CN103084574A - Preparation method of diamond bits and sintering device thereof - Google Patents

Preparation method of diamond bits and sintering device thereof Download PDF

Info

Publication number
CN103084574A
CN103084574A CN2013100554671A CN201310055467A CN103084574A CN 103084574 A CN103084574 A CN 103084574A CN 2013100554671 A CN2013100554671 A CN 2013100554671A CN 201310055467 A CN201310055467 A CN 201310055467A CN 103084574 A CN103084574 A CN 103084574A
Authority
CN
China
Prior art keywords
minutes
pressure
sintering
temperature
preparation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100554671A
Other languages
Chinese (zh)
Other versions
CN103084574B (en
Inventor
刘青
胡郁乐
段隆臣
吴来杰
张建斌
陈家富
刘全心
吴水平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI CHANGJIANG-JINGGONG MATERIALS TECHNOLOGY Co Ltd
Original Assignee
HUBEI CHANGJIANG-JINGGONG MATERIALS TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUBEI CHANGJIANG-JINGGONG MATERIALS TECHNOLOGY Co Ltd filed Critical HUBEI CHANGJIANG-JINGGONG MATERIALS TECHNOLOGY Co Ltd
Priority to CN201310055467.1A priority Critical patent/CN103084574B/en
Publication of CN103084574A publication Critical patent/CN103084574A/en
Application granted granted Critical
Publication of CN103084574B publication Critical patent/CN103084574B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Powder Metallurgy (AREA)

Abstract

The invention discloses a preparation method and a sintering device of diamond bits. The preparation method comprises batching and filling die, hot pressed sintering, heat preservation and receding die, and sequential processing procedures, wherein the hot pressed sintering procedure uses changeable medium frequency sintering, two-way vibration pressure and two-track temperature and pressure curve control. The sintering device is composed of a hot press, a medium frequency power supply and a control system, the control system detects sintering temperature in real time through an infrared thermometer, and adjusts electric current and working efficiency of the medium frequency power supply through a controller, and meanwhile detects hydro-cylinder pressure in real time through a pressure sensor, and the control system is made to operate according to setting temperature and pressure curve of the system. The preparation method and the sintering device of the diamond bits has the advantages of being simple in process, high in degree of automation by using full numerical control, small in graphite dies for sintering, and energy-saving and cost-reducing. By using the preparation method and the sintering device of the diamond bits to manufacture impregnated diamond bits, average manufacturing time of bits is shortened by 40%, power consumption is reduced by 36%, and service life is prolonged by more than 40%.

Description

A kind of preparation method of diamond bit and sintering equipment thereof
Technical field
The invention belongs to a kind of drill bit preparation method and sintering equipment thereof, be specifically related to a kind of preparation method and sintering equipment thereof of diamond-impregnated bit.
Background technology
Diamond-impregnated bit is the requisite instrument of geological prospecting, and the engineering demand amount is large.The main method that Present Domestic is produced diamond-impregnated bit is powder metallurgic method, wherein the master operation link included for four steps: namely: batching dress mould, cold moudling, heat-agglomerating and postorder are processed, wherein " cold moudling " and " heat-agglomerating " two process procedures use respectively independently that hydraulic test and Intermediate Frequency Induction Heating Equipment carry out, and manually-operated connects the operation overall process.
There are following 3 deficiencies in existing diamond drill machine head manufacturing technique: the one, and drill bit is pressed and is fired in the process of making, and cold moudling and heat-agglomerating are separately carried out, and operation is numerous and diverse, and the cycle is longer.The 2nd, cold moudling is unidirectional rigidity mold pressing, and pressure fixing is constant, and bit matrix internal pressure gradient is large, and bit matrix density improves limited, and inhomogeneous.The 3rd, heat-agglomerating is simple Frequency Induction Heating, frequency is fixing non-adjustable, can't satisfy simultaneously the sintering temperature requirement of the different metal powder in formula materials, diamond graphitization phenomenon is uncontrollable, causes bit matrix sintering strength and quality also to have limitation.Therefore, existing drill produced manufacturing process efficient is not high, and it is large that its quality is subjected to the manually-operated factor to affect fluctuation, stable not.
CN102274972 discloses " a kind of manufacture method of annular ultrathin diamond drill bit ", and the method mainly comprises the operations such as steel system work, mixing material, powder are loaded, heating pressure sintering, following process.Wherein heat pressure sintering and adopt high-frequency induction welder to mold heated, powder is directly sintered on the steel body.The method unites two into one " compressing " and " heat-agglomerating " and carries out simultaneously, operational sequence and preparation time have been reduced, alleviated manipulation strength, but because the high-frequency induction frequency is non-adjustable, heating-up temperature can not satisfy the sintering requirement of the different metal powder in the preparation powder simultaneously, the bit matrix degree of consolidation that produces is limited, and the diamond scaling loss is serious in sintering process.
CN101144370 provides a kind of " preparation method of hot pressing high phosphorus iron base diamond drilling bit ", and the method comprises operations such as getting the raw materials ready, join powder and batch mixing, dress mould, hot pressed sintering, and wherein hot pressed sintering adopts the middle frequency furnace sintering.The method adopts hot pressing process, operational sequence and preparation time have been reduced, alleviated manipulation strength, but because hot pressing is that unidirectional rigidity is exerted pressure, there is barometric gradient in the preparation powder, the different parts Density inhomogeneity of carcass, the bit matrix degree of consolidation that produces and service life are also very limited.
For production efficiency and the product quality that improves diamond bit, the applicant once attempted adopting increasing cold moudling pressure, the ways such as the temperature control of raising agglomerating plant and precision are improved the quality of drill bit product, although product quality increases, but still exist the production cycle to extend, the manual operations operation increases, the deficiencies such as unstable product quality, and resultant effect is not ideal enough.
Summary of the invention
The objective of the invention is to overcome the deficiencies in the prior art, provide a kind of the employing to become Median frequency sintering, direction vibration is exerted pressure, double track temperature and pressure curve controlled technique prepares diamond bit method.
Another object of the present invention is to provide a kind of the employing and becomes Median frequency sintering, direction vibration is exerted pressure, double track curve controlled technique prepares diamond bit special-purpose sintering equipment.
the object of the present invention is achieved like this: a kind of preparation method of diamond bit, comprise batching dress mould, hot pressed sintering, mould and subsequent treatment operation are moved back in insulation, it is characterized in that this preparation method's hot pressed sintering operation adopts the change Median frequency sintering, direction vibration is exerted pressure and double track temperature and pressure curve controlled, alloyed powder and the diamond of preparation are in advance mixed to get metal powder material by proportioning, be filled into mould and be placed in change Medium frequency induction circle, the limit heating edge is implemented the pressure sintering of direction vibration formula, its temperature and pressure is implemented the double track curve controlled, after moving back mould, insulation is semi-finished product, get finished product through subsequent treatment again,
Described batching press setter order: described alloyed powder and adamantine proportioning are 1:10~15;
Described hot pressed sintering operation: described hot pressing vibratory sintering temperature is 400~950 ℃, and pressure is 10~70KN, and the pressure head vibration frequency is 700~1000 times/minutes, and amplitude is 4~9mm;
Die process is moved back in described insulation: the graphite jig after hot pressed sintering is placed in the perlite sandstone, and insulation is cooled to room temperature backed off after random mould;
Described subsequent treatment operation: the drill bit after the demoulding need not machining boiling water mouth, directly polishing, polishing, spray paint, mark, packing the diamond bit finished product.
Described hot pressed sintering operation comprises the steps:
1. will be filled with the graphite jig of metal powder material, be placed between the induction coil as the output of intermediate frequency power supply generator, upper push-down head;
2. sintering equipment is set to automatic bidirectional vibration compacting, automatically becomes the Median frequency sintering program, sets each section temperature and pressure parameter value by the technological parameter requirement, will control curve and preserve pending;
3. start sintering equipment, to the pressurization of graphite jig limit heating edge enforcement direction vibration formula, its temperature and pressure is implemented double track curve controlled technique, 480~840 ℃ of hot pressed sintering temperature, pressure 12~65KN, pressure head vibration frequency 800~900 times/minutes, amplitude 5~8mm;
Described double track temperature and pressure is controlled one of curve: temperature raises from 480 ℃~840 ℃ slopes, is elevated to 840 ℃ during by 3 minutes, and insulation is 4 minutes in 3~7 minutes, slope cooling in 7~8.5 minutes, during by 8.5 minutes, stopped heating, oil cylinder backhaul; Pressure raises from 13kN~55kN slope, is elevated to 55kN during by 3 minutes, pressurize in 3~8.5 minutes, oil cylinder backhaul during by 8.5 minutes;
Described double track temperature and pressure is controlled two of curve: temperature heats up from 480 ℃~690 ℃ slopes, reach 690 ℃ during by 2 minutes, insulation is 1 minute in 2~3 minutes, and slope heats up in 3~4 minutes, reaches 860 ℃ by 4 minutes, insulation is 2 minutes in 4~6 minutes, slope cools to 740 ℃ in 6~7 minutes, and insulation is 1 minute in 7~8 minutes, slope cooling in 8~8.5 minutes, stopped heating after 8.5 minutes, the oil cylinder backhaul; Pressure raises from 13kN~45kN slope, be raised to 45kN during by 2 minutes, from pressurize in 2~3 minutes 1 minute, be elevated to 65kN from 3~4 minutes pressure slope, from pressurize in 4~6 minutes 2 minutes, reduce 6~7 minutes pressure slope, drop to 45kN during by 7 minutes, pressurize in 7~8.5 minutes was to oil cylinder backhaul in 8.5 minutes.
a kind of sintering equipment for preparing diamond bit, comprise hot press, intermediate frequency power supply and switch board, the bottom of hot press is provided with hydraulic system, the middle part is provided with, push-down head, induction coil, infrared radiation thermometer, the switch board outer setting has panel and operating desk, inside is provided with controller, controller comprises single-chip microcomputer, Temperature Controlling Chip and trigger unit for thyristor, single-chip microcomputer and hydraulic system, infrared radiation thermometer is connected with Temperature Controlling Chip, Temperature Controlling Chip is connected with trigger unit for thyristor, trigger unit for thyristor is connected with intermediate frequency power supply, intermediate frequency power supply is connected with induction coil, it is characterized in that described hydraulic system is the vibratory hydraulic system with vibrating device, hot press upper, lower two pressure heads are connected with vibratory hydraulic system respectively, described intermediate frequency power supply is for becoming the intermediate frequency power supply generator.
Described change intermediate frequency power supply generator is provided with two-way frequency changer circuit at least.
Apparatus of the present invention form temperature closed loop by controller, infrared radiation thermometer, intermediate frequency power supply and Temperature Controlling Chip to be controlled, by controller, vibratory hydraulic system and the closed-loop control of trigger unit for thyristor decomposition pressure.During work, controller utilizes infrared radiation thermometer to detect in real time the temperature of sintering, and heating current and the operating frequency of regulating intermediate frequency power supply by controller, makes it the temperature curve operation according to default.Simultaneously, utilize the pressure sensor in vibratory hydraulic system to detect in real time the oil cylinder working-pressure of hydraulic system, and regulate electro-hydraulic proportional valve and trigger unit for thyristor by controller, make it the pressure curve operation according to default.
Compared with prior art, advantage of the present invention is:
1, integrated heating, hydraulic pressure and vibrational system on an equipment, " direction vibration hot pressed sintering " process of execution, simultaneously in the hot pressed sintering process, use double track temperature and pressure curve controlled, satisfy the technological requirement of different user and different formulations material, guarantee the uniformity of production process full-automation and product quality, production efficiency and the service life of greatly having improved drill bit.
2, hot operation is become " change intermediate frequency " heating by " permanent intermediate frequency " heating; rationally utilize the exterior heat of different frequency heat effect and diathermanous; heat the metal powder material of carcass different parts; effectively improve the carcass sintering strength; the protection diamond particles is avoided graphitization; and improved the sintering temperature applicability, and ensure and realize the diamond bit constant product quality, realize the manufacture process energy-conserving and environment-protective.
3, " pressure " operation is become " direction vibration is exerted pressure " by " single-direction, constant pressure ", namely be superimposed with the vibration signal of certain frequency and amplitude on the basis of constant voltage control signal, thereby produce the oscillatory type pressurization, realize the vibration compacting in sintering process, utilize vibratory impulse to defeat real and vibration gap exhaust, effectively improve the density of pressed compact.
Description of drawings
Fig. 1 is preparation technology's FB(flow block) of the present invention.
Fig. 2 is one of double track temperature and pressure curve map of the present invention.
Fig. 3 is two of double track temperature and pressure curve map of the present invention.
Fig. 4 is sintering equipment structural representation of the present invention.
Fig. 5 is that sintering equipment circuit of the present invention connects block diagram.
Fig. 6 is sintering equipment control principle block diagram of the present invention.
Fig. 7 is intermediate-frequency power circuit block diagram of the present invention.
In figure: hot press 1, induction coil 11, seaming chuck 12, push-down head 13, hydraulic system 14, Pressure gauge 15, intermediate frequency power supply 2, control button 21, switch board 3, panel 31, operating desk 32, controller 33, single-chip microcomputer 33a, Temperature Controlling Chip 33b, trigger unit for thyristor 33c, infrared radiation thermometer 4.
The specific embodiment
Following examples by reference to the accompanying drawings, the invention will be further described.
Referring to Fig. 1, a kind of preparation method of diamond bit comprising that batching dress mould, hot pressed sintering, insulation move back mould and subsequent treatment operation.To be the alloyed powder of preparation in advance and diamond mix to get metal powder material by the proportioning of 1:10~15 to batching press setter order, is filled into graphite jig, and the present embodiment proportioning is 1:12.The hot pressed sintering operation adopts the change Median frequency sintering, direction vibration is exerted pressure and double track temperature and pressure curve controlled technique, be opposite to the graphite jig that becomes the Medium frequency induction circle and implement direction vibration formula hot pressed sintering, sintering temperature is 400~950 ℃, pressure is 10~70KN, the pressure head vibration frequency is 700~1000 times/minutes, and amplitude is 4~9mm.It is that the graphite jig after hot pressed sintering is placed in the perlite sandstone that die process is moved back in insulation, and it is semi-finished product that insulation is cooled to room temperature backed off after random mould.The subsequent treatment operation is that the drill blank after the demoulding be need not machining boiling water mouth, directly polishing, polishing, sprays paint, mark, is packaged into the diamond bit finished product.
The concrete steps of the present embodiment hot pressed sintering operation are: will be filled with the graphite jig of metal powder material, and be placed between the induction coil as the intermediate frequency power supply output, upper push-down head; Sintering equipment is set to the automatic bidirectional vibration and suppresses, automatically becomes Median frequency sintering, and sets each section temperature and pressure parameter value by the technological parameter requirement, controls curve and preserves pending state; Start hot press and intermediate frequency power supply, to the pressurization of graphite jig limit heating edge enforcement direction vibration formula, 480~860 ℃ of hot pressed sintering temperature, pressure 12~65KN, the pressure head vibration frequency is set to 850 times/minutes, and amplitude is set to 7mm.In the hot pressed sintering process, temperature and pressure is implemented double track curve controlled technique.The double track temperature and pressure is controlled one of curve: temperature raises from 480 ℃~840 ℃ slopes, is elevated to 840 ℃ during by 3 minutes, and insulation is 4 minutes in 3~7 minutes, slope cooling in 7~8.5 minutes, and during by 8.5 minutes, stopped heating, oil cylinder backhaul; Pressure raises from 13kN~55kN slope, is elevated to 55kN during by 3 minutes, pressurize in 3~8.5 minutes, oil cylinder backhaul (referring to Fig. 2) during by 8.5 minutes.The double track temperature and pressure is controlled two of curve: temperature heats up from 480 ℃~690 ℃ slopes, reach 690 ℃ during by 2 minutes, insulation is 1 minute in 2~3 minutes, and slope heats up in 3~4 minutes, reaches 860 ℃ by 4 minutes, insulation is 2 minutes in 4~6 minutes, slope cools to 740 ℃ in 6~7 minutes, and insulation is 1 minute in 7~8 minutes, slope cooling in 8~8.5 minutes, stopped heating after 8.5 minutes, the oil cylinder backhaul; Pressure raises from 13kN~45kN slope, be raised to 45kN during by 2 minutes, from pressurize in 2~3 minutes 1 minute, be elevated to 65kN from 3~4 minutes pressure slope, from pressurize in 4~6 minutes 2 minutes, reduce 6~7 minutes pressure slope, drop to 45kN during by 7 minutes, pressurize in 7~8.5 minutes was to oil cylinder backhaul (referring to Fig. 3) in 8.5 minutes.
Referring to Fig. 4~7, a kind of sintering equipment for preparing diamond bit comprises hot press 1, intermediate frequency power supply 2 and switch board 3, and the bottom of hot press 1 is provided with hydraulic system 11, the middle part is provided with upper and lower pressure head 12 and 13, induction coil 14, infrared radiation thermometer 4, and top is provided with Pressure gauge 15.Switch board 3 outer setting have panel 31 and operating desk 32, and inside is provided with is connected the controller 33 that is connected with operating desk with panel 31.Controller 33 comprises single-chip microcomputer 33a, Temperature Controlling Chip 33b and trigger unit for thyristor 33c, single-chip microcomputer 33a is connected with hydraulic system 14, infrared radiation thermometer 4 and Temperature Controlling Chip 33b, Temperature Controlling Chip 33b is connected with trigger unit for thyristor 33c, trigger unit for thyristor 33c is connected with intermediate frequency power supply 2, and intermediate frequency power supply 2 is connected with induction coil 14.The hydraulic system 11 of hot press is the vibratory hydraulic system with vibrating device, and vibration frequency is 700~1000 times/minutes, amplitude 4~9mm, and the present embodiment vibration frequency is set to 850 times/minutes, and amplitude is set to 7mm.Upper and lower two pressure heads 12 of hot press are connected with vibratory hydraulic system 11 respectively with being connected.Also be provided with pressure sensor and electro-hydraulic proportional valve in vibratory hydraulic system 11.Intermediate frequency power supply 2, need to automatically switch by temperature and realize the frequency conversion sintering by automatic change-over for to have the change intermediate frequency power supply generator of two-way intermediate frequency resonance circuit at least, the present embodiment to be provided with three road intermediate frequency resonance circuits.
Sintering equipment of the present invention has adopted digital Intelligent PID Control technology; 100 groups of above temperature and pressure curve datas have been arranged and have stored; in sintering process; can be according to predefined temperature and pressure curve motion; can select at any time and revise according to the technique needs; when repeatedly repeating sintering; can guarantee stability and the uniformity of technological parameter; and has a self-diagnostic function; operation troubles that can automatic monitoring system; comprise overheated, lack of water, miscommunication etc., can give failure alarm signal and shut down to be repaired.
The control of sintering equipment temperature and pressure of the present invention and the processing of data are realized by special-purpose software, because software does not belong to protection domain of the present invention, do not elaborate at this.
Manufacture craft of the present invention is simple, and sintering equipment adopts Full-numerical-control to control, and automaticity is high, and sintering graphite jig size is little, and is energy-saving and cost-reducing.Adopt preparation technology of the present invention and sintering equipment to make diamond-impregnated bit, can make the average manufacturing time of drill bit shorten 40%, power consumption reduces 36%, and working life improves more than 40%.

Claims (5)

1. the preparation method of a diamond bit, comprise batching dress mould, hot pressed sintering, mould and subsequent treatment operation are moved back in insulation, it is characterized in that this preparation method's hot pressed sintering operation adopts the change Median frequency sintering, direction vibration is exerted pressure and double track temperature and pressure curve controlled technique, alloyed powder and the diamond of preparation are in advance mixed to get metal powder material by proportioning, be filled into mould and be placed in change Medium frequency induction circle, the limit heating edge is implemented the pressure sintering of direction vibration formula, its temperature and pressure is implemented the double track curve controlled, after moving back mould, insulation is semi-finished product, get finished product through the subsequent treatment operation again,
Described batching press setter order: described alloyed powder and adamantine proportioning are 1:10~15;
Described hot pressed sintering operation: described hot pressing vibratory sintering temperature is 400~950 ℃, and pressure is 10~70KN, and the pressure head vibration frequency is 700~1000 times/minutes, and amplitude is 4~9mm;
Die process is moved back in described insulation: the graphite jig after hot pressed sintering is placed in the perlite sandstone, and insulation is cooled to room temperature backed off after random mould;
Described subsequent treatment operation: the drill bit after the demoulding need not machining boiling water mouth, directly polishing, polishing, spray paint, mark, packing the diamond bit finished product.
2. the preparation method of a kind of diamond bit according to claim 1, is characterized in that described hot pressed sintering operation comprises the steps:
1. will be filled with the graphite jig of metal powder material, be placed in as between the induction coil of the output that becomes the intermediate frequency power supply generator, upper push-down head;
2. sintering equipment is set to automatic bidirectional vibration compacting, automatically becomes the Median frequency sintering program, sets each section temperature and pressure parameter value by the technological parameter requirement, will control curve and preserve pending;
3. start sintering equipment, to the pressurization of graphite jig limit heating edge enforcement direction vibration formula, its temperature and pressure is implemented double track curve controlled technique, 480~840 ℃ of hot pressed sintering temperature, pressure 12~65KN, pressure head vibration frequency 800~900 times/minutes, amplitude 5~8mm.
3. the preparation method of a kind of diamond bit according to claim 1 and 2, it is characterized in that one of described double track temperature and pressure control curve is: temperature raises from 480 ℃~840 ℃ slopes, be elevated to 840 ℃ during by 3 minutes, insulation is 4 minutes in 3~7 minutes, slope cooling in 7~8.5 minutes, during by 8.5 minutes, stopped heating, oil cylinder backhaul; Pressure raises from 13kN~55kN slope, is elevated to 55kN during by 3 minutes, pressurize in 3~8.5 minutes, oil cylinder backhaul during by 8.5 minutes; Described double track temperature and pressure is controlled two of curve: temperature heats up from 480 ℃~690 ℃ slopes, reach 690 ℃ during by 2 minutes, insulation is 1 minute in 2~3 minutes, and slope heats up in 3~4 minutes, reaches 860 ℃ by 4 minutes, insulation is 2 minutes in 4~6 minutes, slope cools to 740 ℃ in 6~7 minutes, and insulation is 1 minute in 7~8 minutes, slope cooling in 8~8.5 minutes, stopped heating after 8.5 minutes, the oil cylinder backhaul; Pressure raises from 13kN~45kN slope, be raised to 45kN during by 2 minutes, from pressurize in 2~3 minutes 1 minute, be elevated to 65kN from 3~4 minutes pressure slope, from pressurize in 4~6 minutes 2 minutes, reduce 6~7 minutes pressure slope, drop to 45kN during by 7 minutes, pressurize in 7~8.5 minutes was to oil cylinder backhaul in 8.5 minutes.
4. sintering equipment for preparing diamond bit, comprise hot press (1), intermediate frequency power supply (2) and switch board (3), the bottom of hot press (1) is provided with hydraulic system (11), the middle part is provided with seaming chuck (12), push-down head (13), induction coil (14), infrared radiation thermometer (4), switch board (3) outer setting has panel (31) and operating desk (32), inside is provided with controller (33), controller (33) comprises single-chip microcomputer (33a), Temperature Controlling Chip (33b) and trigger unit for thyristor (33c), single-chip microcomputer (33a) and hydraulic system (11), infrared radiation thermometer (4) is connected 33b with Temperature Controlling Chip) connect, Temperature Controlling Chip (33b) is connected with trigger unit for thyristor (33c), trigger unit for thyristor (33c) is connected with intermediate frequency power supply (2), intermediate frequency power supply (2) is connected with induction coil (14), it is characterized in that described hydraulic system (11) is the vibratory hydraulic system with vibrating device, the seaming chuck (12) of hot press (1) is connected 13 with push-down head) be connected with vibratory hydraulic system respectively, described intermediate frequency power supply (2) is for becoming the intermediate frequency power supply generator.
5. the preparation method of a kind of diamond bit according to claim 4, is characterized in that described change intermediate frequency power supply generator is provided with two-way intermediate frequency resonance circuit at least.
CN201310055467.1A 2013-02-21 2013-02-21 Preparation method of diamond bits and sintering device thereof Expired - Fee Related CN103084574B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310055467.1A CN103084574B (en) 2013-02-21 2013-02-21 Preparation method of diamond bits and sintering device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310055467.1A CN103084574B (en) 2013-02-21 2013-02-21 Preparation method of diamond bits and sintering device thereof

Publications (2)

Publication Number Publication Date
CN103084574A true CN103084574A (en) 2013-05-08
CN103084574B CN103084574B (en) 2014-09-24

Family

ID=48197987

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310055467.1A Expired - Fee Related CN103084574B (en) 2013-02-21 2013-02-21 Preparation method of diamond bits and sintering device thereof

Country Status (1)

Country Link
CN (1) CN103084574B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106352694A (en) * 2016-10-26 2017-01-25 西南交通大学 Intermediate frequency bidirectional vibration sintering furnace
CN106369993A (en) * 2016-10-26 2017-02-01 西南交通大学 Intermediate-frequency two-way vibration atmosphere sintering furnace
CN106524748A (en) * 2016-10-26 2017-03-22 西南交通大学 Medium-frequency unidirectional-vibration atmosphere sintering furnace
CN106643192A (en) * 2016-10-26 2017-05-10 西南交通大学 Medium-frequency one-way vibration sintering furnace
CN108555302A (en) * 2018-01-22 2018-09-21 华中科技大学 A kind of cold increasing material/warm and hot forging combined shaping method of non-crystaline amorphous metal part
CN108655395A (en) * 2018-05-18 2018-10-16 桂林特邦新材料有限公司 A method of improving composite sheet flatness and uniformity
CN110666156A (en) * 2019-10-23 2020-01-10 璞奔(常州)新材料科技有限公司 Hub manufacturing method and system
CN113624014A (en) * 2021-08-16 2021-11-09 吉林大学 Uniform-temperature heating rotary device for preparing energy-saving diamond-impregnated bit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008207334A (en) * 2008-06-09 2008-09-11 Allied Material Corp Single crystal diamond cutting tool and its manufacturing method
US20100300767A1 (en) * 2009-05-28 2010-12-02 Smith International, Inc. Diamond Bonded Construction with Improved Braze Joint
CN102102942A (en) * 2010-12-28 2011-06-22 青岛科技大学 Pressure-adjustable vibratory type hot pressed sintering furnace
CN102828095A (en) * 2012-09-16 2012-12-19 北京科技大学 Preparation method of high-strength oxidation-resistant molybdenum-base composite material
CN102828696A (en) * 2012-09-11 2012-12-19 吉林大学 Iron-based diamond-impregnated bit for drilling in hard slipping foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008207334A (en) * 2008-06-09 2008-09-11 Allied Material Corp Single crystal diamond cutting tool and its manufacturing method
US20100300767A1 (en) * 2009-05-28 2010-12-02 Smith International, Inc. Diamond Bonded Construction with Improved Braze Joint
CN102102942A (en) * 2010-12-28 2011-06-22 青岛科技大学 Pressure-adjustable vibratory type hot pressed sintering furnace
CN102828696A (en) * 2012-09-11 2012-12-19 吉林大学 Iron-based diamond-impregnated bit for drilling in hard slipping foundation
CN102828095A (en) * 2012-09-16 2012-12-19 北京科技大学 Preparation method of high-strength oxidation-resistant molybdenum-base composite material

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106352694A (en) * 2016-10-26 2017-01-25 西南交通大学 Intermediate frequency bidirectional vibration sintering furnace
CN106369993A (en) * 2016-10-26 2017-02-01 西南交通大学 Intermediate-frequency two-way vibration atmosphere sintering furnace
CN106524748A (en) * 2016-10-26 2017-03-22 西南交通大学 Medium-frequency unidirectional-vibration atmosphere sintering furnace
CN106643192A (en) * 2016-10-26 2017-05-10 西南交通大学 Medium-frequency one-way vibration sintering furnace
CN108555302A (en) * 2018-01-22 2018-09-21 华中科技大学 A kind of cold increasing material/warm and hot forging combined shaping method of non-crystaline amorphous metal part
CN108655395A (en) * 2018-05-18 2018-10-16 桂林特邦新材料有限公司 A method of improving composite sheet flatness and uniformity
CN110666156A (en) * 2019-10-23 2020-01-10 璞奔(常州)新材料科技有限公司 Hub manufacturing method and system
CN113649578A (en) * 2019-10-23 2021-11-16 璞奔(常州)新材料科技有限公司 Hub manufacturing system and hub carrier
CN113624014A (en) * 2021-08-16 2021-11-09 吉林大学 Uniform-temperature heating rotary device for preparing energy-saving diamond-impregnated bit

Also Published As

Publication number Publication date
CN103084574B (en) 2014-09-24

Similar Documents

Publication Publication Date Title
CN103084574B (en) Preparation method of diamond bits and sintering device thereof
CN104001862B (en) A kind of rapid forming system of water-soluble core and manufacturing process
CN201833290U (en) Multi-mould cavity material push and scrap cold-hot pressing forming machine for resin sheet grinding wheels
CN106238732B (en) A kind of discharge plasma sintering system
WO2019029022A1 (en) Partitioned lifting forming type selective laser melting workbench
CN104117547B (en) A kind of Warm Extrusion gear stick continuous extrusion die and processing method thereof
CN105728721A (en) Double-powder quick molding and uniform spreading device
CN110976869A (en) Part additive composite manufacturing device and method
CN103770034A (en) Efficient manufacturing technology of abrasive material layers of ceramic bonding agent ultra-hard material grinding wheel
CN203695959U (en) Selected laser sintering molding 3D printing equipment
CN110153348A (en) Forging apparatus and forging method
CN107262714A (en) A kind of microwave sintering 3D printing device and its printing technology suitable for multiple material
CN207592778U (en) Foam metal manufacturing device based on powder metallurgy and extrusion technique
CN109454198A (en) The method for forging and molding and its triple gear of a kind of triple gear and application
CN201267872Y (en) Powder-throwing manipulator
CN202462920U (en) Powder material compression moulding device
CN104526836A (en) Solid inorganic substance powder 3D printing method based on selective laser melting technology
JPH09324202A (en) Sintered die for forming and forming thereof
CN106003637A (en) Pressing control device for injection mold
CN203887164U (en) Quick forming system of water-soluble core
CN211346334U (en) Quick hot-pressing sintering structure
CN107866753A (en) With random cellular structure metals binding agent sand wheel, device and preparation technology
CN208132742U (en) With random cellular structure metals binding agent sand wheel
CN101596594A (en) Throw the powder machine
CN106369993A (en) Intermediate-frequency two-way vibration atmosphere sintering furnace

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140924

Termination date: 20170221

CF01 Termination of patent right due to non-payment of annual fee