CN103064017A - Sulfur hexafluoride (SF6) density relay transmission test control device - Google Patents
Sulfur hexafluoride (SF6) density relay transmission test control device Download PDFInfo
- Publication number
- CN103064017A CN103064017A CN2012105537127A CN201210553712A CN103064017A CN 103064017 A CN103064017 A CN 103064017A CN 2012105537127 A CN2012105537127 A CN 2012105537127A CN 201210553712 A CN201210553712 A CN 201210553712A CN 103064017 A CN103064017 A CN 103064017A
- Authority
- CN
- China
- Prior art keywords
- transmission test
- control device
- density relay
- test control
- extension tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Pipeline Systems (AREA)
- Taps Or Cocks (AREA)
Abstract
The invention relates to a sulfur hexafluoride (SF6) density relay transmission test control device which is characterized by comprising a control valve (1), wherein an inlet tube (2) of the control valve (1) is connected with one end of an extension tube (4) through an interconnecting nut (3), and the other end of the extension tube (4) is connected with a live connection nut (5). Trials prove that after the SF6 density relay transmission test control device is used, the problem that an indicator of a SF6 density replay meter gets stuck, or other failures such as normal rotation failure and abnormal connection of connection points during indicating, and potential safety hazards which can not be found in a traditional SF6 density relay transmission test can be found timely, and the problem that transmission of part of breakers fails due to the installation position of an SF6 density relay is solved, and the transmission test from the root of the SF6 density relay is achieved.
Description
Technical field
The present invention relates to a kind of SF6 (is sulfur hexafluoride SF
6) density monitor transmission test control device.
Background technology
Stipulate according to power equipment preventive trial code of practice, before SF6 isolating switch and the GIS putting equipment in service, after the overhaul, will carry out the transmission verification to locking, anti-performance, the signal that jumps and prevent and treat the sub controlling unit such as non-complete mutually combined floodgate in case of necessity, and require transmission test to carry out from root.The present situation of transmission test is at present: SF6 density monitor tail wiring box is opened at the scene, adopts corresponding warning and the locking contact of the artificial short circuit of shorting stub to test.
But for the SF6 density monitor of installation site near isolating switch framework middle part, terminal box wraps in framework inside, even open shrouding, also can't adopt traditional short circuit method to open terminal box and carry out transmission test, can only take to carry out the short circuit test transmission at upper level mechanism case internal wiring terminal row place, like this, for reporting to the police and the locking contact connects anti-defective and also can't find, more have no way of realizing the root transmission test, virtually buried more device security hidden danger.
Summary of the invention
The purpose of this invention is to provide a kind of SF6 density monitor transmission test control device that can realize carrying out from the root of SF6 density monitor the transmission test function.
A kind of SF6 density monitor transmission test control device, its special feature is: comprise operation valve, the induction pipe of this operation valve is connected with an end of extension tube by interconnecting nut, and the other end of this extension tube is connected with the flexible connection nut.
Wherein the two ends of interconnecting nut respectively with the induction pipe of extension tube and operation valve between being threaded, and the equal hermetic seal in junction.
Wherein be flexibly connected between nut and the extension tube to be threaded, and the junction hermetic seal.
Wherein the outlet of operation valve is connected with a tail gas recycle pipe, and the junction hermetic seal.
Through probationary certificate, after adopting control device of the present invention, can in time find SF6 density monitor table meter pointer card plucked instrument or other faults that can not find in traditional SF6 density monitor transmission test, such as can not normal rotation, contact normal defective and the potential safety hazard such as connection not during indication.Solved the part isolating switch because of SF6 density monitor installation site can't transmission problem, realized carrying out transmission test from the root of SF6 density monitor.
Description of drawings
Accompanying drawing 1 is structural representation of the present invention.
Embodiment
As shown in Figure 1, the present invention is a kind of SF6 density monitor transmission test control device, comprises operation valve 1, and the induction pipe 2 of this operation valve 1 is connected with an end of extension tube 4 by interconnecting nut 3, and the other end of this extension tube 4 is connected with flexible connection nut 5.Wherein, the two ends of interconnecting nut 3 respectively with the induction pipe 2 of extension tube 4 and operation valve 1 between being threaded, and the equal hermetic seal in junction, and be flexibly connected between nut 5 and the extension tube 4 to be threaded, and junction hermetic seal.The outlet 6 of operation valve 1 is connected with a tail gas recycle pipe 7 in addition, and the junction hermetic seal.
Using method of the present invention is:
To be flexibly connected nut 5 during use is tightened on the SF6 density monitor checking joint, can use in case of necessity the seal elements such as O-ring seal to make the junction hermetic seal, then close SF6 breaker body operation valve, utilize the residual gas of SF6 density monitor gauge outfit the inside, exit by the operation valve 1 of slow rotation control device of the present invention and just can realize carrying out transmission test from root.
Claims (4)
1. SF6 density monitor transmission test control device, it is characterized in that: comprise operation valve (1), the induction pipe (2) of this operation valve (1) is connected with an end of extension tube (4) by interconnecting nut (3), and the other end of this extension tube (4) is connected with flexible connection nut (5).
2. a kind of SF6 density monitor transmission test control device as claimed in claim 1, it is characterized in that: wherein the two ends of interconnecting nut (3) respectively with the induction pipe (2) of extension tube (4) and operation valve (1) between being threaded, and the equal hermetic seal in junction.
3. a kind of SF6 density monitor transmission test control device as claimed in claim 1 or 2 is characterized in that: wherein be flexibly connected between nut (5) and the extension tube (4) to be threaded, and the junction hermetic seal.
4. a kind of SF6 density monitor transmission test control device as claimed in claim 1 or 2, it is characterized in that: wherein the outlet (6) of operation valve (1) is connected with a tail gas recycle pipe (7), and the junction hermetic seal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210553712.7A CN103064017B (en) | 2012-12-19 | 2012-12-19 | SF6 density monitor transmission test controls device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210553712.7A CN103064017B (en) | 2012-12-19 | 2012-12-19 | SF6 density monitor transmission test controls device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103064017A true CN103064017A (en) | 2013-04-24 |
CN103064017B CN103064017B (en) | 2016-12-28 |
Family
ID=48106723
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210553712.7A Expired - Fee Related CN103064017B (en) | 2012-12-19 | 2012-12-19 | SF6 density monitor transmission test controls device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103064017B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110907818A (en) * | 2019-12-25 | 2020-03-24 | 浦江乐程电子科技有限公司 | Quick verifying attachment of relay function commonly used |
CN114429884A (en) * | 2021-12-14 | 2022-05-03 | 上海精密计量测试研究所 | Unsealing method of rectangular sealed electromagnetic relay |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5733371A (en) * | 1980-08-08 | 1982-02-23 | Hitachi Ltd | Equivalent tester for breaker |
JP3172989B2 (en) * | 1995-03-03 | 2001-06-04 | 株式会社高岳製作所 | Gas circuit breaker failure detection device |
CN200944374Y (en) * | 2006-04-12 | 2007-09-05 | 苏丽芳 | Anti-vibration pointer type SF gas density relay |
CN201247162Y (en) * | 2008-08-25 | 2009-05-27 | 常州爱特科技有限公司 | Gas recovery apparatus |
CN202013407U (en) * | 2011-03-17 | 2011-10-19 | 重庆市电力公司长寿供电局 | Checkout device for gas density relay |
CN202994989U (en) * | 2012-12-19 | 2013-06-12 | 宁夏电力公司中卫供电局 | Transmission test control device for SF6 density relay |
-
2012
- 2012-12-19 CN CN201210553712.7A patent/CN103064017B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5733371A (en) * | 1980-08-08 | 1982-02-23 | Hitachi Ltd | Equivalent tester for breaker |
JP3172989B2 (en) * | 1995-03-03 | 2001-06-04 | 株式会社高岳製作所 | Gas circuit breaker failure detection device |
CN200944374Y (en) * | 2006-04-12 | 2007-09-05 | 苏丽芳 | Anti-vibration pointer type SF gas density relay |
CN201247162Y (en) * | 2008-08-25 | 2009-05-27 | 常州爱特科技有限公司 | Gas recovery apparatus |
CN202013407U (en) * | 2011-03-17 | 2011-10-19 | 重庆市电力公司长寿供电局 | Checkout device for gas density relay |
CN202994989U (en) * | 2012-12-19 | 2013-06-12 | 宁夏电力公司中卫供电局 | Transmission test control device for SF6 density relay |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110907818A (en) * | 2019-12-25 | 2020-03-24 | 浦江乐程电子科技有限公司 | Quick verifying attachment of relay function commonly used |
CN114429884A (en) * | 2021-12-14 | 2022-05-03 | 上海精密计量测试研究所 | Unsealing method of rectangular sealed electromagnetic relay |
CN114429884B (en) * | 2021-12-14 | 2023-08-25 | 上海精密计量测试研究所 | Unsealing method of rectangular sealed electromagnetic relay |
Also Published As
Publication number | Publication date |
---|---|
CN103064017B (en) | 2016-12-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9246325B2 (en) | Connection device for transformer substation modules | |
CN202957123U (en) | Self-test and self-protection oil-immersed power transformer | |
EA030501B1 (en) | Coal mine remote leakage test method and device | |
CN203644978U (en) | Multifunctional ground wire operating rod | |
CN111013051B (en) | Verification system and method for oil-discharging and nitrogen-injecting fire extinguishing device of oil-immersed transformer | |
CN104215409B (en) | A kind of method of monitoring bushing shell for transformer sealing condition | |
CN103064017A (en) | Sulfur hexafluoride (SF6) density relay transmission test control device | |
CN203415386U (en) | Anti-inflowing and anti-explosion oiled paper capacitance type transformer sleeve | |
CN202994989U (en) | Transmission test control device for SF6 density relay | |
KR100340160B1 (en) | Auto Reclosing Circuit Breaker Tester for Distribution | |
CN202721378U (en) | Fire-proof and explosion-proof monitoring system | |
CN106537162A (en) | Cable testing device and method | |
CN102393505A (en) | Online monitoring device for characteristics of high-voltage circuit breaker | |
CN106099871B (en) | Protective device for power grid | |
CN102570388A (en) | Controllable device of surge protector | |
CN103308799B (en) | The Apparatus and method for that a kind of cable-line parameter be connected with GIS is measured | |
CN204481356U (en) | A kind of fast moving distribution integrated apparatus | |
CN202994909U (en) | Grounding state monitoring device for electrical equipment and grounding network of transformer station | |
CN203503550U (en) | Oil-immersed transformer oil tank pressure relay protection device | |
US10436854B2 (en) | Power supply arrangement | |
CN105186694A (en) | Commercial power switching control apparatus | |
GB2577143A (en) | Device for disconnection of electrical vehicle supply equipment in the event of a fault | |
CN204714244U (en) | Can the test coil of wire box of temperature in monitor box | |
CN104020326A (en) | Switching device for testing mechanical characteristics of switch | |
CN102611019B (en) | Method for charged replacement of isolating switch and current guide device thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161228 Termination date: 20171219 |
|
CF01 | Termination of patent right due to non-payment of annual fee |