CN103166138B - The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch - Google Patents

The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch Download PDF

Info

Publication number
CN103166138B
CN103166138B CN201310056763.3A CN201310056763A CN103166138B CN 103166138 B CN103166138 B CN 103166138B CN 201310056763 A CN201310056763 A CN 201310056763A CN 103166138 B CN103166138 B CN 103166138B
Authority
CN
China
Prior art keywords
section
cable branch
switchgear
bypass cable
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310056763.3A
Other languages
Chinese (zh)
Other versions
CN103166138A (en
Inventor
蔡俊宇
潘小山
李杨杰
陈志勇
苏雪源
陈志坚
蔡晓鸣
杨河林
陈文曲
林文新
张森
谢毅坚
吕文生
高鹭文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310056763.3A priority Critical patent/CN103166138B/en
Publication of CN103166138A publication Critical patent/CN103166138A/en
Application granted granted Critical
Publication of CN103166138B publication Critical patent/CN103166138B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Patch Boards (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to the transformation of a kind of switching cabinet and replacing options, particularly a kind of method changing switching cabinet based on the case segmentation transformation of bypass cable branch. The present invention by means of bypass cable branch case, enable the corresponding power line of switching cabinet and put for electric line temporarily, and obtain the power-on time at interval, substantially reduce the power off time of user, owing to have employed segmentation transformation, make transformation more orderly and simple, it is possible to effectively to shorten the transformation duration, and have a power failure in short-term several times, customer power supply is not affected when transforming basis and more renew bus looped network cabinet, facilitate user, there is good practicality, also substantially increase power supply reliability.

Description

基于旁路电缆分支箱分段改造更换开关柜的方法The method of segmental reconstruction and replacement of switchgear based on bypass cable branch box

技术领域technical field

本发明涉及一种开关柜的改造和更换方法,特别是一种基于旁路电缆分支箱分段改造更换开关柜的方法。The invention relates to a modification and replacement method of a switch cabinet, in particular to a method for segment modification and replacement of a switch cabinet based on a bypass cable branch box.

背景技术Background technique

随着经济的发展,早期建成的10kV开关站、开闭所、配电站投运时间长,开关柜等操作设备型号老旧且老化严重,满足不了负荷日益增长的需求,且故障率高,用户投诉多,急需改造。在对开关站进行整体改造时,需要停电操作,由于改造工期长,造成停电时间长,不但给用户带来极大的不便,还影响了供电的可靠性。With the development of the economy, the 10kV switch stations, switch stations, and distribution stations built in the early stage have been put into operation for a long time, and the operating equipment such as switch cabinets are old and aging, which cannot meet the increasing demand of the load, and the failure rate is high. There are many complaints from users and it is in urgent need of renovation. When the overall transformation of the switch station is carried out, power outage operation is required. Due to the long construction period of the transformation, the power outage time is long, which not only brings great inconvenience to users, but also affects the reliability of power supply.

发明内容Contents of the invention

本发明的目的在于根据现有技术的不足之处而提供一种实现不停电或短时停电改造开关站,缩短用户停电时间,缩短改造工期,提高供电可靠性的基于旁路电缆分支箱分段改造更换开关柜的方法。The purpose of the present invention is to provide a sub-section based on bypass cable branch box to realize non-stop or short-term power outage transformation switch station according to the deficiencies of the prior art, shorten the user power outage time, shorten the transformation period, and improve power supply reliability The method of transforming and replacing the switchgear.

本发明的目的是通过以下途径来实现的:The purpose of the present invention is achieved by the following approach:

基于旁路电缆分支箱分段改造更换开关柜的方法,其要点在于,包括如下依序步骤:The key point of the method for segmentally transforming and replacing the switchgear based on the bypass cable branch box is to include the following steps in sequence:

1、提供一种旁路电缆分支箱,包括箱体和位于箱体下方的槽钢,箱体内安装有三相母线铜排和位于该三相母线铜排上的复数个电缆连接端子;1. A bypass cable branch box is provided, including a box body and a channel steel located below the box body, and a three-phase busbar copper bar and a plurality of cable connection terminals located on the three-phase busbar copper bar are installed in the box body;

2、将上述的旁路电缆分支箱安装到待更换开关柜的现场中,所述待更换开关柜包括有I段母线开关柜和II段母线开关柜;2. Install the above-mentioned bypass cable branch box in the site of the switchgear to be replaced, the switchgear to be replaced includes a section I bus switchgear and a section II bus switchgear;

3、第一阶段短时停电,将I段母线开关柜的进线电源电缆和到单电源用户的出线电缆分别经由箱体下方的槽钢连接到旁路电缆分支箱里的不同电缆连接端子上,I段母线开关柜中到双电源用户的出线电缆停电,双电源用户另行提供进线供电;3. In the first stage of short-term power failure, the incoming power cables of the I-section bus switch cabinet and the outgoing cables to the single power supply users are respectively connected to different cable connection terminals in the bypass cable branch box through the channel steel under the box body , the outgoing cable from the I-section busbar switch cabinet to the dual power supply users is powered off, and the dual power supply users provide incoming power supply separately;

4、拆除I段母线开关柜,并对该柜基础进行改造,并安装上新的I段母线环网柜;4. Remove the I-section busbar switchgear, modify the foundation of the cabinet, and install a new I-section busbar ring network cabinet;

5、第二阶段短时停电,将I段母线开关柜所有进出线电缆按照I段母线环网柜的电气接线图进行搭接安装;5. In the second stage of short-term power failure, all the incoming and outgoing cables of the I-section bus switch cabinet shall be lapped and installed according to the electrical wiring diagram of the I-section bus ring network cabinet;

6、重复步骤3-5更换II段母线开关柜,改造更换结束后,拆除旁路电缆分支箱。6. Repeat steps 3-5 to replace the busbar switchgear of section II. After the transformation and replacement, remove the bypass cable branch box.

这样,本发明借助了旁路电缆分支箱,使开关柜的对应电源线和供电线路能够得到临时置放,并获得间隔的供电时间,大大缩短了用户的停电时间,由于采用了分段改造,使得改造更为有序和简单,能够有效缩短改造工期,且分多次短时停电,在改造基础并更换新母线环网柜时不影响用户供电,方便了用户,具有很好的实用性,也大大提高了供电可靠性。In this way, the present invention uses the bypass cable branch box to temporarily place the corresponding power lines and power supply lines of the switchgear, and obtain interval power supply time, which greatly shortens the user's power outage time. It makes the transformation more orderly and simple, can effectively shorten the transformation period, and divides into multiple short-term power outages, and does not affect the user's power supply when transforming the foundation and replacing the new bus ring network cabinet, which is convenient for users and has good practicability. It also greatly improves the reliability of power supply.

附图说明Description of drawings

图1所示为本发明所述旁路电缆分支箱的结构示意图;Fig. 1 shows the structural representation of bypass cable branch box of the present invention;

下面结合实施例对本发明做进一步描述。The present invention will be further described below in conjunction with the examples.

具体实施例specific embodiment

最佳实施例:Best practice:

以I段母线开关柜为例,基于旁路电缆分支箱分段改造更换开关柜的方法,包括如下依序步骤:Taking the I-section busbar switchgear as an example, the method of segmentally transforming and replacing the switchgear based on the bypass cable branch box includes the following sequential steps:

1、现场勘查待改造10kV开关站是否有足够的空间能够摆放旁路电缆分支箱。1. On-site investigation whether there is enough space for the bypass cable branch box in the 10kV switch station to be transformed.

2、现场勘查10kV进线、馈出电缆是否留有足够裕度能够将电缆回抽搭接至旁路电缆分支箱。2. On-site investigation of 10kV incoming and outgoing cables to see if there is enough margin to draw back the cables and connect them to the bypass cable branch box.

3、提供一种旁路电缆分支箱,包括箱体1和位于箱体下方的槽钢2,箱体1内安装有三相母线铜排3和位于该三相母线铜排上的复数个电缆连接端子4,槽钢2的高度必须保证电缆的弯曲半径。3. Provide a bypass cable branch box, including a box body 1 and a channel steel 2 located below the box body. A three-phase bus bar copper bar 3 and a plurality of cable connections on the three-phase bus bar copper bar are installed in the box body 1. The height of terminal 4 and channel steel 2 must ensure the bending radius of the cable.

4、将上述的旁路电缆分支箱安装到I段母线开关柜的现场中,并开始第一阶段短时停电,将I段母线开关柜的进线电源电缆和到单电源用户的出线电缆分别经由箱体下方的槽钢连接到旁路电缆分支箱里的不同电缆连接端子上,并确认旁路系统与原系统相序一致,I段母线开关柜中到双电源用户的出线电缆停电,双电源用户另行提供进线供电。4. Install the above-mentioned bypass cable branch box in the site of the I-section busbar switchgear, and start the first phase of short-term power failure, and separate the incoming power cables of the I-section busbar switchgear and the outgoing cables to the single power supply users Connect to different cable connection terminals in the bypass cable branch box through the channel steel at the bottom of the box, and confirm that the phase sequence of the bypass system is consistent with that of the original system. The power user shall provide the incoming power supply separately.

5、将进线电源对侧线路由运行转检修,给旁路电缆分支箱供电,将馈线对侧线路由运行转检修,使旁路系统投入运行,恢复对侧用户用电。5. Transfer the line on the opposite side of the incoming power supply from operation to inspection and maintenance, supply power to the branch box of the bypass cable, and transfer the line on the opposite side of the feeder from operation to inspection and maintenance, put the bypass system into operation, and restore the power consumption of the opposite side users.

6、拆除I段母线开关柜,并对该柜基础进行改造,并安装上新的I段母线环网柜。6. Remove the I-section busbar switchgear, modify the foundation of the cabinet, and install a new I-section busbar ring network cabinet.

7、第二阶段短时停电,将I段母线开关柜所有进出线电缆按照I段母线环网柜的电气接线图进行搭接安装。7. In the second stage of short-term power failure, all the incoming and outgoing cables of the I-section bus switch cabinet shall be lapped and installed according to the electrical wiring diagram of the I-section bus ring network cabinet.

本发明未述部分与现有技术相同。The parts not described in the present invention are the same as the prior art.

Claims (1)

1.基于旁路电缆分支箱分段改造更换开关柜的方法,其要点在于,包括如下依序步骤:1. The method for segmentally transforming and replacing the switchgear based on the bypass cable branch box includes the following steps in sequence: (1)提供一种旁路电缆分支箱,包括箱体和位于箱体下方的槽钢,箱体内安装有三相母线铜排和位于该三相母线铜排上的复数个电缆连接端子;(1) Provide a bypass cable branch box, including a box body and a channel steel located below the box body, and a three-phase bus bar copper bar and a plurality of cable connection terminals on the three-phase bus bar copper bar are installed in the box body; (2)将上述的旁路电缆分支箱安装到待更换开关柜的现场中,所述待更换开关柜包括有I段母线开关柜和II段母线开关柜;(2) Install the above-mentioned bypass cable branch box in the site where the switchgear to be replaced includes the I-section busbar switchgear and the II-section busbar switchgear; (3)第一阶段短时停电,将I段母线开关柜的进线电源电缆和到单电源用户的出线电缆分别经由箱体下方的槽钢连接到旁路电缆分支箱里的不同电缆连接端子上,I段母线开关柜中到双电源用户的出线电缆停电,双电源用户另行提供进线供电;(3) In the first stage of short-term power failure, the incoming power cables of the I-section busbar switch cabinet and the outgoing cables to the single power supply users are respectively connected to different cable connection terminals in the bypass cable branch box through the channel steel under the box body In the above, the outgoing cables from the I-section busbar switch cabinet to the dual power supply users are powered off, and the dual power supply users provide incoming power supply separately; (4)拆除I段母线开关柜,并对该I段母线开关柜基础进行改造,并安装上新的I段母线环网柜;(4) Remove the I-section busbar switchgear, transform the foundation of the I-section busbar switchgear, and install a new I-section busbar ring network cabinet; (5)第二阶段短时停电,将I段母线开关柜所有进出线电缆按照I段母线环网柜的电气接线图进行搭接安装;(5) In the second stage of short-term power failure, all the incoming and outgoing cables of the I-section bus switch cabinet shall be lapped and installed according to the electrical wiring diagram of the I-section bus ring network cabinet; (6)重复步骤(3)-(5)更换II段母线开关柜,改造更换结束后,拆除旁路电缆分支箱。(6) Repeat steps (3)-(5) to replace the busbar switchgear of section II. After the transformation and replacement, remove the bypass cable branch box.
CN201310056763.3A 2013-02-22 2013-02-22 The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch Active CN103166138B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310056763.3A CN103166138B (en) 2013-02-22 2013-02-22 The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310056763.3A CN103166138B (en) 2013-02-22 2013-02-22 The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch

Publications (2)

Publication Number Publication Date
CN103166138A CN103166138A (en) 2013-06-19
CN103166138B true CN103166138B (en) 2016-06-01

Family

ID=48588988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310056763.3A Active CN103166138B (en) 2013-02-22 2013-02-22 The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch

Country Status (1)

Country Link
CN (1) CN103166138B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103730852A (en) * 2014-01-03 2014-04-16 国家电网公司 Portable and quick cable load conversion device used during accident
CN110071435B (en) * 2019-04-30 2020-12-15 郑州泰宏电气有限公司 Power distribution cabinet structure
CN112072638B (en) * 2020-07-29 2022-07-08 上海宝冶冶金工程有限公司 High-voltage subsection switching method
CN112332281A (en) * 2020-11-16 2021-02-05 国网江苏省电力有限公司南通供电分公司 Control method for replacing distribution box of low-voltage distribution area without power outage based on mobile energy storage

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2559144Y (en) * 2002-07-18 2003-07-02 吴红兰 Outdoor ball housing type low voltage cable hut
CN2770171Y (en) * 2004-12-15 2006-04-05 沈阳斯沃电器有限公司 Automatic switching dual-power source and bypass cabinet
CN102185260A (en) * 2011-01-26 2011-09-14 河南省电力公司南阳供电公司 A method for replacing a panel or a cubicle in a master control room by using a by-pass wiring method
CN202586124U (en) * 2012-05-30 2012-12-05 广州供电局有限公司 Bypass operation trolley capable of being used to replace distribution transformer without cutting off power
CN202737339U (en) * 2012-06-19 2013-02-13 沈阳电力勘测设计院 Split type medium voltage load switch ring main unit

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04161012A (en) * 1990-10-24 1992-06-04 San'eisha Mfg Co Ltd Method of connecting cable of power distribution line and connecting structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2559144Y (en) * 2002-07-18 2003-07-02 吴红兰 Outdoor ball housing type low voltage cable hut
CN2770171Y (en) * 2004-12-15 2006-04-05 沈阳斯沃电器有限公司 Automatic switching dual-power source and bypass cabinet
CN102185260A (en) * 2011-01-26 2011-09-14 河南省电力公司南阳供电公司 A method for replacing a panel or a cubicle in a master control room by using a by-pass wiring method
CN202586124U (en) * 2012-05-30 2012-12-05 广州供电局有限公司 Bypass operation trolley capable of being used to replace distribution transformer without cutting off power
CN202737339U (en) * 2012-06-19 2013-02-13 沈阳电力勘测设计院 Split type medium voltage load switch ring main unit

Also Published As

Publication number Publication date
CN103166138A (en) 2013-06-19

Similar Documents

Publication Publication Date Title
CN101662132B (en) 110kV/220kV Voltage Class Combined Appliance and Its Application
CN103166138B (en) The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch
CN106451220A (en) Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower
CN103904564B (en) High-voltage distribution device with double breakers used for single bus segmentation and application thereof
CN203674797U (en) Station power microgrid main wiring system
CN204577857U (en) A kind of 110kV transformer station adopting novel wire connecting way
CN111697482A (en) 10KV overhead line non-outage moving and modifying method
CN202940470U (en) Double-bus wiring system
CN103986159B (en) There is the mounting circuit of THE UPFC in multi transformer station
CN203850833U (en) Unified power flow controller installation circuit in transformer station with multiple lines
CN208078653U (en) Double-bus and single busbar mixing wiring high voltage distribution installation
CN201937196U (en) Mobile cabinet type transformer vehicle for high-voltage load transfer
CN201946983U (en) Series compensating system adopting gantry framework
CN103855625A (en) Movable branch box
CN202583830U (en) Feasibility test system for replacement of converter transformer sleeve
CN211089136U (en) 6kV house service power interconnection device
CN108233537A (en) A kind of micro-capacitance sensor electric energy quality monitoring system, method
CN203859518U (en) Wiring structure for medium-voltage distribution network
CN207098399U (en) AC load switching device in transformer station
CN202094512U (en) Mechanism enabling medium pressure side of main transformer to be uninterruptible in overhaul
CN201994614U (en) Conducting-wire expander
CN202190115U (en) Dual-supply automatic switching apparatus of electric power load management terminal
CN203951058U (en) A kind of removable feeder pillar
CN204046192U (en) For the 110 kv substation micro-grid systems in large-scale electricity consumption place
CN204333626U (en) Two-way incoming line single-meter metering input and withdrawal mutual backup device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant