method, method is simple, is convenient to gather experimental data, and the result of test of many times contrasts mutually, draws experiment conclusion.
In order to achieve the above object, the present invention is achieved through the following technical solutions: insulator contamination test method is characterized in,
Above-mentioned method comprises following steps:
Step 1, insulator is placed in the wind tunnel test device;
Step 2, open the wind tunnel test device, to the insulator test of drying;
Step 3, insulator is placed the fog environment;
Step 4, insulator is carried out salt fog test;
Step 5, insulator is carried out drying;
Step 6, step 2, step 3, step 4 and step 5 circulation are carried out, gather the filth of insulator surface after the circulation 1 time, 2 times, 4 times;
Step 7, the filth of the insulator surface that collects is analyzed.
Also need insulator is placed in distilled water or the deionized water before being placed into insulator in the wind tunnel test device in the above-mentioned step 1, clean dunghill and carry out drying.
In the above-mentioned step 2 insulator being dried, to select wind speed for use be 4.5 m/s in test, and the air-supply time is 20 minutes, and air-supply is and with filth.
In the above-mentioned step 2 insulator dried and filthyly in the test mixed by 80% porcelain earth and 20% sodium chloride.
In the above-mentioned step 3 insulator is placed the fog environment, insulator continues 10 minutes in the fog environment.
In the above-mentioned step 4 insulator is carried out salt fog test, insulator was drenched with rain 15 minutes.
In the above-mentioned step 5 insulator is carried out drying, need dry 25 minutes of insulator.
Insulator contamination test method of the present invention compared with prior art has the following advantages: test arranges simple, and a plurality of step revision tests are more near actual value; This method is gathered filthy more convenient, more complete; The experiment process standard has been got rid of the interference of human factor.
Description of drawings
Fig. 1 is insulator contamination test method process flow diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing, by describing a preferable specific embodiment in detail, the present invention is further elaborated.
Insulator contamination test method, method comprises following steps:
Step 1, insulator is placed in distilled water or the deionized water, cleans dunghill and also carry out drying, insulator is placed in the wind tunnel test device then;
Step 2, open the wind tunnel test device, to the insulator test of drying, it is 4.5 m/s that wind speed is selected in the blowing test for use, and the air-supply time is 20 minutes, and air-supply is and with filth, and filth is mixed by 80% porcelain earth and 20% sodium chloride;
Step 3, insulator is placed the fog environment, insulator continues 10 minutes in the fog environment;
Step 4, insulator is carried out salt fog test, insulator was drenched with rain 15 minutes;
Step 5, insulator is carried out drying, dry 25 minutes of insulator;
Step 6, step 2, step 3, step 4 and step 5 circulation are carried out, gather the filth of insulator surface after the circulation 1 time, 2 times, 4 times;
Step 7, the filth of the insulator surface that collects is analyzed.
Although content of the present invention has been done detailed introduction by above preferred embodiment, will be appreciated that above-mentioned description should not be considered to limitation of the present invention.After those skilled in the art have read foregoing, for multiple modification of the present invention with to substitute all will be apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (7)

1. insulator contamination test method is characterized in that, described method comprises following steps:
Step 1, insulator is placed in the wind tunnel test device;
Step 2, open the wind tunnel test device, to the insulator test of drying;
Step 3, insulator is placed the fog environment;
Step 4, insulator is carried out salt fog test;
Step 5, insulator is carried out drying;
Step 6, step 2, step 3, step 4 and step 5 circulation are carried out, gather the filth of insulator surface after the circulation 1 time, 2 times, 4 times;
Step 7, the filth of the insulator surface that collects is analyzed.
2. insulator contamination test method as claimed in claim 1 is characterized in that, also needs insulator is placed in distilled water or the deionized water before in the described step 1 insulator being placed in the wind tunnel test device, cleans dunghill and also carries out drying.
3. insulator contamination test method as claimed in claim 1 is characterized in that, in the described step 2 insulator is dried that to select wind speed for use be 4.5 m/s in test, and the air-supply time is 20 minutes, and air-supply is and with filth.
4. insulator contamination test method as claimed in claim 3 is characterized in that, in the described step 2 insulator being dried filthyly in the test is mixed by 80% porcelain earth and 20% sodium chloride.
5. insulator contamination test method as claimed in claim 1 is characterized in that, in the described step 3 insulator is placed the fog environment, and insulator continues 10 minutes in the fog environment.
6. insulator contamination test method as claimed in claim 1 is characterized in that, in the described step 4 insulator is carried out salt fog test, and insulator was drenched with rain 15 minutes.
7. insulator contamination test method as claimed in claim 1 is characterized in that, in the described step 5 insulator is carried out drying, needs dry 25 minutes of insulator.
CN201310135535.5A 2013-04-18 2013-04-18 Experimental method for insulator dirt deposition Active CN103257292B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310135535.5A CN103257292B (en) 2013-04-18 2013-04-18 Experimental method for insulator dirt deposition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310135535.5A CN103257292B (en) 2013-04-18 2013-04-18 Experimental method for insulator dirt deposition

Publications (2)

Publication Number Publication Date
CN103257292A true CN103257292A (en) 2013-08-21
CN103257292B CN103257292B (en) 2016-08-10

Family

ID=48961322

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310135535.5A Active CN103257292B (en) 2013-04-18 2013-04-18 Experimental method for insulator dirt deposition

Country Status (1)

Country Link
CN (1) CN103257292B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103913657A (en) * 2014-03-25 2014-07-09 南方电网科学研究院有限责任公司 Method and checking field for determining insulator hanging positions of natural dirt accumulation station
CN105759189A (en) * 2016-05-10 2016-07-13 国家电网公司 Suspension insulator filth deposition accelerating device
CN107576896A (en) * 2017-08-30 2018-01-12 中国南方电网有限责任公司电网技术研究中心 The rain lightning pressure test method of porcelain strut insulator
CN109596957A (en) * 2018-12-13 2019-04-09 清华大学深圳研究生院 A kind of method and device for simulating coastal insulator rapid contamination accumulation

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101799515A (en) * 2010-03-10 2010-08-11 北京航空航天大学 Large multifunctional environmental simulator for electrical test
CN202502085U (en) * 2012-03-29 2012-10-24 上海市电力公司 Insulator salt density testing system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101799515A (en) * 2010-03-10 2010-08-11 北京航空航天大学 Large multifunctional environmental simulator for electrical test
CN202502085U (en) * 2012-03-29 2012-10-24 上海市电力公司 Insulator salt density testing system

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
X LIN ET AL.: "Natural insulator contamination test results on various shed shapes in heavy industrial contamination areas", 《TRANSACTIONS ON ELECTRICAL INSULATION》, vol. 27, no. 3, 30 June 1992 (1992-06-30), pages 593 - 600 *
中华人民共和国国家质量监督检验检疫总局: "《直流系统用高压绝缘子的人工污秽试验》", 1 October 2009, article "直流系统用高压绝缘子的人工污秽试验", pages: 7 *
周建国等: "多伞盘式绝缘子的污秽特性", 《电工陶瓷第七次学术年会暨学术交流会论文集》, 1 October 2001 (2001-10-01), pages 79 - 81 *
律方成等: "高海拔地区±800kV特高压直流输电系统绝缘子带电自然积污特性", 《高电压技术》, vol. 39, no. 3, 1 March 2013 (2013-03-01), pages 513 - 519 *
肖嵘: "华东电网输电线路绝缘子饱和污秽(盐密)特性及外绝缘配置方法的研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》, no. 2, 15 December 2011 (2011-12-15), pages 40 - 52 *
钱之银等: "华东电网500 kV 线路绝缘子人工和自然积污比较", 《高电压技术》, vol. 36, no. 3, 31 March 2010 (2010-03-31), pages 705 - 709 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103913657A (en) * 2014-03-25 2014-07-09 南方电网科学研究院有限责任公司 Method and checking field for determining insulator hanging positions of natural dirt accumulation station
CN105759189A (en) * 2016-05-10 2016-07-13 国家电网公司 Suspension insulator filth deposition accelerating device
CN107576896A (en) * 2017-08-30 2018-01-12 中国南方电网有限责任公司电网技术研究中心 The rain lightning pressure test method of porcelain strut insulator
CN109596957A (en) * 2018-12-13 2019-04-09 清华大学深圳研究生院 A kind of method and device for simulating coastal insulator rapid contamination accumulation

Also Published As

Publication number Publication date
CN103257292B (en) 2016-08-10

Similar Documents

Publication Publication Date Title
O'Brien et al. There's something in the air: a review of sources, prevalence and behaviour of microplastics in the atmosphere
Abbasi et al. Dry and wet deposition of microplastics in a semi-arid region (Shiraz, Iran)
CN103257292A (en) Experimental method for insulator dirt deposition
CN108351866B (en) Ultra-short time air pollution forecast
Ghazi et al. The effect of weather conditions on the efficiency of PV panels in the southeast of UK
Winkel et al. Evaluation of a dry filter and an electrostatic precipitator for exhaust air cleaning at commercial non-cage laying hen houses
CN106369971A (en) Intelligent soil drying device
CN102879233B (en) Miniature onboard reverse plug flow cloud droplet sampling device and working method thereof
Zhang et al. Quantifying the capacity of tree branches for retaining airborne submicron particles
CN104634703B (en) Air ion Mobility Spectrum Analysis method and instrument
Rao et al. New insights into the long-term dynamics and deposition-suspension distribution of atmospheric microplastics in an urban area
CN204718318U (en) A kind of Bioexperiment device drying baker
CN108170894B (en) Parameterization calculation method for dry settlement of atmospheric particulate matters of external insulator of power transmission and transformation equipment
Kalasee et al. A review of air pollution and solutions way management related to Ribbed smoked sheets (RSS) production of community-level rubber cooperatives in Thailand: Smoke, soot and PAHs particles
CN103048169B (en) A kind of microenvironment air persistent organic pollutant initiatively sampling apparatus and method thereof
Di‐Giovanni A review of the sampling efficiency of rotating‐arm impactors used in aerobiological studies
CN204008677U (en) A kind of auto-monitor of surrounding air quality sampling apparatus
Hicks Wet and dry surface deposition of air pollutants and their modeling
JPH0933418A (en) Measuring method of concentration in air of particulate material
Ravelomanantsoa et al. Insulator pollution processes under winter conditions
Melik et al. Insulator leakage current monitoring, its application and advantages
CN204911135U (en) Industry flue gas embrane method is gathered dirt desulfurization and is equipped system
CN204933245U (en) Industrial smoke embrane method gathers dirt devulcanizer
CN110944753A (en) (1 → 3) - β -D-glucan as a measure of active mold
CN207689330U (en) A kind of filter detection device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant