CN103061213A - Independent shield trolley sleeper and construction method thereof - Google Patents

Independent shield trolley sleeper and construction method thereof Download PDF

Info

Publication number
CN103061213A
CN103061213A CN2012105809831A CN201210580983A CN103061213A CN 103061213 A CN103061213 A CN 103061213A CN 2012105809831 A CN2012105809831 A CN 2012105809831A CN 201210580983 A CN201210580983 A CN 201210580983A CN 103061213 A CN103061213 A CN 103061213A
Authority
CN
China
Prior art keywords
steel plate
sleeper
shield
spacing
duct piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012105809831A
Other languages
Chinese (zh)
Other versions
CN103061213B (en
Inventor
杨勇
操琪
顾铭峰
万绍涛
杨磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 24th Bureau Group Co Ltd
China Railway 24th Bureau Group Shanghai Railway Co Ltd
Original Assignee
China Railway 24th Bureau Group Co Ltd
China Railway 24th Bureau Group Shanghai Railway Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 24th Bureau Group Co Ltd, China Railway 24th Bureau Group Shanghai Railway Co Ltd filed Critical China Railway 24th Bureau Group Co Ltd
Priority to CN201210580983.1A priority Critical patent/CN103061213B/en
Publication of CN103061213A publication Critical patent/CN103061213A/en
Application granted granted Critical
Publication of CN103061213B publication Critical patent/CN103061213B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to an independent shield trolley sleeper and a construction method thereof. The sleeper comprises a horizontal steel plate with a supporting surface, a vertical steel plate and a limiting steel plate, wherein the vertical steel plate and the limiting steel plate are used for bearing the horizontal steel plate; and the shape of the bottom edge of the vertical steel plate is matched with that of an inner arc surface of a shield segment, the dimension of an outer outline surface of the limiting steel plate is matched with that of an inner outline surface of a hand hole on the shield segment, a limiting shaft is arranged at the lower end portion of the limiting steel plate, and the diameter of the limiting shaft is matched with that of a bolt hole axially arranged in the hand hole of the shield segment. The independent shield trolley sleeper has the advantages of being simple in structure, greatly reducing consumption of steel materials, effectively reducing the weight, and enabling a shield trolley to move stably and reliably by being adhered onto the shield segment stably. Simultaneously, by adopting the structure, the sleeper is fast and convenient to detach when used circularly, reduces investment of manpower and time and improves the extending speed of a rail arranged on the sleeper.

Description

A kind of free-standing shield gantry track pillow and job practices thereof
Technical field
The invention belongs to the Shield Construction Technique field, be specifically related to a kind of free-standing shield gantry track pillow and job practices thereof.
Background technology
Shield method has been widely used in all over the world the tunnel construction with its unique advantage.Horizontal transport is as an important step in the shield-tunneling construction process in the tunnel, and practicality, reasonably horizontal transportation system can be so that whole shield-tunneling construction process be quicker, effective, safety and economy.
In shield-tunneling construction, require the follow-up chassis of shield structure to follow shield machine sleeper in the tunnel and move forward; And the soil body that shield cutter cuts down and be assembled into used section of jurisdiction, tunnel is then transported at sleeper by flat bed transport vehicle.In the construction in the past, the sleeper of the laying imitation railroad track of sleeper, the flat bed transport vehicle sleeper of the chassis sleeper of large gauge and little gauge is joined together to lay, the sleeper weight that the method is made is larger, carrying is inconvenient, and because the track of flat bed transport vehicle can not remove before construction finishes, cause the association type sleeper can't be recycling.
Patent (CN 1888392B) discloses the method that a kind of shield gantry car and electric locomotive are set up sleeper separately, its scheme be the follow-up chassis of shield structure need with large sleeper and flat bed transport vehicle need with little sleeper set up separately respectively and lay, the advance erection mode of large sleeper of construction of the follow-up chassis of pole structure is: the left side of direction of advance, right both sides, each arranges a pair of follow-up chassis of the pole structure left side of propping up respectively relatedly, the sleeper of right wheel, described sleeper is two i iron, consist of unequal-sided one pair of right-angled triangle, minor face vertically withstands the tunnel round bottom, and long limit level is shelved the tunnel side.The shortcoming of its scheme is: the paving mode of large sleeper still is the large gauge continous way sleeper that adopts railroad sleeper, and the weight of single sleeper is still larger, need expend more manpower when recycling and go dismounting, and length consuming time.
Therefore those skilled in the art is badly in need of a kind of weight that can alleviate large gauge sleeper, improves the simplicity of large gauge sleeper in recycling process, and can reduce the sleeper scheme of disassembly and assembly time.
Summary of the invention
The objective of the invention is according to above-mentioned the deficiencies in the prior art part, a kind of free-standing shield gantry track pillow and job practices thereof are provided, this sleeper is by arranging vertical steel plate and spacing steel plate with as supporting construction below its horizontal steel plate, simultaneously by limit shaft being embedded in the bolt hole in the hand hole to reach axially and radially spacing, with easy disassembly with alleviate the sleeper quality.
The object of the invention realizes being finished by following technical scheme:
A kind of free-standing shield gantry track pillow, relate to be used to the hand hole on the shield duct piece that described sleeper is installed and the described shield duct piece, it is characterized in that described sleeper comprises that one has the horizontal steel plate of supporting surface, and the vertical steel plate and the spacing steel plate that are used for supporting described horizontal steel plate, wherein said vertical steel plate one end and described horizontal Plate Welding are fixed, the other end contact described shield duct piece of fitting, and this end shape and described shield duct piece intrados shape are complementary; Described spacing steel plate one end and described horizontal Plate Welding are fixed, the interior contoured surface geomery of the outer surface geomery of its other end and described hand hole is complementary, in the bottom of described spacing steel plate one limit shaft is set, the bolt aperture in the diameter of described limit shaft and the described hand hole is complementary.
Be welded with i iron on the supporting surface of described horizontal steel plate, be provided with reinforcing rib at described i iron.
Vertically offer at least one caging bolt hole on the described i iron.
Be provided with the reinforcing rib that is connected both between described vertical steel plate and the described spacing steel plate, also be provided with reinforcing rib in the outside of described spacing steel plate simultaneously.
A kind of job practices of above-mentioned free-standing shield gantry track pillow, it is characterized in that comprising the steps: at least the spacing steel plate on the described sleeper stretched in the hand hole on the described shield duct piece and with it and fit tightly, the base of described vertical steel plate and the intrados of described shield duct piece fit tightly, axially pass described sleeper along the tunnel, limit shaft on the described spacing steel plate is embedded in the bolt hole of described hand hole, and described limit shaft consists of spacing axially and radially of described sleeper; The rest may be inferred, mounting means by above-mentioned sleeper arranges described sleeper in even interval vertically in the both sides in tunnel respectively, and set up track at the i iron of described sleeper, by screwing in bolt in the caging bolt hole on described i iron with spacing fixing described track, so that the track space of described both sides is identical with the travelling wheel spacing of described shield gantry car.
Advantage of the present invention is, and is simple in structure, reduced widely steel consumption, effectively alleviated the sleeper quality; Sleeper is stable to be fitted on the shield duct piece, and the traveling thereon of shield gantry car is steadily reliable; Adopt simultaneously sleeper easy accessibility when recycling of this kind structure quick, reduced the input of manpower and time, improved the track extension speed that arranges on it.
Description of drawings
Fig. 1 is the front view of the left sleeper of the present invention;
Fig. 2 is the lateral view of the left sleeper of the present invention;
Fig. 3 is the front view of the right sleeper of the present invention;
Fig. 4 is the lateral view of the right sleeper of the present invention;
Fig. 5 is the structural representation that middle left and right sleeper of the present invention is arranged at the shield duct piece both sides;
Fig. 6 is that the left sleeper of the present invention is arranged at the interior local enlarged front view of hand hole on the shield duct piece;
Fig. 7 is that the left sleeper of the present invention is arranged at the interior local enlarged side view of hand hole on the shield duct piece.
The specific embodiment
Feature of the present invention and other correlated characteristic are described in further detail by embodiment below in conjunction with accompanying drawing, so that technician's of the same trade understanding:
Such as Fig. 1-7, mark 1-14 is respectively among the figure: i iron 1, rail 2, caging bolt hole 3, horizontal steel plate 4, vertical steel plate 5, reinforcing rib 6, reinforcing rib 7, spacing steel plate 8, limit shaft 9, bolt hole 10, hand hole 11, sleeper 12, sleeper 13, shield duct piece 14.
Embodiment: shown in Fig. 5,6,7, this implements to adopt the construction of tunnel of shield method is that example describes, when the shield machine tunneling construction, require the shield gantry car at shield machine rear to follow the large gauge sleeper 12 of shield machine in the tunnel and move forward, the soil body that shield cutter cuts down and be assembled into the section of jurisdiction of using in the tunnel and then transport at little gauge sleeper 13 by flat bed transport vehicle.For making things convenient for the recycling of large gauge sleeper 12, adopt the structure of free-standing sleeper, large gauge sleeper 12 is set in that the both sides of shield duct piece 14 hand hole 11 is interior, the axially evenly interval laying along the tunnel, the design feature of large gauge sleeper 12 is the shape of can fit shield duct piece 14 and hand hole 11 thereof, simultaneously its constructional limit shaft 9 can be embedded in the bolt hole 10 that arranges vertically of hand hole 11, consists of axially and radially spacing; When utilizing shield gantry car to move forward by rail transmit the forward frictional force of getting off so that self structure " is held " shield duct piece 14, reach firm self purpose.
Shown in Fig. 1-7, the sleeper 12 that is arranged at the tunnel arranged on left and right sides is symmetric relation, and structure is identical.Take the left sleeper 12 that is arranged at 14 left sides, tunneling shield section of jurisdiction as example, its structure is specially: be vertically welded with a vertical steel plate 5 below horizontal steel plate 4, specifically be inequilateral right angle trigonometry shape, its long right-angle side and horizontal steel plate 4 are fitted and are welded and fixed, short right-angle side vertically withstands horizontal steel plate 4, the intrados shape of the shape of hypotenuse and shield duct piece 14 is complementary, and is arranged on the shield duct piece 14 so that vertical steel plate 5 can be fitted; One spacing steel plate 8 is set below horizontal steel plate 4 simultaneously, spacing steel plate 8 residing planes and horizontal steel plate 4 residing planes are orthogonal, it is the trapezoidal of circular arc that the shape of spacing steel plate 8 roughly is the bottom, and the interior contoured surface shape of its outer surface shape and hand hole 11 is complementary identical; Be provided with an axial limiting axle 9 at the center of arc of spacing steel plate 8 place, the diameter in the axial bolts hole 10 that the diameter of limit shaft 9 and hand hole 11 are interior is identical; Between vertical steel plate 5 and spacing steel plate 8, be welded with reinforcing rib 6 in order to increasing both connection stability, and at the arranged outside reinforcing rib 7 of spacing steel plate 8; Supporting surface at horizontal steel plate 4 arranges i iron 1, and i iron 1 is laterally placed, and offers caging bolt hole 3 thereon, and caging bolt hole 3 fitted bolts use the rail 2 that can prevent from setting up thereon to be offset.
Vertical steel plate 5 in the above-mentioned free-standing sleeper 12 and spacing steel plate 8 structures can be born from the pressure on the vertical direction, have the effect of braced structures; Spacing steel plate 8 is arranged in the hand hole 11, because the outer surface of spacing steel plate 8 fits tightly the internal face of hand hole 11, so it can prevent owing to because the radian of shield duct piece 14 causes the slippage of sleeper 12 oblique belows, have the effect of position limiting structure; Be arranged at limit shaft 9 on the spacing steel plate 8 and in concrete the use, insert in the bolt hole 10 that arranges vertically in the hand hole 11, can play prevent sleeper 12 axially with the displacement that directly makes progress, have the effect of position limiting structure.
Shown in Fig. 1-7, below be the use method to set up of free-standing shield gantry track pillow 12 in the shield tunnel engineering, concrete steps are as follows:
1. at first measure the travelling wheel spacing of shield gantry car both sides, select afterwards the hand hole 11 of suitable interval in the arranged on left and right sides of shield duct piece 14;
2. respectively on a left side, the hand hole 11 of right both sides is interior to arrange free-standing sleeper 12: the spacing steel plate 8 on the sleeper 12 is stretched in the hand hole 11 and with it fit tightly, the hypotenuse of the vertical steel plate 5 on the sleeper 12 and the intrados of shield duct piece 14 also fit tightly, afterwards along the axial passing sleeper 12 in tunnel, limit shaft 9 on the spacing steel plate 8 is inserted in the bolt hole 10 of the vertically setting in the hand hole 11, this moment, horizontal steel plate 4 was in level, these stand alone type sleeper 12 stabilized structures can bear from vertically in the intrados of shield duct piece 14 and its hand hole 11, axially and power radially and slippage does not occur;
3. the rest may be inferred, mounting means by the free-standing sleeper 12 in the previous step, axially even interval arranges sleeper 12 along the tunnel, sleeper to be laid 12 head and the tail length stop to lay when reaching the length of shield gantry car, sleeper 12 in both sides arranges rail 2 respectively, and undertaken spacingly by 3 pairs of rail in caging bolt hole 2, prevent that it from lateral shift occuring;
4. along with the driving of shield machine, whole horizontal transportation system constantly extends forward, therefore needs to remove sleeper 12 and the rail 2 at rear, to be used for replenishing sleeper 12 and the rail 2 of laying the place ahead, reaches the purpose that recycles.

Claims (5)

1. a free-standing shield gantry track is rested the head on, relate to be used to the hand hole on the shield duct piece that described sleeper is installed and the described shield duct piece, it is characterized in that described sleeper comprises that one has the horizontal steel plate of supporting surface, and the vertical steel plate and the spacing steel plate that are used for supporting described horizontal steel plate, wherein said vertical steel plate one end and described horizontal Plate Welding are fixed, the other end contact described shield duct piece of fitting, and this end shape and described shield duct piece intrados shape are complementary; Described spacing steel plate one end and described horizontal Plate Welding are fixed, the interior contoured surface geomery of the outer surface geomery of its other end and described hand hole is complementary, in the bottom of described spacing steel plate one limit shaft is set, the bolt aperture in the diameter of described limit shaft and the described hand hole is complementary.
2. a kind of free-standing shield gantry track pillow according to claim 1 is characterized in that being welded with i iron on the supporting surface of described horizontal steel plate, is provided with reinforcing rib at described i iron.
3. a kind of free-standing shield gantry track pillow according to claim 2 is characterized in that vertically offering on the described i iron at least one caging bolt hole.
4. a kind of free-standing shield gantry track pillow according to claim 1 is characterized in that being provided with the reinforcing rib that is connected both between described vertical steel plate and the described spacing steel plate, and the while also is provided with reinforcing rib in the outside of described spacing steel plate.
5. one kind relates to the job practices that the described free-standing shield gantry track of claim 1-4 is rested the head on, it is characterized in that comprising the steps: at least the spacing steel plate on the described sleeper stretched in the hand hole on the described shield duct piece and with it and fit tightly, the base of described vertical steel plate and the intrados of described shield duct piece fit tightly, axially pass described sleeper along the tunnel, limit shaft on the described spacing steel plate is embedded in the bolt hole of described hand hole, and described limit shaft consists of spacing axially and radially of described sleeper; The rest may be inferred, mounting means by above-mentioned sleeper arranges described sleeper in even interval vertically in the both sides in tunnel respectively, and set up track at the i iron of described sleeper, by screwing in bolt in the caging bolt hole on described i iron with spacing fixing described track, so that the track space of described both sides is identical with the travelling wheel spacing of described shield gantry car.
CN201210580983.1A 2012-12-28 2012-12-28 Independent shield trolley sleeper and construction method thereof Active CN103061213B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210580983.1A CN103061213B (en) 2012-12-28 2012-12-28 Independent shield trolley sleeper and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210580983.1A CN103061213B (en) 2012-12-28 2012-12-28 Independent shield trolley sleeper and construction method thereof

Publications (2)

Publication Number Publication Date
CN103061213A true CN103061213A (en) 2013-04-24
CN103061213B CN103061213B (en) 2014-11-05

Family

ID=48104083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210580983.1A Active CN103061213B (en) 2012-12-28 2012-12-28 Independent shield trolley sleeper and construction method thereof

Country Status (1)

Country Link
CN (1) CN103061213B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239470A (en) * 2015-09-30 2016-01-13 龚金京 Novel portable independent suspended railway sleeper for subsequent trolley matched with shield tunneling machine
CN107144198A (en) * 2017-06-07 2017-09-08 济南重工股份有限公司 With wheel to examining frock and method after one kind
CN107354831A (en) * 2017-08-23 2017-11-17 中铁五局集团第六工程有限责任公司 A kind of track-laying machine traveling support
CN107489447A (en) * 2017-08-03 2017-12-19 中国电建集团铁路建设有限公司 Temporary track fixed system and its construction in a kind of tunnel
CN107574727A (en) * 2017-09-12 2018-01-12 北京城建中南土木工程集团有限公司 A kind of easy assembling type shield chassis composite sleeper and its application method
CN109440544A (en) * 2018-11-05 2019-03-08 中铁四院集团西南勘察设计有限公司 A kind of track girder and the connection structure of shield duct piece and attaching method thereof
CN109915166A (en) * 2019-04-16 2019-06-21 中铁十一局集团第三工程有限公司 A kind of rail supporting leg
CN112343612A (en) * 2020-09-23 2021-02-09 辽宁三三工业有限公司 Trolley wheel structure, track and trolley for enabling shield tunneling machine trolley to move along shield tunneling machine track
CN113512910A (en) * 2021-07-10 2021-10-19 中铁隧道局集团有限公司 Track device and method for rapidly stepping open TBM (tunnel boring machine)
CN114990943A (en) * 2022-06-10 2022-09-02 中交天和机械设备制造有限公司 Shield constructs sleeper and track subassembly for platform truck

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1077778A (en) * 1996-09-02 1998-03-24 Taisei Corp Shield machine and shield method
CN1888392A (en) * 2006-02-23 2007-01-03 上海市第二市政工程有限公司 Method for setting up sleeper separately for truck jumbo and electric locomotive
JP3928987B2 (en) * 1997-06-02 2007-06-13 株式会社イズミ Tunnel sleepers
CN201952686U (en) * 2011-03-22 2011-08-31 中建市政建设有限公司 Assembled sleeper for shield construction
CN201991536U (en) * 2011-03-22 2011-09-28 中建市政建设有限公司 Device for replacing tail brush during shield excavation process
CN202055828U (en) * 2011-02-16 2011-11-30 长江水利委员会长江勘测规划设计研究院 Shield starting reaction support

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1077778A (en) * 1996-09-02 1998-03-24 Taisei Corp Shield machine and shield method
JP3928987B2 (en) * 1997-06-02 2007-06-13 株式会社イズミ Tunnel sleepers
CN1888392A (en) * 2006-02-23 2007-01-03 上海市第二市政工程有限公司 Method for setting up sleeper separately for truck jumbo and electric locomotive
CN202055828U (en) * 2011-02-16 2011-11-30 长江水利委员会长江勘测规划设计研究院 Shield starting reaction support
CN201952686U (en) * 2011-03-22 2011-08-31 中建市政建设有限公司 Assembled sleeper for shield construction
CN201991536U (en) * 2011-03-22 2011-09-28 中建市政建设有限公司 Device for replacing tail brush during shield excavation process

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239470A (en) * 2015-09-30 2016-01-13 龚金京 Novel portable independent suspended railway sleeper for subsequent trolley matched with shield tunneling machine
CN107144198A (en) * 2017-06-07 2017-09-08 济南重工股份有限公司 With wheel to examining frock and method after one kind
CN107489447A (en) * 2017-08-03 2017-12-19 中国电建集团铁路建设有限公司 Temporary track fixed system and its construction in a kind of tunnel
CN107489447B (en) * 2017-08-03 2024-05-10 中国电建集团铁路建设有限公司 Temporary track fixing system in tunnel and construction method thereof
CN107354831A (en) * 2017-08-23 2017-11-17 中铁五局集团第六工程有限责任公司 A kind of track-laying machine traveling support
CN107574727B (en) * 2017-09-12 2023-10-03 北京城建中南土木工程集团有限公司 Conveniently-installed shield trolley combined sleeper and use method thereof
CN107574727A (en) * 2017-09-12 2018-01-12 北京城建中南土木工程集团有限公司 A kind of easy assembling type shield chassis composite sleeper and its application method
CN109440544A (en) * 2018-11-05 2019-03-08 中铁四院集团西南勘察设计有限公司 A kind of track girder and the connection structure of shield duct piece and attaching method thereof
CN109915166A (en) * 2019-04-16 2019-06-21 中铁十一局集团第三工程有限公司 A kind of rail supporting leg
CN112343612A (en) * 2020-09-23 2021-02-09 辽宁三三工业有限公司 Trolley wheel structure, track and trolley for enabling shield tunneling machine trolley to move along shield tunneling machine track
CN113512910A (en) * 2021-07-10 2021-10-19 中铁隧道局集团有限公司 Track device and method for rapidly stepping open TBM (tunnel boring machine)
CN114990943A (en) * 2022-06-10 2022-09-02 中交天和机械设备制造有限公司 Shield constructs sleeper and track subassembly for platform truck
CN114990943B (en) * 2022-06-10 2023-12-22 中交天和机械设备制造有限公司 Sleeper and track assembly for shield machine trolley

Also Published As

Publication number Publication date
CN103061213B (en) 2014-11-05

Similar Documents

Publication Publication Date Title
CN103061213B (en) Independent shield trolley sleeper and construction method thereof
CN202827280U (en) Duct piece transport vehicle
CN108590745B (en) Transportation method and transportation structure for shield tunnel construction
CN204475070U (en) Portable combined shield machine sleeper
CN103161346B (en) Transverse storing and fetching car carrier
CN104562870B (en) Portable combined shield machine sleeper
CN203050731U (en) Grouting trolley for secondary grouting operation
CN102174790B (en) Assembled tie for shield construction and construction method thereof
CN206015442U (en) A kind of removable compound shield-tunneling construction sleeper
CN105369699A (en) Construction method for dividing sleeper of portable novel shielding tunneling machine backup trailer and accumulator car system
CN203021882U (en) Independent type shield trolley sleeper
CN112343612A (en) Trolley wheel structure, track and trolley for enabling shield tunneling machine trolley to move along shield tunneling machine track
CN203780243U (en) Shield machine trailer walking device
CN201952686U (en) Assembled sleeper for shield construction
CN202622149U (en) Railless walking submerged-arc welding trolley
CN203794368U (en) Cable retraction and release trolley in tunnel
CN206938575U (en) The beam car of two-way fortune beam on a kind of asymmetric whole opening box girder beam of achievable large-tonnage
CN204825573U (en) Temporary road surface laying vehicle's guiding mechanism
CN206233043U (en) Rail and railroad track
CN205135656U (en) Modular two lining platform trucks of multipurpose
CN205365810U (en) Preceding trailer frame for transporting long pipeline
CN205055418U (en) Guider of guide rail car travels
CN107489447B (en) Temporary track fixing system in tunnel and construction method thereof
CN202373912U (en) Traveling type manual pay-off stand
CN205223758U (en) Hit rail dolly and hit rail ware

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant