CN103088828A - Construction method for laying underwater geogrids - Google Patents

Construction method for laying underwater geogrids Download PDF

Info

Publication number
CN103088828A
CN103088828A CN2011103397264A CN201110339726A CN103088828A CN 103088828 A CN103088828 A CN 103088828A CN 2011103397264 A CN2011103397264 A CN 2011103397264A CN 201110339726 A CN201110339726 A CN 201110339726A CN 103088828 A CN103088828 A CN 103088828A
Authority
CN
China
Prior art keywords
laying
geo
geotextile
stone
grid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103397264A
Other languages
Chinese (zh)
Inventor
夏宪忠
王刚
林森
张浩栋
李会胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI COMMUNICATIONS CONSTRUCTION GENERAL CONTRACTING Ltd
CCCC Shanghai Dredging Co Ltd.
Original Assignee
SHANGHAI COMMUNICATIONS CONSTRUCTION GENERAL CONTRACTING Ltd
CCCC Shanghai Dredging Co Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI COMMUNICATIONS CONSTRUCTION GENERAL CONTRACTING Ltd, CCCC Shanghai Dredging Co Ltd. filed Critical SHANGHAI COMMUNICATIONS CONSTRUCTION GENERAL CONTRACTING Ltd
Priority to CN2011103397264A priority Critical patent/CN103088828A/en
Publication of CN103088828A publication Critical patent/CN103088828A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Position Fixing By Use Of Radio Waves (AREA)

Abstract

The invention provides a construction method for laying underwater geogrids. By the construction method for laying the underwater geogrids, a phenomenon of floatation can be avoided, and the quality is effectively guaranteed. The technical scheme includes that workboats for implementing the construction method include a geotextile laying vessel and a stone damper, a computer, a GPS (global positioning system) positioning receiver and GPS positioning software are configured on the geotextile laying vessel, the stone damper is a small flat boat and is used for laying and ballasting two stone sheets, and the geotextile laying vessel and the stone damper move to laying positions to carry out laying construction according to the laying positions. The construction method is characterized in that after an entry point of the geotextile laying vessel is positioned, the stone damper with ropes is arranged at the head and the tail of the geotextile laying vessel and is parked on a flip side of the geotextile laying vessel, a geogrid and geotextile are compositely connected with each other on the geotextile laying vessel and descend together to be laid, and the stone damper performs riprap ballast when the geogrid and the geotextile descend and are laid, then moves along with the geotextile laying vessel and performs ballast in a follow-up manner, so that the underwater geogrid is completely laid.

Description

Lay the job practices of geo-grid under water
Technical field
The present invention relates to lay the method for geo-grid under water.
Background technology
Be the low-lying coastal area harbour and coastal engineering ground as of living in harbour, stockyard and road, shore protection, mole and beach coffering, and often be soft foundation, therefore reinforcing soft foundation is the FAQs in harbour and coastal engineering.Geo-grid more and more is applied in the reinforcing soft foundation of these engineerings with its good pull resistance and rigidity.Along with the expansion of works limit, constantly extend to the off-lying sea at present, the depth of water of construction area is more and more darker, and a lot of engineerings are operation at sea.And the limitation of the characteristic large due to the intensity of geo-grid, that rigidity is high and geo-grid specification size, the geo-grid difficulty is large under water for waterborne pavement.Common laying process often causes a large amount of hydro-planings, and construction quality is difficult to guarantee.
Summary of the invention
The purpose of this invention is to provide a kind of hydro-planing of avoiding, the laying of effectively ensuring the quality of products is the geo-grid job practices under water.
the workboat that technical solution of the present invention is used is Working Ships and stone dumper, is furnished with computer on Working Ships, the GPS location receiver, the GPS positioning software, stone dumper is the Small-scale Flat ship, be used for laying ballast two slabstones, according to paving location, Working Ships and stone dumper move to paving location and carry out laying construction, it is characterized in that Working Ships advance a little locate after, stone dumper band cable is at the head and the tail of Working Ships, moor the turnover panel side in Working Ships, geo-grid and geotextiles composite joint on Working Ships, transfer together laying, in geo-grid and geotextiles are transferred process of deployment, stone dumper carries out the jackstone ballast, move ship with Working Ships afterwards, stone dumper follow-up ballast, complete the laying of geo-grid under water.
The present invention is owing to adopting geo-grid and geotextiles compound, disposablely completes laying, can strengthen the globality of geo-grid, effectively avoids hydro-planing; Speed of application is quick, effectively reduces construction cost.Have and improve the efficient of geo-grid laying under water, effectively guaranteed the remarkable result of laying quality.
Description of drawings
Fig. 1 is the schematic diagram that Working Ships and stone dumper carry out laying construction.
Fig. 2 represents to lay the flow chart of geo-grid job practices under water.
The specific embodiment
The construction ship that the present invention's (referring to accompanying drawing) adopts is Working Ships 1 and stone dumper 2.Are furnished with two of computer one cover, GPS location receivers on Working Ships, GPS positioning software one cover.Open computer before construction, operation GPS positioning software, lay parameter relevant to the design conditions input, computer namely shows construction ship dynamic accommodation figure, paving location according to the GPS positioning software shows moves to paving location 4 with workboat, when Computer display deviate and shift value reach in the allowable error scope, the expression workboat has arrived design attitude, can carry out laying construction.Stone dumper adopts the Small-scale Flat ship to lay two slabstones that ballast is used.Working Ships advance a little locate after, Combined roll is on cylinder on the Working Ships deck at first will to splice good geo-grid and woven geotextile, this geo-grid adopts the high-strength geo-grid of 200KN/m simple tension, this woven geotextile adopts 230g/m 2Woven geotextile.Stone dumper band cable is moored the turnover panel side in Working Ships at the head and the tail of Working Ships, and during construction, stone dumper is connected with Working Ships head and the tail two root system cavils by two hawsers of head and the tail.During construction, geo-grid and woven geotextile are transferred laying together, after the file leader of geo-grid and woven geotextile transfers, stone dumper utilizes excavator to shed two slabstone ballast underwater drainage bodies 3, drive stone dumper when Working Ships moves ship and move ship and carry out the jackstone ballast, until whole isostere laying construction is complete.The present invention synchronously carries out the jackstone ballast in the laying construction process of transferring geo-grid and woven geotextile isostere, both satisfied designing requirement, has guaranteed again construction quality and progress.

Claims (2)

1. lay the job practices of geo-grid under water, the workboat that uses is Working Ships and stone dumper, is furnished with computer on Working Ships, the GPS location receiver, the GPS positioning software, stone dumper is the Small-scale Flat ship, be used for laying ballast two slabstones, according to paving location, Working Ships and stone dumper move to paving location and carry out laying construction, it is characterized in that Working Ships advance a little locate after, stone dumper band cable is at the head and the tail of Working Ships, moor the turnover panel side in Working Ships, geo-grid and geotextiles composite joint on Working Ships, transfer together laying, in geo-grid and geotextiles are transferred process of deployment, stone dumper carries out the jackstone ballast, move ship with Working Ships afterwards, stone dumper follow-up ballast, complete the laying of geo-grid under water.
2. the laying according to claim 1 job practices of geo-grid under water, is characterized in that geo-grid adopts the high-strength geo-grid of 200KN/m simple tension, and woven geotextile adopts 230g/m 2Woven geotextile.
CN2011103397264A 2011-11-01 2011-11-01 Construction method for laying underwater geogrids Pending CN103088828A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103397264A CN103088828A (en) 2011-11-01 2011-11-01 Construction method for laying underwater geogrids

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103397264A CN103088828A (en) 2011-11-01 2011-11-01 Construction method for laying underwater geogrids

Publications (1)

Publication Number Publication Date
CN103088828A true CN103088828A (en) 2013-05-08

Family

ID=48201919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103397264A Pending CN103088828A (en) 2011-11-01 2011-11-01 Construction method for laying underwater geogrids

Country Status (1)

Country Link
CN (1) CN103088828A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103744084A (en) * 2014-01-17 2014-04-23 武汉长江航道救助打捞局 Real-time monitoring and detecting method for underwater paving quality
CN110670540A (en) * 2019-10-09 2020-01-10 湖北省港路勘测设计咨询有限公司 Construction method for tying ballast soft row and protecting bottom

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3922865A (en) * 1972-10-06 1975-12-02 Aannemers Comb Zinkwerke Mattress, method of sinking a mattress and vessel suitable for use in said method
CN1442342A (en) * 2002-03-06 2003-09-17 中港第三航务工程局 Under water flexible raft laying engineering ship and under water flexible raft laying technology
CN101289860A (en) * 2008-04-10 2008-10-22 中交三航局第二工程有限公司 Underwater slope protection construction method for foundation ditch in water
CN101565934A (en) * 2008-04-24 2009-10-28 中国神华能源股份有限公司 Method for laying geotextile underwater
CN201785741U (en) * 2010-07-13 2011-04-06 红阳建设集团有限公司 Underwater geotextile laying equipment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3922865A (en) * 1972-10-06 1975-12-02 Aannemers Comb Zinkwerke Mattress, method of sinking a mattress and vessel suitable for use in said method
CN1442342A (en) * 2002-03-06 2003-09-17 中港第三航务工程局 Under water flexible raft laying engineering ship and under water flexible raft laying technology
CN101289860A (en) * 2008-04-10 2008-10-22 中交三航局第二工程有限公司 Underwater slope protection construction method for foundation ditch in water
CN101565934A (en) * 2008-04-24 2009-10-28 中国神华能源股份有限公司 Method for laying geotextile underwater
CN201785741U (en) * 2010-07-13 2011-04-06 红阳建设集团有限公司 Underwater geotextile laying equipment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103744084A (en) * 2014-01-17 2014-04-23 武汉长江航道救助打捞局 Real-time monitoring and detecting method for underwater paving quality
CN103744084B (en) * 2014-01-17 2016-06-08 武汉长江航道救助打捞局 One arranges Real-time quality monitoring detection method under water
CN110670540A (en) * 2019-10-09 2020-01-10 湖北省港路勘测设计咨询有限公司 Construction method for tying ballast soft row and protecting bottom

Similar Documents

Publication Publication Date Title
CN102277853B (en) Novel quick and reliable underwater arrangement technology
CN100516384C (en) Underwater vacuum prepressing reinforcement soft base technique method
CN109506044A (en) A kind of pipeline under the ocean construction technology
CN101597896B (en) Method for building riprap levee island wall of offshore artificial island by large box barge
CN213508514U (en) Offshore operation platform for bagged sand construction
CN108930251A (en) A kind of harbour submerged breakwater structure and its construction method
CN109113020A (en) A kind of harbour mole structure and its construction method
CN101581086A (en) Positioning riprapping method for constructing island breakwater of artificial island
CN109137943B (en) Earth filling construction process for sea reclamation
CN1442342A (en) Under water flexible raft laying engineering ship and under water flexible raft laying technology
CN102561379A (en) Novel bridge installation foundation and construction method thereof
CN104975612B (en) Open caisson construction new technology waterborne
CN103806407A (en) Pile-bucket integrated wharf structure and construction method thereof
CN204112298U (en) Combined type artificial island, Diarrhea lake region
CN103485308B (en) Underwater geotextile fabric laying method
CN202969343U (en) Diffusion device in discharging thick seawater into sea
CN107326909A (en) A kind of flat board is refuted to drawing jackstone construction method
CN103088828A (en) Construction method for laying underwater geogrids
Smith Types of marine concrete structures
CN106088155A (en) Box hat immersed tube tunnel tube coupling prefabricated transportation by driving fitting-out technique
CN106704705B (en) overwater pipeline assembling operation method and system
CN104612128A (en) Vacuum preloading reinforcement construction method applicable to underwater silt environment
CN104878792A (en) Rigid frame-type geotextile covering silt prevention system and method of immersed tunnel foundation bed
Sadeghi et al. Concrete caisson breakwaters: An overview on design and construction
CN209798675U (en) Caisson and tubular pile combined type permeable mooring pier

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130508