CN103161350A - Large span heavy steel structure mast hoisting construction method - Google Patents

Large span heavy steel structure mast hoisting construction method Download PDF

Info

Publication number
CN103161350A
CN103161350A CN2013100875776A CN201310087577A CN103161350A CN 103161350 A CN103161350 A CN 103161350A CN 2013100875776 A CN2013100875776 A CN 2013100875776A CN 201310087577 A CN201310087577 A CN 201310087577A CN 103161350 A CN103161350 A CN 103161350A
Authority
CN
China
Prior art keywords
mast
steel
lifting
truss
adopts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100875776A
Other languages
Chinese (zh)
Inventor
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2013100875776A priority Critical patent/CN103161350A/en
Publication of CN103161350A publication Critical patent/CN103161350A/en
Pending legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The invention discloses a large span heavy steel structure mast hoisting construction method which comprises the steps of transporting a steel column horizontally in a field, assembling the steel column in a hanging mode through a mast, splicing a steel truss in-field, assembling the steel truss in the hanging mode through the mast and the like. The large span heavy steel structure mast hoisting construction method enables construction to be convenient and is safe, good in effect and high in efficiency.

Description

Long-span heavy type steel work mast construction method for hanging
Technical field
The present invention relates to a kind of long-span heavy type steel work mast construction method for hanging.
Background technology
Existing long-span heavy type steel work mast lifting construction, method is complicated, has defective at aspects such as efficiency of construction, safety, construction effects, needs further to improve.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, safe, effective long-span heavy type steel work mast lifting construction.
Technical solution of the present invention is:
A kind of long-span heavy type steel work mast construction method for hanging is characterized in that: comprise the following steps:
(1) steel column is installed
(1) horizontal transport in the steel column field
The steel column member unload at the scene after below member the cushioning sleeper, be convenient to arrange raft-towing and cylinder; Cylinder rolls on the transmission moulding bed beam of H shaped steel, and the fulcrum of H shaped steel adds plank or sleeper between girder steel and concrete layer on the concrete beam;
Member adopts when carrying out horizontal drag fortune on transmitting moulding bed and moves at a slow speed, and speed is no more than 6m per minute; Between member and raft-towing, pad is set level whole;
(2) mast lifting steel column
Adopt gantry gin pole lifting of the two group of high 30m, portal frame center to center distance 5.5m, mast cross section 1.0m * 1.0m, main zeugopodium 4-∠ 90 * 90 * 6mm, web member ∠ 63 * 63 * 6mm, pitch 1.0m*30; Hoisting sheave adopts H32-5D * 2 group, and it is 6 * 37+1 Ф 19.5mm that hoist rope adopts specification, length 300m * 2 piece; The starting hoist engine adopts the electronic hoist engine of 5t at a slow speed, and lifting velocity 4m/ divides; The guy wire rope is no less than 6, and specification is 6*37+1 Ф 19.5mm, length 60m/ root; Before steel column lifting, with Current Collector Sleave, operating platform, cat ladder, slip rope and catching device and be fixed on steel column, the otic placode that welds with the steel column upper end lifts by crane;
The installation of mast adopts 50t vapour to lift up into the row lifting, the long 42m of the arm that 50t vapour hangs, and the height of mast is 30m, and deadweight 4.5t, operating radius is 6~8m; Mast tightens up cable wind rope after erectting, after the mast cable wind rope tightens up, and the wire rope that loose unloading is hung;
Erect 30m gantry mast according to layout plan, simultaneously the central axis of the axial alignment steel column of foot of the mast; The steel plate of foot of the mast can not directly contact with concrete, cushioning plank or sleeper; Lower floor at foot of the mast arranges the reinforcing support column, to guarantee safety; Two groups of pulley jibs are decorateeed and are arranged the balance hanging beam, keep the stress equalization of assembly pulley;
During mast lifting steel column during the lifting of loop wheel machine or mast the bottom of the steel column coaster of should taking to roll mobile with lifting, avoid causing gravity to concentrate and destroy the concrete internal construction; When loop wheel machine or mast lifting, the speed that the bottom of steel column takes the steel column of pulling force control in the other direction to move; Adopt the vapour crane operation when removing portal frame and erectting portal frame, guarantee safe production; When vapour was hung on aspect construction operation, its feet was supported on the concrete beam, and wanted cushioning soil plate or sleeper;
(2) steel truss is installed
(1) steel truss on-site consolidation
Steel truss adopts factory's rod member blanking, processes rear loose mail and is transported to the scene, and interim assembly unit scaffold is set up at the scene, carries out at the scene the truss assembly unit, and then whole Pin carries out lifting construction one time;
No. 18 i iron of assembly unit moulding bed employing and 10# channel-section steel are made, and the assembly unit frame is measured with elevation control with level gauge; Node location is avoided in the moulding bed setting, satisfies welder's welding space;
The truss assembling process is as follows:
Figure 2013100875776100002DEST_PATH_IMAGE002
Assembly unit moulding bed platform is arranged: assembly platform detects and adjusts level, and the moulding bed height is 0.8 meter, and each facing cut is flat, ejects the member projection line on assembly platform;
Figure 2013100875776100002DEST_PATH_IMAGE004
Middle chord member location: make the qualified chord member of detection and hang on moulding bed, decide line of face,mounting location over the ground;
Figure 2013100875776100002DEST_PATH_IMAGE006
Chord member location, both sides: make chord member and hang on moulding bed, fixed line of face,mounting is over the ground located;
Figure 2013100875776100002DEST_PATH_IMAGE008
The straight web member of truss location: make straight web member and hang on moulding bed, fixed line of face,mounting is over the ground located, and tacking adopts hand welding, the welding simultaneously of symmetrical weld seam;
Figure 2013100875776100002DEST_PATH_IMAGE010
Truss diagonal web member location: make diagonal web member and hang on moulding bed, fixed line of face,mounting is over the ground located, and tacking adopts hand welding, and the welding simultaneously of symmetrical weld seam;
Figure 2013100875776100002DEST_PATH_IMAGE012
Detect: the whole detection after truss assembling, whether the locus at each control point of the full brill of utilization instrument measurement truss meets pre-assembly unit requirement, checks ground sample benchmark, and checks each mating interface spacing requirement, the truss diagonal is poor should greater than 8mm, not implemented to correct to overproof position, part;
(2) mast lifting steel truss
Hoisting sheave adopts H20-4D * 4 group, 2 groups, every mast, and it is 6 * 37+1 Ф 19.5mm that hoist rope adopts specification, length 300m * 4 piece; The starting hoist engine adopts the electronic hoist engine of 5t at a slow speed, and lifting velocity 4m/ divides; Every mast of guy wire rope is no less than 6, and specification is 6 * 37+1 Ф 19.5mm, length 60m/ root.
Easy construction of the present invention, safe, effective, efficient is high.
The invention will be further described below in conjunction with embodiment.
The specific embodiment
A kind of long-span heavy type steel work mast construction method for hanging comprises the following steps:
(1) steel column is installed
(1) horizontal transport in the steel column field
The steel column member unload at the scene after below member the cushioning sleeper, be convenient to arrange raft-towing and cylinder; Cylinder rolls on the transmission moulding bed beam of H shaped steel, and the fulcrum of H shaped steel adds plank or sleeper between girder steel and concrete layer on the concrete beam;
Member adopts when carrying out horizontal drag fortune on transmitting moulding bed and moves at a slow speed, and speed is no more than 6m per minute; Between member and raft-towing, pad is set level whole;
(2) mast lifting steel column
Adopt gantry gin pole lifting of the two group of high 30m, portal frame center to center distance 5.5m, mast cross section 1.0m * 1.0m, main zeugopodium 4-∠ 90 * 90 * 6mm, web member ∠ 63 * 63 * 6mm, pitch 1.0m*30; Hoisting sheave adopts H32-5D * 2 group, and it is 6 * 37+1 Ф 19.5mm that hoist rope adopts specification, length 300m * 2 piece; The starting hoist engine adopts the electronic hoist engine of 5t at a slow speed, and lifting velocity 4m/ divides; The guy wire rope is no less than 6, and specification is 6*37+1 Ф 19.5mm, length 60m/ root; Before steel column lifting, with Current Collector Sleave, operating platform, cat ladder, slip rope and catching device and be fixed on steel column, the otic placode that welds with the steel column upper end lifts by crane;
The installation of mast adopts 50t vapour to lift up into the row lifting, the long 42m of the arm that 50t vapour hangs, and the height of mast is 30m, and deadweight 4.5t, operating radius is 6~8m; Mast tightens up cable wind rope after erectting, after the mast cable wind rope tightens up, and the wire rope that loose unloading is hung;
Erect 30m gantry mast according to layout plan, simultaneously the central axis of the axial alignment steel column of foot of the mast; The steel plate of foot of the mast can not directly contact with concrete, cushioning plank or sleeper; Lower floor at foot of the mast arranges the reinforcing support column, to guarantee safety; Two groups of pulley jibs are decorateeed and are arranged the balance hanging beam, keep the stress equalization of assembly pulley;
During mast lifting steel column during the lifting of loop wheel machine or mast the bottom of the steel column coaster of should taking to roll mobile with lifting, avoid causing gravity to concentrate and destroy the concrete internal construction; When loop wheel machine or mast lifting, the speed that the bottom of steel column takes the steel column of pulling force control in the other direction to move; Adopt the vapour crane operation when removing portal frame and erectting portal frame, guarantee safe production; When vapour was hung on aspect construction operation, its feet was supported on the concrete beam, and wanted cushioning soil plate or sleeper;
(2) steel truss is installed
(1) steel truss on-site consolidation
Steel truss adopts factory's rod member blanking, processes rear loose mail and is transported to the scene, and interim assembly unit scaffold is set up at the scene, carries out at the scene the truss assembly unit, and then whole Pin carries out lifting construction one time;
No. 18 i iron of assembly unit moulding bed employing and 10# channel-section steel are made, and the assembly unit frame is measured with elevation control with level gauge; Node location is avoided in the moulding bed setting, satisfies welder's welding space;
The truss assembling process is as follows:
Figure 361630DEST_PATH_IMAGE002
Assembly unit moulding bed platform is arranged: assembly platform detects and adjusts level, and the moulding bed height is 0.8 meter, and each facing cut is flat, ejects the member projection line on assembly platform; Middle chord member location: make the qualified chord member of detection and hang on moulding bed, decide line of face,mounting location over the ground;
Figure 120824DEST_PATH_IMAGE006
Chord member location, both sides: make chord member and hang on moulding bed, fixed line of face,mounting is over the ground located;
Figure 575421DEST_PATH_IMAGE008
The straight web member of truss location: make straight web member and hang on moulding bed, fixed line of face,mounting is over the ground located, and tacking adopts hand welding, the welding simultaneously of symmetrical weld seam;
Figure 452110DEST_PATH_IMAGE010
Truss diagonal web member location: make diagonal web member and hang on moulding bed, fixed line of face,mounting is over the ground located, and tacking adopts hand welding, and the welding simultaneously of symmetrical weld seam;
Figure 274572DEST_PATH_IMAGE012
Detect: the whole detection after truss assembling, whether the locus at each control point of the full brill of utilization instrument measurement truss meets pre-assembly unit requirement, checks ground sample benchmark, and checks each mating interface spacing requirement, the truss diagonal is poor should greater than 8mm, not implemented to correct to overproof position, part;
(2) mast lifting steel truss
Hoisting sheave adopts H20-4D * 4 group, 2 groups, every mast, and it is 6 * 37+1 Ф 19.5mm that hoist rope adopts specification, length 300m * 4 piece; The starting hoist engine adopts the electronic hoist engine of 5t at a slow speed, and lifting velocity 4m/ divides; Every mast of guy wire rope is no less than 6, and specification is 6 * 37+1 Ф 19.5mm, length 60m/ root.

Claims (1)

1. a long-span heavy type steel work mast construction method for hanging, is characterized in that: comprise the following steps:
(1) steel column is installed
(1) horizontal transport in the steel column field
The steel column member unload at the scene after below member the cushioning sleeper, be convenient to arrange raft-towing and cylinder; Cylinder rolls on the transmission moulding bed beam of H shaped steel, and the fulcrum of H shaped steel adds plank or sleeper between girder steel and concrete layer on the concrete beam;
Member adopts when carrying out horizontal drag fortune on transmitting moulding bed and moves at a slow speed, and speed is no more than 6m per minute; Between member and raft-towing, pad is set level whole;
(2) mast lifting steel column
Adopt gantry gin pole lifting of the two group of high 30m, portal frame center to center distance 5.5m, mast cross section 1.0m * 1.0m, main zeugopodium 4-∠ 90 * 90 * 6mm, web member ∠ 63 * 63 * 6mm, pitch 1.0m*30; Hoisting sheave adopts H32-5D * 2 group, and it is 6 * 37+1 Ф 19.5mm that hoist rope adopts specification, length 300m * 2 piece; The starting hoist engine adopts the electronic hoist engine of 5t at a slow speed, and lifting velocity 4m/ divides; The guy wire rope is no less than 6, and specification is 6*37+1 Ф 19.5mm, length 60m/ root; Before steel column lifting, with Current Collector Sleave, operating platform, cat ladder, slip rope and catching device and be fixed on steel column, the otic placode that welds with the steel column upper end lifts by crane;
The installation of mast adopts 50t vapour to lift up into the row lifting, the long 42m of the arm that 50t vapour hangs, and the height of mast is 30m, and deadweight 4.5t, operating radius is 6~8m; Mast tightens up cable wind rope after erectting, after the mast cable wind rope tightens up, and the wire rope that loose unloading is hung;
Erect 30m gantry mast according to layout plan, simultaneously the central axis of the axial alignment steel column of foot of the mast; The steel plate of foot of the mast can not directly contact with concrete, cushioning plank or sleeper; Lower floor at foot of the mast arranges the reinforcing support column, to guarantee safety; Two groups of pulley jibs are decorateeed and are arranged the balance hanging beam, keep the stress equalization of assembly pulley;
During mast lifting steel column during the lifting of loop wheel machine or mast the bottom of the steel column coaster of should taking to roll mobile with lifting, avoid causing gravity to concentrate and destroy the concrete internal construction; When loop wheel machine or mast lifting, the speed that the bottom of steel column takes the steel column of pulling force control in the other direction to move; Adopt the vapour crane operation when removing portal frame and erectting portal frame, guarantee safe production; When vapour was hung on aspect construction operation, its feet was supported on the concrete beam, and wanted cushioning soil plate or sleeper;
(2) steel truss is installed
(1) steel truss on-site consolidation
Steel truss adopts factory's rod member blanking, processes rear loose mail and is transported to the scene, and interim assembly unit scaffold is set up at the scene, carries out at the scene the truss assembly unit, and then whole Pin carries out lifting construction one time;
No. 18 i iron of assembly unit moulding bed employing and 10# channel-section steel are made, and the assembly unit frame is measured with elevation control with level gauge; Node location is avoided in the moulding bed setting, satisfies welder's welding space;
The truss assembling process is as follows:
Figure 2013100875776100001DEST_PATH_IMAGE002
Assembly unit moulding bed platform is arranged: assembly platform detects and adjusts level, and the moulding bed height is 0.8 meter, and each facing cut is flat, ejects the member projection line on assembly platform;
Figure 2013100875776100001DEST_PATH_IMAGE004
Middle chord member location: make the qualified chord member of detection and hang on moulding bed, decide line of face,mounting location over the ground;
Figure 2013100875776100001DEST_PATH_IMAGE006
Chord member location, both sides: make chord member and hang on moulding bed, fixed line of face,mounting is over the ground located;
Figure 2013100875776100001DEST_PATH_IMAGE008
The straight web member of truss location: make straight web member and hang on moulding bed, fixed line of face,mounting is over the ground located, and tacking adopts hand welding, the welding simultaneously of symmetrical weld seam; Truss diagonal web member location: make diagonal web member and hang on moulding bed, fixed line of face,mounting is over the ground located, and tacking adopts hand welding, and the welding simultaneously of symmetrical weld seam;
Figure 2013100875776100001DEST_PATH_IMAGE012
Detect: the whole detection after truss assembling, whether the locus at each control point of the full brill of utilization instrument measurement truss meets pre-assembly unit requirement, checks ground sample benchmark, and checks each mating interface spacing requirement, the truss diagonal is poor should greater than 8mm, not implemented to correct to overproof position, part;
(2) mast lifting steel truss
Hoisting sheave adopts H20-4D * 4 group, 2 groups, every mast, and it is 6 * 37+1 Ф 19.5mm that hoist rope adopts specification, length 300m * 4 piece; The starting hoist engine adopts the electronic hoist engine of 5t at a slow speed, and lifting velocity 4m/ divides; Every mast of guy wire rope is no less than 6, and specification is 6 * 37+1 Ф 19.5mm, length 60m/ root.
CN2013100875776A 2013-03-19 2013-03-19 Large span heavy steel structure mast hoisting construction method Pending CN103161350A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100875776A CN103161350A (en) 2013-03-19 2013-03-19 Large span heavy steel structure mast hoisting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100875776A CN103161350A (en) 2013-03-19 2013-03-19 Large span heavy steel structure mast hoisting construction method

Publications (1)

Publication Number Publication Date
CN103161350A true CN103161350A (en) 2013-06-19

Family

ID=48584853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100875776A Pending CN103161350A (en) 2013-03-19 2013-03-19 Large span heavy steel structure mast hoisting construction method

Country Status (1)

Country Link
CN (1) CN103161350A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104818856A (en) * 2015-04-21 2015-08-05 中国十七冶集团有限公司 Mounting method of roof thin-wall Z-shaped purline
CN104963521A (en) * 2015-07-28 2015-10-07 中铁大桥局集团有限公司 System and construction method used for integral hoisting and rotation of steel tower
CN107090982A (en) * 2017-04-28 2017-08-25 中国二十冶集团有限公司 A kind of ultra-high ultra-large moves the installation method of wheel-track type steel construction
CN107386663A (en) * 2017-09-13 2017-11-24 北京军秀咨询有限公司 A kind of steel construction high level construction method for hanging
CN107717346A (en) * 2017-09-29 2018-02-23 南通振华重型装备制造有限公司 A kind of 1600T masts hang on mast building technology
CN111302228A (en) * 2020-04-25 2020-06-19 中国有色金属工业第六冶金建设有限公司 Hoisting method for hoisting large barrel by multiple masts based on wind condition

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李光等: "重型钢结构桅杆法吊装施工技术", 《建筑施工》 *
王金锋等: "《第十九届华东六省一市建筑施工技术交流会论文集》", 1 November 2011 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104818856A (en) * 2015-04-21 2015-08-05 中国十七冶集团有限公司 Mounting method of roof thin-wall Z-shaped purline
CN104818856B (en) * 2015-04-21 2017-01-18 中国十七冶集团有限公司 Mounting method of roof thin-wall Z-shaped purline
CN104963521A (en) * 2015-07-28 2015-10-07 中铁大桥局集团有限公司 System and construction method used for integral hoisting and rotation of steel tower
CN104963521B (en) * 2015-07-28 2017-11-17 中铁大桥局集团有限公司 A kind of system and construction method for head tower integral hoisting rotation
CN107090982A (en) * 2017-04-28 2017-08-25 中国二十冶集团有限公司 A kind of ultra-high ultra-large moves the installation method of wheel-track type steel construction
CN107386663A (en) * 2017-09-13 2017-11-24 北京军秀咨询有限公司 A kind of steel construction high level construction method for hanging
CN107717346A (en) * 2017-09-29 2018-02-23 南通振华重型装备制造有限公司 A kind of 1600T masts hang on mast building technology
CN111302228A (en) * 2020-04-25 2020-06-19 中国有色金属工业第六冶金建设有限公司 Hoisting method for hoisting large barrel by multiple masts based on wind condition

Similar Documents

Publication Publication Date Title
CN103161350A (en) Large span heavy steel structure mast hoisting construction method
CN103848360B (en) A kind of group tower tower crane being provided with packaged type balance weight system
CN101284628B (en) Hoisting method for framework of large tonnage pressing machine
CN203053686U (en) Hanging basket safety lock detecting bench
CN109081247A (en) A kind of hanging method of vestibule large-span steel girder
CN104989111B (en) Steel construction high level construction method for hanging
CN100417586C (en) Integral lifting method of large bridge crane and its appts
CN101927956B (en) Anti-sway jacklift
CN105781210B (en) A kind of conical tower and its tool section assist punching construction method for lifting whole
CN203959697U (en) The equalizing bar of hoisting platform truss
CN203654191U (en) Device for stay cable to be lifted on bridge
CN208603617U (en) A kind of handling apparatus of vertical shaft construction of concrete lining material
CN201762053U (en) Simple automatic hoisting rod
CN210915073U (en) Steel wire rope replacing device for large bridge crane
CN204897220U (en) Frame bridge crane's bridge hoisting structure
CN201857225U (en) Hoisting device for bridge crane frame
CN102561201A (en) T-beam installer
CN103072903B (en) Method for mounting high-rise pylon by using self-stable double-rocker elevating device
CN203474321U (en) Tower crane used for constructing and erecting electric transmission line iron towers
CN207312978U (en) A kind of Super High boom-type tower crane hand-held C-type beam and climb band device
CN201660377U (en) Special gantry crane for overlength and large-tonnage parts
CN205346600U (en) Big plate -girder hoist and mount specialized tool
CN213011671U (en) Lightweight simple vertical transportation equipment
CN204825670U (en) Inclined to one side hanging beam frame device is prevented turning round by eccentric case roof beam
CN204873421U (en) Frame bridge crane hoist

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130619