CN103166138B - The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch - Google Patents
The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch Download PDFInfo
- Publication number
- CN103166138B CN103166138B CN201310056763.3A CN201310056763A CN103166138B CN 103166138 B CN103166138 B CN 103166138B CN 201310056763 A CN201310056763 A CN 201310056763A CN 103166138 B CN103166138 B CN 103166138B
- Authority
- CN
- China
- Prior art keywords
- section
- cable branch
- switchgear
- bypass cable
- power supply
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000009466 transformation Effects 0.000 title claims abstract description 14
- 238000000034 method Methods 0.000 title claims abstract description 9
- 230000011218 segmentation Effects 0.000 title abstract 3
- 230000001131 transforming effect Effects 0.000 claims abstract description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 claims description 6
- 229910052802 copper Inorganic materials 0.000 claims description 6
- 239000010949 copper Substances 0.000 claims description 6
- 230000009977 dual effect Effects 0.000 claims description 4
- 238000010586 diagram Methods 0.000 claims description 3
- 238000009429 electrical wiring Methods 0.000 claims description 3
- 238000007689 inspection Methods 0.000 description 2
- 238000011835 investigation Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 230000032683 aging Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 238000003339 best practice Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000000819 phase cycle Methods 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
Landscapes
- Patch Boards (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种开关柜的改造和更换方法,特别是一种基于旁路电缆分支箱分段改造更换开关柜的方法。The invention relates to a modification and replacement method of a switch cabinet, in particular to a method for segment modification and replacement of a switch cabinet based on a bypass cable branch box.
背景技术Background technique
随着经济的发展,早期建成的10kV开关站、开闭所、配电站投运时间长,开关柜等操作设备型号老旧且老化严重,满足不了负荷日益增长的需求,且故障率高,用户投诉多,急需改造。在对开关站进行整体改造时,需要停电操作,由于改造工期长,造成停电时间长,不但给用户带来极大的不便,还影响了供电的可靠性。With the development of the economy, the 10kV switch stations, switch stations, and distribution stations built in the early stage have been put into operation for a long time, and the operating equipment such as switch cabinets are old and aging, which cannot meet the increasing demand of the load, and the failure rate is high. There are many complaints from users and it is in urgent need of renovation. When the overall transformation of the switch station is carried out, power outage operation is required. Due to the long construction period of the transformation, the power outage time is long, which not only brings great inconvenience to users, but also affects the reliability of power supply.
发明内容Contents of the invention
本发明的目的在于根据现有技术的不足之处而提供一种实现不停电或短时停电改造开关站,缩短用户停电时间,缩短改造工期,提高供电可靠性的基于旁路电缆分支箱分段改造更换开关柜的方法。The purpose of the present invention is to provide a sub-section based on bypass cable branch box to realize non-stop or short-term power outage transformation switch station according to the deficiencies of the prior art, shorten the user power outage time, shorten the transformation period, and improve power supply reliability The method of transforming and replacing the switchgear.
本发明的目的是通过以下途径来实现的:The purpose of the present invention is achieved by the following approach:
基于旁路电缆分支箱分段改造更换开关柜的方法,其要点在于,包括如下依序步骤:The key point of the method for segmentally transforming and replacing the switchgear based on the bypass cable branch box is to include the following steps in sequence:
1、提供一种旁路电缆分支箱,包括箱体和位于箱体下方的槽钢,箱体内安装有三相母线铜排和位于该三相母线铜排上的复数个电缆连接端子;1. A bypass cable branch box is provided, including a box body and a channel steel located below the box body, and a three-phase busbar copper bar and a plurality of cable connection terminals located on the three-phase busbar copper bar are installed in the box body;
2、将上述的旁路电缆分支箱安装到待更换开关柜的现场中,所述待更换开关柜包括有I段母线开关柜和II段母线开关柜;2. Install the above-mentioned bypass cable branch box in the site of the switchgear to be replaced, the switchgear to be replaced includes a section I bus switchgear and a section II bus switchgear;
3、第一阶段短时停电,将I段母线开关柜的进线电源电缆和到单电源用户的出线电缆分别经由箱体下方的槽钢连接到旁路电缆分支箱里的不同电缆连接端子上,I段母线开关柜中到双电源用户的出线电缆停电,双电源用户另行提供进线供电;3. In the first stage of short-term power failure, the incoming power cables of the I-section bus switch cabinet and the outgoing cables to the single power supply users are respectively connected to different cable connection terminals in the bypass cable branch box through the channel steel under the box body , the outgoing cable from the I-section busbar switch cabinet to the dual power supply users is powered off, and the dual power supply users provide incoming power supply separately;
4、拆除I段母线开关柜,并对该柜基础进行改造,并安装上新的I段母线环网柜;4. Remove the I-section busbar switchgear, modify the foundation of the cabinet, and install a new I-section busbar ring network cabinet;
5、第二阶段短时停电,将I段母线开关柜所有进出线电缆按照I段母线环网柜的电气接线图进行搭接安装;5. In the second stage of short-term power failure, all the incoming and outgoing cables of the I-section bus switch cabinet shall be lapped and installed according to the electrical wiring diagram of the I-section bus ring network cabinet;
6、重复步骤3-5更换II段母线开关柜,改造更换结束后,拆除旁路电缆分支箱。6. Repeat steps 3-5 to replace the busbar switchgear of section II. After the transformation and replacement, remove the bypass cable branch box.
这样,本发明借助了旁路电缆分支箱,使开关柜的对应电源线和供电线路能够得到临时置放,并获得间隔的供电时间,大大缩短了用户的停电时间,由于采用了分段改造,使得改造更为有序和简单,能够有效缩短改造工期,且分多次短时停电,在改造基础并更换新母线环网柜时不影响用户供电,方便了用户,具有很好的实用性,也大大提高了供电可靠性。In this way, the present invention uses the bypass cable branch box to temporarily place the corresponding power lines and power supply lines of the switchgear, and obtain interval power supply time, which greatly shortens the user's power outage time. It makes the transformation more orderly and simple, can effectively shorten the transformation period, and divides into multiple short-term power outages, and does not affect the user's power supply when transforming the foundation and replacing the new bus ring network cabinet, which is convenient for users and has good practicability. It also greatly improves the reliability of power supply.
附图说明Description of drawings
图1所示为本发明所述旁路电缆分支箱的结构示意图;Fig. 1 shows the structural representation of bypass cable branch box of the present invention;
下面结合实施例对本发明做进一步描述。The present invention will be further described below in conjunction with the examples.
具体实施例specific embodiment
最佳实施例:Best practice:
以I段母线开关柜为例,基于旁路电缆分支箱分段改造更换开关柜的方法,包括如下依序步骤:Taking the I-section busbar switchgear as an example, the method of segmentally transforming and replacing the switchgear based on the bypass cable branch box includes the following sequential steps:
1、现场勘查待改造10kV开关站是否有足够的空间能够摆放旁路电缆分支箱。1. On-site investigation whether there is enough space for the bypass cable branch box in the 10kV switch station to be transformed.
2、现场勘查10kV进线、馈出电缆是否留有足够裕度能够将电缆回抽搭接至旁路电缆分支箱。2. On-site investigation of 10kV incoming and outgoing cables to see if there is enough margin to draw back the cables and connect them to the bypass cable branch box.
3、提供一种旁路电缆分支箱,包括箱体1和位于箱体下方的槽钢2,箱体1内安装有三相母线铜排3和位于该三相母线铜排上的复数个电缆连接端子4,槽钢2的高度必须保证电缆的弯曲半径。3. Provide a bypass cable branch box, including a box body 1 and a channel steel 2 located below the box body. A three-phase bus bar copper bar 3 and a plurality of cable connections on the three-phase bus bar copper bar are installed in the box body 1. The height of terminal 4 and channel steel 2 must ensure the bending radius of the cable.
4、将上述的旁路电缆分支箱安装到I段母线开关柜的现场中,并开始第一阶段短时停电,将I段母线开关柜的进线电源电缆和到单电源用户的出线电缆分别经由箱体下方的槽钢连接到旁路电缆分支箱里的不同电缆连接端子上,并确认旁路系统与原系统相序一致,I段母线开关柜中到双电源用户的出线电缆停电,双电源用户另行提供进线供电。4. Install the above-mentioned bypass cable branch box in the site of the I-section busbar switchgear, and start the first phase of short-term power failure, and separate the incoming power cables of the I-section busbar switchgear and the outgoing cables to the single power supply users Connect to different cable connection terminals in the bypass cable branch box through the channel steel at the bottom of the box, and confirm that the phase sequence of the bypass system is consistent with that of the original system. The power user shall provide the incoming power supply separately.
5、将进线电源对侧线路由运行转检修,给旁路电缆分支箱供电,将馈线对侧线路由运行转检修,使旁路系统投入运行,恢复对侧用户用电。5. Transfer the line on the opposite side of the incoming power supply from operation to inspection and maintenance, supply power to the branch box of the bypass cable, and transfer the line on the opposite side of the feeder from operation to inspection and maintenance, put the bypass system into operation, and restore the power consumption of the opposite side users.
6、拆除I段母线开关柜,并对该柜基础进行改造,并安装上新的I段母线环网柜。6. Remove the I-section busbar switchgear, modify the foundation of the cabinet, and install a new I-section busbar ring network cabinet.
7、第二阶段短时停电,将I段母线开关柜所有进出线电缆按照I段母线环网柜的电气接线图进行搭接安装。7. In the second stage of short-term power failure, all the incoming and outgoing cables of the I-section bus switch cabinet shall be lapped and installed according to the electrical wiring diagram of the I-section bus ring network cabinet.
本发明未述部分与现有技术相同。The parts not described in the present invention are the same as the prior art.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310056763.3A CN103166138B (en) | 2013-02-22 | 2013-02-22 | The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310056763.3A CN103166138B (en) | 2013-02-22 | 2013-02-22 | The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103166138A CN103166138A (en) | 2013-06-19 |
CN103166138B true CN103166138B (en) | 2016-06-01 |
Family
ID=48588988
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310056763.3A Active CN103166138B (en) | 2013-02-22 | 2013-02-22 | The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103166138B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103730852A (en) * | 2014-01-03 | 2014-04-16 | 国家电网公司 | Portable and quick cable load conversion device used during accident |
CN110071435B (en) * | 2019-04-30 | 2020-12-15 | 郑州泰宏电气有限公司 | Power distribution cabinet structure |
CN112072638B (en) * | 2020-07-29 | 2022-07-08 | 上海宝冶冶金工程有限公司 | High-voltage subsection switching method |
CN112332281A (en) * | 2020-11-16 | 2021-02-05 | 国网江苏省电力有限公司南通供电分公司 | Control method for replacing distribution box of low-voltage distribution area without power outage based on mobile energy storage |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2559144Y (en) * | 2002-07-18 | 2003-07-02 | 吴红兰 | Outdoor ball housing type low voltage cable hut |
CN2770171Y (en) * | 2004-12-15 | 2006-04-05 | 沈阳斯沃电器有限公司 | Automatic switching dual-power source and bypass cabinet |
CN102185260A (en) * | 2011-01-26 | 2011-09-14 | 河南省电力公司南阳供电公司 | A method for replacing a panel or a cubicle in a master control room by using a by-pass wiring method |
CN202586124U (en) * | 2012-05-30 | 2012-12-05 | 广州供电局有限公司 | Bypass operation trolley capable of being used to replace distribution transformer without cutting off power |
CN202737339U (en) * | 2012-06-19 | 2013-02-13 | 沈阳电力勘测设计院 | Split type medium voltage load switch ring main unit |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04161012A (en) * | 1990-10-24 | 1992-06-04 | San'eisha Mfg Co Ltd | Method of connecting cable of power distribution line and connecting structure |
-
2013
- 2013-02-22 CN CN201310056763.3A patent/CN103166138B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2559144Y (en) * | 2002-07-18 | 2003-07-02 | 吴红兰 | Outdoor ball housing type low voltage cable hut |
CN2770171Y (en) * | 2004-12-15 | 2006-04-05 | 沈阳斯沃电器有限公司 | Automatic switching dual-power source and bypass cabinet |
CN102185260A (en) * | 2011-01-26 | 2011-09-14 | 河南省电力公司南阳供电公司 | A method for replacing a panel or a cubicle in a master control room by using a by-pass wiring method |
CN202586124U (en) * | 2012-05-30 | 2012-12-05 | 广州供电局有限公司 | Bypass operation trolley capable of being used to replace distribution transformer without cutting off power |
CN202737339U (en) * | 2012-06-19 | 2013-02-13 | 沈阳电力勘测设计院 | Split type medium voltage load switch ring main unit |
Also Published As
Publication number | Publication date |
---|---|
CN103166138A (en) | 2013-06-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101662132B (en) | 110kV/220kV Voltage Class Combined Appliance and Its Application | |
CN103166138B (en) | The method of switching cabinet is changed based on the case segmentation transformation of bypass cable branch | |
CN106451220A (en) | Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower | |
CN103904564B (en) | High-voltage distribution device with double breakers used for single bus segmentation and application thereof | |
CN203674797U (en) | Station power microgrid main wiring system | |
CN204577857U (en) | A kind of 110kV transformer station adopting novel wire connecting way | |
CN111697482A (en) | 10KV overhead line non-outage moving and modifying method | |
CN202940470U (en) | Double-bus wiring system | |
CN103986159B (en) | There is the mounting circuit of THE UPFC in multi transformer station | |
CN203850833U (en) | Unified power flow controller installation circuit in transformer station with multiple lines | |
CN208078653U (en) | Double-bus and single busbar mixing wiring high voltage distribution installation | |
CN201937196U (en) | Mobile cabinet type transformer vehicle for high-voltage load transfer | |
CN201946983U (en) | Series compensating system adopting gantry framework | |
CN103855625A (en) | Movable branch box | |
CN202583830U (en) | Feasibility test system for replacement of converter transformer sleeve | |
CN211089136U (en) | 6kV house service power interconnection device | |
CN108233537A (en) | A kind of micro-capacitance sensor electric energy quality monitoring system, method | |
CN203859518U (en) | Wiring structure for medium-voltage distribution network | |
CN207098399U (en) | AC load switching device in transformer station | |
CN202094512U (en) | Mechanism enabling medium pressure side of main transformer to be uninterruptible in overhaul | |
CN201994614U (en) | Conducting-wire expander | |
CN202190115U (en) | Dual-supply automatic switching apparatus of electric power load management terminal | |
CN203951058U (en) | A kind of removable feeder pillar | |
CN204046192U (en) | For the 110 kv substation micro-grid systems in large-scale electricity consumption place | |
CN204333626U (en) | Two-way incoming line single-meter metering input and withdrawal mutual backup device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |