CN103177401A - Distribution network e power failure method for fault maintenance - Google Patents

Distribution network e power failure method for fault maintenance Download PDF

Info

Publication number
CN103177401A
CN103177401A CN2013100928078A CN201310092807A CN103177401A CN 103177401 A CN103177401 A CN 103177401A CN 2013100928078 A CN2013100928078 A CN 2013100928078A CN 201310092807 A CN201310092807 A CN 201310092807A CN 103177401 A CN103177401 A CN 103177401A
Authority
CN
China
Prior art keywords
power failure
power
distribution network
user
range
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100928078A
Other languages
Chinese (zh)
Inventor
吴丽贤
张哲军
余永忠
陈旭宇
王永才
雷炳晖
韩利群
王俊丰
吴树鸿
宋才华
蓝源娟
陈科师
肖招娣
范婷
江锦荣
詹西竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Topway Network Co ltd
Foshan Power Supply Bureau of Guangdong Power Grid Corp
Original Assignee
Guangdong Topway Network Co ltd
Foshan Power Supply Bureau of Guangdong Power Grid Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Topway Network Co ltd, Foshan Power Supply Bureau of Guangdong Power Grid Corp filed Critical Guangdong Topway Network Co ltd
Priority to CN2013100928078A priority Critical patent/CN103177401A/en
Publication of CN103177401A publication Critical patent/CN103177401A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a distribution network fault maintenance method for power failure, which comprises the following steps of: acquiring user profile data from an electricity marketing information system, acquiring equipment account data from a distribution network production management system, and acquiring power network topology information from a distribution network global information system (GIS) system; establishing a corresponding relationship of substation-circuit-transformer-user according to acquired information; acquiring fault equipment information and selecting the power failure range according to the fault equipment information and power network topology information; performing power network topology tracking on a selected power failure range according to the corresponding relationship, and determining power failure users in the power failure range; calculating power failure indexes according to the fault maintenance time and the power failure users; and performing power failure on a distribution network according to the power failure indexes during fault maintenance. According to the distribution network fault maintenance power failure method, the working efficiency of the formulated power failure scheme is improved, the scientific power failure indexes are taken as the power failure basis, an optimized power failure scheme can be obtained, the power failure frequency is small, the time is short, the influence of power failure to the users is reduced, and the power supply reliability is improved.

Description

Distribution network failure maintenance power failure method
Technical field
The present invention relates to the electric power project engineering field, particularly relate to a kind of distribution network failure maintenance power failure method.
Background technology
Power supply quality is one of index that the most directly embodies management in power supply enterprise and service level, power supply quality comprises the quality of power supply and power supply reliability, user's outage management is an important content of reliability management of power supply, directly embodies the rationality of electrical network shelf structure and power supply enterprise to the ability of user's continued power.
When power distribution network produces equipment failure, power supply enterprise need to have a power failure that relevant device is overhauled to power distribution network, formulating corresponding power failure scheme has a power failure to power distribution network, can make to have a power failure and customer impact is dropped to minimum and formulate a power failure scheme, be the significant consideration of carrying out when having a power failure.
At first conventional art is realized selecting power failure equipments (as the power distribution network transformer) by manual type when power distribution network being carried out the trouble hunting power failure, by the user profile that certain manual calculations distribution transforming has influence on, carries out the reference that has a power failure during as trouble hunting.This mode manual operation, calculate too much, inefficiency, and because the artificial error of calculation is many, when causing trouble hunting, power off time is often, the time is long, and the power distribution network power supply reliability is low, and user's electricity consumption is produced serious influence.
Summary of the invention
Based on this, be necessary the problem low for above-mentioned efficient, that reliability is low, provide a kind of efficient, reliability higher distribution network failure maintenance power failure method.
A kind of distribution network failure maintenance power failure method comprises the steps:
Obtain subscriber profile data from the power marketing infosystem, obtain the Unit account of plant data from Distribution Network Job Management System, obtain power network topology information from the Distribution power network GIS system;
Corresponding relation according to described subscriber profile data, Unit account of plant data and power network topology information architecture transformer station-circuit-transformer-user;
Obtain faulty equipment information and select power failure range according to described faulty equipment information and described power network topology information;
According to described corresponding relation, selected power failure range is carried out power network topology and follow the trail of, determine the customer interrupted in described power failure range;
Calculate the power failure index according to corrective maintenance time and described customer interrupted;
According to described power failure index, power distribution network is had a power failure when trouble hunting.
Above-mentioned distribution network failure maintenance power failure method, obtain the basic datas such as power distribution network subscriber profile data, Unit account of plant data and power network topology information, build transformer station-circuit-transformer-user's corresponding relation, power network topology information by the distribution generalized information system is carried out the power failure range analysis in conjunction with the faulty equipment information of obtaining, follow the trail of the user who has a power failure and have influence on, then the power failure desired value of accurate Calculation science, and then have a power failure to power distribution network being carried out trouble hunting according to these power failure indexs.Based on information-based requirement, adopt the calculating means of robotization, improve the work efficiency of formulating the power failure scheme, as the power failure foundation, can obtain optimum power failure scheme with the power failure index of science, the power off time number of times is few, the time is short, reduce the impact that has a power failure on the user, improved power supply reliability.
Description of drawings
Fig. 1 is the distribution network failure maintenance power failure method flow diagram of an embodiment.
Embodiment
Be described in detail below in conjunction with the embodiment of accompanying drawing to distribution network failure maintenance power failure method of the present invention.
Fig. 1 shows the distribution network failure maintenance power failure method flow diagram of an embodiment, comprises the steps:
Step S10 obtains subscriber profile data from the power marketing infosystem, obtain the Unit account of plant data from Distribution Network Job Management System, obtains power network topology information from the Distribution power network GIS system.
Concrete, subscriber profile data bag user's user profile and power information etc., the account data that equipment account packet is drawn together the equipment such as transformer station, circuit, transformer, power network topology information comprise power network topology, Distribution power network GIS figure etc.
Step S20 is according to described subscriber profile data, Unit account of plant data and power network topology information architecture transformer station-circuit-transformer-user's corresponding relation.
Concrete, the basic datas such as the subscriber profile data that utilization is obtained, Unit account of plant data build transformer station-circuit-transformer-user's corresponding relation on the Distribution power network GIS figure according to power network topology.
Step S30 obtains faulty equipment information and selectes power failure range according to described faulty equipment information and described power network topology information.
Concrete, transfer the mode of lock, wireline inspection (as line data-logging) to find out the equipment that produces fault, the then relevant information of typing faulty equipment according to switch; For example, the information such as faulty equipment and device type thereof, in power distribution network positional information etc.
After obtaining the relevant information of faulty equipment, be directed to zone and the circuit at faulty equipment place, be selected in the power failure range when faulty equipment is overhauled; Wherein, selected power failure range is in conjunction with the Distribution power network GIS figure, and selected power-off switch, divide power supply interrupted district by power-off switch on the GIS figure, determines power failure range by power-off switch.
As an embodiment, the method for selected power failure range can comprise as follows:
(1) be power failure range by the zone between selected former and later two power-off switches of faulty equipment of direction of current; Concrete, according to sense of current, the zone before and after faulty equipment between selected two power-off switches is power failure range, when formulating the power failure scheme; For example, selected power-off switch A presses direction of current to power-off switch B(, and the A switch is before the B switch), the zone between switch A, B is power failure range.
(2) press the front single power-off switch of the selected faulty equipment of direction of current and down partly be power failure range; Generally, can't turn involved area under electric power thus supplied, selected single power-off switch before faulty equipment, by single power-off switch power failure range, the following part of switch is all as power failure range.For example, selected power-off switch A(is with direction of current), the following All Ranges of switch A is power failure range
Step S40 carries out power network topology according to described corresponding relation to selected power failure range and follows the trail of, and determines the customer interrupted in this power failure range;
Particularly, call the Distribution power network GIS service, carrying out power failure range follows the trail of, take Distribution power network GIS topological structure of electric structure as the basis, press direction of current, selected power failure range is carried out follow-up analysis, in conjunction with transformer station-circuit-transformer-user's corresponding relation, obtain the customer interrupted information of selected power failure range impact.
In one embodiment, the process of step 40 comprises the steps:
A, call the Distribution power network GIS service, the power failure range that input is selected is followed the trail of the power distribution network transformer that power failure range has influence on.
B, determine the user that has influence in power failure range according to described corresponding relation and described power distribution network transformer; Concrete, after tracking relevant power distribution network transformer, on this basis in conjunction with transformer station-circuit-transformer-user's corresponding relation, thereby can find the user that power failure range has influence on, obtain customer interrupted information by subscriber profile data.
The user that the power failure condition is not satisfied in c, filtration obtains customer interrupted; The user who does not wherein satisfy the power failure condition mainly refers to the user who repeats to have a power failure, the user who turns electricity, the user of instantaneous power-off etc.
Step S50 calculates the power failure index according to corrective maintenance time and described customer interrupted,
In one embodiment, before calculating the power failure index, to the described user pre-service of classifying; Whether be about to the user and classify, be that responsible consumer carries out statistic of classification and storage by electric pressure, user's character, trade power consumption, wherein, statistical items comprises low-voltage customer number, Middle Voltage number, responsible consumer number and industrial amount; After statistic of classification, can be directed to all types of user and calculate the power failure index.
Generally, power failure index mainly comprises the customer interrupted number, number of users, scarce delivery and power failure capacity etc. when having a power failure.In conjunction with power off time and customer interrupted, calculate all kinds of power failure indexs, amount when having a power failure as low pressure, amount when mesohigh has a power failure, lack delivery, average power off time and frequency of power cut etc.
Step S60 has a power failure to power distribution network according to described power failure index when trouble hunting.
Concrete, power distribution network is had a power failure in order to reduce customer outage hours, frequency of power cut, should select best power failure range and power off time.
In one embodiment, when needs carry out trouble hunting to faulty equipment, be foundation according to the various power failure desired values of above-mentioned calculating, the power failure scheme of optimum power failure range and power off time of formulating is carried out power failure, thereby reduce frequency of power cut, power off time, reduce the impact that trouble hunting is had a power failure the user is produced.
The distribution network failure maintenance power failure method of above-described embodiment, use based on power distribution network is information-based, utilize the power distribution network basic data, by the customer interrupted that the topological analysis trouble hunting has a power failure and has influence on, the power failure desired value that the reflection of all kinds of science of COMPREHENSIVE CALCULATING has a power failure and affects, the foundation that maintenance has a power failure as distribution network failure, obtain optimum power failure scheme, when having reduced the trouble hunting power failure, customer outage hours and number of times, reduce the impact that has a power failure on the user, improves distribution network reliability.
The above embodiment has only expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to the scope of the claims of the present invention.Should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (6)

1. a distribution network failure maintenance power failure method, is characterized in that, comprises the steps:
Obtain subscriber profile data from the power marketing infosystem, obtain the Unit account of plant data from Distribution Network Job Management System, obtain power network topology information from the Distribution power network GIS system;
Corresponding relation according to described subscriber profile data, Unit account of plant data and power network topology information architecture transformer station-circuit-transformer-user;
Obtain faulty equipment information and select power failure range according to described faulty equipment information and described power network topology information;
According to described corresponding relation, selected power failure range is carried out power network topology and follow the trail of, determine the customer interrupted in described power failure range;
Calculate the power failure index according to corrective maintenance time and described customer interrupted;
According to described power failure index, power distribution network is had a power failure when trouble hunting.
2. distribution network failure maintenance power failure method according to claim 1, is characterized in that, the method for described selected power failure range comprises:
Be power failure range by the zone between selected former and later two power-off switches of faulty equipment of direction of current,
Or
Press the front single power-off switch of the selected faulty equipment of direction of current and down partly be power failure range.
3. distribution network failure maintenance power failure method according to claim 1, is characterized in that, the described step of obtaining faulty equipment information comprises:
Transfer the mode of lock, wireline inspection to find out the equipment that produces fault, the relevant information of the described faulty equipment of typing according to switch.
4. distribution network failure according to claim 1 maintenance power failure method, is characterized in that, describedly according to described corresponding relation, selected power failure range carried out power network topology and follow the trail of, and determines that the step of the customer interrupted in this power failure range comprises:
Call the Distribution power network GIS service, the power failure range that input is selected is followed the trail of the power distribution network transformer that power failure range has influence on;
Determine the user that has influence in power failure range according to described corresponding relation and described power distribution network transformer;
Filter the user who does not satisfy the power failure condition and obtain customer interrupted; Wherein, the described user who does not satisfy the power failure condition comprises the user who repeats to have a power failure, the user who turns electricity, the user of instantaneous power-off.
5. distribution network failure maintenance power failure method according to claim 1, is characterized in that, comprises before the step of calculating the power failure index according to described customer interrupted:
To the described user pre-service of classifying; Whether the user is classified, is that responsible consumer carries out statistic of classification and storage by electric pressure, user's character, trade power consumption, and wherein, statistical items comprises low-voltage customer number, Middle Voltage number, responsible consumer number and industrial amount.
6. distribution network failure maintenance power failure method according to claim 1, is characterized in that, described power failure index comprises: customer interrupted number, number of users, scarce delivery and power failure capacity when having a power failure.
CN2013100928078A 2013-03-21 2013-03-21 Distribution network e power failure method for fault maintenance Pending CN103177401A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100928078A CN103177401A (en) 2013-03-21 2013-03-21 Distribution network e power failure method for fault maintenance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100928078A CN103177401A (en) 2013-03-21 2013-03-21 Distribution network e power failure method for fault maintenance

Publications (1)

Publication Number Publication Date
CN103177401A true CN103177401A (en) 2013-06-26

Family

ID=48637234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100928078A Pending CN103177401A (en) 2013-03-21 2013-03-21 Distribution network e power failure method for fault maintenance

Country Status (1)

Country Link
CN (1) CN103177401A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103501049A (en) * 2013-10-16 2014-01-08 国家电网公司 Control method and system for distribution network
CN104112240A (en) * 2014-07-18 2014-10-22 国家电网公司 Power failure analytical method based on topological island analysis
CN104935007A (en) * 2015-06-16 2015-09-23 国网天津市电力公司 Control method for gird-connected operation of distributed power supply
CN105988407A (en) * 2016-06-22 2016-10-05 国网山东省电力公司蓬莱市供电公司 Interactive intelligent electric power service control platform
CN106022967A (en) * 2016-05-27 2016-10-12 中国南方电网有限责任公司 Intelligent power supply interruption range analyzing method and intelligent power supply interruption range analyzing system
CN108287294A (en) * 2018-01-29 2018-07-17 国网江苏省电力有限公司电力科学研究院 Distribution network failure region Fast Identification Method based on power failure distribution transforming and topological analysis
CN109921417A (en) * 2019-03-20 2019-06-21 国网浙江省电力有限公司嵊泗县供电公司 The optimal interruption maintenance method of maintenance requirement index analysis based on BPNN
CN110188895A (en) * 2019-05-30 2019-08-30 国电南瑞科技股份有限公司 A kind of scheduled outage user determines method
CN111141994A (en) * 2020-01-15 2020-05-12 广东电网有限责任公司 Method and system for rapidly notifying power line fault
CN112763846A (en) * 2020-12-23 2021-05-07 国网河南省电力公司电力科学研究院 Multi-data source information fusion-based intelligent power failure judgment method for distribution line

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100114475A1 (en) * 2008-10-30 2010-05-06 Korea Electric Power Corporation System for power facility navigation
CN102044020A (en) * 2010-12-03 2011-05-04 湖州电力局 Power distribution reliability pre-control method based on distribution network topology
CN102236841A (en) * 2011-06-28 2011-11-09 中国电力科学研究院 Method for handling accidents of electric power system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100114475A1 (en) * 2008-10-30 2010-05-06 Korea Electric Power Corporation System for power facility navigation
CN102044020A (en) * 2010-12-03 2011-05-04 湖州电力局 Power distribution reliability pre-control method based on distribution network topology
CN102236841A (en) * 2011-06-28 2011-11-09 中国电力科学研究院 Method for handling accidents of electric power system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王建: "配电设备在线监测与状态检修系统", 《中国优秀博硕士学位论文全文数据库(硕士),工程科技Ⅱ辑》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103501049B (en) * 2013-10-16 2016-01-06 国家电网公司 A kind of control method of power distribution network and system
CN103501049A (en) * 2013-10-16 2014-01-08 国家电网公司 Control method and system for distribution network
CN104112240A (en) * 2014-07-18 2014-10-22 国家电网公司 Power failure analytical method based on topological island analysis
CN104935007B (en) * 2015-06-16 2017-07-28 国网天津市电力公司 The control method that a kind of distributed power source is incorporated into the power networks
CN104935007A (en) * 2015-06-16 2015-09-23 国网天津市电力公司 Control method for gird-connected operation of distributed power supply
CN106022967A (en) * 2016-05-27 2016-10-12 中国南方电网有限责任公司 Intelligent power supply interruption range analyzing method and intelligent power supply interruption range analyzing system
CN105988407A (en) * 2016-06-22 2016-10-05 国网山东省电力公司蓬莱市供电公司 Interactive intelligent electric power service control platform
CN108287294A (en) * 2018-01-29 2018-07-17 国网江苏省电力有限公司电力科学研究院 Distribution network failure region Fast Identification Method based on power failure distribution transforming and topological analysis
CN108287294B (en) * 2018-01-29 2020-05-22 国网江苏省电力有限公司电力科学研究院 Power failure distribution transformer and topology analysis based power distribution network fault area rapid identification method
CN109921417A (en) * 2019-03-20 2019-06-21 国网浙江省电力有限公司嵊泗县供电公司 The optimal interruption maintenance method of maintenance requirement index analysis based on BPNN
CN109921417B (en) * 2019-03-20 2022-08-09 国网浙江省电力有限公司嵊泗县供电公司 BPNN-based maintenance demand index analysis optimal power failure maintenance method
CN110188895A (en) * 2019-05-30 2019-08-30 国电南瑞科技股份有限公司 A kind of scheduled outage user determines method
CN111141994A (en) * 2020-01-15 2020-05-12 广东电网有限责任公司 Method and system for rapidly notifying power line fault
CN112763846A (en) * 2020-12-23 2021-05-07 国网河南省电力公司电力科学研究院 Multi-data source information fusion-based intelligent power failure judgment method for distribution line

Similar Documents

Publication Publication Date Title
CN103177401A (en) Distribution network e power failure method for fault maintenance
CN103150688A (en) Power distribution network power cutting method
CN102257694B (en) Power grid outage and fault condition management
CN111835002B (en) Power distribution network reliability assessment method, device and storage medium
CN106814267B (en) A kind of implementation method that the power distribution station failure based on topology is studied and judged
CN104636450A (en) Database table space monitoring method
CN103926891B (en) Mobile Telecommunication Equipment Room environment in mobile stations equipment monitoring system and method
CN102497017B (en) Power grid failure information comprehensive collection platform and collection method
CN103376348A (en) Method of controlling fault current in system for monitoring and controlling power system
CN103500999A (en) Low voltage distribution area power supply radius optimization method based on real-time loss
CN103926485B (en) Power failure event judging method based on electric energy collecting terminal
CN103457249A (en) Smart distribution network distributed type pilot protection method and system
CN104730393A (en) District line loss rate detecting method and system
CN112986746A (en) Distribution network feeder fault cure rate automatic analysis method, system and equipment
CN105870956B (en) A kind of dc circuit breaker selection method for Multi-end flexible direct current transmission system
CN103618782A (en) Remote household appliance electricity utilization situation managing system with automatic repair reporting function
CN109767108A (en) A kind of accurate analysis method of electric power dispatching system line status
CN106452837B (en) A kind of intelligent substation switch Dynamic Configuration
CN104317868A (en) Control integration method based on single-front and multi-SCADA (Supervisory Control and Data Acquisition) application
CN105634781A (en) Multi-fault data decoupling method and device
CN103903195A (en) Power transmission and transformation equipment online monitoring data alarm monitoring method
CN114662333B (en) Smart power grids line loss detecting system based on thing networking
CN106208042B (en) Power distribution network outage information sharing method based on battalion's auxiliary tone fusion
Valtari et al. Requirements and proposed solutions for future smart distribution substations
CN109460896A (en) A kind of power grid 110kV route N-1 risk automatically scanning analysis method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Wu Lixian

Inventor after: Song Caihua

Inventor after: Lan Yuanjuan

Inventor after: Chen Keshi

Inventor after: Xiao Zhaodi

Inventor after: Fan Ting

Inventor after: Guan Zhiwei

Inventor after: Chen Haosheng

Inventor after: Liang Huiyi

Inventor after: Zhan Xizhu

Inventor after: Zhang Zhejun

Inventor after: Yu Yongzhong

Inventor after: Chen Xuyu

Inventor after: Wang Yongcai

Inventor after: Lei Binghui

Inventor after: Han Liqun

Inventor after: Wang Junfeng

Inventor after: Wu Shuhong

Inventor before: Wu Lixian

Inventor before: Song Caihua

Inventor before: Lan Yuanjuan

Inventor before: Chen Keshi

Inventor before: Xiao Zhaodi

Inventor before: Fan Ting

Inventor before: Jiang Jinrong

Inventor before: Zhan Xizhu

Inventor before: Zhang Zhejun

Inventor before: Yu Yongzhong

Inventor before: Chen Xuyu

Inventor before: Wang Yongcai

Inventor before: Lei Binghui

Inventor before: Han Liqun

Inventor before: Wang Junfeng

Inventor before: Wu Shuhong

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: WU LIXIAN ZHANG ZHEJUN YU YONGZHONG CHEN XUYU WANG YONGCAI LEI BINGHUI HAN LIQUN WANG JUNFENG WU SHUHONG SONG CAIHUA LAN YUANJUAN CHEN KESHI XIAO ZHAODI FAN TING JIANG JINRONG ZHAN XIZHU TO: WU LIXIAN ZHANG ZHEJUN YU YONGZHONG CHEN XUYU WANG YONGCAI LEI BINGHUI HAN LIQUN WANG JUNFENG WU SHUHONG SONG CAIHUA LAN YUANJUAN CHEN KESHI XIAO ZHAODI FAN TING GUAN ZHIWEI CHEN HAOSHENG LIANG HUIYI ZHAN XIZHU

RJ01 Rejection of invention patent application after publication

Application publication date: 20130626

RJ01 Rejection of invention patent application after publication