CN103245379A CN2013101168170A CN201310116817A CN103245379A CN 103245379 A CN103245379 A CN 103245379A CN 2013101168170 A CN2013101168170 A CN 2013101168170A CN 201310116817 A CN201310116817 A CN 201310116817A CN 103245379 A CN103245379 A CN 103245379A
Authority
CN
China
Prior art keywords
transmission line
power transmission
early warning
limit value
warning limit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101168170A
Other languages
English (en)
Inventor
李昌
张如明
张溯宁
宋丽华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI SUNRISE POWER TECHNOLOGY Co Ltd
Original Assignee
SHANGHAI SUNRISE POWER TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI SUNRISE POWER TECHNOLOGY Co Ltd filed Critical SHANGHAI SUNRISE POWER TECHNOLOGY Co Ltd
Priority to CN2013101168170A priority Critical patent/CN103245379A/zh
Publication of CN103245379A publication Critical patent/CN103245379A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Emergency Alarm Devices (AREA)

Abstract

一种高压输电线实时状态监测方法,涉及电力系统技术领域,所解决的是降低劳动强度及监测数据传输量的技术问题。该方法先采集12种监测量的数据,再根据采集的数据采用加权计算方式计算出输电线的实时状态监测综合值,然后再将输电线的实时状态监测综合值与线路预警上限值进行比较,并根据比较结果判断输电线的工况。本发明提供的方法,适用于监控高压输电线。

Description

高压输电线实时状态监测方法
技术领域
本发明涉及电力系统技术,特别是涉及一种高压输电线实时状态监测方法的技术。
背景技术
高压输电线路多分布在野外,具有距离远、地点分散的特点,高压输电线路对用户供电起着至关重要的作用,最基本的要求就是安全运行。随着智能电网的发展,高压线路实时在线监测系统逐步推广,可以采集众多的实时在线信息以供决策,而大量的监测信息对调度中心数据传输和处理是一个挑战。
影响高压输电线路的因素包括:环境条件、线路实时状态、线路覆冰、线路舞动、污染情况、线路电气等。目前,对电力线路工况的掌握,一般采用定期巡视或者在线监测的方法,采用经验比对的方法来预防运行线路故障,以达到输电线路安全运行的目的。采用定期巡视的方式存在着严重的滞后问题,无法有效的实时发现线路故障隐患。采用在线监测的方式则由于输电线路的状态一直处于变化中,监测数据的采集量很大,远程上传大量的数据存在着一定的困难,而且现有监测方式都是由工作人员从单个监测项目来表征线路的运行工况,使得工作人员的劳动强度很高。
发明内容
针对上述现有技术中存在的缺陷,本发明所要解决的技术问题是提供一种能降低输电线监测数据传输量,降低工作人员的劳动强度的高压输电线实时状态监测方法。
为了解决上述技术问题,本发明所提供的一种高压输电线实时状态监测方法,其特征在于,具体步骤如下:
1)设定输电线的环境温度预警限值、环境湿度预警限值、环境风速预警限值、导线悬垂高度预警限值、导线跨越弧度预警限值、导线覆冰厚度预警限值、导线张力预警限值、导线舞动频率预警限值、导线舞动张力预警限值、导线表面污染度预警限值、大气污染浓度预警限值、线路潮流预警限值;
2)获取输电线所处环境的环境温度、环境湿度、环境风速、大气污染浓度,及输电线的导线悬垂高度、导线跨越弧度、导线覆冰厚度、导线张力、导线舞动频率、导线舞动张力、导线表面污染度、线路潮流;
其中,大气污染浓度是指大气中的二氧化硫气体浓度,导线悬垂高度是指输电线的最高点与最低点之间的竖向间距,导线跨越弧度是指输电线的弧长与弧半径的比值,导线覆冰厚度是指覆盖在输电线测量点部的冰层的厚度,导线张力是指输电线测量点处在切线方向的最大张力,导线舞动频率是指输电线在外力作用下的竖向舞动频率,导线舞动张力是指输电线在外力作用下舞动时的竖向最大张力,导线表面污染度是指输电线外表面受污染后泄露的电流值,线路潮流是指输电线的单相运行电流值;
3)计算输电线的实时状态监测综合值,具体计算公式为:
y = Σ i = 1 n ( ( - 1 + 2 / n ) f ( x i ) + 2 ( 1 - 1 / n ) f ( x i ) f ( x i ) ) ;
式中: f ( x i ) = λ i Σ j = 1 m ( r ij - a ij ) ;
式中:1≤i≤n,n=6,1≤j≤m;
其中,y为输电线的实时状态监测综合值,λi为f(xi)的权值,f(x1)为输电线的环境因素,f(x2)为输电线的物理因素,f(x3)为输电线的覆冰因素,f(x4)为输电线的舞动因素,f(x5)为输电线的污染因素,f(x6)为输电线的电气因素;
当i=1时,m=3,此时r11为输电线所处环境的环境温度,a11为输电线的环境温度预警限值,r12为输电线所处环境的环境湿度,a12为输电线的环境湿度预警限值,r13为输电线所处环境的环境风速,a13为输电线的环境风速预警限值,如果f(x1)中存在着r1j>a1j,则λ1=max(r1j-a1j),反之则λ1=0;
当i=2时,m=2,此时r21为输电线的导线悬垂高度,a21为输电线的导线悬垂高度预警限值,r22为输电线的导线跨越弧度,a22为输电线的导线跨越弧度预警限值,如果f(x2)中存在着r2j>a2j,则λ2=max(r2j-a2j),反之则λ2=0;
当i=3时,m=2,此时r31为输电线的导线覆冰厚度,a31为输电线的导线覆冰厚度预警限值,r32为输电线的导线张力,a32为输电线的导线张力预警限值,如果f(x3)中存在着r3j>a3j,则λ3=max(r3j-a3j),反之则λ3=0;
当i=4时,m=2,此时r41为输电线的导线舞动频率,a41为输电线的导线舞动频率预警限值,r42为输电线的导线舞动张力,a42为输电线的导线舞动张力预警限值,如果f(x4)中存在着r4j>a4j,则λ4=max(r4j-a4j),反之则λ4=0;
当i=5时,m=2,此时r51为输电线的导线表面污染度,a51为输电线的导线表面污染度预警限值,r52为输电线所处环境的大气污染浓度,a52为输电线的大气污染浓度预警限值,如果f(x5)中存在着r5j>a5j,则λ5=max(r5j-a5j),反之则λ5=0;
当i=6时,m=1,此时r61为输电线的线路潮流,a61为输电线的线路潮流预警限值,如果f(x6)中存在着r6j>a6j,则λ6=max(r6j-a6j),反之则λ6=0;
4)计算线路预警上限值,具体计算公式为:
limup = Σ i = 1 n ( ( ( - 1 + 2 / n ) Σ j = 1 m a ij ) + 2 ( 1 - 1 / n ) Σ j = 1 m a ij Σ j = 1 m a ij )
其中,limup为线路预警上限值;
5)判断输电线状态,如果y>limup,则表明输电线状态出现异常,需要发出输电线预警信号,反之则表明输电线状态正常。
本发明提供的高压输电线实时状态监测方法,采用加权因子,综合了影响输电线状态的多种因素,对输电线的实时状态监测综合值进行计算,再将计算结果与线路预警上限值进行比对,判断出输电线的实时状态有否异常,输电线实时状态监测综合值的计算可以在本地进行,需要远程上传给监控中心的只有输电线实时状态监测综合值的计算结果,无需把所有监测数据一并上传,能有效降低输电线监测数据的传输量,工作人员只需要比对输电线实时状态监测综合值即可知晓输电线运行状态,能降低工作人员的劳动强度。
附图说明
图1是本发明实施例的高压输电线实时状态监测方法的监测流程图。
具体实施方式
以下结合附图说明对本发明的实施例作进一步详细描述,但本实施例并不用于限制本发明,凡是采用本发明的相似结构及其相似变化,均应列入本发明的保护范围。
如图1所示,本发明实施例所提供的一种高压输电线实时状态监测方法,其特征在于,具体步骤如下:
1)设定输电线的环境温度预警限值、环境湿度预警限值、环境风速预警限值、导线悬垂高度预警限值、导线跨越弧度预警限值、导线覆冰厚度预警限值、导线张力预警限值、导线舞动频率预警限值、导线舞动张力预警限值、导线表面污染度预警限值、大气污染浓度预警限值、线路潮流预警限值;
2)获取输电线所处环境的环境温度、环境湿度、环境风速、大气污染浓度,及输电线的导线悬垂高度、导线跨越弧度、导线覆冰厚度、导线张力、导线舞动频率、导线舞动张力、导线表面污染度、线路潮流;
其中,大气污染浓度是指大气中的二氧化硫气体浓度(会影响导线热稳定容量),导线悬垂高度是指输电线的最高点与最低点之间的竖向间距,导线跨越弧度是指输电线的弧长与弧半径的比值,导线覆冰厚度是指覆盖在输电线测量点部的冰层的厚度,导线张力是指输电线测量点处在切线方向的最大张力,导线舞动频率是指输电线在外力作用下的竖向舞动频率,导线舞动张力是指输电线在外力作用下舞动时的竖向最大张力,导线表面污染度是指输电线外表面受污染后泄露的电流值,线路潮流是指输电线的单相运行电流值;
3)计算输电线的实时状态监测综合值,具体计算公式为:
y = Σ i = 1 n ( ( - 1 + 2 / n ) f ( x i ) + 2 ( 1 - 1 / n ) f ( x i ) f ( x i ) ) ;
式中: f ( x i ) = λ i Σ j = 1 m ( r ij - a ij ) ;
式中:1≤i≤n,n=6,1≤j≤m;
其中,y为输电线的实时状态监测综合值,λi为f(xi)的权值,f(x1)为输电线的环境因素,f(x2)为输电线的物理因素,f(x3)为输电线的覆冰因素,f(x4)为输电线的舞动因素,f(x5)为输电线的污染因素,f(x6)为输电线的电气因素;
当i=1时,m=3,此时r11为输电线所处环境的环境温度,a11为输电线的环境温度预警限值,r12为输电线所处环境的环境湿度,a12为输电线的环境湿度预警限值,r13为输电线所处环境的环境风速,a13为输电线的环境风速预警限值,如果f(x1)中存在着r1j>a1j,则λ1=max(r1j-a1j),反之则λ1=0;
当i=2时,m=2,此时r21为输电线的导线悬垂高度,a21为输电线的导线悬垂高度预警限值,r22为输电线的导线跨越弧度,a22为输电线的导线跨越弧度预警限值,如果f(x2)中存在着r2j>a2j,则λ2=max(r2j-a2j),反之则λ2=0,max为取最大数;
当i=3时,m=2,此时r31为输电线的导线覆冰厚度,a31为输电线的导线覆冰厚度预警限值,r32为输电线的导线张力,a32为输电线的导线张力预警限值,如果f(x3)中存在着r3j>a3j,则λ3=max(r3j-a3j),反之则λ3=0;
当i=4时,m=2,此时r41为输电线的导线舞动频率,a41为输电线的导线舞动频率预警限值,r42为输电线的导线舞动张力,a42为输电线的导线舞动张力预警限值,如果f(x4)中存在着r4j>a4j,则λ4=max(r4j-a4j),反之则λ4=0;
当i=5时,m=2,此时r51为输电线的导线表面污染度,a51为输电线的导线表面污染度预警限值,r52为输电线所处环境的大气污染浓度,a52为输电线的大气污染浓度预警限值,如果f(x5)中存在着r5j>a5j,则λ5=max(r5j-a5j),反之则λ5=0;
当i=6时,m=1,此时r61为输电线的线路潮流,a61为输电线的线路潮流预警限值,如果f(x6)中存在着r6j>a6j,则λ6=max(r6j-a6j),反之则λ6=0;
4)计算线路预警上限值,具体计算公式为:
limup = Σ i = 1 n ( ( ( - 1 + 2 / n ) Σ j = 1 m a ij ) + 2 ( 1 - 1 / n ) Σ j = 1 m a ij Σ j = 1 m a ij )
其中,limup为线路预警上限值;
5)判断输电线状态,如果y>limup,则表明输电线状态出现异常,需要发出输电线预警信号,反之则表明输电线状态正常。

Claims (1)

1.一种高压输电线实时状态监测方法,其特征在于,具体步骤如下:
1)设定输电线的环境温度预警限值、环境湿度预警限值、环境风速预警限值、导线悬垂高度预警限值、导线跨越弧度预警限值、导线覆冰厚度预警限值、导线张力预警限值、导线舞动频率预警限值、导线舞动张力预警限值、导线表面污染度预警限值、大气污染浓度预警限值、线路潮流预警限值;
2)获取输电线所处环境的环境温度、环境湿度、环境风速、大气污染浓度,及输电线的导线悬垂高度、导线跨越弧度、导线覆冰厚度、导线张力、导线舞动频率、导线舞动张力、导线表面污染度、线路潮流;
其中,大气污染浓度是指大气中的二氧化硫气体浓度,导线悬垂高度是指输电线的最高点与最低点之间的竖向间距,导线跨越弧度是指输电线的弧长与弧半径的比值,导线覆冰厚度是指覆盖在输电线测量点部的冰层的厚度,导线张力是指输电线测量点处在切线方向的最大张力,导线舞动频率是指输电线在外力作用下的竖向舞动频率,导线舞动张力是指输电线在外力作用下舞动时的竖向最大张力,导线表面污染度是指输电线外表面受污染后泄露的电流值,线路潮流是指输电线的单相运行电流值;
3)计算输电线的实时状态监测综合值,具体计算公式为:
y = Σ i = 1 n ( ( - 1 + 2 / n ) f ( x i ) + 2 ( 1 - 1 / n ) f ( x i ) f ( x i ) ) ;
式中: f ( x i ) = λ i Σ j = 1 m ( r ij - a ij ) ;
式中:1≤i≤n,n=6,1≤j≤m;
其中,y为输电线的实时状态监测综合值,λi为f(xi)的权值,f(x1)为输电线的环境因素,f(x2)为输电线的物理因素,f(x3)为输电线的覆冰因素,f(x4)为输电线的舞动因素,f(x5)为输电线的污染因素,f(x6)为输电线的电气因素;
当i=1时,m=3,此时r11为输电线所处环境的环境温度,a11为输电线的环境温度预警限值,r12为输电线所处环境的环境湿度,a12为输电线的环境湿度预警限值,r13为输电线所处环境的环境风速,a13为输电线的环境风速预警限值,如果f(x1)中存在着r1j>a1j,则λ1=max(r1j-a1j),反之则λ1=0;
当i=2时,m=2,此时r21为输电线的导线悬垂高度,a21为输电线的导线悬垂高度预警限值,r22为输电线的导线跨越弧度,a22为输电线的导线跨越弧度预警限值,如果f(x2)中存在着r2j>a2j,则λ2=max(r2j-a2j),反之则λ2=0;
当i=3时,m=2,此时r31为输电线的导线覆冰厚度,a31为输电线的导线覆冰厚度预警限值,r32为输电线的导线张力,a32为输电线的导线张力预警限值,如果f(x3)中存在着r3j>a3j,则λ3=max(r3j-a3j),反之则λ3=0;
当i=4时,m=2,此时r41为输电线的导线舞动频率,a41为输电线的导线舞动频率预警限值,r42为输电线的导线舞动张力,a42为输电线的导线舞动张力预警限值,如果f(x4)中存在着r4j>a4j,则λ4=max(r4j-a4j),反之则λ4=0;
当i=5时,m=2,此时r51为输电线的导线表面污染度,a51为输电线的导线表面污染度预警限值,r52为输电线所处环境的大气污染浓度,a52为输电线的大气污染浓度预警限值,如果f(x5)中存在着r5j>a5j,则λ5=max(r5j-a5j),反之则λ5=0;
当i=6时,m=1,此时r61为输电线的线路潮流,a61为输电线的线路潮流预警限值,如果f(x6)中存在着r6j>a6j,则λ6=max(r6j-a6j),反之则λ6=0;
4)计算线路预警上限值,具体计算公式为:
limup = Σ i = 1 n ( ( ( - 1 + 2 / n ) Σ j = 1 m a ij ) + 2 ( 1 - 1 / n ) Σ j = 1 m a ij Σ j = 1 m a ij )
其中,limup为线路预警上限值;
5)判断输电线状态,如果y>limup,则表明输电线状态出现异常,需要发出输电线预警信号,反之则表明输电线状态正常。
CN2013101168170A 2013-04-07 2013-04-07 高压输电线实时状态监测方法 Pending CN103245379A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101168170A CN103245379A (zh) 2013-04-07 2013-04-07 高压输电线实时状态监测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101168170A CN103245379A (zh) 2013-04-07 2013-04-07 高压输电线实时状态监测方法

Publications (1)

Publication Number Publication Date
CN103245379A true CN103245379A (zh) 2013-08-14

Family

ID=48925054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101168170A Pending CN103245379A (zh) 2013-04-07 2013-04-07 高压输电线实时状态监测方法

Country Status (1)

Country Link
CN (1) CN103245379A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104239970A (zh) * 2014-09-04 2014-12-24 国家电网公司 一种基于Adaboost的输电线舞动风险预警方法
CN114034339A (zh) * 2021-11-05 2022-02-11 北京国网富达科技发展有限责任公司 一种基于多传感器融合的输电线路舞动监测方法及系统
CN117117756A (zh) * 2023-10-25 2023-11-24 江苏利宏原电力科技有限公司 一种电力输送用电线架线街码

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102221381A (zh) * 2011-06-10 2011-10-19 国网信息通信有限公司 电网输电线路监测方法和系统
CN202033053U (zh) * 2011-04-18 2011-11-09 广西电网公司电力科学研究院 基于多信息融合的一体化输电线路状态监测装置
US20110279278A1 (en) * 2010-05-17 2011-11-17 Al-Absi Munir A Monitoring and early warning alarm system for high voltage insulator failure
CN102494723A (zh) * 2011-12-13 2012-06-13 北京航空航天大学 一种无人值守环境试验系统和方法
CN102628373A (zh) * 2012-04-27 2012-08-08 天地科技股份有限公司 煤矿冲击地压分源综合预警方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110279278A1 (en) * 2010-05-17 2011-11-17 Al-Absi Munir A Monitoring and early warning alarm system for high voltage insulator failure
CN202033053U (zh) * 2011-04-18 2011-11-09 广西电网公司电力科学研究院 基于多信息融合的一体化输电线路状态监测装置
CN102221381A (zh) * 2011-06-10 2011-10-19 国网信息通信有限公司 电网输电线路监测方法和系统
CN102494723A (zh) * 2011-12-13 2012-06-13 北京航空航天大学 一种无人值守环境试验系统和方法
CN102628373A (zh) * 2012-04-27 2012-08-08 天地科技股份有限公司 煤矿冲击地压分源综合预警方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104239970A (zh) * 2014-09-04 2014-12-24 国家电网公司 一种基于Adaboost的输电线舞动风险预警方法
WO2016033883A1 (zh) * 2014-09-04 2016-03-10 国家电网公司 一种基于Adaboost的输电线舞动风险预警方法
CN104239970B (zh) * 2014-09-04 2017-11-28 国网河南省电力公司电力科学研究院 一种基于Adaboost的输电线舞动风险预警方法
CN114034339A (zh) * 2021-11-05 2022-02-11 北京国网富达科技发展有限责任公司 一种基于多传感器融合的输电线路舞动监测方法及系统
CN117117756A (zh) * 2023-10-25 2023-11-24 江苏利宏原电力科技有限公司 一种电力输送用电线架线街码
CN117117756B (zh) * 2023-10-25 2024-01-30 江苏利宏原电力科技有限公司 一种电力输送用电线架线街码

Similar Documents

Publication Publication Date Title
CN202041178U (zh) 输电线路弧垂在线监测系统
CN201628558U (zh) 一种输电线路的数字化在线监测系统和监测装置
CN102564493B (zh) 一种架空输电线路舞动在线监测系统
CN101989767B (zh) 一种高压杆塔的综合测控装置
CN207335774U (zh) 一种输电线路综合在线监测与巡检系统
CN202734796U (zh) 一种覆冰厚度监测系统
CN105117538B (zh) 一种输电通道舞动预警方法
CN104390710A (zh) 输电线路导线温度在线检测系统和方法
Yan et al. Application status and development trends for intelligent perception of distribution network
CN202928617U (zh) 输电线路导线覆冰及舞动在线监测单元
CN105444814A (zh) 一种输电线路在线监控系统
CN105469156A (zh) Moa健康管理和故障预测方法及系统
CN203605975U (zh) 一种无线通信电力输电线路的环境参数监测系统
CN103245379A (zh) 高压输电线实时状态监测方法
CN106054850A (zh) 一种智能变电站环境监测及智能控制系统
CN105553101A (zh) 一种电力输电线路智能检测方法
CN103674291A (zh) 全绝缘母线的温度监测系统
CN204089886U (zh) 基于气象信息的电网动态监控预警系统
CN110695997A (zh) 一种5g/nb通信交警机器人远程监控系统及应用方法
CN209014643U (zh) 离子风机的平衡电压检测终端及其平衡电压检测系统
CN205246243U (zh) 一种输电线路温度在线监测系统
CN204304606U (zh) 一种变压器负荷预测与管理研究系统
CN204119531U (zh) 分布式能源线路多维感知系统
CN206505195U (zh) 一种微气象在线监测系统
CN116168502B (zh) 一种自优化工业园区消防传感器节能控制系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130814