CN103206191A - Integrated technique of liner cementing and channeling in heavy oil production - Google Patents

Integrated technique of liner cementing and channeling in heavy oil production Download PDF

Info

Publication number
CN103206191A
CN103206191A CN2013101336458A CN201310133645A CN103206191A CN 103206191 A CN103206191 A CN 103206191A CN 2013101336458 A CN2013101336458 A CN 2013101336458A CN 201310133645 A CN201310133645 A CN 201310133645A CN 103206191 A CN103206191 A CN 103206191A
Authority
CN
China
Prior art keywords
cement paste
well
tail pipe
hanger
liner cementing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101336458A
Other languages
Chinese (zh)
Other versions
CN103206191B (en
Inventor
王学
于广鹏
朱国良
姜筠也
武文福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Kun Cheng Industrial Co., Ltd.
Original Assignee
PANJIN LIAOHE OILFIELD KUNCHENG INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PANJIN LIAOHE OILFIELD KUNCHENG INDUSTRY Co Ltd filed Critical PANJIN LIAOHE OILFIELD KUNCHENG INDUSTRY Co Ltd
Priority to CN201310133645.8A priority Critical patent/CN103206191B/en
Publication of CN103206191A publication Critical patent/CN103206191A/en
Application granted granted Critical
Publication of CN103206191B publication Critical patent/CN103206191B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention relates to the technical field of oil well workover, in particular to an integrated technique of liner cementing and channeling in heavy oil production. The technique includes the steps of firstly, estimating the size of a channel according the stratum structure, lithology, production data and section characteristics, and calculating the amount of required cement paste for sealing; secondly, calculating the amount of required cement paste for liner cementing according the size of a liner; and thirdly, adding the amounts of required cement paste in the step 1 and step 2 to obtain the amount of required cement paste in the technique. Water channeling of the stratum around a liner cementing section is sealed, an original extra-casing cement sheath is reinforced, fluid transfer and casing damage are prevented, and the yield of crude oil is increased. The defect that water channeling of the stratum around the liner cementing section and damage of the original extra-casing cement sheath cannot be solved by the existing liner cementing technique is overcome.

Description

The viscous crude drilling liner cementing squeezes scurries a body technique
Technical field:
The present invention relates to a kind of petroleum well workover operation technique field, particularly a kind of viscous crude drilling liner cementing squeezes and scurries a body technique.
Background technology:
The exploitation of oil be unable to do without workover treatment, and drilling liner cementing is technology commonly used in the workover treatment.
In the thickened oil recovery process, owing to oil reservoir position sleeve pipe damages or well recovery needs carry out sidetracking or reinforces sleeve pipe, following drilling liner cementing completion.After exploitation a period of time, often there is the phenomenon of water breakthrough in the well of drilling liner cementing completion under the viscous crude, makes the moisture rising of the crude output underproduction.The reason of water breakthrough: because the thickened oil recovery inclement condition, as: formation skeleton is loose, stratum deficit, range of temperature greatly, easily shake out, the permeability extreme difference is bigger etc. causes cement sheath damage water breakthrough and interlayer water breakthrough sleeve pipe outside.
Drilling liner cementing is exactly the outer annular space oil well cement paste filling at tail pipe, and with tail pipe and formation rock, or tail pipe and former casing bonding became a firm integral body, reaches the purpose of control well inner fluid after cement paste solidified.Situation near the stratum water breakthrough drilling liner cementing section or the outer stratum water breakthrough of former casing or the outer cement sheath damage of former casing adopts the drilling liner cementing technology not solve.
Summary of the invention:
The technical problem to be solved in the present invention provides the crowded body technique of scurrying of a kind of viscous crude drilling liner cementing, and this technology has realized near the stratum water breakthrough of shutoff drilling liner cementing section and added the outer cement sheath of Guyuan casing, prevented that fluid migration and sleeve pipe from damaging, and increases crude output.Overcome the deficiency that existing drilling liner cementing technology can not solve near the stratum water breakthrough of drilling liner cementing section and the outer cement sheath damage of former casing.
The technical solution used in the present invention is: a kind of viscous crude drilling liner cementing squeezes and scurries a body technique, and this technical step is as follows:
One, according to earth formation, lithology, oil recovery data and block characteristics, the size of groove is scurried in estimation, calculates envelope and scurries required cement paste consumption;
Two, calculate the solid required cement paste consumption of tail pipe according to the tail pipe size;
Three, the summation of step 1 and two required cement paste consumptions is exactly the required cement slurry volume of present technique;
Four, construction sequence:
(1) well is prepared: the well of tail pipe is repaiied cover or bore hole is crept into or drifting to being used for down;
(2) tail pipe under: following float collar, float shoe, tail pipe, hollow plug, suspension organ pipe string;
(3) circulation well cleanup: put circulation workover fluid in back under the tail pipe in place more than one week;
(4) hanger is sat and is hung: hanger is sat extension, drive central tube;
(5) replace into oil well cement paste: replace into oil well cement paste, throw little plug, pump into displacement fluid;
(6) bruising: come downwards to the spoiler bruising after little plug and hollow plug are compound;
(7) upper lifting pipe post: the up and hanger of central tube is thrown off, the upper lifting pipe post to the precalculated position namely apart from hanger 100-300m;
(8) circulation well cleanup: circulation well cleanup washes out superfluous water mud in the well;
(9) close half envelope blowout preventer, the cement paste more than the hanger is clamp-oned scurried groove location, band is pressed closing well Hou Ning;
(10) bore plug: following bit drills cement plug;
(11) drifting: select jack rabbit to carry out drifting to design attitude, circulation well cleanup is more than one week;
(12) test: detect solid tail pipe quality, completion.
The invention has the beneficial effects as follows: the present invention owing to adopted estimates the mode that groove is scurried in the required cement paste consumption of groove and shutoff of scurrying in advance, thereby have near the stratum water breakthrough of shutoff drilling liner cementing section and add the Guyuan casing function of cement sheath outward, prevent that fluid migration and sleeve pipe from damaging, and increases crude output.
Description of drawings:
The present invention will be further described in detail below in conjunction with the drawings and specific embodiments.
Fig. 1 is the effect schematic diagram after the employing shutoff water breakthrough of the present invention.
The specific embodiment:
As shown in Figure 1, a kind of viscous crude drilling liner cementing squeezes and scurries a body technique, and this technical step is as follows:
One, according to earth formation, lithology, oil recovery data and block characteristics, the size of groove is scurried in estimation, calculates envelope and scurries required cement paste consumption;
Two, calculate the solid required cement paste consumption of tail pipe according to the tail pipe size;
Three, the summation of step 1 and two required cement paste consumptions is exactly the required cement slurry volume of present technique;
Four, construction sequence:
(1) well is prepared: the well of tail pipe is repaiied cover or bore hole is crept into or drifting to being used for down;
(2) tail pipe under: following float collar, float shoe, tail pipe, hollow plug, suspension organ pipe string;
(3) circulation well cleanup: put circulation workover fluid in back under the tail pipe in place more than one week;
(4) hanger is sat and is hung: hanger is sat extension, drive central tube;
(5) replace into oil well cement paste: replace into oil well cement paste, throw little plug, pump into displacement fluid;
(6) bruising: come downwards to the spoiler bruising after little plug and hollow plug are compound;
(7) upper lifting pipe post: the up and hanger of central tube is thrown off, the upper lifting pipe post to the precalculated position namely apart from hanger 100-300m;
(8) circulation well cleanup: circulation well cleanup washes out superfluous water mud in the well;
(9) close half envelope blowout preventer, the cement paste more than the hanger is clamp-oned scurried groove location, band is pressed closing well Hou Ning;
(10) bore plug: following bit drills cement plug;
(11) drifting: select jack rabbit to carry out drifting to design attitude, circulation well cleanup is more than one week;
(12) test: detect solid tail pipe quality, completion.
Be understandable that, more than about specific descriptions of the present invention, only for the present invention being described and being not to be subject to the described technical scheme of the embodiment of the invention, those of ordinary skill in the art is to be understood that, still can make amendment or be equal to replacement the present invention, to reach identical technique effect; Use needs as long as satisfy, all within protection scope of the present invention.

Claims (1)

1. a viscous crude drilling liner cementing squeezes and scurries a body technique, and it is characterized in that: this technical step is as follows:
One, according to earth formation, lithology, oil recovery data and block characteristics, the size of groove is scurried in estimation, calculates envelope and scurries required cement paste consumption;
Two, calculate the solid required cement paste consumption of tail pipe according to the tail pipe size;
Three, the summation of step 1 and two required cement paste consumptions is exactly the required cement slurry volume of present technique;
Four, construction sequence:
(1) well is prepared: the well of tail pipe is repaiied cover or bore hole is crept into or drifting to being used for down;
(2) tail pipe under: following float collar, float shoe, tail pipe, hollow plug, suspension organ pipe string;
(3) circulation well cleanup: put circulation workover fluid in back under the tail pipe in place more than one week;
(4) hanger is sat and is hung: hanger is sat extension, drive central tube;
(5) replace into oil well cement paste: replace into oil well cement paste, throw little plug, pump into displacement fluid;
(6) bruising: come downwards to the spoiler bruising after little plug and hollow plug are compound;
(7) upper lifting pipe post: the up and hanger of central tube is thrown off, the upper lifting pipe post to the precalculated position namely apart from hanger 100-300m;
(8) circulation well cleanup: circulation well cleanup washes out superfluous water mud in the well;
(9) close half envelope blowout preventer, the cement paste more than the hanger is clamp-oned scurried groove location, band is pressed closing well Hou Ning;
(10) bore plug: following bit drills cement plug;
(11) drifting: select jack rabbit to carry out drifting to design attitude, circulation well cleanup is more than one week;
(12) test: detect solid tail pipe quality, completion.
CN201310133645.8A 2013-04-17 2013-04-17 Viscous crude drilling liner cementing squeezes and alters integrated method Active CN103206191B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310133645.8A CN103206191B (en) 2013-04-17 2013-04-17 Viscous crude drilling liner cementing squeezes and alters integrated method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310133645.8A CN103206191B (en) 2013-04-17 2013-04-17 Viscous crude drilling liner cementing squeezes and alters integrated method

Publications (2)

Publication Number Publication Date
CN103206191A true CN103206191A (en) 2013-07-17
CN103206191B CN103206191B (en) 2015-09-30

Family

ID=48753578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310133645.8A Active CN103206191B (en) 2013-04-17 2013-04-17 Viscous crude drilling liner cementing squeezes and alters integrated method

Country Status (1)

Country Link
CN (1) CN103206191B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948788A (en) * 2017-03-21 2017-07-14 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 A kind of method for implementing secondary well cementation in net horizontal section
CN114109298A (en) * 2020-08-26 2022-03-01 中国石油天然气股份有限公司 Method for cementing lost-circulation zone well section
CN114320217A (en) * 2020-09-30 2022-04-12 中国石油天然气股份有限公司 Secondary well cementation and water plugging method for pipe outside channeling well

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5566757A (en) * 1995-03-23 1996-10-22 Halliburton Company Method and apparatus for setting sidetrack plugs in open or cased well bores
US6772835B2 (en) * 2002-08-29 2004-08-10 Halliburton Energy Services, Inc. Apparatus and method for disconnecting a tail pipe and maintaining fluid inside a workstring
CN1621658A (en) * 2003-11-28 2005-06-01 大港油田集团有限责任公司 Well cementing technology by center tube replacing elutriation method
CN1632278A (en) * 2003-12-24 2005-06-29 大港油田集团有限责任公司 Big tail pipe side drilling well cementing technology

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5566757A (en) * 1995-03-23 1996-10-22 Halliburton Company Method and apparatus for setting sidetrack plugs in open or cased well bores
EP0733775B1 (en) * 1995-03-23 2004-05-19 Halliburton Company Method and apparatus for setting a sidetrack plug in a well bore
US6772835B2 (en) * 2002-08-29 2004-08-10 Halliburton Energy Services, Inc. Apparatus and method for disconnecting a tail pipe and maintaining fluid inside a workstring
CN1621658A (en) * 2003-11-28 2005-06-01 大港油田集团有限责任公司 Well cementing technology by center tube replacing elutriation method
CN1632278A (en) * 2003-12-24 2005-06-29 大港油田集团有限责任公司 Big tail pipe side drilling well cementing technology

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948788A (en) * 2017-03-21 2017-07-14 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 A kind of method for implementing secondary well cementation in net horizontal section
CN106948788B (en) * 2017-03-21 2020-03-17 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 Method for implementing secondary well cementation in horizontal well section
CN114109298A (en) * 2020-08-26 2022-03-01 中国石油天然气股份有限公司 Method for cementing lost-circulation zone well section
CN114320217A (en) * 2020-09-30 2022-04-12 中国石油天然气股份有限公司 Secondary well cementation and water plugging method for pipe outside channeling well

Also Published As

Publication number Publication date
CN103206191B (en) 2015-09-30

Similar Documents

Publication Publication Date Title
CN101864921B (en) Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN201165866Y (en) Horizontal well division and combination extracting pipe column
CN101787854B (en) Subsection well completion system of bottom water reservoir horizontal well
CN101624904B (en) Open hole completion well sand resistant pipe string of sidetracking branch well and inserting type acid cleaning filling inner pipe string thereof
CN105134141B (en) A kind of process pipe string
CN201705219U (en) Lateral drilling gravel pack completion string
CN104213846B (en) Cased hole completion multistage frac water horizontal well selectivity mining tubular column and method of work thereof
CN107762444B (en) Integrated tubular column for well cementation and sand prevention and use method
CN104088599A (en) Expansion bridge blinding method for outer packer of cement paste filled pipe
CN103806837A (en) Well completion technology of oil field horizontal well
CN202882846U (en) Downhole isolating valve
CN109723403A (en) A kind of tail pipe pressure control well shaft fixing technology
CN110886594B (en) Method for exploiting coal bed gas
CN103206191B (en) Viscous crude drilling liner cementing squeezes and alters integrated method
CN201738822U (en) String for upper horizontal well cementation and lower screen pipe gravel pack completion
CN201486538U (en) Sand prevention pipe string used for open-hole well completion of side-drilled multilateral well and plug-in type acid cleaning filling inner pipe string thereof
CN104088601A (en) Channeling sealing tool for outer packer of cement paste filled pipe
CN103089193A (en) Tail pipe completion method by plugging expandable casing on top of screen pipe
CN204532299U (en) A kind of laminated distributor under well pitching and receipts ball instrument
CN203961897U (en) A kind of cement paste filling tube external packer envelope is altered instrument
CN207813559U (en) The self-priming external packer of pipe of cement
CN104695914B (en) High-pressure packing sand-control tubing string is segmented in horizontal well tube
CN1456785A (en) Selective multi-stage inner pipe cementing process and cemented tubular column there from
CN202451074U (en) Interlayer packer centralizer capable of expanding initiatively when meeting oil/water
CN201225121Y (en) Oil gas well selective completion tool

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20151209

Address after: Tian Dawa County 124114 Liaoning city of Panjin Province Town Industrial Park

Patentee after: Liaoning Kun Cheng Industrial Co., Ltd.

Address before: Tian Dawa County 124114 Liaoning city of Panjin Province Town Industrial Park

Patentee before: Panjin Liaohe Oilfield Kuncheng Industry Co., Ltd.