Divide the dish admission machine
Technical field
The present invention is a kind of electromechanical appliance, especially is the accessory equipment that steel bead wire and steel cord are produced.
Background technology
At present in steel bead wire and the production practice of steel cord, heavy coil steel wires is fallen dish do not have good way for the shallow bid steel wire, general runner or the manual type of adopting carried out, the steel wire degree of tightness that dish is good is inconsistent, cause next step production efficiency to reduce, unstable product quality, and the work capacity of falling to coil is large, wastes time and energy.
Summary of the invention
The object of the invention is to avoid the deficiencies in the prior art and a kind of minute dish admission machine is provided.
Technical scheme of the present invention is: minute dish admission machine, comprise support assembly, well cabinet frame assembly, traction wheel assembly, swage assembly, wire-crossing wheel assembly, wheel flutter assembly, flower wheel assembly and take-up pulley assembly, and well cabinet frame wheel assembly is installed on an end of frame; The wheel shaft of traction wheel assembly, wheel flutter assembly, flower wheel assembly, wire-crossing wheel assembly, take-up pulley assembly and well cabinet frame wheel assembly is to be arrangeding in parallel; Well cabinet frame wheel assembly, traction wheel assembly, swage assembly and wire-crossing wheel assembly are sequentially arranged on the same straight line; Flower wheel assembly and take-up pulley assembly are sequentially arranged on the same straight line; The wheel flutter assembly is arranged at the other end of frame; Take-up pulley assembly and traction wheel assembly are equipped with respectively retarder.Tangent line is at same straight line on swage hole and the traction wheel.The wire-crossing wheel assembly has three wire-crossing wheels, is the equilateral triangle setting.The retarder of take-up pulley assembly and traction wheel assembly is synchronous.
Compared with prior art, advantage of the present invention is: simple to operate, easy to use, coil efficient high, and the elasticity of steel wire winding is consistent, and is time saving and energy saving.
Description of drawings
Fig. 1 is of the present invention minute dish admission machine structural representation.
Fig. 2 is plan structure schematic diagram of the present invention.
Among the figure: 1 is frame, and 2 is the wheel flutter assembly, and 3 is the flower wheel assembly, and 4 is the swage assembly, and 5 is the traction wheel assembly, and 6 is well cabinet frame wheel assembly, and 7 is the take-up pulley assembly, and 8 is the wire-crossing wheel assembly, and 9 is retarder, and 10 is retarder.
The specific embodiment
Be described in detail embodiments of the invention below in conjunction with accompanying drawing.
Divide the dish admission machine, comprise frame 1 assembly, well cabinet frame assembly 6, traction wheel assembly 5, swage assembly 4, wire-crossing wheel assembly 8, wheel flutter assembly 2, flower wheel assembly 3 and take-up pulley assembly 7, well cabinet frame wheel assembly 6 is installed on an end of frame 1; The wheel shaft of traction wheel assembly 5, wheel flutter assembly 2, flower wheel assembly 3, wire-crossing wheel assembly 8, take-up pulley assembly 7 and well cabinet frame wheel assembly 6 is to be arrangeding in parallel; Well cabinet frame wheel assembly 6, traction wheel assembly 5, swage assembly 4 and wire-crossing wheel assembly 8 are sequentially arranged on the same straight line; Flower wheel assembly 3 is sequentially arranged on the same straight line with take-up pulley assembly 7; Wheel flutter assembly 2 is arranged at the other end of frame 1; Take-up pulley assembly 7 and traction wheel assembly 5 are equipped with respectively retarder 9 and 10.Tangent line is at same straight line on swage hole and the traction wheel.Wire-crossing wheel assembly 8 has three wire-crossing wheels, is the equilateral triangle setting.The retarder 10 and 9 of take-up pulley assembly 7 and traction wheel assembly 5 is synchronous.
Frame 1 assembly is the basic bearing part of this equipment, for each working portion provides the running platform; Well cabinet frame wheel assembly 6 is positioned at equipment incoming line place, has effectively prevented the generation of random line phenomenon, defines direct of travel and the path of wire; Traction wheel assembly 5 for take-up pulley assembly 7 alleviates the traction burden, is regulated steel wire tension and circle footpath for steel wire provides traction; Swage assembly 4 adjustment of tonicity and circle footpath; Wire-crossing wheel assembly 8 and wheel flutter assembly 2 prevent the steel wire wire jumper, allow steel wire guide to flower wheel assembly 3 according to normal route; Flower wheel assembly 3 is realized the front adjusting to the circle footpath of take-up, carries out pre-take-up, control tension force; Finally under the control of electric-control system, finished coiling dividing of wire by take-up pulley assembly 7.
Inflow point arranges well cabinet frame wheel assembly 6, and wire is passed by well cabinet frame wheel, guarantees the steady inlet wire of steel wire; After enclosing draw, the traction wheel two of wire winding traction wheel assembly 5 passes swage assembly 4, adjust distance between the swage wheel according to technological requirement, wire is behind three groups of wire-crossing wheels, adjust direction to flower wheel by wheel flutter, after twining flower wheel one circle steel wire is suspended on the take-up pulley hanging wire hole, realizes that take-up divides dish.To the reductor 10 of the reductor 9 of traction wheel assembly 5 and take-up pulley assembly 7 synchronous debugging that turns round, guarantee that two reductors 9 and 10 are synchronous, thereby guarantee that steel wire tension is stable, guarantee steadily carrying out of take-up.
The existing pay off rack of equipment utilization carries out unwrapping wire, and pay off rack carries tension regulating system, and steel wire is drawn from pay off rack and carried out threading according to diagram afterwards, and threading is finished and checked and press start button after normal, and equipment moves automatically; Equipment carries the metering system, and when steel wire rice reached setting value, equipment was automatically out of service.