CN103174149B - 一种坝体接缝循环灌浆方法 - Google Patents

一种坝体接缝循环灌浆方法 Download PDF

Info

Publication number
CN103174149B
CN103174149B CN201310104082.XA CN201310104082A CN103174149B CN 103174149 B CN103174149 B CN 103174149B CN 201310104082 A CN201310104082 A CN 201310104082A CN 103174149 B CN103174149 B CN 103174149B
Authority
CN
China
Prior art keywords
grouting
dam body
agitator
stack
inlet pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310104082.XA
Other languages
English (en)
Other versions
CN103174149A (zh
Inventor
余英
李焰
李建斌
刘显斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gezhouba Group Testing and Inspection Co Ltd
Original Assignee
Gezhouba Group Testing and Inspection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gezhouba Group Testing and Inspection Co Ltd filed Critical Gezhouba Group Testing and Inspection Co Ltd
Priority to CN201310104082.XA priority Critical patent/CN103174149B/zh
Publication of CN103174149A publication Critical patent/CN103174149A/zh
Application granted granted Critical
Publication of CN103174149B publication Critical patent/CN103174149B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

一种坝体接缝循环灌浆方法,包括:进浆管、回浆管、排气管,将所述进浆管、回浆管、排气管与搅拌桶,灌浆泵连接成循环回路;每一进浆管、回浆管、排气管构成一套灌浆组件,每个灌浆区配备两套灌浆组件;对每个灌浆区的灌浆组件进行通水检查;通水检查完毕后,在灌浆区的两套灌浆组件中选择一个相对通畅性好的进浆管与灌浆泵连接,并安装阀门和压力表,其它5根管件连接到搅拌桶,进行回浆;灌浆开始后,对回到搅拌桶的浆液,进行原位再配置,配置所需要的浆液水灰比,再由搅拌桶内灌入到坝体缝内,形成循环灌浆。本发明改变了传统的间歇放浆式接缝灌浆方式,减少了容易堵塞缝面和管路事故发生的概率。

Description

一种坝体接缝循环灌浆方法
技术领域
本发明一种坝体接缝循环灌浆方法,适用于各类混凝土坝体接缝灌浆施工领域。
背景技术
水工大坝采取柱状法分缝浇筑。平行坝轴线的称为纵缝,垂直坝轴线的称为横缝。纵缝对坝体应力和稳定性不利,设计要求采取水泥浆液进行灌浆处理,横缝除混凝土重力拱坝或拱坝有整体要求灌浆外,一般不做灌浆处理。灌浆的目的是将胶凝材料通过管路灌入坝体接缝内,使其均匀分布,将坝体胶结成一个整体联合受力,并传递应力,以确保坝体稳定和安全运行。
实现灌浆成败的关键除接缝管路的布置形式外,还有灌浆工艺。灌浆管路无外乎由进浆管、回浆管、排气管三大类管道组成,每一进、回、排为一组,每个灌区一般通常有两套灌浆管路即进浆管和回浆管(一套)和备用进浆管及备用回浆管(另一套)。加之排气槽引出管,共计6根管。固定的灌浆管路布置形式,决定了灌浆工艺。传统常规的灌浆工艺一般是,选择2~3级水灰比浆液,即3:1、1:1、0.6(0.5):1,由稀到浓依次按比例由进浆管进浆,回浆管和排气管定时弃掉全部的稀浆,最终缝内留下0.6(0.5):1的浓浆至灌浆结束。该方法存在的问题是,由于弃浆不能重复利用。不仅造成浆液浪费加大了工程成本,还造成严重的环境污染,弃浆还需要清理同时也加大了作业人员不必要的劳动强度。其二,传统的灌浆方式为间歇放浆式灌注,浆液在缝内不能保持循环状态,容易造成堵塞缝面和管路事故,特别是灌区面积较大时更是如此。
发明内容
为解决上述技术问题,本发明提供一种坝体接缝循环灌浆方法,改变传统落后、粗放的工艺方法。采用循环灌浆法工艺更简单,质量更可靠。有效解决接缝灌浆弃浆量大,造成浆液浪费和环境污染问题,减轻作业人员的劳动强度。
本发明的上述目的是通过这样的技术方案来实现的:一种坝体接缝循环灌浆方法,包括:进浆管、回浆管、排气管,包括以下步骤:步骤1:将所述进浆管、回浆管、排气管与搅拌桶,灌浆泵连接成循环回路;步骤2:每一进浆管、回浆管、排气管构成一套灌浆组件,每个灌浆区配备两套灌浆组件;步骤3:对每个灌浆区的灌浆组件进行通水检查;步骤4:通水检查完毕后,在每个灌浆区的两套灌浆组件中选择其中一进浆管进浆,其它5根管件连接到搅拌桶,进行回浆;步骤5:灌浆开始后,对回到搅拌桶的浆液,进行原位再配置,配置所需要的浆液水灰比,再由搅拌桶内灌入到坝体缝内,形成循环灌浆。
所述通水检查中,通水压力为设计灌浆压力的80%,通水检查内容及应具备的基本条件为:
a.查明灌浆组件的管路通畅情况,每个灌浆区至少应具备一套灌浆组件管路畅通,其流量控制在:大于30L/min;
b.查明坝体缝面通畅情况,采用“单开通水”检查法,测得的两套灌浆组件中的两个排气管的“单开流量”控制在:大于25L/min;
c.查明灌浆区密闭情况,坝体缝面的漏水量控制在:小于15L/min。
所述浆液水灰比按先稀后浓的三级顺序灌注:2:1、1:1、0.6:1。
所述浆液水灰比按先稀后浓的三级顺序灌注:2:1、1:1、0.5:1。
所述灌浆压力0.2MPa~0.3MPa。
所述坝体缝面增开度允许值:纵缝不大于0.5㎜,横缝不大于0.3㎜。
所述排气管排浆达到或接近最浓比级浆液,且排气管管口压力或坝体缝面增开度达到设计规定值,注入率不大于0.4L/min时,持续20min,可结束灌浆。
本发明一种坝体接缝循环灌浆方法,采取全部回浆到搅拌桶内,再对回浆进行原位配置,配置所需要的水灰比,再由桶内灌入到缝内,形成循环灌浆。做到不弃浆、连续不停的循环灌注流程。有效的解决了以上浪费、污染等问题。做到了便捷施工、经济适用,环保,体现了良好的经济和社会效益。
附图说明
图1为本发明坝体接缝的纵缝灌浆管路系统布置示意图。
图2为本发明坝体接缝的横缝灌浆管路系统布置示意图。
图3为本发明坝体接缝循环灌浆布置示意图。
具体实施方式
一种坝体接缝循环灌浆方法,包括:进浆管1、回浆管2、排气管3,出浆盒4,排气槽5,升浆管6。
包括以下步骤:
将所述进浆管1、回浆管2、排气管3与搅拌桶9,灌浆泵10连接成循环回路;并在各灌浆管口安装控制阀7、压力表8。具体如下。
1、如图3所示,每个灌浆区配备两套灌浆组件,每一进浆管1、每一回浆管2、每一排气管3构成一套灌浆组件,每一套灌浆组件对缝面均分别进行通水检查。目的是彻底查清各组管路自身的通畅情况和与缝面的通畅情况。通水检查压力一般为设计灌浆压力的80%。检查内容及应具备的基本条件为:
a.查明灌浆组件的管路的通畅情况。每个灌浆区至少应具备一套灌浆管路畅通,其流量控制在:大于30L/min;
b.查明坝体缝面通畅情况,采用“单开通水”检查法,测得的两套灌浆组件中的两个排气管3的“单开流量”控制在:大于25L/min;
c.查明灌区密闭情况。坝体缝面的漏水量控制在:小于15L/min。
2、根据“单开通水”检查、灌浆区封闭情况和预灌性压水成果等,在图3两套灌浆组件中,选择相对通畅性好的一根进浆管1与灌浆泵10连接,并安装阀门7和压力表8。功能作用是,开泵后由此管向接缝内灌浆。
3、上述进浆管1安装完毕,其他的进浆管1、回浆管2、排气浆管3;共5根管。全部与搅拌桶9连接。(传统工艺中是不连接的)并分别安装好阀门7和压力表8。所述5根管与搅拌桶9连接其功能作用是回浆。传统工艺不回浆,直接弃浆。
3、灌浆时,上述进浆管1向缝内灌浆,浆液经升浆管6到出浆盒4、到接缝面、到排气槽5。最后到所述5根管中,经所述5根管到搅拌桶9,最后再经灌浆泵10由进浆管1向缝内灌浆,如此反复形成一个封闭的浆液流动大循环。
4、灌浆时,对回到搅拌桶9的浆液,进行原位再配置,配置成新的、需要的水灰比,再由搅拌桶9内灌入到坝体缝内,形成循环灌浆。做到不弃浆、连续不停的循环灌注流程。
5、水泥浆液的水灰比可按先稀后浓的三级顺序灌注:2:1、1:1、0.6(或0.5):1。
6、灌入计量:缝内灌入量(L)=浆液总量(L)-桶内剩余量(L)
7、缝内浆液密度:量测排气管3回浆密度即可。
8、灌浆压力:根据设计规定,按照排气管3增开度控制。一般情况下除顶层外,灌浆压力可取0.2MPa~0.3MPa;坝体缝面增开度允许值,纵缝不大于0.5㎜,横缝不大于0.3㎜。
9、灌浆结束标准:一般正常情况下,当排气管3排浆达到或接近最浓比级浆液,且排气管3管口压力或缝面增开度达到设计规定值,注入率不大于0.4L/min时,持续20min,可结束灌浆。

Claims (3)

1.一种坝体接缝循环灌浆方法,包括:进浆管(1)、回浆管(2)、排气管(3),其特征在于包括以下步骤:
步骤1:将所述进浆管(1)、回浆管(2)、排气管(3)与搅拌桶(9),灌浆泵(10)连接成循环回路;
步骤2:每一进浆管(1)、回浆管(2)、排气管(3)构成一套灌浆组件,每个灌浆区配备两套灌浆组件;
步骤3:对每个灌浆区的灌浆组件进行通水检查;
步骤4:通水检查完毕后,在每个灌浆区的两套灌浆组件中选择其中一进浆管(1)进浆,其它5根管件连接到搅拌桶(9),进行回浆;
步骤5:灌浆开始后,对回到搅拌桶(9)的浆液,进行原位再配置,配置所需要的浆液水灰比,再由搅拌桶(9)内灌入到坝体缝内,形成循环灌浆;
所述灌浆压力0.2MPa~0.3MPa;所述坝体缝面增开度允许值:纵缝不大于0.5㎜,横缝不大于0.3㎜;
所述通水检查中,通水压力为设计灌浆压力的80%,通水检查内容及应具备的基本条件为:
a.查明灌浆组件的管路通畅情况,每个灌浆区至少应具备一套灌浆组件管路畅通,其流量控制在:大于30L/min;
b.查明坝体缝面通畅情况,采用“单开通水”检查法,测得的两套灌浆组件中的两个排气管3的“单开流量”控制在:大于25L/min;
c.查明灌浆区密闭情况,坝体缝面的漏水量控制在:小于15L/min;
所述排气管(3)排浆达到或接近最浓比级浆液,且排气管(3)管口压力或坝体缝面增开度达到设计规定值,注入率不大于0.4L/min时,持续20min,可结束灌浆。
2.根据权利要求1所述一种坝体接缝循环灌浆方法,其特征在于,所述浆液水灰比按先稀后浓的三级顺序灌注:2:1、1:1、0.6:1。
3.根据权利要求1所述一种坝体接缝循环灌浆方法,其特征在于,所述浆液水灰比按先稀后浓的三级顺序灌注:2:1、1:1、0.5:1。
CN201310104082.XA 2013-03-28 2013-03-28 一种坝体接缝循环灌浆方法 Expired - Fee Related CN103174149B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310104082.XA CN103174149B (zh) 2013-03-28 2013-03-28 一种坝体接缝循环灌浆方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310104082.XA CN103174149B (zh) 2013-03-28 2013-03-28 一种坝体接缝循环灌浆方法

Publications (2)

Publication Number Publication Date
CN103174149A CN103174149A (zh) 2013-06-26
CN103174149B true CN103174149B (zh) 2015-12-09

Family

ID=48634304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310104082.XA Expired - Fee Related CN103174149B (zh) 2013-03-28 2013-03-28 一种坝体接缝循环灌浆方法

Country Status (1)

Country Link
CN (1) CN103174149B (zh)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953050B (zh) * 2014-04-14 2016-06-15 中国葛洲坝集团三峡建设工程有限公司 一种混凝土结合面二次灌浆装置及方法
CN104480902B (zh) * 2014-11-21 2016-08-24 淮海工学院 一种混凝土坝缝隙的堵漏方法
CN104480901B (zh) * 2014-11-21 2016-06-29 淮海工学院 一种土石坝的堵漏方法
CN105735200B (zh) * 2016-04-25 2019-04-30 长江勘测规划设计研究有限责任公司 用于止水检查槽封堵的止水浆液灌浆方法及装置
CN106587795B (zh) * 2016-11-07 2019-04-16 广东省水利水电科学研究院 一种双掺膨胀剂的水泥基大坝灌浆工艺及其施工方法
CN106930237A (zh) * 2017-05-09 2017-07-07 中国葛洲坝集团国际工程有限公司 一种大坝接缝灌浆复灌施工方法
CN108532557A (zh) * 2018-06-05 2018-09-14 中国电建集团贵阳勘测设计研究院有限公司 一种拱坝坝肩建基面接触灌浆系统布置方法
CN109518693A (zh) * 2019-01-14 2019-03-26 中水电第十工程局(郑州)有限公司 一种基岩固结-接触灌浆合二为一的施工方法
CN112647507A (zh) * 2020-12-18 2021-04-13 长江勘测规划设计研究有限责任公司 一种双向供浆孔内循环式接触灌浆系统及其使用方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1441125A (zh) * 2003-04-03 2003-09-10 武汉长江仪器自动化研究所 双只流量计循环灌浆多阀控制管路连接结构及其流量检测方法
CN2863903Y (zh) * 2006-01-20 2007-01-31 北京中大华瑞科技有限公司 带有密度采样支路的三参数大循环灌浆测量系统
CN101492917A (zh) * 2009-02-23 2009-07-29 成都现代万通锚固技术有限公司 中空锚杆循环压力注浆工法及其专用注浆系统
KR20100089375A (ko) * 2009-02-03 2010-08-12 주식회사 일청엔지니어링 수위조절이 용이한 고무댐 및 그 가동방법
CN201908307U (zh) * 2010-12-08 2011-07-27 中国水电顾问集团成都勘测设计研究院 接缝灌浆系统
CN102839650A (zh) * 2012-09-19 2012-12-26 中国水电顾问集团中南勘测设计研究院 一种钻灌一体、自上而下、高压冲挤灌浆系统

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1441125A (zh) * 2003-04-03 2003-09-10 武汉长江仪器自动化研究所 双只流量计循环灌浆多阀控制管路连接结构及其流量检测方法
CN2863903Y (zh) * 2006-01-20 2007-01-31 北京中大华瑞科技有限公司 带有密度采样支路的三参数大循环灌浆测量系统
KR20100089375A (ko) * 2009-02-03 2010-08-12 주식회사 일청엔지니어링 수위조절이 용이한 고무댐 및 그 가동방법
CN101492917A (zh) * 2009-02-23 2009-07-29 成都现代万通锚固技术有限公司 中空锚杆循环压力注浆工法及其专用注浆系统
CN201908307U (zh) * 2010-12-08 2011-07-27 中国水电顾问集团成都勘测设计研究院 接缝灌浆系统
CN102839650A (zh) * 2012-09-19 2012-12-26 中国水电顾问集团中南勘测设计研究院 一种钻灌一体、自上而下、高压冲挤灌浆系统

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
峡口拱坝接缝灌浆施工与质量控制;张建军等;《水利水电施工》;20060331(第1期);期刊第15-20页第1-3节 *
循环式灌浆在坝体防渗加固工程中的应用;勾有辉;《西部探矿工程》;19940731;第6卷(第4期);期刊第87-88页第3.2节-3.5节及图2 *

Also Published As

Publication number Publication date
CN103174149A (zh) 2013-06-26

Similar Documents

Publication Publication Date Title
CN103174149B (zh) 一种坝体接缝循环灌浆方法
CN201908307U (zh) 接缝灌浆系统
CN105442862A (zh) 一种混凝土裂缝渗漏水堵漏加固修复方法
CN103541550B (zh) 一种超高层建筑钢管混凝土的施工泵送系统
CN202440787U (zh) 一种河道导流装置
CN207778028U (zh) 输浆管路减压装置
CN206189365U (zh) 用于导流洞封堵体浇筑的导流封堵结构
CN207227077U (zh) 一种工业用水反渗透过滤系统
CN206985811U (zh) 一种富氢水机集成水道
CN202559321U (zh) 导流隧洞堵头混凝土排水管装置
CN105268574B (zh) 一种喷雾主机及其工作方法
CN205822146U (zh) 一种水库预泄兼生态流量下泄结构
CN202207633U (zh) 一种新型石膏浆液过流箱
CN209817282U (zh) 一种灌浆口在上的钢筋连接用灌浆套筒
CN209975479U (zh) 一种新型输水建筑物
CN103114601A (zh) 强渗漏地层的速凝高喷灌浆截渗方法及其装置
CN207919510U (zh) 导流隧洞利用永久堵头首段联合闸门下闸封堵布置
CN204435398U (zh) 一种截水导水系统
CN207034292U (zh) 消防用泡沫液灭火剂的混合器
CN206598397U (zh) 混凝土添加剂上料装置
CN205918395U (zh) 固控系统吸入管线布置结构
CN207333807U (zh) 一种壁式暗装单柄双控水龙头
CN203671582U (zh) 注入式锅炉给水泵防汽蚀装置
CN205557458U (zh) 一种土建用水管道混凝土预制件
CN204299534U (zh) 钻井管汇

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151209

Termination date: 20180328