CN103186135B CN201110443029.3A CN201110443029A CN103186135B CN 103186135 B CN103186135 B CN 103186135B CN 201110443029 A CN201110443029 A CN 201110443029A CN 103186135 B CN103186135 B CN 103186135B
Authority
CN
China
Prior art keywords
fire
debugging
fighting
normal
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110443029.3A
Other languages
Chinese (zh)
Other versions
CN103186135A (en
Inventor
肖宇峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201110443029.3A priority Critical patent/CN103186135B/en
Publication of CN103186135A publication Critical patent/CN103186135A/en
Application granted granted Critical
Publication of CN103186135B publication Critical patent/CN103186135B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)
  • Alarm Systems (AREA)

Abstract

An adjustment method for rise residential fire-fighting linkage control system, is characterized in that comprising the following steps: a checks specification of equipment, model, standby redundancy, inspection record, the completion report of construction work of control system; B checks the main line of Central Control Room, c checks the main frame of Central Control Room, d debugs flat bed detector branch road, fire broadcast, intercom system and fire resistance rolling shutter door, e forceful electric power switches debugging, the debugging of f air-valve and blower fan, g elevator debugging, the debugging of h spray pump and fire extinguishing pump, i primary power and standby power supply test, the debugging of j total system and k total system are checked and accepted.The adjustment method of rise residential fire-fighting linkage control system of the present invention has that debugging step is reasonable in design, simple to operate, debugged program systematization, standardization, workable advantage, the debugging for rise residential fire-fighting linkage control system provides successfully practical and implements example.

Description

The adjustment method of rise residential fire-fighting linkage control system
Technical field
The present invention relates to a kind of adjustment method of fire-fighting linkage control system, specifically, is a kind of adjustment method of rise residential fire-fighting linkage control system.
Background technology
Along with the development of China's building cause, skyscraper and building group get more and more, thus facilitate the fast development of fire-fighting cause, and the design for fire protection of skyscraper, installation, debugging are the complex engineering projects of a multi-specialized cooperation.The control center of rise residential fire-fighting linkage control system patrols survey to detection circuit, when catching fire in a certain search coverage, the detecting area device at this place collects on-site signal, and immediately signal is beamed back the controller of control center, this signal judges by controller, catch fire if confirm, then controller sends sound and light alarm signal and fire disaster emergency broadcast to scene of fire, and send executive signal by linkage controller to needing the fire fighting equipment of interlock, and cut off non fire fighting power supply, eliminate initial fire disaster.The control center of rise residential fire-fighting linkage control system is arranged on the building's management center first floor, and arranges dual power supply, to guarantee that power supply is reliable.Control center's major equipment is: fire alarm control unit, multi-thread fire protection linkage control device, bus fire protection linkage control device, fire telephone exchange, fire broadcasting equipment, fire-fighting link power supply etc.
The debugging of rise residential fire-fighting linkage control system is based on following condition:
A. system debug should be carried out after interior of building finishing and fire protection alarm system construction terminate.
B. an automatic equipment which can report a fire should according to the requirement of design drawing, model, quantity, specification, kind, outward appearance are checked, and the effective qualification test report in NFA Quality of electronic products supervisory detection center is provided, and other data required about installing wiring, simultaneously with provide the unit of equipment to handle approach facility to check formality.
C. the necessary first commissioning test of fire-fighting link relevant devices is qualified, and in advance the logical program of reporting to the police and link is finished by this completion of works figure by equipment manufacturer.
Adopt the electric fire-control systems such as the high-rise building automatic fire alarm of concentrated alarm and fire-fighting link, as the forecasting in advance of fire, the putting out in time of fire, ensure the person and property safety, play irreplaceable effect.When a set of perfect automatic fire alarm system is buildings breaking out of fire, can the effective guarantee of people's lives and properties find the condition of a fire rapidly and accurately, and fire is eliminated the key point in bud.
The adjustment method of current domestic rise residential fire-fighting linkage control system is still in the stage lack of standardization, there is a lot of not science, irrational place, lacks systematization, normalized debugging method and program.
The adjustment method of therefore known rise residential fire-fighting linkage control system also exists above-mentioned all inconvenience and problem.
Summary of the invention
Object of the present invention, is that after proposing a kind of fire occurs, the various fire fighting equipment of combined launch reaches the adjustment method of the rise residential fire-fighting linkage control system of the effect of reporting to the police and stamping out a fire.
For achieving the above object, technical solution of the present invention is:
An adjustment method for rise residential fire-fighting linkage control system, is characterized in that comprising the following steps:
Specification of equipment, model, standby redundancy, inspection record, the completion report of construction work of a, examination control system;
The main line of b, inspection Central Control Room
The flat bed circuit of fire-fighting junction box in Vertical Shaft for Light-Current and the main line entering Central Control Room are disconnected, with megger, Insulation test is carried out to main line, make main line without short circuit, breaking phenomena;
The main frame of c, inspection Central Control Room
By main frame inner member and the wiring of input power source of main frame manufacturer personnel inspection Central Control Room, then energising without exception checks host function;
D, debugging flat bed detector branch road, fire broadcast, intercom system and fire resistance rolling shutter door
One by one branch road, fire compartment are debugged, until all qualified;
E, forceful electric power switch debugging
By forceful electric power unit in charge of construction technician scene, manual power-off inspection is carried out to each lighting loop, whether checking emergency starting is normal, the debugging of fire-fighting light current is carried out after normal, whether unanimously with wiring diagram connection terminal is checked by power distribution cabinet producer, then 24V power supply is connected in respective terminal, open power supply, thread off in switch and rear portion, and measure whether have return signal with multimeter, after normal, whether short circuit is had with the control line insulation status of multimeter Survey control circuit, breaking phenomena, again control line is connected on corresponding terminal, and carry out mark, the control line entered on joint action table also should be pressed on corresponding terminal, and carry out mark, now use manually at Central Control Room, interlock dish is tested, export 24V power supply, after power-off, on joint action table, return signal lamp is bright, prove this network and function normal,
The debugging of f, air-valve and blower fan
First by air-valve factory Domestic hand, air valve body is tested, electronic test is carried out with 24V power supply again after normal, and have signal to return, then valve class control line multimeter is tested, after normal, line is connected on the corresponding terminal of valve body, in vertical shaft, branch line is connected on main line simultaneously; At Central Control Room, carry out testing once with Non-follow control dish, show after qualified circuit and function debugging complete;
G, elevator debugging
First by fire-fighting connection terminal in elevator professional personnel inspection rack and wiring diagram correctly whether before debugging, fire-fighting operation circuit tested by errorless rear megger, then control line accessed on corresponding fire-fighting terminal, and carry out mark, Central Control Room control line is pressed, manually export 24V power supply with manually coiling, the first floor is down to by elevator simultaneously, and have signal to return, after non-Fire lift is down to the first floor, return signal, then export 24V power supply, cut off forceful electric power, and return signal shows on joint action table;
The debugging of h, spray pump and fire extinguishing pump
Fire extinguishing pump and spray pump are that single stay enters Central Control Room, and console panel manual/autoly can carry out switching and control; First check that whether switch board internal wiring terminal is consistent with fire-fighting wiring diagram by switch board producer before fire extinguishing pump debugging, open fire pump system discharge opening, first on switch board, manual start and stop test is carried out by forceful electric power professional, and throw running test mutually, after normal operation, control line being pressed into switch board, carrying out start and stop test with manually coiling, and to receive corresponding signal be that function is normal, then carry out simulation test to meeting the requirements;
I, primary power and standby power supply are tested
Check that the primary power of automatic fire alarm system and the capacity of standby power supply should meet the countries concerned's standard-required, the continuous discharge and recharge of standby power supply three times should be normal, and the conversion of primary power, standby power supply should be normal;
J, total system are debugged:
More than subitem debugging complete and qualified after, each controller interlock dish, fire broadcast, intercom system carries out entirety debugging after reaching normal condition, debugging is undertaken by each fire compartment, all fire fighting equipment normal using states of this fire compartment, the smoke detector of same fire compartment, heat detector special smoke adding and exerciser of heating, and respectively warning test is carried out one by one to all kinds of detector, Central Control Room receives fire alarm and records time of fire alarming display alarm region, and connect corresponding urgent broadcast, cut off forceful electric power and connect the decline of emergency lighting fire resistance rolling shutter door, and open corresponding exhaust smoke valve, forced draft valve, start relevant induced-draft fan and forced draft machine simultaneously, press fire-fighting pushbutton enable fire extinguishing pump,
K, total system are checked and accepted
From mutual check system work well errorless after, specifically to be implemented interrelated data, conformity certification, examining report, fire department to put on record the completion information reports such as proof and supervision companies, overall budget by fire-fighting company responsible official, require that each other does this work about subpackage simultaneously simultaneously, after management overall budget, examination & verification approval, fill in examination declaration form on request.
The adjustment method of rise residential fire-fighting linkage control system of the present invention can also be further achieved by the following technical measures.
Aforesaid method, in wherein said step e, also comprises and testing every primary Ioops by forceful electric power switching adjustment method, comprise illumination, Air Conditioning Facilities and power power-off, all reaches normal qualified rear explanation forceful electric power switching debugging complete.
Aforesaid method, in wherein said step g, also comprises electricity consumption trapeziodal modulation method for testing and every portion elevator is debugged, and all reaches function normally for debugging is complete.
Aforesaid method, wherein, in described step j, also comprises and debugging each fire compartment by total system adjustment method, reach function normal after, for total system debugging is complete.
Aforesaid method, in wherein said step j, automatic fire alarm system carries out 120h non-fault continuously and is debugging and completes.
After adopting technique scheme, the adjustment method of rise residential fire-fighting linkage control system of the present invention has the following advantages:
1, debugging step is reasonable in design, simple to operate;
2, debugged program systematization, standardization, workable;
3, for the debugging of rise residential fire-fighting linkage control system provides successfully practical example.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
The adjustment method of rise residential fire-fighting linkage control system of the present invention, is characterized in that comprising the following steps:
Specification of equipment, model, standby redundancy, inspection record, the completion report of construction work of a, examination control system;
The main line of b, inspection Central Control Room
The flat bed circuit of fire-fighting junction box in Vertical Shaft for Light-Current and the main line entering Central Control Room are disconnected, with megger, Insulation test is carried out to main line, without short circuit, breaking phenomena;
The main frame of c, inspection Central Control Room
By main frame inner member and the wiring of input power source of main frame manufacturer personnel inspection Central Control Room, then energising without exception checks host function;
D, debugging flat bed detector branch road, fire broadcast, intercom system and fire resistance rolling shutter door
One by one branch road, fire compartment are debugged, until all qualified;
E, forceful electric power switch debugging
Undertaken manually by forceful electric power unit in charge of construction technician scene, power-off is carried out to each lighting loop and checks that whether emergency starting is normal, the debugging of fire-fighting light current is carried out after normal, whether unanimously with wiring diagram connection terminal is checked by power distribution cabinet producer, then 24V power supply is connected in respective terminal, open power supply, thread off in switch and rear portion, and measure whether have return signal with multimeter, after normal, whether short circuit is had with the insulation of multimeter Survey control circuit, breaking phenomena, then control line is connected on corresponding terminal, and carry out mark, the control line entered on joint action table also should be pressed on corresponding terminal, and carry out mark, now use manually at Central Control Room, interlock dish is tested, export 24V power supply, after power-off, joint action table lamp last time is bright, prove this network and function normal, by this kind of method, every primary Ioops is tested, (comprising illumination, Air Conditioning Facilities, power power-off) all reach normally qualified after, illustrate that this debugging efforts is complete,
The debugging of f, air-valve and blower fan
First by air-valve factory Domestic hand, valve body is tested, carry out electronic test with 24V power supply again after normal, and have signal to return, then valve class control line multimeter is tested, after normal, line is connected on the corresponding terminal of valve body, in vertical shaft, branch line is connected on main line simultaneously; At Central Control Room, carry out testing once with Non-follow control dish, show after qualified circuit and function debugging complete;
G, elevator debugging
First by fire-fighting connection terminal in elevator professional personnel inspection rack and wiring diagram correctly whether before debugging, fire-fighting operation circuit tested by errorless rear megger, then line accessed on corresponding fire-fighting terminal, and carry out mark, and simultaneously that Central Control Room line pressure is good, manually export 24V power supply with manually coiling, the first floor is down to by elevator, and have signal to return, and after non-Fire lift is down to the first floor, return signal, export 24V power supply again, cut off forceful electric power, and return signal, joint action table shows; In order to upper method, every portion elevator is debugged, all reach function normally for debugging is complete;
The debugging of h, spray pump, fire extinguishing pump
Fire extinguishing pump, spray pump are that single stay enters Central Control Room, and console panel manual/autoly can carry out switching and control; First check that whether switch board internal wiring terminal is consistent with fire-fighting wiring diagram by switch board producer before fire extinguishing pump debugging, open fire pump system discharge opening, first on switch board, manual start and stop test is carried out by forceful electric power specialty, and throw running test mutually, after normal operation, line pressure being entered switch board, carrying out start and stop test with manually coiling, and to receive corresponding signal be that function is normal, then carry out simulation test to meeting the requirements;
I, primary power and standby power supply are tested
Check primary power: the primary power of automatic fire alarm system and standby power supply, its capacity should meet the countries concerned's standard-required, and the continuous discharge and recharge of standby power supply three times should be normal, and the conversion of primary power, standby power supply should be normal;
J, total system are debugged:
More than subitem debugging complete and qualified after, each controller interlock dish, fire broadcast, intercom system carries out entirety debugging after reaching normal condition, debugging is undertaken by each fire compartment, all fire fighting equipment normal using states of this fire compartment, the smoke detector of same fire compartment, the smoke adding of heat detector application specific, the exerciser such as to heat, and respectively warning test is carried out one by one to all kinds of detector, Central Control Room receives fire alarm and records time of fire alarming display alarm region, and connect corresponding urgent broadcast, cut off forceful electric power and connect the decline of emergency lighting fire resistance rolling shutter door, and open corresponding exhaust smoke valve, forced draft valve, start relevant induced-draft fan and forced draft machine simultaneously, press fire-fighting pushbutton enable fire extinguishing pump.By above method, each fire compartment is debugged, reach function normal after, complete for debugging; Automatic fire alarm system carries out 120h non-fault continuously and is debugging and completes;
K, total system are checked and accepted
From mutual check system work well errorless after, to be put on record the completion information reports such as proof and supervision companies, overall budget by fire-fighting company responsible official specifically implement to apply for checking and examination interrelated data, conformity certification, examining report, fire department, require that each other does this work about subpackage simultaneously simultaneously, after management overall budget, examination & verification approval, fill in examination declaration form on request.
The adjustment method of rise residential fire-fighting linkage control system of the present invention is obtained for utilization in the Housing Project (27) of plot three, Mei Long town 209, Minhang District, Shanghai phase Ancillary Commercial Housing project, Be very effective, obtains construction unit (Mei Long town, Minxing District) and community owner abundant affirmation.
Above embodiment is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, all equivalent technical schemes also should belong to category of the present invention, should be limited by each claim.

Claims (5)

1. an adjustment method for rise residential fire-fighting linkage control system, is characterized in that comprising the following steps:
Specification of equipment, model, standby redundancy, inspection record, the completion report of construction work of a, examination control system;
The main line of b, inspection Central Control Room
The flat bed circuit of fire-fighting junction box in Vertical Shaft for Light-Current and the main line entering Central Control Room are disconnected, with megger, Insulation test is carried out to main line, make main line without short circuit, breaking phenomena;
The main frame of c, inspection Central Control Room
By main frame inner member and the wiring of input power source of main frame manufacturer personnel inspection Central Control Room, then energising without exception checks host function;
D, debugging flat bed detector branch road, fire broadcast, intercom system and fire resistance rolling shutter door
One by one branch road, fire compartment are debugged, until all qualified;
E, forceful electric power switch debugging
By forceful electric power unit in charge of construction technician scene, manual power-off inspection is carried out to each lighting loop, whether checking emergency starting is normal, the debugging of fire-fighting light current is carried out after normal, whether unanimously with wiring diagram connection terminal is checked by power distribution cabinet producer, then 24V power supply is connected in respective terminal, open power supply, thread off in switch and rear portion, and measure whether have return signal with multimeter, after normal, whether short circuit is had with the control line insulation status of multimeter Survey control circuit, breaking phenomena, again control line is connected on corresponding terminal, and carry out mark, the control line entered on joint action table also will be pressed on corresponding terminal, and carry out mark, now use manually at Central Control Room, interlock dish is tested, export 24V power supply, after power-off, on joint action table, return signal lamp is bright, prove this network and function normal,
The debugging of f, air-valve and blower fan
First by air-valve factory Domestic hand, air valve body is tested, electronic test is carried out with 24V power supply again after normal, and have signal to return, then valve class control line multimeter is tested, after normal, line is connected on the corresponding terminal of valve body, in vertical shaft, branch line is connected on main line simultaneously; At Central Control Room, carry out testing once with Non-follow control dish, show after qualified circuit and function debugging complete;
G, elevator debugging
First by fire-fighting connection terminal in elevator professional personnel inspection rack and wiring diagram correctly whether before debugging, fire-fighting operation circuit tested by errorless rear megger, then control line accessed on corresponding fire-fighting terminal, and carry out mark, Central Control Room control line is pressed, manually export 24V power supply with manually coiling, the first floor is down to by elevator simultaneously, and have signal to return, after non-Fire lift is down to the first floor, return signal, then export 24V power supply, cut off forceful electric power, and return signal shows on joint action table;
The debugging of h, spray pump and fire extinguishing pump
Fire extinguishing pump and spray pump are that single stay enters Central Control Room, and console panel manual/autoly can carry out switching and control; First check that whether switch board internal wiring terminal is consistent with fire-fighting wiring diagram by switch board producer before fire extinguishing pump debugging, open fire pump system discharge opening, first on switch board, manual start and stop test is carried out by forceful electric power professional, and throw running test mutually, after normal operation, control line being pressed into switch board, carrying out start and stop test with manually coiling, and to receive corresponding signal be that function is normal, then carry out simulation test to meeting the requirements;
I, primary power and standby power supply are tested
Check that the primary power of automatic fire alarm system and the capacity of standby power supply should meet the countries concerned's standard-required, the continuous discharge and recharge of standby power supply three times should be normal, and the conversion of primary power, standby power supply should be normal;
J, total system are debugged:
More than subitem debugging complete and qualified after, each controller interlock dish, fire broadcast, intercom system carries out entirety debugging after reaching normal condition, debugging is undertaken by each fire compartment, all fire fighting equipment normal using states of this fire compartment, the smoke detector of same fire compartment, heat detector special smoke adding and exerciser of heating, and respectively warning test is carried out one by one to all kinds of detector, Central Control Room receives fire alarm and records time of fire alarming display alarm region, and connect corresponding urgent broadcast, cut off forceful electric power and connect the decline of emergency lighting fire resistance rolling shutter door, and open corresponding exhaust smoke valve, forced draft valve, start relevant induced-draft fan and forced draft machine simultaneously, press fire-fighting pushbutton enable fire extinguishing pump,
K, total system are checked and accepted
From mutual check system work well errorless after, specifically implemented interrelated data, conformity certification, examining report, fire department to put on record by fire-fighting company responsible official and prove completion information report and supervision companies, overall budget, require that each other does this work about subpackage simultaneously simultaneously, after management overall budget, examination & verification approval, fill in examination declaration form on request.
2. the adjustment method of rise residential fire-fighting linkage control system as claimed in claim 1, it is characterized in that, in described step e, also comprise and by forceful electric power switching adjustment method, every primary Ioops being tested, comprise illumination, Air Conditioning Facilities and power power-off, all reach normal qualified rear explanation forceful electric power switching debugging complete.
3. the adjustment method of rise residential fire-fighting linkage control system as claimed in claim 1, is characterized in that, in described step g, also comprise electricity consumption trapeziodal modulation method for testing and every portion elevator is debugged, and all reaches function normally for debugging is complete.
4. the adjustment method of rise residential fire-fighting linkage control system as claimed in claim 1, it is characterized in that, in described step j, also comprise and by total system adjustment method, each fire compartment being debugged, reach function normal after, for total system debugging is complete.
5. the adjustment method of rise residential fire-fighting linkage control system as claimed in claim 1, is characterized in that, in described step j, automatic fire alarm system carries out 120h non-fault continuously and is debugging and completes.
CN201110443029.3A 2011-12-27 2011-12-27 The adjustment method of rise residential fire-fighting linkage control system Active CN103186135B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110443029.3A CN103186135B (en) 2011-12-27 2011-12-27 The adjustment method of rise residential fire-fighting linkage control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110443029.3A CN103186135B (en) 2011-12-27 2011-12-27 The adjustment method of rise residential fire-fighting linkage control system

Publications (2)

Publication Number Publication Date
CN103186135A CN103186135A (en) 2013-07-03
CN103186135B true CN103186135B (en) 2016-01-27

Family

ID=48677350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110443029.3A Active CN103186135B (en) 2011-12-27 2011-12-27 The adjustment method of rise residential fire-fighting linkage control system

Country Status (1)

Country Link
CN (1) CN103186135B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106485894B (en) * 2015-08-31 2020-12-11 霍尼韦尔国际公司 Security system, method and device for commissioning a security system
CN115140264B (en) * 2022-05-17 2023-07-25 中船黄埔文冲船舶有限公司 Partition debugging method
CN116540622B (en) * 2023-05-30 2023-12-08 北京上德自动化系统有限公司 Intelligent safety controller of programmable logic controller based on SIL authentication

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1556623A (en) * 2003-12-31 2004-12-22 中国电力科学研究院 Intelligent community and intelligent domestic automation system based on full electric power line and method
CN101826894A (en) * 2010-04-23 2010-09-08 深圳市鼎盛威电子有限公司 Intelligent community integrated interconnected system
CN102749902A (en) * 2012-07-04 2012-10-24 江苏省电力公司扬州供电公司 Integrated intelligent information monitoring platform of power distribution system in residential district

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6759946B2 (en) * 2001-12-06 2004-07-06 Mitsubishi Electric Research Laboratories, Inc. Home appliances network
EP2283403B1 (en) * 2008-05-16 2015-08-26 ABB Technology AG System and method for implementing a power control application in a distributed control system using iec61850

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1556623A (en) * 2003-12-31 2004-12-22 中国电力科学研究院 Intelligent community and intelligent domestic automation system based on full electric power line and method
CN101826894A (en) * 2010-04-23 2010-09-08 深圳市鼎盛威电子有限公司 Intelligent community integrated interconnected system
CN102749902A (en) * 2012-07-04 2012-10-24 江苏省电力公司扬州供电公司 Integrated intelligent information monitoring platform of power distribution system in residential district

Also Published As

Publication number Publication date
CN103186135A (en) 2013-07-03

Similar Documents

Publication Publication Date Title
CN104331042B (en) State evaluation method of hydropower plant computer monitoring system
CN204790529U (en) Novel intelligent home systems
CN202998169U (en) Intelligent power source monitoring device
CN201965477U (en) Comprehensive building information management system
CN103400481A (en) Detection method used for fire control alarm linkage system as well as system and device thereof
CN103186135B (en) The adjustment method of rise residential fire-fighting linkage control system
CN113082588A (en) Museum fire extinguishing system
CN106502152A (en) A kind of Internet of Things energy-saving safe intelligent control method and system
CN110320440A (en) A kind of terminal area power monitoring system
CN110975214B (en) Data acquisition system and fire extinguishing method of underground pipe gallery suspension type dry powder fire extinguishing device
TW202046258A (en) Dual-purpose relay isolator for fire alarm loop fault and repair including a signal receiving and transmitting module, a fire alarm signal transmission switch, a processing unit, a buzzer, a power module and a voltage detecting module
CN207304150U (en) Secondary equipment in power system dual power supply comprehensive management apparatus
CN201947062U (en) Misoperation-preventing device for pressure plate
CN115442181A (en) Fire-fighting equipment power monitoring system developed based on An Zhuobing
CN109507918B (en) Subway fan field control box
CN111210687B (en) Operation and maintenance training platform for electromechanical equipment system of urban rail transit
Suli et al. Automatic fire alarm and fire control linkage system in intelligent buildings
CN104240466B (en) Benzene hydrogenation engineering fire warning system adjustment method
CN211015105U (en) Granary automatic control system
CN204203756U (en) A kind of distributed locker control system
CN105977858A (en) Intelligent and safe distribution box
CN205182060U (en) Fire -fighting linkage control system
CN202887367U (en) Main board of fire hazard alarm controller
CN207249861U (en) Relay alarm and the automatic fire alarm system using the relaying alarm
CN215643000U (en) Anti-misoperation sound-light alarm system for distribution room

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant