CN103243707A - 一种桩承载力增强构件的施工方法 - Google Patents

一种桩承载力增强构件的施工方法 Download PDF

Info

Publication number
CN103243707A
CN103243707A CN201310158032XA CN201310158032A CN103243707A CN 103243707 A CN103243707 A CN 103243707A CN 201310158032X A CN201310158032X A CN 201310158032XA CN 201310158032 A CN201310158032 A CN 201310158032A CN 103243707 A CN103243707 A CN 103243707A
Authority
CN
China
Prior art keywords
reinforcement
pile
soil
stake
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310158032XA
Other languages
English (en)
Inventor
陈灿斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310158032XA priority Critical patent/CN103243707A/zh
Publication of CN103243707A publication Critical patent/CN103243707A/zh
Pending legal-status Critical Current

Links

Images

Abstract

一种桩承载力增强构件的施工方法,通过在桩上设置锚板,并且通过顶推装置压入土中,在锚板间通过预应力锚杆进行连接,增大了预制桩和土壤之间的结合力,节省了材料;本发明具有应用范围广,施工方便性强等特点,施工周期较以往施工方法有很大优势,虽然形式类似,但方法、用途、施工顺序不同;并且保护环境,且可先注浆后施工桩,减少施工时间;是一种达到增加桩承载力,提高桩施工速度的简易的方法。

Description

一种桩承载力增强构件的施工方法
技术领域
本发明涉及一种桩的辅助构件,特别是一种桩承载力增强构件。
背景技术
1现有技术中挤扩多支盘灌注桩至少需要16项以上的措施保证灌注桩质量,且施工周期长。
2现有注浆工艺:注浆设备2时间要求钻孔灌注桩成桩后(2—7天)且周边8~10m范围内无钻进成孔作业时,清水开塞;钻孔灌注桩成桩后(7—30天)且周边8~10m范围内的桩已成桩,及时进行桩端后注浆;群桩按先外后里的顺序注浆;尽量先注主体外围的桩。3注浆管的制作和安放4开塞5注浆6注浆后的保养龄期。
现有注浆工艺也存在很多缺点,比如待灌注桩施工结束后灌注浆,施工时间长,注浆量大,且会在土层中扩散,浪费水泥,并造成地下水污染。
发明内容
本发明的目的在于:提供一种可单独设置的桩承载力增强构件,通过埋入预制增强构件提高桩承载力,施工方便且适合所有桩型,且可提前完成施工,节约工期。
  本发明是通过如下方法实现的:
一种桩承载力增强构件的施工方法,在所述桩上设置若干锚板;
所述锚板可侧向朝外展开插入土壤中,或者斜向、水平推入土壤中;
所述增强构件可在桩压入土壤前提前设置在土壤中或与桩同时压入在土壤中;
所述增强构件与桩为接触连接或者锚固连接。
作为本发明的进一步创新,所述桩和增强构件上包裹有柔性材料,在桩和增强构件在压入土壤后进行注浆,所述柔性材料为厚度2毫米以下钢板、橡胶或网格边长小于5毫米的纤维布。
作为本发明的进一步创新,所述增强构件之间通过锚杆连接,并在增强构件之上施加预应力,对土壤采用预应力堆载方法进行堆载固结。
作为本发明的进一步创新,所述预应力堆载法为真空堆载法,所述固结法采用排水固结法。
本发明的有益效果在于:
本发明提出一种可单独设置的桩承载力辅助增强构件,通过埋入预制增强构件提高桩承载力,施工方便,且适合所有桩型,且可提前完成施工,节约工期。
本发明应用范围广,施工方便性强,施工周期较以往施工方法有很大优势,虽然形式类似,但方法、用途、施工顺序不同。并且节约材料,保护环境,且可先注浆后施工桩,减少施工时间。为一种达到增加桩承载力,提高桩施工速度的简易的方法。
附图说明:
图1 是可注浆桩承载力增强辅助构件。
图2 是软土区的固结的预应力堆载。
图3 是斜向施加预应力预应力堆载。
图中:1、钢注浆管道;2、顶推装置;3、可活动上部钢环;4、柔性纤维网;5、可侧向伸展杆件;6、固定底环;7、液压顶推装置的顶推杆;8、液压顶推装置的顶推构件;9、水平压入的桩承载力增强构件A;10、水平压入的桩承载力增强构件B;11、预应力锚杆;12、预应力锚杆。
具体实施方式
下面结合附图做进一步的说明
如图1、2、3所示施工步骤为:
1、根据图纸要求桩位置,定位放线;顶推装置2和可活动上部钢环3设置在钢注浆管道1上,且位于可注浆桩承载力增强构件最上部,固定底环6垂直设置于增强构件的最下部,此时可侧向伸展杆件5处于伸直状态,随后用压桩机压入增强构件,且压入设备构件与钢注浆管道1接触连接,在桩完全压入后,用顶推装置顶推可活动上部钢环3,此时固定底环6不移动,可侧向伸展杆件5被压缩弯曲,在注浆段上围绕柔性材料,并且注浆,注浆量取包裹体积的1.0~1.5倍,和土的渗透能力有关,土的渗透能力强取高值,此时柔性纤维网4被撑开,最后通过注浆孔对可侧向伸展杆件6撑起的柔性纤维网4内部进行注浆。
2、开挖凹槽,在凹槽中安装液压顶推装置,首先收缩液压顶推杆7,之后放入用于水平压入的桩承载力增强构件A,之后通过液压顶推杆的顶推构件8顶推水平桩承载力增强构件A9使其伸入土壤中,并且填土,随后通过同样的方法设置入用于水平压入的桩承载力增强构件B10,通过预应力锚杆11将增强构件A和B连接锚固,并且压紧。
3、斜向施加预应力堆载,在所述桩承载力增强构件之间斜向通过预应力斜向拉紧预应力锚杆12,并且在钢注浆管道1内加入砂石。

Claims (4)

1.一种桩承载力增强构件的施工方法,其特征在于:在所述桩上设置若干锚板;
所述锚板可侧向朝外展开插入土壤中,或者斜向、水平推入土壤中;
所述增强构件可在桩压入土壤前提前设置在土壤中或与桩同时压入在土壤中;
所述增强构件与桩为接触连接或者锚固连接。
2.如权利要求1所述的一种桩承载力增强构件,其特征在于:所述桩和增强构件上包裹有柔性材料,在桩和增强构件在压入土壤后进行注浆,所述柔性材料为厚度2毫米以下钢板、橡胶或网格边长小于5毫米的纤维布。
3.如权利要求1所述的一种桩承载力增强构件,其特征在于:所述增强构件之间通过锚杆连接,并在增强构件之上施加预应力,对土壤采用预应力堆载方法进行堆载固结。
4.如权利要求1或3所述的一种桩承载力增强构件,其特征在于:所述预应力堆载法为真空堆载法,所述固结法采用排水固结法。
CN201310158032XA 2013-05-02 2013-05-02 一种桩承载力增强构件的施工方法 Pending CN103243707A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310158032XA CN103243707A (zh) 2013-05-02 2013-05-02 一种桩承载力增强构件的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310158032XA CN103243707A (zh) 2013-05-02 2013-05-02 一种桩承载力增强构件的施工方法

Publications (1)

Publication Number Publication Date
CN103243707A true CN103243707A (zh) 2013-08-14

Family

ID=48923559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310158032XA Pending CN103243707A (zh) 2013-05-02 2013-05-02 一种桩承载力增强构件的施工方法

Country Status (1)

Country Link
CN (1) CN103243707A (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1488818A (zh) * 2003-08-04 2004-04-14 吕怀民 一种套盘桩和成桩方法和挤扩装置、沉桩机和用途
US20100178115A1 (en) * 2009-01-12 2010-07-15 University Of Florida Research Foundation, Inc. Systems and Methods for Securing Foundation Members in a Substrate
WO2010106216A1 (en) * 2009-03-20 2010-09-23 Aponox Oy Method for placing a pile or anchoring pile into ground
CN102191772A (zh) * 2010-03-01 2011-09-21 张继红 预制扩孔桩及其施工方法
CN202055239U (zh) * 2011-04-12 2011-11-30 中国建筑第七工程局有限公司 一种支盘桩挤扩旋削装置
CN202450519U (zh) * 2012-02-17 2012-09-26 浙江泰合建设有限公司 一种建筑用深孔旋挤扩装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1488818A (zh) * 2003-08-04 2004-04-14 吕怀民 一种套盘桩和成桩方法和挤扩装置、沉桩机和用途
US20100178115A1 (en) * 2009-01-12 2010-07-15 University Of Florida Research Foundation, Inc. Systems and Methods for Securing Foundation Members in a Substrate
WO2010106216A1 (en) * 2009-03-20 2010-09-23 Aponox Oy Method for placing a pile or anchoring pile into ground
CN102191772A (zh) * 2010-03-01 2011-09-21 张继红 预制扩孔桩及其施工方法
CN202055239U (zh) * 2011-04-12 2011-11-30 中国建筑第七工程局有限公司 一种支盘桩挤扩旋削装置
CN202450519U (zh) * 2012-02-17 2012-09-26 浙江泰合建设有限公司 一种建筑用深孔旋挤扩装置

Similar Documents

Publication Publication Date Title
CN204059124U (zh) 一种砂桩排水强夯后注浆地基加固结构
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN203741868U (zh) 一种带组合锚索的钢筋混凝土挡墙结构
CN101736738B (zh) 一种抗压、抗拔两用型注浆碎石桩的制作工法
CN107119917B (zh) 条形基础房屋后增地下室结构的施工方法
CN103184734A (zh) 一种植入注浆组合桩及施工方法
CN104674802B (zh) 预应力碎石锚拉桩及其滑坡治理施工方法
EA027027B1 (ru) Способ создания подпорной стенки
CN103993598A (zh) 一种引孔植入布袋碎石注浆桩及施工方法
CN103774674A (zh) 一种钢管托换桩与锚杆深基坑支护结构及其施工方法
CN103195060B (zh) 软土地基预应力锚杆加固结构及其用途
CN111636414B (zh) 一种承载式透水混凝土-ecc复合预制桩及其制备方法
CN111794216A (zh) 抗拔载体桩的施工方法
CN103603379A (zh) 抗浮水泥土桩和抗浮锚杆相结合的抗浮体系及其施工工艺
CN104294823B (zh) 一种预应力管桩抗浮桩筏结构的施工方法
CN103410144B (zh) 预应力钢筋嵌岩灌注桩及施工方法
CN104328790B (zh) 现浇喷射混凝土暗承台及暗地梁胎模
CN204174616U (zh) 预应力管桩抗浮桩筏结构
CN104929101B (zh) 一种扩底‑多段侧扩的抗拔预应力锚固碎石桩及施工方法
CN201284461Y (zh) 便于预应力锚索锚固的装置
CN103243707A (zh) 一种桩承载力增强构件的施工方法
CN110528572B (zh) 一种用减压方式修复有倾斜趋势挡土墙的方法
CN102433882A (zh) 一种混凝土桩墙与旋喷锚桩组合形成基坑支护的施工方法及锚筋结构件
CN203684236U (zh) 一种深基坑支护挡墙
CN105421446A (zh) 一种用于软基处理的混合土挤压固化预制桩及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130814